Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline, 59890-59891 [2023-18752]

Download as PDF 59890 Federal Register / Vol. 88, No. 167 / Wednesday, August 30, 2023 / Notices being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission’s Rules and Regulations.11 A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties. Tracking the Proceeding Throughout the proceeding, additional information about the project will be available from the Commission’s Office of External Affairs, at (866) 208– FERC, or on the FERC website at www.ferc.gov using the ‘‘eLibrary’’ link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/docs-filing/ esubscription.asp. Intervention Deadline: 5:00 p.m. Eastern Time on September 13, 2023. Dated: August 23, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–18639 Filed 8–29–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2333–094] lotter on DSK11XQN23PROD with NOTICES1 Rumford Falls Hydro LLC; Notice of Waiver Period for Water Quality Certification Application On August 22, 2023, Rumford Falls Hydro LLC submitted to the Federal Energy Regulatory Commission (Commission) a copy of its application for a Clean Water Act Section 401(a)(1) water quality certification filed with the Maine Department of Environmental Protection (Maine DEP), in conjunction with the above captioned project. Pursuant to Section 401 of the Clean Water Act 1 and section 5.23(b) of the Dated: August 23, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–18637 Filed 8–29–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP23–529–000] Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline Take notice that on August 17, 2023, Columbia Gas Transmission, LLC (Columbia), 700 Louisiana Street, Suite 1300, Houston, Texas 77002–2700, filed in the above referenced docket, a prior notice request for authorization, in accordance with section 7 of the Natural Gas Act, and part 157 Sections 157.205 and 157.216 of the Federal Energy Regulatory Commission’s (Commission) regulations under the Natural Gas Act and Columbia’s blanket certificate issued in Docket No. CP83–76–000. Columbia seeks authorization to abandon two injection/withdrawal well, connecting pipeline, and appurtenances located in the Victory B Storage Field in Marshall County, West Virginia, all as more fully set forth in the application which is on file with the Commission and open for public inspection. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the 11 18 1 33 CFR 385.214(b)(3) and (d). U.S.C. 1341(a)(1). Commission’s regulations,2 a state certifying agency is deemed to have waived its certifying authority if it fails or refuses to act on a certification request within a reasonable period of time, which is one year after the date the certification request was received. Accordingly, we hereby notify Maine DEP of the following: Date Maine DEP received the certification request: August 22, 2023. If Maine DEP fails or refuses to act on the water quality certification request on or before August 22, 2024, then the agency certifying authority is deemed waived pursuant to section 401(a)(1) of the Clean Water Act, 33 U.S.C. 1341(a)(1). VerDate Sep<11>2014 17:31 Aug 29, 2023 2 18 Jkt 259001 PO 00000 CFR 5.23(b) (2022). Frm 00027 Fmt 4703 Sfmt 4703 last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Any questions regarding this prior notice request should be directed to David A. Alonzo, Manager, Project Authorizations, Columbia Gas Transmission, LLC, 700 Louisiana Street, Suite 1300, Houston, Texas 77002–2700, at (832) 320–5477 or david. alonzo@tcenergy.com. Public Participation There are three ways to become involved in the Commission’s review of this project: you can file a protest to the project, you can file a motion to intervene in the proceeding, and you can file comments on the project. There is no fee or cost for filing protests, motions to intervene, or comments. The deadline for filing protests, motions to intervene, and comments is 5:00 p.m. Eastern Time on October 23, 2023. How to file protests, motions to intervene, and comments is explained below. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Protests Pursuant to section 157.205 of the Commission’s regulations under the NGA,1 any person 2 or the Commission’s staff may file a protest to the request. If no protest is filed within the time allowed or if a protest is filed and then withdrawn within 30 days after the allowed time for filing a protest, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request for authorization will be considered by the Commission. 1 18 CFR 157.205. include individuals, organizations, businesses, municipalities, and other entities. 18 CFR 385.102(d). 2 Persons E:\FR\FM\30AUN1.SGM 30AUN1 Federal Register / Vol. 88, No. 167 / Wednesday, August 30, 2023 / Notices Protests must comply with the requirements specified in section 157.205(e) of the Commission’s regulations,3 and must be submitted by the protest deadline, which is October 23, 2023. A protest may also serve as a motion to intervene so long as the protestor states it also seeks to be an intervenor. lotter on DSK11XQN23PROD with NOTICES1 Interventions Any person has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission’s orders in the U.S. Circuit Courts of Appeal. To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure 4 and the regulations under the NGA 5 by the intervention deadline for the project, which is October 23, 2023. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https:// www.ferc.gov/resources/guides/how-to/ intervene.asp. All timely, unopposed motions to intervene are automatically granted by operation of Rule 214(c)(1). Motions to intervene that are filed after the intervention deadline are untimely and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission’s Rules and Regulations. A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties. Comments Any person wishing to comment on the project may do so. The Commission considers all comments received about the project in determining the 3 18 CFR 157.205(e). CFR 385.214. 5 18 CFR 157.10. 4 18 VerDate Sep<11>2014 17:31 Aug 29, 2023 Jkt 259001 appropriate action to be taken. To ensure that your comments are timely and properly recorded, please submit your comments on or before October 23, 2023. The filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding. How To File Protests, Interventions, and Comments There are two ways to submit protests, motions to intervene, and comments. In both instances, please reference the Project docket number CP23–529–000 in your submission. (1) You may file your protest, motion to intervene, and comments by using the Commission’s eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select General’’ and then select ‘‘Protest’’, ‘‘Intervention’’, or ‘‘Comment on a Filing’’; or 6 (2) You can file a paper copy of your submission by mailing it to the address below. Your submission must reference the Project docket number CP23–529– 000. To mail via USPS, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. To send via any other courier, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The Commission encourages electronic filing of submissions (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. Protests and motions to intervene must be served on the applicant either by mail at: David A. Alonzo, Manager, Project Authorizations, Columbia Gas Transmission, LLC, 700 Louisiana Street, Suite 1300, Houston, Texas, 77002–2700, at david alonzo@ tcenergy.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. 6 Additionally, you may file your comments electronically by using the eComment feature, which is located on the Commission’s website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project. PO 00000 Frm 00028 Fmt 4703 Sfmt 4703 59891 Tracking the Proceeding Throughout the proceeding, additional information about the project will be available from the Commission’s Office of External Affairs, at (866) 208– FERC, or on the FERC website at FERC.gov using the ‘‘eLibrary’’ link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/docs-filing/ esubscription.asp. Dated: August 24, 2023. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2023–18752 Filed 8–29–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP21–31–001] Texas Eastern Transmission, LP; Notice of Request for Extension of Time Take notice that on August 22, 2023, Texas Eastern Transmission, LP (Texas Eastern), requested that the Federal Energy Regulatory Commission (Commission) grant an extension of time until December 23, 2023, to complete construction of the Perulack Compressor Units Replacement Project (Project) and place the Project facilities into service, as authorized in the September 23, 2021 Order Issuing Certificate and Approving Abandonment (Certificate Order),1 under section 7 of the Natural Gas Act (NGA). Texas Eastern states it has completed abandonment activities as of June 30, 2023, and since that time has installed major foundations, set prefabricated buildings, installed major equipment, erected the compressor building, set the turbines, installed a portion of the main gas and utility pipeline, and installed electrical raceways and wiring. The remaining Project activities include the 1 Texas Eastern Transmission, LP, 176 FERC ¶ 61,206 (2021). E:\FR\FM\30AUN1.SGM 30AUN1

