ANR Pipeline Company; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Oak Grove Enhancement Project, 59901-59903 [2023-18638]
Download as PDF
lotter on DSK11XQN23PROD with NOTICES1
Federal Register / Vol. 88, No. 167 / Wednesday, August 30, 2023 / Notices
clear bar-space; (7) a 36-inch-diameter
bypass pipe; (8) a 22.5-foot-high, 49.5foot-long, 48.75-foot-wide powerhouse
containing two Francis-type generating
units with a total capacity of 0.64
megawatts; (9) a concrete lined tailrace
discharging flows back into the South
Fork Catawba River; (10) a substation
containing a 2.3/44-kilovolt (kV)
transformer and interconnection to
Duke Energy’s 44 kV transmission line;
and (11) appurtenant facilities.
The project operates in a run-of-river
mode with a minimum bypass flow of
76 cubic feet per second. Spencer
Mountain Hydropower, LLC proposes
no changes to the project facilities or
operations. The project has an average
annual generation of 4,064 megawatthours.
m. In addition to publishing the full
text of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room. For assistance, contact
FERC Online Support at
FERCOnllineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TTY, (202)
502–8659.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Anyone may submit a protest or a
motion to intervene in accordance with
the requirements of Rules of Practice
and Procedure, 18 CFR 385.210,
385.211, and 385.214. In determining
the appropriate action to take, the
Commission will consider all protests
filed, but only those who file a motion
to intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any protests or
motions to intervene must be received
on or before the specified deadline date
for the particular application.
All filings must (1) bear in all capital
letters the title ‘‘PROTEST’’ or
‘‘MOTION TO INTERVENE;’’ (2) set
forth in the heading the name of the
applicant and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
protesting or intervening; and (4)
otherwise comply with the requirements
VerDate Sep<11>2014
17:31 Aug 29, 2023
Jkt 259001
of 18 CFR 385.2001 through 385.2005.
Agencies may obtain copies of the
application directly from the applicant.
A copy of any protest or motion to
intervene must be served upon each
representative of the applicant specified
in the particular application.
o. Procedural schedule: The
application will be processed according
to the following schedule. Revisions to
the schedule will be made as
appropriate.
Issue Scoping Document 1
for comments.
Scoping Document 1 comments due.
Request Additional Information (if necessary).
Issue Scoping Document 2 (if
necessary).
Issue Notice of Ready for Environmental Analysis.
September
2023.
October 2023.
November
2023.
November
2023.
January 2024.
Dated: August 24, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–18744 Filed 8–29–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP23–523–000]
ANR Pipeline Company; Notice of
Scoping Period Requesting Comments
on Environmental Issues for the
Proposed Oak Grove Enhancement
Project
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental document, that will
discuss the environmental impacts of
the Oak Grove Enhancement Project
involving construction and operation of
facilities by ANR Pipeline Company
(ANR) in Richland and West Carroll
Parishes, Louisiana. The Commission
will use this environmental document
in its decision-making process to
determine whether the project is in the
public convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies regarding the
project. As part of the National
Environmental Policy Act (NEPA)
review process, the Commission takes
into account concerns the public may
have about proposals and the
environmental impacts that could result
from its action whenever it considers
the issuance of a Certificate of Public
PO 00000
Frm 00038
Fmt 4703
Sfmt 4703
59901
Convenience and Necessity. This
gathering of public input is referred to
as ‘‘scoping.’’ The main goal of the
scoping process is to focus the analysis
in the environmental document on the
important environmental issues.
Additional information about the
Commission’s NEPA process is
described below in the NEPA Process
and Environmental Document section of
this notice.
By this notice, the Commission
requests public comments on the scope
of issues to address in the
environmental document. To ensure
that your comments are timely and
properly recorded, please submit your
comments so that the Commission
receives them in Washington, DC, on or
before 5:00 p.m. Eastern Time on
September 25, 2023. Comments may be
submitted in written form. Further
details on how to submit comments are
provided in the Public Participation
section of this notice.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
Your input will help the Commission
staff determine what issues they need to
evaluate in the environmental
document. Commission staff will
consider all written comments during
the preparation of the environmental
document.
