Applications for Amendments to Facility Operating Licenses Involving Proposed No Significant Hazards Consideration(s) and Containing Sensitive Unclassified Non-Safeguards Information and Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information, 50183-50188 [2023-15031]

Download as PDF Federal Register / Vol. 88, No. 146 / Tuesday, August 1, 2023 / Notices instructions may be obtained without charge by contacting the NRC’s Clearance Officer, David C. Cullison, Office of the Chief Information Officer, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001; telephone: 301–415–2084; email: Infocollects.Resource@nrc.gov. lotter on DSK11XQN23PROD with NOTICES1 B. Submitting Comments The NRC encourages electronic comment submission through the Federal rulemaking website (https:// www.regulations.gov). Please include Docket ID NRC–2023–0065, in your comment submission. The NRC cautions you not to include identifying or contact information in comment submissions that you do not want to be publicly disclosed in your comment submission. All comment submissions are posted at https:// www.regulations.gov and entered into ADAMS. Comment submissions are not routinely edited to remove identifying or contact information. If you are requesting or aggregating comments from other persons for submission to the NRC, then you should inform those persons not to include identifying or contact information that they do not want to be publicly disclosed in their comment submission. Your request should state that comment submissions are not routinely edited to remove such information before making the comment submissions available to the public or entering the comment into ADAMS. II. Background In accordance with the Paperwork Reduction Act of 1995 (44 U.S.C. chapter 35), the NRC is requesting public comment on its intention to request the OMB’s approval for the information collection summarized below. 1. The title of the information collection: 10 CFR part 35, Medical Use of Byproduct Material. 2. OMB approval number: 3150–0010. 3. Type of submission: Revision. 4. The form number, if applicable: Not applicable. 5. How often the collection is required or requested: Reports of medical events, doses to an embryo/fetus or nursing child, or leaking source are reportable on occurrence. A specialty board certifying entity desiring to be recognized by the NRC must submit a one-time request for recognition and infrequently revise the information. 6. Who will be required or asked to respond: Physicians and medical institutions holding an NRC license authorizing the administration of byproduct material or radiation from VerDate Sep<11>2014 18:34 Jul 31, 2023 Jkt 259001 this material to humans for medical use. A specialty board certification entity desiring to have its certifying process and board certificate recognized by NRC. 7. The estimated number of annual responses: 313,982 (234,272 reporting responses + 7,327 recordkeepers + 72,383 third party disclosure responses). 8. The estimated number of annual respondents: 7,328 (862 NRC licensees + 6,465 Agreement State licensees + 1 specialty board certification entity). 9. The estimated number of hours needed annually to comply with the information collection requirement or request: 1,117,269 hours (61,506 reporting + 1,043,235 recordkeeping + 12,528 third party disclosure). 10. Abstract: Part 35 of title 10 of the Code of Federal Regulations, ‘‘Medical Use of Byproduct Material,’’ contains NRC’s requirements and provisions for the medical use of byproduct material and for issuance of specific licenses authorizing the medical use of this material. These requirements and provisions provide for the radiation safety of workers, the general public, patients, and human research subjects. Part 35 contains mandatory requirements that apply to NRC licensees authorized to administer byproduct material or radiation to humans for medical use. These requirements also provide voluntary provisions for specialty boards to apply to have their certification processes recognized by the NRC so that their board-certified individuals can use the certifications as proof of training and experience. III. Specific Requests for Comments The NRC is seeking comments that address the following questions: 1. Is the proposed collection of information necessary for the NRC to properly perform its functions? Does the information have practical utility? Please explain your answer. 2. Is the estimate of the burden of the information collection accurate? Please explain your answer. 3. Is there a way to enhance the quality, utility, and clarity of the information to be collected? 4. How can the burden of the information collection on respondents be minimized, including the use of automated collection techniques or other forms of information technology? PO 00000 Dated: July 27, 2023. Frm 00085 Fmt 4703 Sfmt 4703 50183 For the Nuclear Regulatory Commission. David C. Cullison, NRC Clearance Officer, Office of the Chief Information Officer. [FR Doc. 2023–16256 Filed 7–31–23; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION [NRC–2023–0122] Applications for Amendments to Facility Operating Licenses Involving Proposed No Significant Hazards Consideration(s) and Containing Sensitive Unclassified Non-Safeguards Information and Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information Nuclear Regulatory Commission. ACTION: License amendment request; notice of opportunity to comment, request a hearing, and petition for leave to intervene; order imposing procedures. AGENCY: The U.S. Nuclear Regulatory Commission (NRC) received and is considering approval of two amendment requests. The amendment requests are for Millstone Power Station, Unit 3. For each amendment request, the NRC proposes to determine that it involves no significant hazards consideration (NSHC). Because each amendment request contains sensitive unclassified non-safeguards information (SUNSI), an order imposes procedures to obtain access to SUNSI for contention preparation by persons who file a hearing request or petition for leave to intervene. DATES: Comments must be filed by August 31, 2023. A request for a hearing or petitions for leave to intervene must be filed by October 2, 2023. Any potential party as defined in section 2.4 of title 10 of the Code of Federal Regulations (10 CFR) who believes access to SUNSI is necessary to respond to this notice must request document access by August 11, 2023. ADDRESSES: You may submit comments by any of the following methods; however, the NRC encourages electronic comment submission through the Federal rulemaking website: • Federal rulemaking website: Go to https://www.regulations.gov and search for Docket ID NRC–2023–0122. Address questions about Docket IDs in Regulations.gov to Stacy Schumann; telephone: 301–415–0624; email: Stacy.Schumann@nrc.gov. For technical SUMMARY: E:\FR\FM\01AUN1.SGM 01AUN1 50184 Federal Register / Vol. 88, No. 146 / Tuesday, August 1, 2023 / Notices questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document. • Mail comments to: Office of Administration, Mail Stop: TWFN–7– A60M, U.S. Nuclear Regulatory Commission, Washington, DC 20555– 0001, ATTN: Program Management, Announcements and Editing Staff. For additional direction on obtaining information and submitting comments, see ‘‘Obtaining Information and Submitting Comments’’ in the SUPPLEMENTARY INFORMATION section of this document. FOR FURTHER INFORMATION CONTACT: Kay Goldstein, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555– 0001, telephone: 301–415–1506; email: Kay.Goldstein@nrc.gov. SUPPLEMENTARY INFORMATION: lotter on DSK11XQN23PROD with NOTICES1 I. Obtaining Information and Submitting Comments A. Obtaining Information Please refer to Docket ID NRC–2023– 0122, facility name, unit number(s), docket number(s), application date, and subject when contacting the NRC about the availability of information for this action. You may obtain publicly available information related to this action by any of the following methods: • Federal Rulemaking website: Go to https://www.regulations.gov and search for Docket ID NRC–2023–0122. • NRC’s Agencywide Documents Access and Management System (ADAMS): You may obtain publicly available documents online in the ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/ adams.html. To begin the search, select ‘‘Begin Web-based ADAMS Search.’’ For problems with ADAMS, please contact the NRC’s Public Document Room (PDR) reference staff at 1–800–397–4209, at 301–415–4737, or by email to PDR.Resource@nrc.gov. The Millstone Power Station, Unit 3, documents are available in ADAMS under Accession Nos. ML23123A279 and ML23145A195. • NRC’s PDR: The PDR, where you may examine and order copies of publicly available documents, is open by appointment. To make an appointment to visit the PDR, please send an email to PDR.Resource@nrc.gov or call 1–800–397–4209 or 301–415– 4737, between 8 a.m. and 4 p.m. eastern time (ET), Monday through Friday, except Federal holidays. B. Submitting Comments The NRC encourages electronic comment submission through the Federal rulemaking website (https:// VerDate Sep<11>2014 18:34 Jul 31, 2023 Jkt 259001 www.regulations.gov). Please include Docket ID NRC–2023–0122, facility name, unit number(s), docket number(s), application date, and subject, in your comment submission. The NRC cautions you not to include identifying or contact information that you do not want to be publicly disclosed in your comment submission. The NRC will post all comment submissions at https:// www.regulations.gov as well as enter the comment submissions into ADAMS. The NRC does not routinely edit comment submissions to remove identifying or contact information. If you are requesting or aggregating comments from other persons for submission to the NRC, then you should inform those persons not to include identifying or contact information that they do not want to be publicly disclosed in their comment submission. Your request should state that the NRC does not routinely edit comment submissions to remove such information before making the comment submissions available to the public or entering the comment into ADAMS. II. Background Pursuant to section 189a.