Southern Star Central Gas Pipeline, Inc.; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline, 50137-50138 [2023-16301]

Download as PDF lotter on DSK11XQN23PROD with NOTICES1 Federal Register / Vol. 88, No. 146 / Tuesday, August 1, 2023 / Notices acres of land to the Riley-Jay-Livermore Project boundary, and approximately 5.3 acres of land to the Otis Project boundary due the change in interconnection point. The licensee is not proposing any changes to project operations, recreation facilities, or public access. l. Locations of the Application: This filing may be viewed on the Commission’s website at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. Agencies may obtain copies of the application directly from the applicant. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214, respectively. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person commenting, protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. Any filing made by an intervenor must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. VerDate Sep<11>2014 18:34 Jul 31, 2023 Jkt 259001 p. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202)502–6595 or OPP@ ferc.gov. Dated: July 25, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–16238 Filed 7–31–23; 8:45 am] DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP23–515–000] Southern Star Central Gas Pipeline, Inc.; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline Take notice that on July 17, 2023 Southern Star Central Gas Pipeline, Inc. (Southern Star), 4700 State Route 56, Owensboro, Kentucky 42301., filed in the above referenced docket, a prior notice request pursuant to sections 157.205 and 157.216(b)of the Commission’s regulations under the Natural Gas Act (NGA), and Southern Star’s blanket certificate issued in Docket No. CP82–479–000, for authorization to abandon two wells in Southern Star’s South Welda Storage Field in Anderson County, Kansas and one well in Southern Star’s Piqua Storage Field in Woodson County, Kansas. (South Welda and Piqua Well Abandonment Project). The Project will allow Southern Star to comply with its Storage Integrity Management Plan implementing the storage integrity regulations of the Pipeline and Hazardous Materials Administration. The estimated cost for the project is $153,902, all as more fully set forth in the request which is on file with the Commission and open to public inspection. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page Frm 00039 Fmt 4703 (www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room. For assistance, contact the Federal Energy Regulatory Commission at FercOnlineSupport@ ferc.gov or call toll-free, (886) 208–3676 or TTY (202) 502–8659. Any questions concerning this request should be directed to Cindy Thompson, Director, Regulatory, Compliance, and Information Governance, Southern Star Central Gas Pipeline, Inc., 4700 State Route 56, Owensboro, Kentucky 42301, by phone at 270–852–4655, or by email to cindy.thompson@southernstar.com. Public Participation BILLING CODE 6717–01–P PO 00000 50137 Sfmt 4703 There are three ways to become involved in the Commission’s review of this project: you can file a protest to the project, you can file a motion to intervene in the proceeding, and you can file comments on the project. There is no fee or cost for filing protests, motions to intervene, or comments. The deadline for filing protests, motions to intervene, and comments is 5:00 p.m. Eastern Time on September 25, 2023. How to file protests, motions to intervene, and comments is explained below. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Protests Pursuant to section 157.205 of the Commission’s regulations under the NGA,1 any person 2 or the Commission’s staff may file a protest to the request. If no protest is filed within the time allowed or if a protest is filed and then withdrawn within 30 days after the allowed time for filing a protest, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days 1 18 CFR 157.205. include individuals, organizations, businesses, municipalities, and other entities. 18 CFR 385.102(d). 2 Persons E:\FR\FM\01AUN1.SGM 01AUN1 lotter on DSK11XQN23PROD with NOTICES1 50138 Federal Register / Vol. 88, No. 146 / Tuesday, August 1, 2023 / Notices after the time allowed for filing a protest, the instant request for authorization will be considered by the Commission. Protests must comply with the requirements specified in section 157.205(e) of the Commission’s regulations,3 and must be submitted by the protest deadline, which is September 25, 2023. A protest may also serve as a motion to intervene so long as the protestor states it also seeks to be an intervenor. Comments Interventions How To File Protests, Interventions, and Comments Any person has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission’s orders in the U.S. Circuit Courts of Appeal. To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure 4 and the regulations under the NGA 5 by the intervention deadline for the project, which is September 25, 2023. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https:// www.ferc.gov/resources/guides/how-to/ intervene.asp. All timely, unopposed motions to intervene are automatically granted by operation of Rule 214(c)(1). Motions to intervene that are filed after the intervention deadline are untimely and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission’s Rules and Regulations. A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties. 3 18 CFR 157.205(e). CFR 385.214. 5 18 CFR 157.10. 4 18 VerDate Sep<11>2014 18:34 Jul 31, 2023 Jkt 259001 Any person wishing to comment on the project may do so. The Commission considers all comments received about the project in determining the appropriate action to be taken. To ensure that your comments are timely and properly recorded, please submit your comments on or before September 25, 2023. The filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding. There are two ways to submit protests, motions to intervene, and comments. In both instances, please reference the Project docket number CP23–515–000 in your submission. (1) You may file your protest, motion to intervene, and comments by using the Commission’s eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select ‘‘General’’ and then select ‘‘Protest’’, ‘‘Intervention’’, or ‘‘Comment on a Filing’’; or 6 (2) You can file a paper copy of your submission by mailing it to the address below. Your submission must reference the Project docket number CP23–515– 000. To file via USPS: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426 To file via any other method: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852 The Commission encourages electronic filing of submissions (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. Protests and motions to intervene must be served on the applicant either by mail or email (with a link to the document) at: Cindy Thompson, Director, Regulatory, Compliance, and Information Governance, Southern Star Central Gas Pipeline, Inc., 4700 State Route 56, Owensboro, Kentucky 42301, or by email to cindy.thompson@ 6 Additionally, you may file your comments electronically by using the eComment feature, which is located on the Commission’s website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project. PO 00000 Frm 00040 Fmt 4703 Sfmt 4703 southernstar.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. Tracking the Proceeding Throughout the proceeding, additional information about the project will be available from the Commission’s Office of External Affairs, at (866) 208– FERC, or on the FERC website at www.ferc.gov using the ‘‘eLibrary’’ link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/docs-filing/ esubscription.asp. Dated: July 26, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–16301 Filed 7–31–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings Take notice that the Commission has received the following Natural Gas and Oil Pipeline Rate and Refund Report filings: Filings Instituting Proceedings Docket Numbers: RP23–910–000. Applicants: Sea Robin Pipeline Company, LLC. Description: § 4(d) Rate Filing: Update to GT&C Section 6 to be effective 6/1/ 2023. Filed Date: 7/25/23. Accession Number: 20230725–5094. Comment Date: 5 p.m. ET 8/7/23. Any person desiring to intervene, to protest, or to answer a complaint in any of the above proceedings must file in accordance with Rules 211, 214, or 206 of the Commission’s Regulations (18 CFR 385.211, 385.214, or 385.206) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be E:\FR\FM\01AUN1.SGM 01AUN1