If you submitted comments on this
project to the Commission before the
opening of this docket on August 1,
2023, you will need to file those
comments in Docket No. CP23–523–000
to ensure they are considered as part of
this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
easement agreement. You are not
required to enter into an agreement.
However, if the Commission approves
the project, the Natural Gas Act conveys
the right of eminent domain to the
company. Therefore, if you and the
company do not reach an easement
agreement, the pipeline company could
initiate condemnation proceedings in
court. In such instances, compensation
would be determined by a judge in
accordance with State law. The
E:\FR\FM\30AUN1.SGM
30AUN1
59902
Federal Register / Vol. 88, No. 167 / Wednesday, August 30, 2023 / Notices
lotter on DSK11XQN23PROD with NOTICES1
Commission does not subsequently
grant, exercise, or oversee the exercise
of that eminent domain authority. The
courts have exclusive authority to
handle eminent domain cases; the
Commission has no jurisdiction over
these matters.
ANR provided landowners with a fact
sheet prepared by the FERC entitled
‘‘An Interstate Natural Gas Facility On
My Land? What Do I Need To Know? ’’
which addresses typically asked
questions, including the use of eminent
domain and how to participate in the
Commission’s proceedings. This fact
sheet along with other landowner topics
of interest are available for viewing on
the FERC website (www.ferc.gov) under
the Natural Gas, Landowner Topics link.
Public Participation
There are three methods you can use
to submit your comments to the
Commission. Please carefully follow
these instructions so that your
comments are properly recorded. The
Commission encourages electronic filing
of comments and has staff available to
assist you at (866) 208–3676 or
FercOnlineSupport@ferc.gov.
(1) You can file your comments
electronically using the eComment
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. Using
eComment is an easy method for
submitting brief, text-only comments on
a project;
(2) You can file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. With
eFiling, you can provide comments in a
variety of formats by attaching them as
a file with your submission. New
eFiling users must first create an
account by clicking on ‘‘eRegister.’’ You
will be asked to select the type of filing
you are making; a comment on a
particular project is considered a
‘‘Comment on a Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
Commission. Be sure to reference the
project docket number (CP23–523–000)
on your letter. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852.
Additionally, the Commission offers a
free service called eSubscription which
VerDate Sep<11>2014
17:31 Aug 29, 2023
Jkt 259001
makes it easy to stay informed of all
issuances and submittals regarding the
dockets/projects to which you
subscribe. These instant email
notifications are the fastest way to
receive notification and provide a link
to the document files which can reduce
the amount of time you spend
researching proceedings. Go to https://
www.ferc.gov/ferc-online/overview to
register for eSubscription.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Summary of the Proposed Project
ANR proposes to construct and
operate 34.1 miles of new 30-inchdiameter natural gas pipeline to replace
33.6 miles of existing 30-inch-diameter
natural gas pipeline that ANR would
abandon. The Oak Grove Enhancement
Project would continue to provide about
1,233 million square cubic feet per day
of natural gas to its existing end user.
No increase in natural gas capacity is
anticipated. According to ANR, its
project would improve the integrity and
reliability of ANR’s system by replacing
vintage pipeline facilities installed in
the 1950’s with new pipeline facilities.
The Oak Grove Enhancement Project
would consist of the following facilities:
• Installation of 34.1 miles of new 30inch-diameter segment of natural gas
pipeline, which will begin at ANR’s
existing Delhi Compressor Station (CS)
in Richland Parish and primarily
parallel the existing Line 0–501, 1–501,
and 2–501 pipelines before the new
segment ties into the existing route just
south of State Route 586 in West Carroll
Parish at the terminus of the existing
Line 0–501 segment to be abandoned.
• Abandonment in place and by
removal of 33.6 miles of existing 30inch-diameter natural gas pipeline,
which begins at ANR’s existing Delhi CS
in Richland Parish and terminates just
south of State Route 586 in West Carroll
Parish. Approximately 1 percent (0.25
mile) of the existing Line 0–501 segment
would be abandoned by removal, while
the remaining existing pipeline
segments (totaling 33.35 miles) would
be abandoned in place.