(1)–(2) of the Atomic Energy Act of 1954, as amended (the Act), the NRC is publishing this notice. The Act requires the Commission to publish notice of any amendments issued or proposed to be issued and grants the Commission the authority to issue and make immediately effective any amendment to an operating license or combined license, as applicable, upon a determination by the Commission that such amendment involves NSHC, notwithstanding the pendency before the Commission of a request for a hearing from any person. This notice includes two notices of amendments containing SUNSI. III. Notice of Consideration of Issuance of Amendments to Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing The Commission has made a proposed determination that the following amendment requests involve NSHC. Under the Commission’s regulations in 10 CFR 50.92, this means that operation of the facility in accordance with the proposed amendments would not (1) involve a significant increase in the probability or consequences of an accident previously evaluated, or (2) create the possibility of a new or different kind of accident from any accident previously evaluated, or (3) involve a significant reduction in a PO 00000 Frm 00086 Fmt 4703 Sfmt 4703 margin of safety. The basis for this proposed determination for each amendment request is shown as follows. The Commission is seeking public comments on these proposed determinations. Any comments received within 30 days after the date of publication of this notice will be considered in making any final determination. Normally, the Commission will not issue the amendments until the expiration of 60 days after the date of publication of this notice. The Commission may issue any of these license amendments before expiration of the 60-day period provided that its final determination is that the amendments involve no significant hazards consideration. In addition, the Commission may issue any of these amendments prior to the expiration of the 30-day comment period if circumstances change during the 30-day comment period such that failure to act in a timely way would result, for example, in derating or shutdown of the facility. If the Commission takes action on any of these amendments prior to the expiration of either the comment period or the notice period, it will publish a notice of issuance in the Federal Register. If the Commission makes a final no significant hazards consideration determination for any of these amendments, any hearing on those amendments will take place after issuance. The Commission expects that the need to take this action will occur very infrequently. A. Opportunity To Request a Hearing and Petition for Leave To Intervene Within 60 days after the date of publication of this notice, any person (petitioner) whose interest may be affected by any of these actions may file a request for a hearing and petition for leave to intervene (petition) with respect to that action. Petitions shall be filed in accordance with the Commission’s ‘‘Agency Rules of Practice and Procedure’’ in 10 CFR part 2. Interested persons should consult a current copy of 10 CFR 2.309. If a petition is filed, the Commission or a presiding officer will rule on the petition and, if appropriate, a notice of a hearing will be issued. Petitions must be filed no later than 60 days from the date of publication of this notice in accordance with the filing instructions in the ‘‘Electronic Submissions (E-Filing)’’ section of this document. Petitions and motions for leave to file new or amended contentions that are filed after the deadline will not be entertained absent a determination by the presiding officer that the filing demonstrates good cause E:\FR\FM\01AUN1.SGM 01AUN1 Federal Register / Vol. 88, No. 146 / Tuesday, August 1, 2023 / Notices lotter on DSK11XQN23PROD with NOTICES1 by satisfying the three factors in 10 CFR 2.309(c)(1)(i) through (iii). If a hearing is requested, and the Commission has not made a final determination on the issue of no significant hazards consideration, the Commission will make a final determination on the issue of no significant hazards consideration, which will serve to establish when the hearing is held. If the final determination is that the amendment request involves no significant hazards consideration, the Commission may issue the amendment and make it immediately effective, notwithstanding the request for a hearing. Any hearing would take place after issuance of the amendment. If the final determination is that the amendment request involves a significant hazards consideration, then any hearing held would take place before the issuance of the amendment unless the Commission finds an imminent danger to the health or safety of the public, in which case it will issue an appropriate order or rule under 10 CFR part 2. A State, local governmental body, federally recognized Indian Tribe, or designated agency thereof, may submit a petition to the Commission to participate as a party under 10 CFR 2.309(h) no later than 60 days from the date of publication of this notice. Alternatively, a State, local governmental body, federally recognized Indian Tribe, or agency thereof may participate as a non-party under 10 CFR 2.315(c). For information about filing a petition and about participation by a person not a party under 10 CFR 2.315, see ADAMS Accession No. ML20340A053 (https:// adamswebsearch2.nrc.gov/webSearch2/ main.jsp?AccessionNumber= ML20340A053) and on the NRC’s public website at https://www.nrc.gov/aboutnrc/regulatory/adjudicatory/ hearing.html#participate. B. Electronic Submissions (E-Filing) All documents filed in NRC adjudicatory proceedings, including documents filed by an interested State, local governmental body, federally recognized Indian Tribe, or designated agency thereof that requests to participate under 10 CFR 2.315(c), must be filed in accordance with 10 CFR 2.302. The E-Filing process requires participants to submit and serve all adjudicatory documents over the internet, or in some cases, to mail copies on electronic storage media, unless an exemption permitting an alternative filing method, as further discussed, is granted. Detailed guidance on electronic submissions is located in the ‘‘Guidance VerDate Sep<11>2014 18:34 Jul 31, 2023 Jkt 259001 for Electronic Submissions to the NRC’’ (ADAMS Accession No. ML13031A056) and on the NRC’s public website at https://www.nrc.gov/site-help/esubmittals.html. To comply with the procedural requirements of E-Filing, at least 10 days prior to the filing deadline, the participant should contact the Office of the Secretary by email at Hearing.Docket@nrc.gov, or by telephone at 301–415–1677, to (1) request a digital identification (ID) certificate, which allows the participant (or its counsel or representative) to digitally sign submissions and access the E-Filing system for any proceeding in which it is participating; and (2) advise the Secretary that the participant will be submitting a petition or other adjudicatory document (even in instances in which the participant, or its counsel or representative, already holds an NRC-issued digital ID certificate). Based upon this information, the Secretary will establish an electronic docket for the proceeding if the Secretary has not already established an electronic docket. Information about applying for a digital ID certificate is available on the NRC’s public website at https:// www.nrc.gov/site-help/e-submittals/ getting-started.html. After a digital ID certificate is obtained and a docket created, the participant must submit adjudicatory documents in Portable Document Format. Guidance on submissions is available on the NRC’s public website at https://www.nrc.gov/ site-help/electronic-sub-ref-mat.html. A filing is considered complete at the time the document is submitted through the NRC’s E-Filing system. To be timely, an electronic filing must be submitted to the E-Filing system no later than 11:59 p.m. ET on the due date. Upon receipt of a transmission, the E-Filing system time-stamps the document and sends the submitter an email confirming receipt of the document. The E-Filing system also distributes an email that provides access to the document to the NRC’s Office of the General Counsel and any others who have advised the Office of the Secretary that they wish to participate in the proceeding, so that the filer need not serve the document on those participants separately. Therefore, applicants and other participants (or their counsel or representative) must apply for and receive a digital ID certificate before adjudicatory documents are filed to obtain access to the documents via the E-Filing system. A person filing electronically using the NRC’s adjudicatory E-Filing system may seek assistance by contacting the NRC’s Electronic Filing Help Desk PO 00000 Frm 00087 Fmt 4703 Sfmt 4703 50185 through the ‘‘Contact Us’’ link located on the NRC’s public website at https:// www.nrc.gov/site-help/esubmittals.html, by email to MSHD.Resource@nrc.gov, or by a tollfree call at 1–866–672–7640. The NRC Electronic Filing Help Desk is available between 9 a.m. and 6 p.m., ET, Monday through Friday, except Federal holidays. Participants who believe that they have good cause for not submitting documents electronically must file an exemption request, in accordance with 10 CFR 2.302(g), with their initial paper filing stating why there is good cause for not filing electronically and requesting authorization to continue to submit documents in paper format. Such filings must be submitted in accordance with 10 CFR 2.302(b)–(d). Participants filing adjudicatory documents in this manner are responsible for serving their documents on all other participants. Participants granted an exemption under 10 CFR 2.302(g)(2) must still meet the electronic formatting requirement in 10 CFR 2.302(g)(1), unless the participant also seeks and is granted an exemption from 10 CFR 2.302(g)(1). Documents submitted in adjudicatory proceedings will appear in the NRC’s electronic hearing docket, which is publicly available at https:// adams.nrc.gov/ehd, unless excluded pursuant to an order of the presiding officer. If you do not have an NRCissued digital ID certificate as previously described, click ‘‘cancel’’ when the link requests certificates and you will be automatically directed to the NRC’s electronic hearing dockets where you will be able to access any publicly available documents in a particular hearing docket. Participants are requested not to include personal privacy information such as social security numbers, home addresses, or personal phone numbers in their filings unless an NRC regulation or other law requires submission of such information. With respect to copyrighted works, except for limited excerpts that serve the purpose of the adjudicatory filings and would constitute a Fair Use application, participants should not include copyrighted materials in their submission. The following table provides the plant names, docket numbers, date of application, ADAMS accession number, and location in the application of the licensee proposed NSHC determination. For further details with respect to these license amendment applications, see the applications for amendment, publicly available portions of which are available for public inspection in ADAMS. For additional direction on accessing E:\FR\FM\01AUN1.SGM 01AUN1 50186 Federal Register / Vol. 88, No. 146 / Tuesday, August 1, 2023 / Notices information related to this document, see the ‘‘Obtaining Information and Submitting Comments’’ section of this document. Dominion Energy Nuclear Connecticut, Inc.; Millstone Power Station, Unit 3; New London County, CT Docket No(s) ....................................................... Application Date .................................................. ADAMS Accession No ........................................ Location in Application of NSHC ........................ Brief Description of Amendment ......................... Proposed Determination ..................................... Name of Attorney for Licensee, Mailing Address NRC Project Manager, Telephone Number ....... 50–423. May 2, 2023. ML23123A279. Pages 9–11 of Attachment 1. The proposed amendment would revise Technical Specification (TS) 6.9.1.6.b to support the transition to Framatome (FRM) GAIA fuel with M5TM cladding at Millstone Power Station, Unit 3 (Millstone, Unit 3), which requires the application of the FRM Small Break Loss of Coolant Accident and Realistic Large Break Loss of Coolant Accident methodologies and the associated use of the GALILEO fuel performance code within the loss-of-coolant accident (LOCA) methods. Specifically, TS 6.9.1.6.b would add FRM Topical Reports EMF– 2328–P–A, ‘‘PWR Small Break LOCA Evaluation Model, S–RELAP5 Based,’’ EMF–2103–P– A, ‘‘Realistic Large Break LOCA Methodology for Pressurized Water Reactors,’’ and ANP– 10349–P–A, ‘‘GALILEO Implementation in LOCA Methods’’ to the list of methodologies for establishing core operating limits. The proposed revision to TS 6.9.1.6.b would also delete one methodology no longer used to define core operating limits at Millstone, Unit 3. Dominion Energy Nuclear Connecticut, Inc. is also requesting an exemption to facilitate the use of FRM GAIA fuel assemblies containing fuel rods fabricated with M5TM cladding material at Millstone, Unit 3. NSHC. W.S. Blair, Senior Counsel, Dominion Energy Services, Inc., 120 Tredegar St., RS–2, Richmond, VA 23219. Richard Guzman, 301–415–1030. Dominion Energy Nuclear Connecticut, Inc.; Millstone Power Station, Unit 3; New London County, CT Docket No(s) ....................................................... Application Date .................................................. ADAMS Accession No ........................................ Location in Application of NSHC ........................ Brief Description of Amendment(s) .................... Proposed Determination ..................................... Name of Attorney for Licensee, Mailing Address lotter on DSK11XQN23PROD with NOTICES1 NRC Project Manager, Telephone Number ....... Order Imposing Procedures for Access to Sensitive Unclassified NonSafeguards Information for Contention Preparation A. This Order contains instructions regarding how potential parties to this proceeding may request access to documents containing Sensitive Unclassified Non-Safeguards Information (SUNSI). B. Within 10 days after publication of this notice of hearing or opportunity for hearing, any potential party who believes access to SUNSI is necessary to respond to this notice may request access to SUNSI. A ‘‘potential party’’ is any person who intends to participate as a party by demonstrating standing and filing an admissible contention under 10 CFR 2.309. Requests for access to SUNSI submitted later than 10 days after publication of this notice will not be considered absent a showing of good cause for the late filing, addressing why the request could not have been filed earlier. VerDate Sep<11>2014 18:34 Jul 31, 2023 Jkt 259001 50–423. May 23, 2023. ML23145A195. Pages 10–14 of Attachment 1. The proposed amendment would revise the Millstone Power Station, Unit 3 (Millstone, Unit 3), technical specifications (TSs) to support the use of Framatome GAIA fuel with M5TM fuel cladding material, which is currently scheduled for insertion into the Millstone, Unit 3, reactor during the spring 2025 refueling outage. The proposed TS changes include updating the reactor core safety limits (TS 2.1.1.2), fuel assemblies design features (TS 5.3.1), and list of approved methodologies for the Core Operating Limits Report (TS 6.9.1.6.b). NSHC. W.S. Blair, Senior Counsel, Dominion Energy Services, Inc., 120 Tredegar St., RS–2, Richmond, VA 23219. Richard Guzman, 301–415–1030. C. The requestor shall submit a letter requesting permission to access SUNSI to the Office of the Secretary, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001, Attention: Rulemakings and Adjudications Staff, and provide a copy to the Deputy General Counsel for Licensing, Hearings, and Enforcement, Office of the General Counsel, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001. The expedited delivery or courier mail address for both offices is: U.S. Nuclear Regulatory Commission, 11555 Rockville Pike, Rockville, Maryland 20852. The email addresses for the Office of the Secretary and the Office of the General Counsel are Hearing.Docket@nrc.gov and RidsOgcMailCenter.Resource@nrc.gov, respectively.1 The request must include the following information: 1 While a request for hearing or petition to intervene in this proceeding must comply with the filing requirements of the NRC’s ‘‘E-Filing Rule,’’ the initial request to access SUNSI under these PO 00000 Frm 00088 Fmt 4703 Sfmt 4703 (1) A description of the licensing action with a citation to this Federal Register notice; (2) The name and address of the potential party and a description of the potential party’s particularized interest that could be harmed by the action identified in C.(1); and (3) The identity of the individual or entity requesting access to SUNSI and the requestor’s basis for the need for the information in order to meaningfully participate in this adjudicatory proceeding. In particular, the request must explain why publicly available versions of the information requested would not be sufficient to provide the basis and specificity for a proffered contention. D. Based on an evaluation of the information submitted under paragraph C, the NRC staff will determine within procedures should be submitted as described in this paragraph. E:\FR\FM\01AUN1.SGM 01AUN1 Federal Register / Vol. 88, No. 146 / Tuesday, August 1, 2023 / Notices 10 days of receipt of the request whether: (1) There is a reasonable basis to believe the petitioner is likely to establish standing to participate in this NRC proceeding; and (2) The requestor has established a legitimate need for access to SUNSI. E. If the NRC staff determines that the requestor satisfies both D.(1) and D.(2), the NRC staff will notify the requestor in writing that access to SUNSI has been granted. The written notification will contain instructions on how the requestor may obtain copies of the requested documents, and any other conditions that may apply to access to those documents. These conditions may include, but are not limited to, the signing of a Non-Disclosure Agreement or Affidavit, or Protective Order 2 setting forth terms and conditions to prevent the unauthorized or inadvertent disclosure of SUNSI by each individual who will be granted access to SUNSI. F. Filing of Contentions. Any contentions in these proceedings that are based upon the information received as a result of the request made for SUNSI must be filed by the requestor no later than 25 days after receipt of (or access to) that information. However, if more than 25 days remain between the petitioner’s receipt of (or access to) the information and the deadline for filing all other contentions (as established in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI contentions by that later deadline. G. Review of Denials of Access. jurisdiction pursuant to 10 CFR 2.318(a); or (c) if another officer has been designated to rule on information access issues, with that officer. If challenges to the NRC staff determinations are filed, these procedures give way to the normal process for litigating disputes concerning access to information. The availability of interlocutory review by the Commission of orders ruling on such NRC staff determinations (whether granting or denying access) is governed by 10 CFR 2.311.3 I. The Commission expects that the NRC staff and presiding officers (and any other reviewing officers) will consider and resolve requests for access to SUNSI, and motions for protective orders, in a timely fashion in order to minimize any unnecessary delays in identifying those petitioners who have standing and who have propounded contentions meeting the specificity and basis requirements in 10 CFR part 2. The attachment to this Order summarizes the general target schedule for processing and resolving requests under these procedures. It is so ordered. Dated: July 11, 2023. For the Nuclear Regulatory Commission. Brooke P. Clark, Secretary of the Commission. Attachment 1—General Target Schedule for Processing and Resolving Requests for Access to Sensitive Unclassified Non-Safeguards Information in This Proceeding Day Event/activity 0 ................... Publication of Federal Register notice of hearing or opportunity for hearing, including order with instructions for access requests. Deadline for submitting requests