Download as PDF ddrumheller on DSK120RN23PROD with NOTICES1 48458 Federal Register / Vol. 88, No. 143 / Thursday, July 27, 2023 / Notices contractors listed in this notice, where this system of records is maintained, is controlled and monitored by security personnel who check each individual entering the building for his or her employee or visitor badge. In accordance with the Department’s Administrative Communications System Directive ACSD–OFO–013 entitled ‘‘Contractor Employee Personnel Security Screenings,’’ all contract personnel who have facility access and system access are required to undergo a security clearance investigation. Individuals requiring access to Privacy Act records are required to hold, at a minimum, a moderate-risk security clearance level. These individuals are required to undergo periodic screening at five-year intervals. In addition to conducting security clearances, contract and Department employees are required to complete security awareness training on an annual basis. Annual security awareness training is required to ensure that contract and Department users are appropriately trained in safeguarding Privacy Act records. The computer system employed by the Department offers a high degree of resistance to tampering and circumvention. This security system limits data access to Department and contract staff on a ‘‘need-to-know’’ basis and controls individual users’ ability to access and alter records within the system. All users of this system of records are given a unique user identification and password. The Department’s Information Technology (IT) Identification and Authentication (IA) Standard requires the enforcement of a complex password policy. In addition to the enforcement of a complex password policy, users are required to change their password at least every 90 days or based on the Zero Trust Strategy/Plan in accordance with the Department’s IT IA standards. In accordance with the Federal Information Security Management Act of 2002 (FISMA), as amended by the Federal Information Security Modernization Act of 2014, every Department system must receive a signed Authorization to Operate (ATO) from a designated Department official. The ATO process includes a rigorous assessment of security and privacy controls, a plan of actions and milestones to remediate any identified deficiencies, and a continuous monitoring program. FISMA controls implemented comprise a combination of management, operational, and technical controls, and include the following control families: access control, awareness and training, VerDate Sep<11>2014 17:21 Jul 26, 2023 Jkt 259001 audit and accountability, assessment, authorization, and monitoring, configuration management, contingency planning, identification and authentication, incident response, maintenance, media protection, physical and environmental protection, planning, program management, personnel security, personally identifiable information processing and transparency, risk assessment, system and services acquisition, system and communications protection, system and information integrity, and supply chain risk management. All of the Federal Loan Servicers, NFP Federal Loan Servicers, the Federal Perkins Loan Servicer, PCAs, and other contractors, as listed in ‘‘SYSTEM LOCATION,’’ undergo FISMA security authorizations. In addition, access is monitored 24 hours per day, 7 days a week. RECORD ACCESS PROCEDURES: If you wish to gain access to a record in this system, provide the system manager with your name, date of birth, and SSN. Requests by an individual for access to a record must meet the requirements of the regulations in 34 CFR 5b.5, including proof of identity. CONTESTING RECORD PROCEDURE: If you wish to contest the content of a record in this system of records, contact the system manager with your name, date of birth, and SSN; identify the specific items to be changed; and provide a written justification for the change. Requests to amend a record must meet the requirements of the regulations in 34 CFR 5b.7. NOTIFICATION PROCEDURES: If you wish to determine whether a record exists regarding you in this system of records, provide the system manager with your name, date of birth, and SSN. Requests must meet the requirements of the regulations in 34 CFR 5b.5 and 5b.7, including proof of identity. EXEMPTIONS PROMULGATED FOR THE SYSTEM: None. HISTORY: The system of records entitled ‘‘Common Services for Borrowers (CSB)’’ (18–11–16) was originally published in the Federal Register on January 23, 2006 (71 FR 3503–3507), modified on September 12, 2014 (79 FR 54685–54695) and on September 2, 2016 (81 FR 60683–60691), and last modified on September 13, 2022 (87 FR 56003– 56015). [FR Doc. 2023–15931 Filed 7–26–23; 8:45 am] BILLING CODE 4000–01–P PO 00000 Frm 00034 Fmt 4703 Sfmt 4703 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP23–518–000] NFEnergı´a LLC; Notice of Application and Establishing Intervention Deadline Take notice that on July 18, 2023, NFEnergı´a LLC (NFEnergı´a), 111 W 19th Street, New York, New York 10011, filed a request under section 3 of the Natural Gas Act (NGA), and part 153 of the Commission’s regulations requesting authorization to permit construction and interconnection of a new pipeline at its MFH Facility located at the Port of San Juan, Puerto Rico (Project). NFEnergı´a states that the U.S. Army Corps of Engineers’ (USACE) emergency temporary generation project, located adjacent to the Puerto Rico Electric Power Authority’s San Juan Power Plant, must interconnect to an existing, available blind flange MFH Facility in order for that project to meet its objectives timely. Thus, NFEnergı´a seeks authorization to construct an interconnection of approximately 220 feet of 10-inch-diameter pipeline to an existing, available blind flange at the MFH Facility in order to deliver natural gas to USACE’s project. NFEnergı´a avers that the existing capacity at the MFH Facility is adequate to make available the fuel necessary to support the temporary power generation, all as more fully set forth in the application which is on file with the Commission and open for public inspection. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room. For assistance, contact the Federal Energy Regulatory Commission at FercOnlineSupport@ ferc.gov or call toll-free, (886) 208–3676 or TTY (202) 502–8659. Any questions regarding the proposed project should be directed to Cameron MacDougall, General Counsel, NFEnergı´a LLC, 111 W 19th Street, New York, New York 10011, by phone at (212) 479–1522, or by email at cmacdougall@fortress.com. Pursuant to section 157.9 of the Commission’s Rules of Practice and E:\FR\FM\27JYN1.SGM 27JYN1 Federal Register / Vol. 88, No. 143 / Thursday, July 27, 2023 / Notices Procedure,1 within 90 days of this Notice the Commission staff will either: complete its environmental review and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or environmental assessment (EA) for this proposal. The filing of an EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Public Participation There are three ways to become involved in the Commission’s review of this project: you can file comments on the project, you can protest the filing, and you can file a motion to intervene in the proceeding. There is no fee or cost for filing comments or intervening. The deadline for filing a motion to intervene is 5:00 p.m. Eastern Time on July 25, 2023. How to file protests, motions to intervene, and comments is explained below. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. ddrumheller on DSK120RN23PROD with NOTICES1 Comments Any person wishing to comment on the project may do so. Comments may include statements of support or objections, to the project as a whole or specific aspects of the project. The more specific your comments, the more useful they will be. 1 18 CFR (Code of Federal Regulations) 157.9. VerDate Sep<11>2014 17:21 Jul 26, 2023 Jkt 259001 Protests Pursuant to sections 157.10(a)(4) 2 and 385.211 3 of the Commission’s regulations under the NGA, any person 4 may file a protest to the application. Protests must comply with the requirements specified in section 385.2001 5 of the Commission’s regulations. A protest may also serve as a motion to intervene so long as the protestor states it also seeks to be an intervenor. To ensure that your comments or protests are timely and properly recorded, please submit your comments on or before July 25, 2023. There are three methods you can use to submit your comments or protests to the Commission. In all instances, please reference the Project docket number CP23–518–000 in your submission. (1) You may file your comments electronically by using the eComment feature, which is located on the Commission’s website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project; (2) You may file your comments or protests electronically by using the eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select ‘‘General’’ and then select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments or protests by mailing them to the following address below. Your written comments must reference the Project docket number (CP23–518–000). To file via USPS: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. To file via any other courier: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The Commission encourages electronic filing of comments (options 1 and 2 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. Persons who comment on the environmental review of this project CFR 157.10(a)(4). CFR 385.211. 4 Persons include individuals, organizations, businesses, municipalities, and other entities. 18 CFR 385.102(d). 5 18 CFR 385.20013. PO 00000 2 18 3 18 Frm 00035 Fmt 4703 Sfmt 4703 48459 will be placed on the Commission’s environmental mailing list, and will receive notification when the environmental documents (EA or EIS) are issued for this project and will be notified of meetings associated with the Commission’s environmental review process. The Commission considers all comments received about the project in determining the appropriate action to be taken. However, the filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding. For instructions on how to intervene, see below. Interventions Any person, which includes individuals, organizations, businesses, municipalities, and other entities,6 has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission’s orders in the U.S. Circuit Courts of Appeal. To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure 7 and the regulations under the NGA 8 by the intervention deadline for the project, which is July 25, 2023. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as the your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https:// www.ferc.gov/resources/guides/how-to/ intervene.asp. There are two ways to submit your motion to intervene. In both instances, please reference the Project docket number CP23–518–000 in your submission. (1) You may file your motion to intervene by using the Commission’s eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first 6 18 CFR 385.102(d). CFR 385.214. 8 18 CFR 157.10. 7 18 E:\FR\FM\27JYN1.SGM 27JYN1 48460 Federal Register / Vol. 88, No. 143 / Thursday, July 27, 2023 / Notices select ‘‘General’’ and then select ‘‘Intervention.’’ The eFiling feature includes a document-less intervention option; for more information, visit https://www.ferc.gov/docs-filing/efiling/ document-less-intervention.pdf; or (2) You can file a paper copy of your motion to intervene, along with three copies, by mailing the documents to the address below. Your motion to intervene must reference the Project docket number CP23–518–000. To file via USPS: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. To file via any other courier: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The Commission encourages electronic filing of motions to intervene (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. Protests and motions to intervene must be served on the applicant either by mail or email at: Cameron MacDougall, General Counsel, NFEnergı´a LLC, 111 W 19th Street, New York, New York 10011, or at email at cmacdougall@fortress.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. Service can be via email with a link to the document. All timely, unopposed 9 motions to intervene are automatically granted by operation of Rule 214(c)(1).10 Motions to intervene that are filed after the intervention deadline are untimely, and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission’s Rules and Regulations.11 A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties. ddrumheller on DSK120RN23PROD with NOTICES1 Tracking the Proceeding Throughout the proceeding, additional information about the project will be available from the Commission’s 9 The applicant has 15 days from the submittal of a motion to intervene to file a written objection to the intervention. 10 18 CFR 385.214(c)(1). 11 18 CFR 385.214(b)(3) and (d). VerDate Sep<11>2014 17:21 Jul 26, 2023 Jkt 259001 Office of External Affairs, at (866) 208– FERC, or on the FERC website at www.ferc.gov using the ‘‘eLibrary’’ link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/docs-filing/ esubscription.asp. Intervention Deadline: 5:00 p.m. Eastern Time on July 25, 2023. Dated: July 21, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–15942 Filed 7–26–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER23–2451–000] Great Cove Solar II LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding of Great Cove Solar II LLC’s application for market-based rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is August 10, 2023. The Commission encourages electronic submission of protests and PO 00000 Frm 00036 Fmt 4703 Sfmt 9990 interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: July 21, 2023. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2023–15954 Filed 7–26–23; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\27JYN1.SGM 27JYN1