PO 00000
Frm 00039
Fmt 4703
Sfmt 4703
The general location of the project
facilities is shown in appendix 1.1
Land Requirements for Construction
Construction and abandonment of the
proposed facilities would disturb about
702.4 acres of land for the replacement
pipeline. Following construction, ANR
would maintain about 170.3 acres for
permanent operation of the project’s
facilities; the remaining acreage would
be restored. Approximately 91 percent
(31.1 miles) of the new pipeline would
be co-located with existing rights-of-way
or paralleling existing utility corridors.
Areas where ANR was unable to colocate the pipeline with existing rightsof-way or parallel existing corridors was
primarily due to reroutes around
Wetland Reserve Program easements,
sensitive environmental areas, and
constructability issues (e.g., crossings of
waterbodies).
NEPA Process and the Environmental
Document
Any environmental document issued
by the Commission will discuss impacts
that could occur as a result of the
abandonment, construction, and
operation of the proposed project under
the relevant general resource areas:
• geology and soils;
• water resources and wetlands;
• vegetation and wildlife;
• threatened and endangered species;
• cultural resources;
• land use;
• environmental justice;
• air quality and noise; and
• reliability and safety.
Commission staff will also evaluate
reasonable alternatives to the proposed
project or portions of the project and
make recommendations on how to
lessen or avoid impacts on the various
resource areas. Your comments will
help Commission staff identify and
focus on the issues that might have an
effect on the human environment and
potentially eliminate others from further
study and discussion in the
environmental document.
Following this scoping period,
Commission staff will determine
whether to prepare an Environmental
Assessment (EA) or an Environmental
Impact Statement (EIS). The EA or the
EIS will present Commission staff’s
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of the
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’. For instructions on
connecting to eLibrary, refer to the last page of this
notice. At this time, the Commission has suspended
access to the Commission’s Public Reference Room.
For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll free, (886)
208–3676 or TTY (202) 502–8659.
E:\FR\FM\30AUN1.SGM
30AUN1
Federal Register / Vol. 88, No. 167 / Wednesday, August 30, 2023 / Notices
independent analysis of the issues. If
Commission staff prepares an EA, a
Notice of Schedule for the Preparation
of an Environmental Assessment will be
issued. The EA may be issued for an
allotted public comment period. The
Commission would consider timely
comments on the EA before making its
decision regarding the proposed project.
If Commission staff prepares an EIS, a
Notice of Intent to Prepare an EIS/
Notice of Schedule will be issued,
which will open up an additional
comment period. Staff will then prepare
a draft EIS which will be issued for
public comment. Commission staff will
consider all timely comments received
during the comment period on the draft
EIS and revise the document, as
necessary, before issuing a final EIS.
Any EA or draft and final EIS will be
available in electronic format in the
public record through eLibrary 2 and the
Commission’s natural gas
environmental documents web page
(https://www.ferc.gov/industries-data/
natural-gas/environment/
environmental-documents). If
eSubscribed, you will receive instant
email notification when the
environmental document is issued.
With this notice, the Commission is
asking agencies with jurisdiction by law
and/or special expertise with respect to
the environmental issues of this project
to formally cooperate in the preparation
of the environmental document.3
Agencies that would like to request
cooperating agency status should follow
the instructions for filing comments
provided under the Public Participation
section of this notice.
lotter on DSK11XQN23PROD with NOTICES1
Consultation Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, the Commission is
using this notice to initiate consultation
with the applicable State Historic
Preservation Office(s), and to solicit
their views and those of other
government agencies, interested Indian
tribes, and the public on the project’s
potential effects on historic properties.4
2 For instructions on connecting to eLibrary, refer
to the last page of this notice.
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at title 40, Code of Federal
Regulations, section 1501.8.
4 The Advisory Council on Historic Preservation’s
regulations are at title 36, Code of Federal
Regulations, part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
VerDate Sep<11>2014
17:31 Aug 29, 2023
Jkt 259001
The environmental document for this
project will document findings on the
impacts on historic properties and
summarize the status of consultations
under section 106.