Agencies

[Federal Register Volume 88, Number 146 (Tuesday, August 1, 2023)]
[Notices]
[Pages 50137-50138]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-16301]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP23-515-000]


Southern Star Central Gas Pipeline, Inc.; Notice of Request Under 
Blanket Authorization and Establishing Intervention and Protest 
Deadline

    Take notice that on July 17, 2023 Southern Star Central Gas 
Pipeline, Inc. (Southern Star), 4700 State Route 56, Owensboro, 
Kentucky 42301., filed in the above referenced docket, a prior notice 
request pursuant to sections 157.205 and 157.216(b)of the Commission's 
regulations under the Natural Gas Act (NGA), and Southern Star's 
blanket certificate issued in Docket No. CP82-479-000, for 
authorization to abandon two wells in Southern Star's South Welda 
Storage Field in Anderson County, Kansas and one well in Southern 
Star's Piqua Storage Field in Woodson County, Kansas. (South Welda and 
Piqua Well Abandonment Project). The Project will allow Southern Star 
to comply with its Storage Integrity Management Plan implementing the 
storage integrity regulations of the Pipeline and Hazardous Materials 
Administration. The estimated cost for the project is $153,902, all as 
more fully set forth in the request which is on file with the 
Commission and open to public inspection.
    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (www.ferc.gov) using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. At this time, 
the Commission has suspended access to the Commission's Public 
Reference Room. For assistance, contact the Federal Energy Regulatory 
Commission at [email protected] or call toll-free, (886) 208-
3676 or TTY (202) 502-8659.
    Any questions concerning this request should be directed to Cindy 
Thompson, Director, Regulatory, Compliance, and Information Governance, 
Southern Star Central Gas Pipeline, Inc., 4700 State Route 56, 
Owensboro, Kentucky 42301, by phone at 270-852-4655, or by email to 
[email protected].

Public Participation

    There are three ways to become involved in the Commission's review 
of this project: you can file a protest to the project, you can file a 
motion to intervene in the proceeding, and you can file comments on the 
project. There is no fee or cost for filing protests, motions to 
intervene, or comments. The deadline for filing protests, motions to 
intervene, and comments is 5:00 p.m. Eastern Time on September 25, 
2023. How to file protests, motions to intervene, and comments is 
explained below.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or [email protected].