Agencies

[Federal Register Volume 88, Number 143 (Thursday, July 27, 2023)]
[Notices]
[Pages 48458-48460]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-15942]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP23-518-000]


NFEnerg[iacute]a LLC; Notice of Application and Establishing 
Intervention Deadline

    Take notice that on July 18, 2023, NFEnerg[iacute]a LLC 
(NFEnerg[iacute]a), 111 W 19th Street, New York, New York 10011, filed 
a request under section 3 of the Natural Gas Act (NGA), and part 153 of 
the Commission's regulations requesting authorization to permit 
construction and interconnection of a new pipeline at its MFH Facility 
located at the Port of San Juan, Puerto Rico (Project). 
NFEnerg[iacute]a states that the U.S. Army Corps of Engineers' (USACE) 
emergency temporary generation project, located adjacent to the Puerto 
Rico Electric Power Authority's San Juan Power Plant, must interconnect 
to an existing, available blind flange MFH Facility in order for that 
project to meet its objectives timely. Thus, NFEnerg[iacute]a seeks 
authorization to construct an interconnection of approximately 220 feet 
of 10-inch-diameter pipeline to an existing, available blind flange at 
the MFH Facility in order to deliver natural gas to USACE's project. 
NFEnerg[iacute]a avers that the existing capacity at the MFH Facility 
is adequate to make available the fuel necessary to support the 
temporary power generation, all as more fully set forth in the 
application which is on file with the Commission and open for public 
inspection.
    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (www.ferc.gov) using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. At this time, 
the Commission has suspended access to the Commission's Public 
Reference Room. For assistance, contact the Federal Energy Regulatory 
Commission at [email protected] or call toll-free, (886) 208-
3676 or TTY (202) 502-8659.
    Any questions regarding the proposed project should be directed to 
Cameron MacDougall, General Counsel, NFEnerg[iacute]a LLC, 111 W 19th 
Street, New York, New York 10011, by phone at (212) 479-1522, or by 
email at [email protected].
    Pursuant to section 157.9 of the Commission's Rules of Practice and