Environmental Mailing List
The environmental mailing list
includes Federal, State, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project and includes a
mailing address with their comments.
Commission staff will update the
environmental mailing list as the
analysis proceeds to ensure that
Commission notices related to this
environmental review are sent to all
individuals, organizations, and
government entities interested in and/or
potentially affected by the proposed
project.
If you need to make changes to your
name/address, or if you would like to
remove your name from the mailing list,
please complete one of the following
steps:
(1) Send an email to
GasProjectAddressChange@ferc.gov
stating your request. You must include
the docket number CP23–523–000 in
your request. If you are requesting a
change to your address, please be sure
to include your name and the correct
address. If you are requesting to delete
your address from the mailing list,
please include your name and address
as it appeared on this notice. This email
address is unable to accept comments.
OR
(2) Return the attached ‘‘Mailing List
Update Form’’ (appendix 2).
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website at www.ferc.gov using the
eLibrary link. Click on the eLibrary link,
click on ‘‘General Search’’ and enter the
docket number in the ‘‘Docket Number’’
field. Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or (866)
208–3676, or for TTY, contact (202)
502–8659. The eLibrary link also
PO 00000
Frm 00040
Fmt 4703
Sfmt 4703
59903
provides access to the texts of all formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
Public sessions or site visits will be
posted on the Commission’s calendar
located at https://www.ferc.gov/newsevents/events along with other related
information.
Dated: August 23, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–18638 Filed 8–29–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2146–275]
Alabama Power Company; Notice of
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Non-Capacity
Amendment of License.
b. Project No: P–2146–275.
c. Date Filed: August 8, 2023.
d. Applicant: Alabama Power
Company (Alabama Power).
e. Name of Project: Coosa River
Project.
f. Location: The project is located on
the Coosa River, in Coosa, Chilton,
Talladega and Shelby counties,
Alabama.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Alan L. Peeples,
Alabama Power Company, 600 North
18th Street, P.O. Box 2641, Birmingham,
AL 35291–8180, (205) 257–1401.
i. FERC Contact: Zeena Aljibury, (202)
502–6065, zeena.aljibury@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests is 30
days from the issuance date of this
notice by the Commission.
The Commission strongly encourages
electronic filing. Please file motions to
intervene, protests, comments, or
recommendations using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
E:\FR\FM\30AUN1.SGM
30AUN1
Agencies
[Federal Register Volume 88, Number 167 (Wednesday, August 30, 2023)]
[Notices]
[Pages 59901-59903]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-18638]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP23-523-000]
ANR Pipeline Company; Notice of Scoping Period Requesting
Comments on Environmental Issues for the Proposed Oak Grove Enhancement
Project
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental document, that will discuss
the environmental impacts of the Oak Grove Enhancement Project
involving construction and operation of facilities by ANR Pipeline
Company (ANR) in Richland and West Carroll Parishes, Louisiana. The
Commission will use this environmental document in its decision-making
process to determine whether the project is in the public convenience
and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies regarding the project. As part of the National Environmental
Policy Act (NEPA) review process, the Commission takes into account
concerns the public may have about proposals and the environmental
impacts that could result from its action whenever it considers the
issuance of a Certificate of Public Convenience and Necessity. This
gathering of public input is referred to as ``scoping.'' The main goal
of the scoping process is to focus the analysis in the environmental
document on the important environmental issues. Additional information
about the Commission's NEPA process is described below in the NEPA
Process and Environmental Document section of this notice.
By this notice, the Commission requests public comments on the
scope of issues to address in the environmental document. To ensure
that your comments are timely and properly recorded, please submit your
comments so that the Commission receives them in Washington, DC, on or
before 5:00 p.m. Eastern Time on September 25, 2023. Comments may be
submitted in written form. Further details on how to submit comments
are provided in the Public Participation section of this notice.
Your comments should focus on the potential environmental effects,
reasonable alternatives, and measures to avoid or lessen environmental
impacts. Your input will help the Commission staff determine what
issues they need to evaluate in the environmental document. Commission
staff will consider all written comments during the preparation of the
environmental document.