for access to Sensitive Unclassified Non-Safeguards Information (SUNSI) with information: supporting the standing of a potential party identified by name and address; describing the need for the information in order for the potential party to participate meaningfully in an adjudicatory proceeding. Deadline for submitting petition for intervention containing: (i) demonstration of standing; and (ii) all contentions whose formulation does not require access to SUNSI (+25 Answers to petition for intervention; +7 petitioner/requestor reply). U.S. Nuclear Regulatory Commission (NRC) staff informs the requestor of the staff’s determination whether the request for access provides a reasonable basis to believe standing can be established and shows need for SUNSI. (NRC staff also informs any party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information.) If NRC staff makes the finding of need for SUNSI and likelihood of standing, NRC staff begins document processing (preparation of redactions or review of redacted documents). If NRC staff finds no ‘‘need’’ or no likelihood of standing, the deadline for petitioner/requestor to file a motion seeking a ruling to reverse the NRC staff’s denial of access; NRC staff files copy of access determination with the presiding officer (or Chief Administrative Judge or other designated officer, as appropriate). If NRC staff finds ‘‘need’’ for SUNSI, the deadline for any party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information to file a motion seeking a ruling to reverse the NRC staff’s grant of access. Deadline for NRC staff reply to motions to reverse NRC staff determination(s). (Receipt +30) If NRC staff finds standing and need for SUNSI, deadline for NRC staff to complete information processing and file motion for Protective Order and draft Non-Disclosure Agreement or Affidavit. Deadline for applicant/licensee to file NonDisclosure Agreement or Affidavit for SUNSI. 10 ................. 60 ................. 20 ................. 25 ................. 30 ................. 40 ................. lotter on DSK11XQN23PROD with NOTICES1 (1) If the request for access to SUNSI is denied by the NRC staff after a determination on standing and requisite need, the NRC staff shall immediately notify the requestor in writing, briefly stating the reason or reasons for the denial. (2) The requestor may challenge the NRC staff’s adverse determination by filing a challenge within 5 days of receipt of that determination with: (a) the presiding officer designated in this proceeding; (b) if no presiding officer has been appointed, the Chief Administrative Judge, or if this individual is unavailable, another administrative judge, or an Administrative Law Judge with jurisdiction pursuant to 10 CFR 2.318(a); or (c) if another officer has been designated to rule on information access issues, with that officer. (3) Further appeals of decisions under this paragraph must be made pursuant to 10 CFR 2.311. H. Review of Grants of Access. A party other than the requestor may challenge an NRC staff determination granting access to SUNSI whose release would harm that party’s interest independent of the proceeding. Such a challenge must be filed within 5 days of the notification by the NRC staff of its grant of access and must be filed with: (a) the presiding officer designated in this proceeding; (b) if no presiding officer has been appointed, the Chief Administrative Judge, or if this individual is unavailable, another administrative judge, or an Administrative Law Judge with 50187 2 Any motion for Protective Order or draft NonDisclosure Affidavit or Agreement for SUNSI must be filed with the presiding officer or the Chief Administrative Judge if the presiding officer has not yet been designated, within 30 days of the deadline for the receipt of the written access request. VerDate Sep<11>2014 18:34 Jul 31, 2023 Jkt 259001 3 Requestors should note that the filing requirements of the NRC’s E-Filing Rule (72 FR 49139; August 28, 2007, as amended at 77 FR 46562; August 3, 2012, 78 FR 34247, June 7, 2013) apply to appeals of NRC staff determinations (because they must be served on a presiding officer PO 00000 Frm 00089 Fmt 4703 Sfmt 4703 or the Commission, as applicable), but not to the initial SUNSI request submitted to the NRC staff under these procedures. E:\FR\FM\01AUN1.SGM 01AUN1 50188 Federal Register / Vol. 88, No. 146 / Tuesday, August 1, 2023 / Notices Day Event/activity A ................... If access granted: issuance of presiding officer or other designated officer decision on motion for protective order for access to sensitive information (including schedule for providing access and submission of contentions) or decision reversing a final adverse determination by the NRC staff. Deadline for filing executed Non-Disclosure Agreements or Affidavits. Access provided to SUNSI consistent with decision issuing the protective order. Deadline for submission of contentions whose development depends upon access to SUNSI. However, if more than 25 days remain between the petitioner’s receipt of (or access to) the information and the deadline for filing all other contentions (as established in the notice of hearing or notice of opportunity for hearing), the petitioner may file its SUNSI contentions by that later deadline. (Contention receipt +25) Answers to contentions whose development depends upon access to SUNSI. (Answer receipt +7) Petitioner/Intervenor reply to answers. Decision on contention admission. A + 3 ............ A + 28 .......... A + 53 .......... A + 60 .......... >A + 60 ........ [FR Doc. 2023–15031 Filed 7–31–23; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION [NRC–2022–0170] Information Collection: Requests to Federally Recognized Indian Tribes for Information; Correction Nuclear Regulatory Commission. ACTION: Notice of submission to the Office of Management and Budget; request for comment; correction. AGENCY: The U.S. Nuclear Regulatory Commission (NRC) is correcting a notice that was published in the Federal Register (FR) on July 25, 2023, regarding submission of the renewal of an existing collection of information to the Office of Management and Budget (OMB) for review. This action is necessary to correct the number of anticipated responses and respondents to the information collection. DATES: The correction takes effect on August 1, 2023. ADDRESSES: Please refer to Docket ID NRC–2022–0170 when contacting the NRC about the availability of information regarding this document. You may obtain publicly available information related to this document using any of the following methods: • Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC–2022–0170. Address questions about Docket IDs in Regulations.gov to Stacy Schumann; telephone: 301–415–0624; email: Stacy.Schumann@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document. • NRC’s Agencywide Documents Access and Management System (ADAMS): You may obtain publicly available documents online in the ADAMS Public Documents collection at lotter on DSK11XQN23PROD with NOTICES1 SUMMARY: VerDate Sep<11>2014 18:34 Jul 31, 2023 Jkt 259001 https://www.nrc.gov/reading-rm/ adams.html. To begin the search, select ‘‘Begin Web-based ADAMS Search.’’ For problems with ADAMS, please contact the NRC’s Public Document Room (PDR) reference staff at 1–800–397–4209, at 301–415–4737, or by email to PDR.Resource@nrc.gov. The supporting statement is available in ADAMS under Accession No. ML23159A048. • NRC’s PDR: The PDR, where you may examine and order copies of publicly available documents, is open by appointment. To make an appointment to visit the PDR, please send an email to PDR.Resource@nrc.gov or call 1–800–397–4209 or 301–415– 4737, between 8 a.m. and 4 p.m. eastern time (ET), Monday through Friday, except Federal holidays. FOR FURTHER INFORMATION CONTACT: David Cullison, Office of the Chief Information Officer, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001, telephone: 301–415– 2084; email: David.Cullison@nrc.gov. In the FR on July 25, 2023, in FR Doc. 2023– 15691, on page 47926, in the second column under the heading ‘‘II. Background,’’ second paragraph, item number 7, ‘‘The estimated number of annual responses,’’ replace ‘‘32’’ with ‘‘640 (20 requests annually × 32 responses per request).’’ In the third column, item number 8, ‘‘The estimated number of annual respondents,’’ replace ‘‘637’’ with ‘‘45.’’ SUPPLEMENTARY INFORMATION: Dated: July 27, 2023. For the Nuclear Regulatory Commission. David C. Cullison, NRC Clearance Officer, Office of the Chief Information Officer. [FR Doc. 2023–16255 Filed 7–31–23; 8:45 am] BILLING CODE 7590–01–P PO 00000 Frm 00090 Fmt 4703 Sfmt 4703 NUCLEAR REGULATORY COMMISSION [Docket No. 70–7020; NRC–2022–0053] Sensor Concepts & Applications, Inc. Nuclear Regulatory Commission. ACTION: License renewal; issuance. AGENCY: The U.S. Nuclear Regulatory Commission (NRC) has renewed Special Nuclear Materials (SNM) License No. SNM–2017, to Sensor Concepts & Applications, Inc. (SCA, the licensee) located in Glen Arm, Maryland. The renewed license authorizes SCA to continue to possess and use SNM for a period of 10 years and will expire on July 26, 2033. DATES: License No. SNM–2017 was issued on July 27, 2023, and is effective as of the date of issuance. ADDRESSES: Please refer to Docket ID NRC–2022–0053 when contacting the NRC about the availability of information regarding this document. You may obtain publicly available information related to this document using any of the following methods: • Federal Rulemaking website: Go to https://www.regulations.gov and search for Docket ID NRC–2022–0053. Address questions about Docket IDs in Regulations.gov to Stacy Schumann; telephone: 301–415–0624; email: Stacy.Schumann@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document. • NRC’s Agencywide Documents Access and Management System (ADAMS): You may obtain publicly available documents online in the ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/ adams.html. To begin the search, select ‘‘Begin Web-based ADAMS Search.’’ For problems with ADAMS, please contact the NRC’s Public Document Room (PDR) reference staff at 1–800–397–4209, at 301–415–4737, or by email to PDR.Resource@nrc.gov. The ADAMS SUMMARY: E:\FR\FM\01AUN1.SGM 01AUN1