[[Page 48459]]

Procedure,\1\ within 90 days of this Notice the Commission staff will 
either: complete its environmental review and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or environmental 
assessment (EA) for this proposal. The filing of an EA in the 
Commission's public record for this proceeding or the issuance of a 
Notice of Schedule for Environmental Review will serve to notify 
federal and state agencies of the timing for the completion of all 
necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's FEIS or EA.
---------------------------------------------------------------------------

    \1\ 18 CFR (Code of Federal Regulations) 157.9.
---------------------------------------------------------------------------

Public Participation

    There are three ways to become involved in the Commission's review 
of this project: you can file comments on the project, you can protest 
the filing, and you can file a motion to intervene in the proceeding. 
There is no fee or cost for filing comments or intervening. The 
deadline for filing a motion to intervene is 5:00 p.m. Eastern Time on 
July 25, 2023. How to file protests, motions to intervene, and comments 
is explained below.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or [email protected].

Comments

    Any person wishing to comment on the project may do so. Comments 
may include statements of support or objections, to the project as a 
whole or specific aspects of the project. The more specific your 
comments, the more useful they will be.

Protests

    Pursuant to sections 157.10(a)(4) \2\ and 385.211 \3\ of the 
Commission's regulations under the NGA, any person \4\ may file a 
protest to the application. Protests must comply with the requirements 
specified in section 385.2001 \5\ of the Commission's regulations. A 
protest may also serve as a motion to intervene so long as the 
protestor states it also seeks to be an intervenor.
---------------------------------------------------------------------------

    \2\ 18 CFR 157.10(a)(4).
    \3\ 18 CFR 385.211.
    \4\ Persons include individuals, organizations, businesses, 
municipalities, and other entities. 18 CFR 385.102(d).
    \5\ 18 CFR 385.20013.
---------------------------------------------------------------------------

    To ensure that your comments or protests are timely and properly 
recorded, please submit your comments on or before July 25, 2023.
    There are three methods you can use to submit your comments or 
protests to the Commission. In all instances, please reference the 
Project docket number CP23-518-000 in your submission.
    (1) You may file your comments electronically by using the eComment 
feature, which is located on the Commission's website at www.ferc.gov 
under the link to Documents and Filings. Using eComment is an easy 
method for interested persons to submit brief, text-only comments on a 
project;
    (2) You may file your comments or protests electronically by using 
the eFiling feature, which is located on the Commission's website 
(www.ferc.gov) under the link to Documents and Filings. With eFiling, 
you can provide comments in a variety of formats by attaching them as a 
file with your submission. New eFiling users must first create an 
account by clicking on ``eRegister.'' You will be asked to select the 
type of filing you are making; first select ``General'' and then select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments or protests by 
mailing them to the following address below. Your written comments must 
reference the Project docket number (CP23-518-000).
    To file via USPS: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426.
    To file via any other courier: Kimberly D. Bose, Secretary, Federal 
Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 
20852.
    The Commission encourages electronic filing of comments (options 1 
and 2 above) and has eFiling staff available to assist you at (202) 
502-8258 or [email protected].
    Persons who comment on the environmental review of this project 
will be placed on the Commission's environmental mailing list, and will 
receive notification when the environmental documents (EA or EIS) are 
issued for this project and will be notified of meetings associated 
with the Commission's environmental review process.
    The Commission considers all comments received about the project in 
determining the appropriate action to be taken. However, the filing of 
a comment alone will not serve to make the filer a party to the 
proceeding. To become a party, you must intervene in the proceeding. 
For instructions on how to intervene, see below.