If you submitted comments on this project to the Commission before
the opening of this docket on August 1, 2023, you will need to file
those comments in Docket No. CP23-523-000 to ensure they are considered
as part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable easement agreement. You
are not required to enter into an agreement. However, if the Commission
approves the project, the Natural Gas Act conveys the right of eminent
domain to the company. Therefore, if you and the company do not reach
an easement agreement, the pipeline company could initiate condemnation
proceedings in court. In such instances, compensation would be
determined by a judge in accordance with State law. The
[[Page 59902]]
Commission does not subsequently grant, exercise, or oversee the
exercise of that eminent domain authority. The courts have exclusive
authority to handle eminent domain cases; the Commission has no
jurisdiction over these matters.
ANR provided landowners with a fact sheet prepared by the FERC
entitled ``An Interstate Natural Gas Facility On My Land? What Do I
Need To Know? '' which addresses typically asked questions, including
the use of eminent domain and how to participate in the Commission's
proceedings. This fact sheet along with other landowner topics of
interest are available for viewing on the FERC website (www.ferc.gov)
under the Natural Gas, Landowner Topics link.
Public Participation
There are three methods you can use to submit your comments to the
Commission. Please carefully follow these instructions so that your
comments are properly recorded. The Commission encourages electronic
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected].
(1) You can file your comments electronically using the eComment
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. Using eComment is an easy method for
submitting brief, text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. With eFiling, you can provide comments
in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making; a comment on a particular project is considered a ``Comment
on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the Commission. Be sure to reference the project docket number (CP23-
523-000) on your letter. Submissions sent via the U.S. Postal Service
must be addressed to: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC
20426. Submissions sent via any other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission,
12225 Wilkins Avenue, Rockville, Maryland 20852.
Additionally, the Commission offers a free service called
eSubscription which makes it easy to stay informed of all issuances and
submittals regarding the dockets/projects to which you subscribe. These
instant email notifications are the fastest way to receive notification
and provide a link to the document files which can reduce the amount of
time you spend researching proceedings. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
Summary of the Proposed Project
ANR proposes to construct and operate 34.1 miles of new 30-inch-
diameter natural gas pipeline to replace 33.6 miles of existing 30-
inch-diameter natural gas pipeline that ANR would abandon. The Oak
Grove Enhancement Project would continue to provide about 1,233 million
square cubic feet per day of natural gas to its existing end user. No
increase in natural gas capacity is anticipated. According to ANR, its
project would improve the integrity and reliability of ANR's system by
replacing vintage pipeline facilities installed in the 1950's with new
pipeline facilities.
The Oak Grove Enhancement Project would consist of the following
facilities:
Installation of 34.1 miles of new 30-inch-diameter segment
of natural gas pipeline, which will begin at ANR's existing Delhi
Compressor Station (CS) in Richland Parish and primarily parallel the
existing Line 0-501, 1-501, and 2-501 pipelines before the new segment
ties into the existing route just south of State Route 586 in West
Carroll Parish at the terminus of the existing Line 0-501 segment to be
abandoned.
Abandonment in place and by removal of 33.6 miles of
existing 30-inch-diameter natural gas pipeline, which begins at ANR's
existing Delhi CS in Richland Parish and terminates just south of State
Route 586 in West Carroll Parish. Approximately 1 percent (0.25 mile)
of the existing Line 0-501 segment would be abandoned by removal, while
the remaining existing pipeline segments (totaling 33.35 miles) would
be abandoned in place.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
www.ferc.gov using the link called ``eLibrary''. For instructions on
connecting to eLibrary, refer to the last page of this notice. At
this time, the Commission has suspended access to the Commission's
Public Reference Room. For assistance, contact FERC at
[email protected] or call toll free, (886) 208-3676 or TTY
(202) 502-8659.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction and abandonment of the proposed facilities would
disturb about 702.4 acres of land for the replacement pipeline.