Protests

    Pursuant to section 157.205 of the Commission's regulations under 
the NGA,\1\ any person \2\ or the Commission's staff may file a protest 
to the request. If no protest is filed within the time allowed or if a 
protest is filed and then withdrawn within 30 days after the allowed 
time for filing a protest, the proposed activity shall be deemed to be 
authorized effective the day after the time allowed for protest. If a 
protest is filed and not withdrawn within 30 days

[[Page 50138]]

after the time allowed for filing a protest, the instant request for 
authorization will be considered by the Commission.
---------------------------------------------------------------------------

    \1\ 18 CFR 157.205.
    \2\ Persons include individuals, organizations, businesses, 
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------

    Protests must comply with the requirements specified in section 
157.205(e) of the Commission's regulations,\3\ and must be submitted by 
the protest deadline, which is September 25, 2023. A protest may also 
serve as a motion to intervene so long as the protestor states it also 
seeks to be an intervenor.
---------------------------------------------------------------------------

    \3\ 18 CFR 157.205(e).
---------------------------------------------------------------------------

Interventions

    Any person has the option to file a motion to intervene in this 
proceeding. Only intervenors have the right to request rehearing of 
Commission orders issued in this proceeding and to subsequently 
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
    To intervene, you must submit a motion to intervene to the 
Commission in accordance with Rule 214 of the Commission's Rules of 
Practice and Procedure \4\ and the regulations under the NGA \5\ by the 
intervention deadline for the project, which is September 25, 2023. As 
described further in Rule 214, your motion to intervene must state, to 
the extent known, your position regarding the proceeding, as well as 
your interest in the proceeding. For an individual, this could include 
your status as a landowner, ratepayer, resident of an impacted 
community, or recreationist. You do not need to have property directly 
impacted by the project in order to intervene. For more information 
about motions to intervene, refer to the FERC website at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------

    \4\ 18 CFR 385.214.
    \5\ 18 CFR 157.10.
---------------------------------------------------------------------------

    All timely, unopposed motions to intervene are automatically 
granted by operation of Rule 214(c)(1). Motions to intervene that are 
filed after the intervention deadline are untimely and may be denied. 
Any late-filed motion to intervene must show good cause for being late 
and must explain why the time limitation should be waived and provide 
justification by reference to factors set forth in Rule 214(d) of the 
Commission's Rules and Regulations. A person obtaining party status 
will be placed on the service list maintained by the Secretary of the 
Commission and will receive copies (paper or electronic) of all 
documents filed by the applicant and by all other parties.

Comments

    Any person wishing to comment on the project may do so. The 
Commission considers all comments received about the project in 
determining the appropriate action to be taken. To ensure that your 
comments are timely and properly recorded, please submit your comments 
on or before September 25, 2023. The filing of a comment alone will not 
serve to make the filer a party to the proceeding. To become a party, 
you must intervene in the proceeding.

How To File Protests, Interventions, and Comments

    There are two ways to submit protests, motions to intervene, and 
comments. In both instances, please reference the Project docket number 
CP23-515-000 in your submission.
    (1) You may file your protest, motion to intervene, and comments by 
using the Commission's eFiling feature, which is located on the 
Commission's website (www.ferc.gov) under the link to Documents and 
Filings. New eFiling users must first create an account by clicking on 
``eRegister.'' You will be asked to select the type of filing you are 
making; first select ``General'' and then select ``Protest'', 
``Intervention'', or ``Comment on a Filing''; or \6\
---------------------------------------------------------------------------

    \6\ Additionally, you may file your comments electronically by 
using the eComment feature, which is located on the Commission's 
website at www.ferc.gov under the link to Documents and Filings. 
Using eComment is an easy method for interested persons to submit 
brief, text-only comments on a project.
---------------------------------------------------------------------------

    (2) You can file a paper copy of your submission by mailing it to 
the address below. Your submission must reference the Project docket 
number CP23-515-000.

To file via USPS: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426
To file via any other method: Kimberly D. Bose, Secretary, Federal 
Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 
20852

    The Commission encourages electronic filing of submissions (option 
1 above) and has eFiling staff available to assist you at (202) 502-
8258 or [email protected].
    Protests and motions to intervene must be served on the applicant 
either by mail or email (with a link to the document) at: Cindy 
Thompson, Director, Regulatory, Compliance, and Information Governance, 
Southern Star Central Gas Pipeline, Inc., 4700 State Route 56, 
Owensboro, Kentucky 42301, or by email to 
[email protected]. Any subsequent submissions by an 
intervenor must be served on the applicant and all other parties to the 
proceeding. Contact information for parties can be downloaded from the 
service list at the eService link on FERC Online.

Tracking the Proceeding

    Throughout the proceeding, additional information about the project 
will be available from the Commission's Office of External Affairs, at 
(866) 208-FERC, or on the FERC website at www.ferc.gov using the 
``eLibrary'' link as described above. The eLibrary link also provides 
access to the texts of all formal documents issued by the Commission, 
such as orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. For more information and to register, go to 
www.ferc.gov/docs-filing/esubscription.asp.

    Dated: July 26, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-16301 Filed 7-31-23; 8:45 am]
BILLING CODE 6717-01-P