Great Basin Gas Transmission Company; Notice of Schedule for the Preparation of an Environmental Assessment for the 2024 Expansion Project, 45202 [2023-14987]

Download as PDF 45202 Federal Register / Vol. 88, No. 134 / Friday, July 14, 2023 / Notices Project Description DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP23–466–000] Great Basin Gas Transmission Company; Notice of Schedule for the Preparation of an Environmental Assessment for the 2024 Expansion Project On May 1, 2023, Great Basin Gas Transmission Company (Great Basin) filed an application in Docket No. CP23–466–000 requesting a Certificate of Public Convenience and Necessity pursuant to section 7(c) and Authorization pursuant to section 7(b) of the Natural Gas Act to construct, operate, and abandon certain natural gas pipeline facilities. The proposed project is known as the 2024 Expansion Project (Project), and would provide 5,674 dekatherms per day of incremental firm transportation service for two existing firm transportation shippers. The expansion would require construction of approximately 3.41 miles of upsized or looped pipeline segments across Douglas, Lyon, and Storey Counties, Nevada. On May 15, 2023, the Federal Energy Regulatory Commission (Commission or FERC) issued its Notice of Application for the Project. Among other things, that notice alerted agencies issuing federal authorizations of the requirement to complete all necessary reviews and to reach a final decision on a request for a federal authorization within 90 days of the date of issuance of the Commission staff’s environmental document for the Project. This notice identifies Commission staff’s intention to prepare an environmental assessment (EA) for the Project and the planned schedule for the completion of the environmental review.1 Schedule for Environmental Review Issuance of EA—November 28, 2023 90-day Federal Authorization Decision Deadline 2—February 26, 2024 If a schedule change becomes necessary, additional notice will be provided so that the relevant agencies are kept informed of the Project’s progress. lotter on DSK11XQN23PROD with NOTICES1 1 40 CFR 1501.10 (2020). 2 The Commission’s deadline applies to the decisions of other federal agencies, and state agencies acting under federally delegated authority, that are responsible for federal authorizations, permits, and other approvals necessary for proposed projects under the Natural Gas Act. Per 18 CFR 157.22(a), the Commission’s deadline for other agency’s decisions applies unless a schedule is otherwise established by federal law. VerDate Sep<11>2014 17:54 Jul 13, 2023 Jkt 259001 Great Basin proposes to: (1) construct approximately 0.25 mile of 20-inchdiameter pipeline loop along its Carson Lateral in Storey County, Nevada, referred to as the Truckee Canal segment; (2) abandon and replace approximately 2.88 miles of existing 10inch-diameter pipeline with new 20inch-diameter pipeline along the Carson Lateral in Lyon County, Nevada, referred to as the Silver Springs segment; and (3) construct approximately 0.28 mile of 12-inchdiameter pipeline loop paralleling its South Tahoe Lateral in Douglas County, Nevada, referred to as the Kingsbury segment. Additionally, Great Basin would install new aboveground valves and associated piping at its existing White Sage Pressure Limiting Station and at the Fort Churchill Valve Assembly on the Silver Springs pipeline segment in Lyon County, Nevada. Great Basin would also install one new belowground valve assembly and a below-ground hot tap at the terminus point of the Kingsbury pipeline segment in Douglas County, Nevada. Background On June 15, 2023, the Commission issued a Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Great Basin 2024 Expansion Project (Notice of Scoping). The Notice of Scoping was sent to affected landowners; federal, state, and local government agencies; elected officials; environmental and public interest groups; Native American tribes; other interested parties; and local libraries and newspapers. In response to the Notice of Scoping, the Commission received comments in support of the Project from Southwest Gas Corporation and comments in protest from the Office of the Nevada Attorney General, Bureau of Consumer Protection. The primary issues raised by the Nevada Attorney General are associated with project need, capacity, and rates. All substantive environmental comments will be addressed in the EA. The Bureau of Land Management is a cooperating agency in the preparation of the EA. Additional Information In order to receive notification of the issuance of the EA and to keep track of formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This service provides automatic notification of filings made to subscribed dockets, document summaries, and direct links PO 00000 Frm 00075 Fmt 4703 Sfmt 4703 to the documents. Go to https:// www.ferc.gov/ferc-online/overview to register for eSubscription. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Additional information about the Project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the ‘‘eLibrary’’ link, select ‘‘General Search’’ from the eLibrary menu, enter the selected date range and ‘‘Docket Number’’ excluding the last three digits (i.e., CP23–466), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Dated: July 10, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–14987 Filed 7–13–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP23–492–000] Florida Gas Transmission Company, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed South Louisiana Project The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental document, that will discuss the environmental impacts of the South Louisiana Project involving construction and operation of facilities by Florida Gas Transmission Company, LLC (FGT) in St. Landry, East Baton Rouge, and Washington Parishes, Louisiana and Perry County, Mississippi. The Commission will use E:\FR\FM\14JYN1.SGM 14JYN1