Agencies

[Federal Register Volume 88, Number 146 (Tuesday, August 1, 2023)]
[Notices]
[Pages 50183-50188]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-15031]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[NRC-2023-0122]


Applications for Amendments to Facility Operating Licenses 
Involving Proposed No Significant Hazards Consideration(s) and 
Containing Sensitive Unclassified Non-Safeguards Information and Order 
Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards 
Information

AGENCY: Nuclear Regulatory Commission.

ACTION: License amendment request; notice of opportunity to comment, 
request a hearing, and petition for leave to intervene; order imposing 
procedures.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) received and is 
considering approval of two amendment requests. The amendment requests 
are for Millstone Power Station, Unit 3. For each amendment request, 
the NRC proposes to determine that it involves no significant hazards 
consideration (NSHC). Because each amendment request contains sensitive 
unclassified non-safeguards information (SUNSI), an order imposes 
procedures to obtain access to SUNSI for contention preparation by 
persons who file a hearing request or petition for leave to intervene.

DATES: Comments must be filed by August 31, 2023. A request for a 
hearing or petitions for leave to intervene must be filed by October 2, 
2023. Any potential party as defined in section 2.4 of title 10 of the 
Code of Federal Regulations (10 CFR) who believes access to SUNSI is 
necessary to respond to this notice must request document access by 
August 11, 2023.

ADDRESSES: You may submit comments by any of the following methods; 
however, the NRC encourages electronic comment submission through the 
Federal rulemaking website:
     Federal rulemaking website: Go to https://www.regulations.gov and search for Docket ID NRC-2023-0122. Address 
questions about Docket IDs in Regulations.gov to Stacy Schumann; 
telephone: 301-415-0624; email: [email protected]. For technical

[[Page 50184]]

questions, contact the individual listed in the FOR FURTHER INFORMATION 
CONTACT section of this document.
     Mail comments to: Office of Administration, Mail Stop: 
TWFN-7-A60M, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001, ATTN: Program Management, Announcements and Editing Staff.
    For additional direction on obtaining information and submitting 
comments, see ``Obtaining Information and Submitting Comments'' in the 
SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT: Kay Goldstein, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001, telephone: 301-415-1506; email: [email protected].

SUPPLEMENTARY INFORMATION:

I. Obtaining Information and Submitting Comments

A. Obtaining Information

    Please refer to Docket ID NRC-2023-0122, facility name, unit 
number(s), docket number(s), application date, and subject when 
contacting the NRC about the availability of information for this 
action. You may obtain publicly available information related to this 
action by any of the following methods:
     Federal Rulemaking website: Go to https://www.regulations.gov and search for Docket ID NRC-2023-0122.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS 
Search.'' For problems with ADAMS, please contact the NRC's Public 
Document Room (PDR) reference staff at 1-800-397-4209, at 301-415-4737, 
or by email to [email protected]. The Millstone Power Station, Unit 
3, documents are available in ADAMS under Accession Nos. ML23123A279 
and ML23145A195.
     NRC's PDR: The PDR, where you may examine and order copies 
of publicly available documents, is open by appointment. To make an 
appointment to visit the PDR, please send an email to 
[email protected] or call 1-800-397-4209 or 301-415-4737, between 8 
a.m. and 4 p.m. eastern time (ET), Monday through Friday, except 
Federal holidays.

B. Submitting Comments

    The NRC encourages electronic comment submission through the 
Federal rulemaking website (https://www.regulations.gov). Please 
include Docket ID NRC-2023-0122, facility name, unit number(s), docket 
number(s), application date, and subject, in your comment submission.
    The NRC cautions you not to include identifying or contact 
information that you do not want to be publicly disclosed in your 
comment submission. The NRC will post all comment submissions at 
https://www.regulations.gov as well as enter the comment submissions 
into ADAMS. The NRC does not routinely edit comment submissions to 
remove identifying or contact information.
    If you are requesting or aggregating comments from other persons 
for submission to the NRC, then you should inform those persons not to 
include identifying or contact information that they do not want to be 
publicly disclosed in their comment submission. Your request should 
state that the NRC does not routinely edit comment submissions to 
remove such information before making the comment submissions available 
to the public or entering the comment into ADAMS.