Agencies

[Federal Register Volume 88, Number 167 (Wednesday, August 30, 2023)]
[Notices]
[Pages 59890-59891]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-18752]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP23-529-000]


Columbia Gas Transmission, LLC; Notice of Request Under Blanket 
Authorization and Establishing Intervention and Protest Deadline

    Take notice that on August 17, 2023, Columbia Gas Transmission, LLC 
(Columbia), 700 Louisiana Street, Suite 1300, Houston, Texas 77002-
2700, filed in the above referenced docket, a prior notice request for 
authorization, in accordance with section 7 of the Natural Gas Act, and 
part 157 Sections 157.205 and 157.216 of the Federal Energy Regulatory 
Commission's (Commission) regulations under the Natural Gas Act and 
Columbia's blanket certificate issued in Docket No. CP83-76-000. 
Columbia seeks authorization to abandon two injection/withdrawal well, 
connecting pipeline, and appurtenances located in the Victory B Storage 
Field in Marshall County, West Virginia, all as more fully set forth in 
the application which is on file with the Commission and open for 
public inspection.
    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (https://ferc.gov) using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. At this time, 
the Commission has suspended access to the Commission's Public 
Reference Room. For assistance, contact FERC at 
[email protected] or call toll-free, (886) 208-3676 or TYY, 
(202) 502-8659.
    Any questions regarding this prior notice request should be 
directed to David A. Alonzo, Manager, Project Authorizations, Columbia 
Gas Transmission, LLC, 700 Louisiana Street, Suite 1300, Houston, Texas 
77002-2700, at (832) 320-5477 or david. [email protected].

Public Participation

    There are three ways to become involved in the Commission's review 
of this project: you can file a protest to the project, you can file a 
motion to intervene in the proceeding, and you can file comments on the 
project. There is no fee or cost for filing protests, motions to 
intervene, or comments. The deadline for filing protests, motions to 
intervene, and comments is 5:00 p.m. Eastern Time on October 23, 2023. 
How to file protests, motions to intervene, and comments is explained 
below.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or [email protected].