Agencies

[Federal Register Volume 88, Number 134 (Friday, July 14, 2023)]
[Notices]
[Page 45202]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-14987]



[[Page 45202]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP23-466-000]


Great Basin Gas Transmission Company; Notice of Schedule for the 
Preparation of an Environmental Assessment for the 2024 Expansion 
Project

    On May 1, 2023, Great Basin Gas Transmission Company (Great Basin) 
filed an application in Docket No. CP23-466-000 requesting a 
Certificate of Public Convenience and Necessity pursuant to section 
7(c) and Authorization pursuant to section 7(b) of the Natural Gas Act 
to construct, operate, and abandon certain natural gas pipeline 
facilities. The proposed project is known as the 2024 Expansion Project 
(Project), and would provide 5,674 dekatherms per day of incremental 
firm transportation service for two existing firm transportation 
shippers. The expansion would require construction of approximately 
3.41 miles of upsized or looped pipeline segments across Douglas, Lyon, 
and Storey Counties, Nevada.
    On May 15, 2023, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
environmental document for the Project.
    This notice identifies Commission staff's intention to prepare an 
environmental assessment (EA) for the Project and the planned schedule 
for the completion of the environmental review.\1\
---------------------------------------------------------------------------

    \1\ 40 CFR 1501.10 (2020).
---------------------------------------------------------------------------

Schedule for Environmental Review

Issuance of EA--November 28, 2023
90-day Federal Authorization Decision Deadline \2\--February 26, 2024
---------------------------------------------------------------------------

    \2\ The Commission's deadline applies to the decisions of other 
federal agencies, and state agencies acting under federally 
delegated authority, that are responsible for federal 
authorizations, permits, and other approvals necessary for proposed 
projects under the Natural Gas Act. Per 18 CFR 157.22(a), the 
Commission's deadline for other agency's decisions applies unless a 
schedule is otherwise established by federal law.
---------------------------------------------------------------------------

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    Great Basin proposes to: (1) construct approximately 0.25 mile of 
20-inch-diameter pipeline loop along its Carson Lateral in Storey 
County, Nevada, referred to as the Truckee Canal segment; (2) abandon 
and replace approximately 2.88 miles of existing 10-inch-diameter 
pipeline with new 20-inch-diameter pipeline along the Carson Lateral in 
Lyon County, Nevada, referred to as the Silver Springs segment; and (3) 
construct approximately 0.28 mile of 12-inch-diameter pipeline loop 
paralleling its South Tahoe Lateral in Douglas County, Nevada, referred 
to as the Kingsbury segment. Additionally, Great Basin would install 
new aboveground valves and associated piping at its existing White Sage 
Pressure Limiting Station and at the Fort Churchill Valve Assembly on 
the Silver Springs pipeline segment in Lyon County, Nevada. Great Basin 
would also install one new belowground valve assembly and a below-
ground hot tap at the terminus point of the Kingsbury pipeline segment 
in Douglas County, Nevada.

Background

    On June 15, 2023, the Commission issued a Notice of Scoping Period 
Requesting Comments on Environmental Issues for the Proposed Great 
Basin 2024 Expansion Project (Notice of Scoping). The Notice of Scoping 
was sent to affected landowners; federal, state, and local government 
agencies; elected officials; environmental and public interest groups; 
Native American tribes; other interested parties; and local libraries 
and newspapers. In response to the Notice of Scoping, the Commission 
received comments in support of the Project from Southwest Gas 
Corporation and comments in protest from the Office of the Nevada 
Attorney General, Bureau of Consumer Protection. The primary issues 
raised by the Nevada Attorney General are associated with project need, 
capacity, and rates. All substantive environmental comments will be 
addressed in the EA.
    The Bureau of Land Management is a cooperating agency in the 
preparation of the EA.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of formal issuances and submittals in specific dockets, the 
Commission offers a free service called eSubscription. This service 
provides automatic notification of filings made to subscribed dockets, 
document summaries, and direct links to the documents. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or [email protected].
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the ``eLibrary'' link, select 
``General Search'' from the eLibrary menu, enter the selected date 
range and ``Docket Number'' excluding the last three digits (i.e., 
CP23-466), and follow the instructions. For assistance with access to 
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at [email protected]. The eLibrary link on the FERC 
website also provides access to the texts of formal documents issued by 
the Commission, such as orders, notices, and rule makings.

    Dated: July 10, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-14987 Filed 7-13-23; 8:45 am]
BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.