II. Background

    Pursuant to section 189a.(1)-(2) of the Atomic Energy Act of 1954, 
as amended (the Act), the NRC is publishing this notice. The Act 
requires the Commission to publish notice of any amendments issued or 
proposed to be issued and grants the Commission the authority to issue 
and make immediately effective any amendment to an operating license or 
combined license, as applicable, upon a determination by the Commission 
that such amendment involves NSHC, notwithstanding the pendency before 
the Commission of a request for a hearing from any person.
    This notice includes two notices of amendments containing SUNSI.

III. Notice of Consideration of Issuance of Amendments to Facility 
Operating Licenses, Proposed No Significant Hazards Consideration 
Determination, and Opportunity for a Hearing

    The Commission has made a proposed determination that the following 
amendment requests involve NSHC. Under the Commission's regulations in 
10 CFR 50.92, this means that operation of the facility in accordance 
with the proposed amendments would not (1) involve a significant 
increase in the probability or consequences of an accident previously 
evaluated, or (2) create the possibility of a new or different kind of 
accident from any accident previously evaluated, or (3) involve a 
significant reduction in a margin of safety. The basis for this 
proposed determination for each amendment request is shown as follows.
    The Commission is seeking public comments on these proposed 
determinations. Any comments received within 30 days after the date of 
publication of this notice will be considered in making any final 
determination.
    Normally, the Commission will not issue the amendments until the 
expiration of 60 days after the date of publication of this notice. The 
Commission may issue any of these license amendments before expiration 
of the 60-day period provided that its final determination is that the 
amendments involve no significant hazards consideration. In addition, 
the Commission may issue any of these amendments prior to the 
expiration of the 30-day comment period if circumstances change during 
the 30-day comment period such that failure to act in a timely way 
would result, for example, in derating or shutdown of the facility. If 
the Commission takes action on any of these amendments prior to the 
expiration of either the comment period or the notice period, it will 
publish a notice of issuance in the Federal Register. If the Commission 
makes a final no significant hazards consideration determination for 
any of these amendments, any hearing on those amendments will take 
place after issuance. The Commission expects that the need to take this 
action will occur very infrequently.

A. Opportunity To Request a Hearing and Petition for Leave To Intervene

    Within 60 days after the date of publication of this notice, any 
person (petitioner) whose interest may be affected by any of these 
actions may file a request for a hearing and petition for leave to 
intervene (petition) with respect to that action. Petitions shall be 
filed in accordance with the Commission's ``Agency Rules of Practice 
and Procedure'' in 10 CFR part 2. Interested persons should consult a 
current copy of 10 CFR 2.309. If a petition is filed, the Commission or 
a presiding officer will rule on the petition and, if appropriate, a 
notice of a hearing will be issued.
    Petitions must be filed no later than 60 days from the date of 
publication of this notice in accordance with the filing instructions 
in the ``Electronic Submissions (E-Filing)'' section of this document. 
Petitions and motions for leave to file new or amended contentions that 
are filed after the deadline will not be entertained absent a 
determination by the presiding officer that the filing demonstrates 
good cause

[[Page 50185]]

by satisfying the three factors in 10 CFR 2.309(c)(1)(i) through (iii).
    If a hearing is requested, and the Commission has not made a final 
determination on the issue of no significant hazards consideration, the 
Commission will make a final determination on the issue of no 
significant hazards consideration, which will serve to establish when 
the hearing is held. If the final determination is that the amendment 
request involves no significant hazards consideration, the Commission 
may issue the amendment and make it immediately effective, 
notwithstanding the request for a hearing. Any hearing would take place 
after issuance of the amendment. If the final determination is that the 
amendment request involves a significant hazards consideration, then 
any hearing held would take place before the issuance of the amendment 
unless the Commission finds an imminent danger to the health or safety 
of the public, in which case it will issue an appropriate order or rule 
under 10 CFR part 2.
    A State, local governmental body, federally recognized Indian 
Tribe, or designated agency thereof, may submit a petition to the 
Commission to participate as a party under 10 CFR 2.309(h) no later 
than 60 days from the date of publication of this notice. 
Alternatively, a State, local governmental body, federally recognized 
Indian Tribe, or agency thereof may participate as a non-party under 10 
CFR 2.315(c).
    For information about filing a petition and about participation by 
a person not a party under 10 CFR 2.315, see ADAMS Accession No. 
ML20340A053 (https://adamswebsearch2.nrc.gov/webSearch2/main.jsp?AccessionNumber=ML20340A053) and on the NRC's public website 
at https://www.nrc.gov/about-nrc/regulatory/adjudicatory/hearing.html#participate.

B. Electronic Submissions (E-Filing)

    All documents filed in NRC adjudicatory proceedings, including 
documents filed by an interested State, local governmental body, 
federally recognized Indian Tribe, or designated agency thereof that 
requests to participate under 10 CFR 2.315(c), must be filed in 
accordance with 10 CFR 2.302. The E-Filing process requires 
participants to submit and serve all adjudicatory documents over the 
internet, or in some cases, to mail copies on electronic storage media, 
unless an exemption permitting an alternative filing method, as further 
discussed, is granted. Detailed guidance on electronic submissions is 
located in the ``Guidance for Electronic Submissions to the NRC'' 
(ADAMS Accession No. ML13031A056) and on the NRC's public website at 
https://www.nrc.gov/site-help/e-submittals.html.
    To comply with the procedural requirements of E-Filing, at least 10 
days prior to the filing deadline, the participant should contact the 
Office of the Secretary by email at [email protected], or by 
telephone at 301-415-1677, to (1) request a digital identification (ID) 
certificate, which allows the participant (or its counsel or 
representative) to digitally sign submissions and access the E-Filing 
system for any proceeding in which it is participating; and (2) advise 
the Secretary that the participant will be submitting a petition or 
other adjudicatory document (even in instances in which the 
participant, or its counsel or representative, already holds an NRC-
issued digital ID certificate). Based upon this information, the 
Secretary will establish an electronic docket for the proceeding if the 
Secretary has not already established an electronic docket.
    Information about applying for a digital ID certificate is 
available on the NRC's public website at https://www.nrc.gov/site-help/e-submittals/getting-started.html. After a digital ID certificate is 
obtained and a docket created, the participant must submit adjudicatory 
documents in Portable Document Format. Guidance on submissions is 
available on the NRC's public website at https://www.nrc.gov/site-help/electronic-sub-ref-mat.html. A filing is considered complete at the 
time the document is submitted through the NRC's E-Filing system. To be 
timely, an electronic filing must be submitted to the E-Filing system 
no later than 11:59 p.m. ET on the due date. Upon receipt of a 
transmission, the E-Filing system time-stamps the document and sends 
the submitter an email confirming receipt of the document. The E-Filing 
system also distributes an email that provides access to the document 
to the NRC's Office of the General Counsel and any others who have 
advised the Office of the Secretary that they wish to participate in 
the proceeding, so that the filer need not serve the document on those 
participants separately. Therefore, applicants and other participants 
(or their counsel or representative) must apply for and receive a 
digital ID certificate before adjudicatory documents are filed to 
obtain access to the documents via the E-Filing system.
    A person filing electronically using the NRC's adjudicatory E-
Filing system may seek assistance by contacting the NRC's Electronic 
Filing Help Desk through the ``Contact Us'' link located on the NRC's 
public website at https://www.nrc.gov/site-help/e-submittals.html, by 
email to [email protected], or by a toll-free call at 1-866-672-
7640. The NRC Electronic Filing Help Desk is available between 9 a.m. 
and 6 p.m., ET, Monday through Friday, except Federal holidays.
    Participants who believe that they have good cause for not 
submitting documents electronically must file an exemption request, in 
accordance with 10 CFR 2.302(g), with their initial paper filing 
stating why there is good cause for not filing electronically and 
requesting authorization to continue to submit documents in paper 
format. Such filings must be submitted in accordance with 10 CFR 
2.302(b)-(d). Participants filing adjudicatory documents in this manner 
are responsible for serving their documents on all other participants. 
Participants granted an exemption under 10 CFR 2.302(g)(2) must still 
meet the electronic formatting requirement in 10 CFR 2.302(g)(1), 
unless the participant also seeks and is granted an exemption from 10 
CFR 2.302(g)(1).
    Documents submitted in adjudicatory proceedings will appear in the 
NRC's electronic hearing docket, which is publicly available at https://adams.nrc.gov/ehd, unless excluded pursuant to an order of the 
presiding officer. If you do not have an NRC-issued digital ID 
certificate as previously described, click ``cancel'' when the link 
requests certificates and you will be automatically directed to the 
NRC's electronic hearing dockets where you will be able to access any 
publicly available documents in a particular hearing docket. 
Participants are requested not to include personal privacy information 
such as social security numbers, home addresses, or personal phone 
numbers in their filings unless an NRC regulation or other law requires 
submission of such information. With respect to copyrighted works, 
except for limited excerpts that serve the purpose of the adjudicatory 
filings and would constitute a Fair Use application, participants 
should not include copyrighted materials in their submission.
    The following table provides the plant names, docket numbers, date 
of application, ADAMS accession number, and location in the application 
of the licensee proposed NSHC determination. For further details with 
respect to these license amendment applications, see the applications 
for amendment, publicly available portions of which are available for 
public inspection in ADAMS. For additional direction on accessing

