during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The pumped storage hydropower
project will consist of: (1) a new upper
reservoir with a surface area of 4,800
acres and a storage volume of 400,000
acre-feet at a maximum water-surface
elevation of 8,810 feet mean sea level;
(2) a new lower reservoir with a surface
area of 5,400 acres and a storage volume
of 400,000 acre-feet at a maximum
water-surface elevation of 5,910 MSL;
(3) a 60-foot-wide, 1,200-foot-long and
100-foot-high subterranean powerhouse
with twelve pump/turbines rated at 250
megawatts; (4) a 40-foot wide and
33,000-foot-long conduit to the
powerhouse; (5) 12-foot-wide, 1,000foot-long powerhouse lower conduit;
and (6) approximately 50 miles of 550kilovolt transmission line for
connection to existing lines. The
estimated annual energy production of
the project would be approximately
6,570,000 megawatt-hours.
Applicant Contact: Mr. Denis Payre,
Nature and People First Arizona PHS,
LLC, 405 Waltham St., Suite 145,
Lexington, MA 02421; email:
denis.payre@natureandpeoplefirst.com;
phone: (781) 491–5364.
FERC Contact: Shannon Archuleta;
email; shannon.archuleta@ferc.gov;
phone (503) 552–2739.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members, and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov. Comments, motions to
intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications
should be submitted within 60 days
from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
ferconline.ferc.gov/FERCOnline.aspx.
Commenters can submit brief comments
up to 6,000 characters without prior
VerDate Sep<11>2014
00:36 Jul 19, 2023
Jkt 259001
registration using the eComment system
at https://ferconline.ferc.gov/
QuickComment.aspx. You must include
your name and contact information at
the end of your comments. For
assistance, please get in touch with
FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll-free), or (202) 502–8659
(TTY). Instead of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. The first
page of any filing should include docket
number P–15309–000.
More information about this project,
including a copy of the application, can
be viewed on the Commission’s website
(https://www.ferc.gov) using the
‘‘eLibrary’’ link. Enter the docket
number (P–15309) in the docket number
field to access the document. For
assistance, do not hesitate to get in
touch with FERC Online Support.
Dated: July 13, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–15313 Filed 7–18–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 15038–001]
Let It Go, LLC; Notice Updating
Procedural Schedule
Take notice that the schedule for
processing the Jefferson Mill
Hydroelectric Project No. 15038
exemption application has been
updated. Subsequent revisions to the
schedule may be made as appropriate.
MILESTONE
Target date
Commission issues EA ..........
July 2023.1
1 The Council on Environmental Quality’s (CEQ)
regulations under 40 CFR 1501.10(b)(1) require that
EAs be completed within 1 year of the Federal
action agency’s decision to prepare an EA. The
Commission’s October 28, 2022, notice established
the Commission’s intent to prepare an EA for the
Jefferson Mill Project. Therefore, in accordance with
CEQ’s regulations, the EA must be issued by
October 28, 2023.
PO 00000
Frm 00025
Fmt 4703
Sfmt 9990
MILESTONE
Commission issues draft Programmatic Agreement (PA).
Comments on EA (due 30
days after EA issuance).
Comments on draft PA (due
30 days after draft PA
issuance).
Target date
July 2023.
August 2023.
August 2023.
Dated: July 13, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–15315 Filed 7–18–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 3309–022]
Marlow Hydro, LLC; Notice of
Effectiveness of Withdrawal of
Application for Surrender and of
Ongoing Effectiveness of
Authorization for Continued Project
Operation
On June 17, 2022, the Marlow Hydro,
LLC, filed an application for surrender
of the Nash Mill Dam Hydroelectric
Project No. 3309. On June 20, 2023, the
Marlow Hydro, LLC, filed a request to
withdraw its surrender application.
No motion in opposition to the
request for withdrawal has been filed,
and the Commission has taken no action
to disallow the withdrawal. Pursuant to
Rule 216(b) of the Commission’s Rules
of Practice and Procedure,1 the
withdrawal of the application became
effective on July 5, 2023, and this
proceeding is hereby terminated.
The Commission issued Notice of
Authorization for Continued Project
Operation on December 22, 2022.
Accordingly, Marlow Hydro, LLC, has
been authorized to continue operation
of the Nash Mill Dam Hydroelectric
Project under the terms and conditions
of the prior license until the issuance of
a new license for the project or the
project is otherwise disposed of under
the FPA.
Dated: July 13, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–15316 Filed 7–18–23; 8:45 am]
BILLING CODE 6717–01–P
1 18
E:\FR\FM\19JYN1.SGM
CFR 385.216(b) (2022).
19JYN1
Agencies
[Federal Register Volume 88, Number 137 (Wednesday, July 19, 2023)]
[Notices]
[Page 46151]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-15316]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 3309-022]
Marlow Hydro, LLC; Notice of Effectiveness of Withdrawal of
Application for Surrender and of Ongoing Effectiveness of Authorization
for Continued Project Operation
On June 17, 2022, the Marlow Hydro, LLC, filed an application for
surrender of the Nash Mill Dam Hydroelectric Project No. 3309. On June
20, 2023, the Marlow Hydro, LLC, filed a request to withdraw its
surrender application.
No motion in opposition to the request for withdrawal has been
filed, and the Commission has taken no action to disallow the
withdrawal. Pursuant to Rule 216(b) of the Commission's Rules of
Practice and Procedure,\1\ the withdrawal of the application became
effective on July 5, 2023, and this proceeding is hereby terminated.
---------------------------------------------------------------------------
\1\ 18 CFR 385.216(b) (2022).
---------------------------------------------------------------------------
The Commission issued Notice of Authorization for Continued Project
Operation on December 22, 2022. Accordingly, Marlow Hydro, LLC, has
been authorized to continue operation of the Nash Mill Dam
Hydroelectric Project under the terms and conditions of the prior
license until the issuance of a new license for the project or the
project is otherwise disposed of under the FPA.
Dated: July 13, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023-15316 Filed 7-18-23; 8:45 am]