Interventions

    Any person, which includes individuals, organizations, businesses, 
municipalities, and other entities,\6\ has the option to file a motion 
to intervene in this proceeding. Only intervenors have the right to 
request rehearing of Commission orders issued in this proceeding and to 
subsequently challenge the Commission's orders in the U.S. Circuit 
Courts of Appeal.
---------------------------------------------------------------------------

    \6\ 18 CFR 385.102(d).
---------------------------------------------------------------------------

    To intervene, you must submit a motion to intervene to the 
Commission in accordance with Rule 214 of the Commission's Rules of 
Practice and Procedure \7\ and the regulations under the NGA \8\ by the 
intervention deadline for the project, which is July 25, 2023. As 
described further in Rule 214, your motion to intervene must state, to 
the extent known, your position regarding the proceeding, as well as 
the your interest in the proceeding. For an individual, this could 
include your status as a landowner, ratepayer, resident of an impacted 
community, or recreationist. You do not need to have property directly 
impacted by the project in order to intervene. For more information 
about motions to intervene, refer to the FERC website at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------

    \7\ 18 CFR 385.214.
    \8\ 18 CFR 157.10.
---------------------------------------------------------------------------

    There are two ways to submit your motion to intervene. In both 
instances, please reference the Project docket number CP23-518-000 in 
your submission.
    (1) You may file your motion to intervene by using the Commission's 
eFiling feature, which is located on the Commission's website 
(www.ferc.gov) under the link to Documents and Filings. New eFiling 
users must first create an account by clicking on ``eRegister.'' You 
will be asked to select the type of filing you are making; first

[[Page 48460]]

select ``General'' and then select ``Intervention.'' The eFiling 
feature includes a document-less intervention option; for more 
information, visit https://www.ferc.gov/docs-filing/efiling/document-less-intervention.pdf; or
    (2) You can file a paper copy of your motion to intervene, along 
with three copies, by mailing the documents to the address below. Your 
motion to intervene must reference the Project docket number CP23-518-
000.
    To file via USPS: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426.
    To file via any other courier: Kimberly D. Bose, Secretary, Federal 
Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 
20852.
    The Commission encourages electronic filing of motions to intervene 
(option 1 above) and has eFiling staff available to assist you at (202) 
502-8258 or [email protected].
    Protests and motions to intervene must be served on the applicant 
either by mail or email at: Cameron MacDougall, General Counsel, 
NFEnerg[iacute]a LLC, 111 W 19th Street, New York, New York 10011, or 
at email at [email protected]. Any subsequent submissions by an 
intervenor must be served on the applicant and all other parties to the 
proceeding. Contact information for parties can be downloaded from the 
service list at the eService link on FERC Online. Service can be via 
email with a link to the document.
    All timely, unopposed \9\ motions to intervene are automatically 
granted by operation of Rule 214(c)(1).\10\ Motions to intervene that 
are filed after the intervention deadline are untimely, and may be 
denied. Any late-filed motion to intervene must show good cause for 
being late and must explain why the time limitation should be waived 
and provide justification by reference to factors set forth in Rule 
214(d) of the Commission's Rules and Regulations.\11\ A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies (paper or 
electronic) of all documents filed by the applicant and by all other 
parties.
---------------------------------------------------------------------------

    \9\ The applicant has 15 days from the submittal of a motion to 
intervene to file a written objection to the intervention.
    \10\ 18 CFR 385.214(c)(1).
    \11\ 18 CFR 385.214(b)(3) and (d).
---------------------------------------------------------------------------

Tracking the Proceeding

    Throughout the proceeding, additional information about the project 
will be available from the Commission's Office of External Affairs, at 
(866) 208-FERC, or on the FERC website at www.ferc.gov using the 
``eLibrary'' link as described above. The eLibrary link also provides 
access to the texts of all formal documents issued by the Commission, 
such as orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. For more information and to register, go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Intervention Deadline: 5:00 p.m. Eastern Time on July 25, 2023.

    Dated: July 21, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-15942 Filed 7-26-23; 8:45 am]
BILLING CODE 6717-01-P