[[Page 50186]]

information related to this document, see the ``Obtaining Information 
and Submitting Comments'' section of this document.

------------------------------------------------------------------------
 
------------------------------------------------------------------------
Dominion Energy Nuclear Connecticut, Inc.; Millstone Power Station, Unit
                        3; New London County, CT
------------------------------------------------------------------------
Docket No(s).................  50-423.
Application Date.............  May 2, 2023.
ADAMS Accession No...........  ML23123A279.
Location in Application of     Pages 9-11 of Attachment 1.
 NSHC.
Brief Description of           The proposed amendment would revise
 Amendment.                     Technical Specification (TS) 6.9.1.6.b
                                to support the transition to Framatome
                                (FRM) GAIA fuel with M5\TM\ cladding at
                                Millstone Power Station, Unit 3
                                (Millstone, Unit 3), which requires the
                                application of the FRM Small Break Loss
                                of Coolant Accident and Realistic Large
                                Break Loss of Coolant Accident
                                methodologies and the associated use of
                                the GALILEO fuel performance code within
                                the loss-of-coolant accident (LOCA)
                                methods. Specifically, TS 6.9.1.6.b
                                would add FRM Topical Reports EMF-2328-P-
                                A, ``PWR Small Break LOCA Evaluation
                                Model, S-RELAP5 Based,'' EMF-2103-P-A,
                                ``Realistic Large Break LOCA Methodology
                                for Pressurized Water Reactors,'' and
                                ANP-10349-P-A, ``GALILEO Implementation
                                in LOCA Methods'' to the list of
                                methodologies for establishing core
                                operating limits. The proposed revision
                                to TS 6.9.1.6.b would also delete one
                                methodology no longer used to define
                                core operating limits at Millstone, Unit
                                3. Dominion Energy Nuclear Connecticut,
                                Inc. is also requesting an exemption to
                                facilitate the use of FRM GAIA fuel
                                assemblies containing fuel rods
                                fabricated with M5\TM\ cladding material
                                at Millstone, Unit 3.
Proposed Determination.......  NSHC.
Name of Attorney for           W.S. Blair, Senior Counsel, Dominion
 Licensee, Mailing Address.     Energy Services, Inc., 120 Tredegar St.,
                                RS-2, Richmond, VA 23219.
NRC Project Manager,           Richard Guzman, 301-415-1030.
 Telephone Number.
------------------------------------------------------------------------
Dominion Energy Nuclear Connecticut, Inc.; Millstone Power Station, Unit
                        3; New London County, CT
------------------------------------------------------------------------
Docket No(s).................  50-423.
Application Date.............  May 23, 2023.
ADAMS Accession No...........  ML23145A195.
Location in Application of     Pages 10-14 of Attachment 1.
 NSHC.
Brief Description of           The proposed amendment would revise the
 Amendment(s).                  Millstone Power Station, Unit 3
                                (Millstone, Unit 3), technical
                                specifications (TSs) to support the use
                                of Framatome GAIA fuel with M5\TM\ fuel
                                cladding material, which is currently
                                scheduled for insertion into the
                                Millstone, Unit 3, reactor during the
                                spring 2025 refueling outage. The
                                proposed TS changes include updating the
                                reactor core safety limits (TS 2.1.1.2),
                                fuel assemblies design features (TS
                                5.3.1), and list of approved
                                methodologies for the Core Operating
                                Limits Report (TS 6.9.1.6.b).
Proposed Determination.......  NSHC.
Name of Attorney for           W.S. Blair, Senior Counsel, Dominion
 Licensee, Mailing Address.     Energy Services, Inc., 120 Tredegar St.,
                                RS-2, Richmond, VA 23219.
NRC Project Manager,           Richard Guzman, 301-415-1030.
 Telephone Number.
------------------------------------------------------------------------

Order Imposing Procedures for Access to Sensitive Unclassified Non-
Safeguards Information for Contention Preparation

    A. This Order contains instructions regarding how potential parties 
to this proceeding may request access to documents containing Sensitive 
Unclassified Non-Safeguards Information (SUNSI).
    B. Within 10 days after publication of this notice of hearing or 
opportunity for hearing, any potential party who believes access to 
SUNSI is necessary to respond to this notice may request access to 
SUNSI. A ``potential party'' is any person who intends to participate 
as a party by demonstrating standing and filing an admissible 
contention under 10 CFR 2.309. Requests for access to SUNSI submitted 
later than 10 days after publication of this notice will not be 
considered absent a showing of good cause for the late filing, 
addressing why the request could not have been filed earlier.
    C. The requestor shall submit a letter requesting permission to 
access SUNSI to the Office of the Secretary, U.S. Nuclear Regulatory 
Commission, Washington, DC 20555-0001, Attention: Rulemakings and 
Adjudications Staff, and provide a copy to the Deputy General Counsel 
for Licensing, Hearings, and Enforcement, Office of the General 
Counsel, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001. 
The expedited delivery or courier mail address for both offices is: 
U.S. Nuclear Regulatory Commission, 11555 Rockville Pike, Rockville, 
Maryland 20852. The email addresses for the Office of the Secretary and 
the Office of the General Counsel are [email protected] and 
[email protected], respectively.\1\ The request must 
include the following information:
---------------------------------------------------------------------------

    \1\ While a request for hearing or petition to intervene in this 
proceeding must comply with the filing requirements of the NRC's 
``E-Filing Rule,'' the initial request to access SUNSI under these 
procedures should be submitted as described in this paragraph.
---------------------------------------------------------------------------

    (1) A description of the licensing action with a citation to this 
Federal Register notice;
    (2) The name and address of the potential party and a description 
of the potential party's particularized interest that could be harmed 
by the action identified in C.(1); and
    (3) The identity of the individual or entity requesting access to 
SUNSI and the requestor's basis for the need for the information in 
order to meaningfully participate in this adjudicatory proceeding. In 
particular, the request must explain why publicly available versions of 
the information requested would not be sufficient to provide the basis 
and specificity for a proffered contention.
    D. Based on an evaluation of the information submitted under 
paragraph C, the NRC staff will determine within

[[Page 50187]]