Following construction, ANR would maintain about 170.3 acres for
permanent operation of the project's facilities; the remaining acreage
would be restored. Approximately 91 percent (31.1 miles) of the new
pipeline would be co-located with existing rights-of-way or paralleling
existing utility corridors. Areas where ANR was unable to co-locate the
pipeline with existing rights-of-way or parallel existing corridors was
primarily due to reroutes around Wetland Reserve Program easements,
sensitive environmental areas, and constructability issues (e.g.,
crossings of waterbodies).
NEPA Process and the Environmental Document
Any environmental document issued by the Commission will discuss
impacts that could occur as a result of the abandonment, construction,
and operation of the proposed project under the relevant general
resource areas:
geology and soils;
water resources and wetlands;
vegetation and wildlife;
threatened and endangered species;
cultural resources;
land use;
environmental justice;
air quality and noise; and
reliability and safety.
Commission staff will also evaluate reasonable alternatives to the
proposed project or portions of the project and make recommendations on
how to lessen or avoid impacts on the various resource areas. Your
comments will help Commission staff identify and focus on the issues
that might have an effect on the human environment and potentially
eliminate others from further study and discussion in the environmental
document.
Following this scoping period, Commission staff will determine
whether to prepare an Environmental Assessment (EA) or an Environmental
Impact Statement (EIS). The EA or the EIS will present Commission
staff's
[[Page 59903]]
independent analysis of the issues. If Commission staff prepares an EA,
a Notice of Schedule for the Preparation of an Environmental Assessment
will be issued. The EA may be issued for an allotted public comment
period. The Commission would consider timely comments on the EA before
making its decision regarding the proposed project. If Commission staff
prepares an EIS, a Notice of Intent to Prepare an EIS/Notice of
Schedule will be issued, which will open up an additional comment
period. Staff will then prepare a draft EIS which will be issued for
public comment. Commission staff will consider all timely comments
received during the comment period on the draft EIS and revise the
document, as necessary, before issuing a final EIS. Any EA or draft and
final EIS will be available in electronic format in the public record
through eLibrary \2\ and the Commission's natural gas environmental
documents web page (https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents). If eSubscribed, you will receive
instant email notification when the environmental document is issued.
---------------------------------------------------------------------------
\2\ For instructions on connecting to eLibrary, refer to the
last page of this notice.
---------------------------------------------------------------------------
With this notice, the Commission is asking agencies with
jurisdiction by law and/or special expertise with respect to the
environmental issues of this project to formally cooperate in the
preparation of the environmental document.\3\ Agencies that would like
to request cooperating agency status should follow the instructions for
filing comments provided under the Public Participation section of this
notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at title 40, Code of Federal
Regulations, section 1501.8.
---------------------------------------------------------------------------
Consultation Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, the Commission is using this notice to initiate
consultation with the applicable State Historic Preservation Office(s),
and to solicit their views and those of other government agencies,
interested Indian tribes, and the public on the project's potential
effects on historic properties.\4\ The environmental document for this
project will document findings on the impacts on historic properties
and summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at title 36, Code of Federal Regulations, part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes Federal, State, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project and includes a mailing address with their
comments. Commission staff will update the environmental mailing list
as the analysis proceeds to ensure that Commission notices related to
this environmental review are sent to all individuals, organizations,
and government entities interested in and/or potentially affected by
the proposed project.
If you need to make changes to your name/address, or if you would
like to remove your name from the mailing list, please complete one of
the following steps:
(1) Send an email to [email protected] stating your
request. You must include the docket number CP23-523-000 in your
request. If you are requesting a change to your address, please be sure
to include your name and the correct address. If you are requesting to
delete your address from the mailing list, please include your name and
address as it appeared on this notice. This email address is unable to
accept comments. OR
(2) Return the attached ``Mailing List Update Form'' (appendix 2).
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website at www.ferc.gov using the eLibrary link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number
in the ``Docket Number'' field. Be sure you have selected an
appropriate date range. For assistance, please contact FERC Online
Support at [email protected] or (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of all formal documents issued by the Commission, such as orders,
notices, and rulemakings.
Public sessions or site visits will be posted on the Commission's
calendar located at https://www.ferc.gov/news-events/events along with
other related information.
Dated: August 23, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-18638 Filed 8-29-23; 8:45 am]
BILLING CODE 6717-01-P