Protests

    Pursuant to section 157.205 of the Commission's regulations under 
the NGA,\1\ any person \2\ or the Commission's staff may file a protest 
to the request. If no protest is filed within the time allowed or if a 
protest is filed and then withdrawn within 30 days after the allowed 
time for filing a protest, the proposed activity shall be deemed to be 
authorized effective the day after the time allowed for protest. If a 
protest is filed and not withdrawn within 30 days after the time 
allowed for filing a protest, the instant request for authorization 
will be considered by the Commission.
---------------------------------------------------------------------------

    \1\ 18 CFR 157.205.
    \2\ Persons include individuals, organizations, businesses, 
municipalities, and other entities. 18 CFR 385.102(d).

---------------------------------------------------------------------------

[[Page 59891]]

    Protests must comply with the requirements specified in section 
157.205(e) of the Commission's regulations,\3\ and must be submitted by 
the protest deadline, which is October 23, 2023. A protest may also 
serve as a motion to intervene so long as the protestor states it also 
seeks to be an intervenor.
---------------------------------------------------------------------------

    \3\ 18 CFR 157.205(e).
---------------------------------------------------------------------------

Interventions

    Any person has the option to file a motion to intervene in this 
proceeding. Only intervenors have the right to request rehearing of 
Commission orders issued in this proceeding and to subsequently 
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
    To intervene, you must submit a motion to intervene to the 
Commission in accordance with Rule 214 of the Commission's Rules of 
Practice and Procedure \4\ and the regulations under the NGA \5\ by the 
intervention deadline for the project, which is October 23, 2023. As 
described further in Rule 214, your motion to intervene must state, to 
the extent known, your position regarding the proceeding, as well as 
your interest in the proceeding. For an individual, this could include 
your status as a landowner, ratepayer, resident of an impacted 
community, or recreationist. You do not need to have property directly 
impacted by the project in order to intervene. For more information 
about motions to intervene, refer to the FERC website at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------

    \4\ 18 CFR 385.214.
    \5\ 18 CFR 157.10.
---------------------------------------------------------------------------

    All timely, unopposed motions to intervene are automatically 
granted by operation of Rule 214(c)(1). Motions to intervene that are 
filed after the intervention deadline are untimely and may be denied. 
Any late-filed motion to intervene must show good cause for being late 
and must explain why the time limitation should be waived and provide 
justification by reference to factors set forth in Rule 214(d) of the 
Commission's Rules and Regulations. A person obtaining party status 
will be placed on the service list maintained by the Secretary of the 
Commission and will receive copies (paper or electronic) of all 
documents filed by the applicant and by all other parties.

Comments

    Any person wishing to comment on the project may do so. The 
Commission considers all comments received about the project in 
determining the appropriate action to be taken. To ensure that your 
comments are timely and properly recorded, please submit your comments 
on or before October 23, 2023. The filing of a comment alone will not 
serve to make the filer a party to the proceeding. To become a party, 
you must intervene in the proceeding.

How To File Protests, Interventions, and Comments

    There are two ways to submit protests, motions to intervene, and 
comments. In both instances, please reference the Project docket number 
CP23-529-000 in your submission.
    (1) You may file your protest, motion to intervene, and comments by 
using the Commission's eFiling feature, which is located on the 
Commission's website (www.ferc.gov) under the link to Documents and 
Filings. New eFiling users must first create an account by clicking on 
``eRegister.'' You will be asked to select the type of filing you are 
making; first select General'' and then select ``Protest'', 
``Intervention'', or ``Comment on a Filing''; or \6\
---------------------------------------------------------------------------

    \6\ Additionally, you may file your comments electronically by 
using the eComment feature, which is located on the Commission's 
website at www.ferc.gov under the link to Documents and Filings. 
Using eComment is an easy method for interested persons to submit 
brief, text-only comments on a project.
---------------------------------------------------------------------------

    (2) You can file a paper copy of your submission by mailing it to 
the address below. Your submission must reference the Project docket 
number CP23-529-000.
    To mail via USPS, use the following address: Kimberly D. Bose, 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426.
    To send via any other courier, use the following address: Kimberly 
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins 
Avenue, Rockville, Maryland 20852.
    The Commission encourages electronic filing of submissions (option 
1 above) and has eFiling staff available to assist you at (202) 502-
8258 or [email protected]. Protests and motions to intervene 
must be served on the applicant either by mail at: David A. Alonzo, 
Manager, Project Authorizations, Columbia Gas Transmission, LLC, 700 
Louisiana Street, Suite 1300, Houston, Texas, 77002-2700, at david 
[email protected]. Any subsequent submissions by an intervenor must 
be served on the applicant and all other parties to the proceeding. 
Contact information for parties can be downloaded from the service list 
at the eService link on FERC Online.

Tracking the Proceeding

    Throughout the proceeding, additional information about the project 
will be available from the Commission's Office of External Affairs, at 
(866) 208-FERC, or on the FERC website at FERC.gov using the 
``eLibrary'' link as described above. The eLibrary link also provides 
access to the texts of all formal documents issued by the Commission, 
such as orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. For more information and to register, go to 
www.ferc.gov/docs-filing/esubscription.asp.

    Dated: August 24, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023-18752 Filed 8-29-23; 8:45 am]
BILLING CODE 6717-01-P