10 days of receipt of the request whether:
    (1) There is a reasonable basis to believe the petitioner is likely 
to establish standing to participate in this NRC proceeding; and
    (2) The requestor has established a legitimate need for access to 
SUNSI.
    E. If the NRC staff determines that the requestor satisfies both 
D.(1) and D.(2), the NRC staff will notify the requestor in writing 
that access to SUNSI has been granted. The written notification will 
contain instructions on how the requestor may obtain copies of the 
requested documents, and any other conditions that may apply to access 
to those documents. These conditions may include, but are not limited 
to, the signing of a Non-Disclosure Agreement or Affidavit, or 
Protective Order \2\ setting forth terms and conditions to prevent the 
unauthorized or inadvertent disclosure of SUNSI by each individual who 
will be granted access to SUNSI.
---------------------------------------------------------------------------

    \2\ Any motion for Protective Order or draft Non-Disclosure 
Affidavit or Agreement for SUNSI must be filed with the presiding 
officer or the Chief Administrative Judge if the presiding officer 
has not yet been designated, within 30 days of the deadline for the 
receipt of the written access request.
---------------------------------------------------------------------------

    F. Filing of Contentions. Any contentions in these proceedings that 
are based upon the information received as a result of the request made 
for SUNSI must be filed by the requestor no later than 25 days after 
receipt of (or access to) that information. However, if more than 25 
days remain between the petitioner's receipt of (or access to) the 
information and the deadline for filing all other contentions (as 
established in the notice of hearing or opportunity for hearing), the 
petitioner may file its SUNSI contentions by that later deadline.
    G. Review of Denials of Access.
    (1) If the request for access to SUNSI is denied by the NRC staff 
after a determination on standing and requisite need, the NRC staff 
shall immediately notify the requestor in writing, briefly stating the 
reason or reasons for the denial.
    (2) The requestor may challenge the NRC staff's adverse 
determination by filing a challenge within 5 days of receipt of that 
determination with: (a) the presiding officer designated in this 
proceeding; (b) if no presiding officer has been appointed, the Chief 
Administrative Judge, or if this individual is unavailable, another 
administrative judge, or an Administrative Law Judge with jurisdiction 
pursuant to 10 CFR 2.318(a); or (c) if another officer has been 
designated to rule on information access issues, with that officer.
    (3) Further appeals of decisions under this paragraph must be made 
pursuant to 10 CFR 2.311.
    H. Review of Grants of Access. A party other than the requestor may 
challenge an NRC staff determination granting access to SUNSI whose 
release would harm that party's interest independent of the proceeding. 
Such a challenge must be filed within 5 days of the notification by the 
NRC staff of its grant of access and must be filed with: (a) the 
presiding officer designated in this proceeding; (b) if no presiding 
officer has been appointed, the Chief Administrative Judge, or if this 
individual is unavailable, another administrative judge, or an 
Administrative Law Judge with jurisdiction pursuant to 10 CFR 2.318(a); 
or (c) if another officer has been designated to rule on information 
access issues, with that officer.
    If challenges to the NRC staff determinations are filed, these 
procedures give way to the normal process for litigating disputes 
concerning access to information. The availability of interlocutory 
review by the Commission of orders ruling on such NRC staff 
determinations (whether granting or denying access) is governed by 10 
CFR 2.311.\3\
---------------------------------------------------------------------------

    \3\ Requestors should note that the filing requirements of the 
NRC's E-Filing Rule (72 FR 49139; August 28, 2007, as amended at 77 
FR 46562; August 3, 2012, 78 FR 34247, June 7, 2013) apply to 
appeals of NRC staff determinations (because they must be served on 
a presiding officer or the Commission, as applicable), but not to 
the initial SUNSI request submitted to the NRC staff under these 
procedures.
---------------------------------------------------------------------------

    I. The Commission expects that the NRC staff and presiding officers 
(and any other reviewing officers) will consider and resolve requests 
for access to SUNSI, and motions for protective orders, in a timely 
fashion in order to minimize any unnecessary delays in identifying 
those petitioners who have standing and who have propounded contentions 
meeting the specificity and basis requirements in 10 CFR part 2. The 
attachment to this Order summarizes the general target schedule for 
processing and resolving requests under these procedures.
    It is so ordered.

    Dated: July 11, 2023.

    For the Nuclear Regulatory Commission.
Brooke P. Clark,
Secretary of the Commission.

Attachment 1--General Target Schedule for Processing and Resolving 
Requests for Access to Sensitive Unclassified Non-Safeguards 
Information in This Proceeding

------------------------------------------------------------------------
             Day                            Event/activity
------------------------------------------------------------------------
0...........................  Publication of Federal Register notice of
                               hearing or opportunity for hearing,
                               including order with instructions for
                               access requests.
10..........................  Deadline for submitting requests for
                               access to Sensitive Unclassified Non-
                               Safeguards Information (SUNSI) with
                               information: supporting the standing of a
                               potential party identified by name and
                               address; describing the need for the
                               information in order for the potential
                               party to participate meaningfully in an
                               adjudicatory proceeding.
60..........................  Deadline for submitting petition for
                               intervention containing: (i)
                               demonstration of standing; and (ii) all
                               contentions whose formulation does not
                               require access to SUNSI (+25 Answers to
                               petition for intervention; +7 petitioner/
                               requestor reply).
20..........................  U.S. Nuclear Regulatory Commission (NRC)
                               staff informs the requestor of the
                               staff's determination whether the request
                               for access provides a reasonable basis to
                               believe standing can be established and
                               shows need for SUNSI. (NRC staff also
                               informs any party to the proceeding whose
                               interest independent of the proceeding
                               would be harmed by the release of the
                               information.) If NRC staff makes the
                               finding of need for SUNSI and likelihood
                               of standing, NRC staff begins document
                               processing (preparation of redactions or
                               review of redacted documents).
25..........................  If NRC staff finds no ``need'' or no
                               likelihood of standing, the deadline for
                               petitioner/requestor to file a motion
                               seeking a ruling to reverse the NRC
                               staff's denial of access; NRC staff files
                               copy of access determination with the
                               presiding officer (or Chief
                               Administrative Judge or other designated
                               officer, as appropriate). If NRC staff
                               finds ``need'' for SUNSI, the deadline
                               for any party to the proceeding whose
                               interest independent of the proceeding
                               would be harmed by the release of the
                               information to file a motion seeking a
                               ruling to reverse the NRC staff's grant
                               of access.
30..........................  Deadline for NRC staff reply to motions to
                               reverse NRC staff determination(s).
40..........................  (Receipt +30) If NRC staff finds standing
                               and need for SUNSI, deadline for NRC
                               staff to complete information processing
                               and file motion for Protective Order and
                               draft Non-Disclosure Agreement or
                               Affidavit. Deadline for applicant/
                               licensee to file Non-Disclosure Agreement
                               or Affidavit for SUNSI.

[[Page 50188]]

 
A...........................  If access granted: issuance of presiding
                               officer or other designated officer
                               decision on motion for protective order
                               for access to sensitive information
                               (including schedule for providing access
                               and submission of contentions) or
                               decision reversing a final adverse
                               determination by the NRC staff.
A + 3.......................  Deadline for filing executed Non-
                               Disclosure Agreements or Affidavits.
                               Access provided to SUNSI consistent with
                               decision issuing the protective order.
A + 28......................  Deadline for submission of contentions
                               whose development depends upon access to
                               SUNSI. However, if more than 25 days
                               remain between the petitioner's receipt
                               of (or access to) the information and the
                               deadline for filing all other contentions
                               (as established in the notice of hearing
                               or notice of opportunity for hearing),
                               the petitioner may file its SUNSI
                               contentions by that later deadline.
A + 53......................  (Contention receipt +25) Answers to
                               contentions whose development depends
                               upon access to SUNSI.
A + 60......................  (Answer receipt +7) Petitioner/Intervenor
                               reply to answers.
>A + 60.....................  Decision on contention admission.
------------------------------------------------------------------------