Transmission System Planning Performance Requirements for Extreme Weather, 41262-41287 [2023-13286]
Download as PDF
41262
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
18 CFR Part 40
[Docket No. RM22–10–000; Order No. 896]
Transmission System Planning
Performance Requirements for
Extreme Weather
Federal Energy Regulatory
Commission, Department of Energy.
ACTION: Final rule.
AGENCY:
The Federal Energy
Regulatory Commission directs the
North American Electric Reliability
Corporation, the Commission-certified
Electric Reliability Organization, to
develop a new or modified Reliability
Standard no later than 18 months of the
SUMMARY:
date of publication of this final rule in
the Federal Register to address
reliability concerns pertaining to
transmission system planning for
extreme heat and cold weather events
that impact the Reliable Operation of
the Bulk-Power System. Specifically, we
direct the North American Electric
Reliability Corporation to develop a new
or modified Reliability Standard that
requires the following: development of
benchmark planning cases based on
prior extreme heat and cold weather
events and/or future meteorological
projections; planning for extreme heat
and cold events using steady state and
transient stability analyses that cover a
range of extreme weather scenarios,
including the expected resource mix’s
availability during extreme weather
conditions and the broad area impacts
of extreme weather; and corrective
action plans that include mitigation
activities for specified instances where
performance requirements during
extreme heat and cold events are not
met.
This rule is effective September
21, 2023.
FOR FURTHER INFORMATION CONTACT:
Mahmood Mirheydar (Technical
Information), Office of Electric
Reliability, Federal Energy Regulatory
Commission, 888 First Street NE,
Washington, DC 20426, (202) 502–
8034, mahmood.mirheydar@ferc.gov
Gonzalo E. Rodriguez (Legal
Information), Office of the General
Counsel, Federal Energy Regulatory
Commission, 888 First Street NE,
Washington, DC 20426, (202) 502–
8568, gonzalo.rodriguez@ferc.gov
SUPPLEMENTARY INFORMATION:
DATES:
Table of Contents
lotter on DSK11XQN23PROD with RULES3
Paragraph
Nos.
Introduction ..............................................................................................................................................................................................
II. Background ...........................................................................................................................................................................................
A. Legal Authority .............................................................................................................................................................................
B. Reliability Standard TPL–001–5.1 (Transmission System Planning Performance Requirements) ..........................................
C. Prior Commission Actions To Address the Reliability Impacts of Extreme Weather ..............................................................
D. Notice of Proposed Rulemaking ..................................................................................................................................................
III. The Need for Reform ..........................................................................................................................................................................
IV. Discussion ...........................................................................................................................................................................................
A. Directive to NERC To Develop New or Modified Reliability Standard ....................................................................................
B. Develop Benchmark Events and Planning Cases Based on Major Prior Extreme Heat and Cold Weather Events and/or
Meteorological Projections ............................................................................................................................................................
1. Comments ...............................................................................................................................................................................
2. Commission Determination ...................................................................................................................................................
C. Definition of ‘‘Wide-Area’’ ...........................................................................................................................................................
1. Comments ...............................................................................................................................................................................
2. Commission Determination ...................................................................................................................................................
D. Entities Responsible for Developing Benchmark Events and Planning Cases, and for Conducting Transmission Planning
Studies of Wide-Area Events ........................................................................................................................................................
1. Comments ...............................................................................................................................................................................
a. Entity Responsible for Development of Benchmark Events .........................................................................................
b. Entity Responsible for Development of Planning Cases and Conducting Transmission Planning Studies of
Wide-Area Events ............................................................................................................................................................
2. Commission Determination ...................................................................................................................................................
a. Entity Responsible for Establishing Benchmark Events ...............................................................................................
b. Entities Responsible for Development of Planning Cases and Conducting Transmission Planning Studies of
Wide-Area Events ............................................................................................................................................................
E. Coordination Among Registered Entities and Sharing of Data and Study Results ..................................................................
1. Comments ...............................................................................................................................................................................
2. Commission Determination ...................................................................................................................................................
F. Concurrent/Correlated Generator and Transmission Outages ....................................................................................................
1. Comments ...............................................................................................................................................................................
2. Commission Determination ...................................................................................................................................................
G. Conduct Transmission System Planning Studies for Extreme Heat and Cold Weather Events ..............................................
1. Steady State and Transient Stability Analyses ....................................................................................................................
a. Comments ........................................................................................................................................................................
b. Commission Determination ............................................................................................................................................
2. Sensitivity Analysis ...............................................................................................................................................................
a. Comments ........................................................................................................................................................................
b. Commission Determination ............................................................................................................................................
3. Modifications to the Traditional Planning Approach .........................................................................................................
a. Comments ........................................................................................................................................................................
b. Commission Determination ............................................................................................................................................
H. Implement a Corrective Action Plan if Performance Standards Are Not Met .........................................................................
1. Comments ...............................................................................................................................................................................
a. Jurisdictional Issues ........................................................................................................................................................
b. Corrective Action Plans ..................................................................................................................................................
c. Generation and Transmission Capacity Increase and Resource Adequacy Issues .....................................................
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
PO 00000
Frm 00002
Fmt 4701
Sfmt 4700
E:\FR\FM\23JNR3.SGM
23JNR3
1
8
8
10
14
17
20
25
25
30
32
35
41
44
50
51
53
53
54
58
58
60
63
66
72
78
82
88
95
95
98
111
118
121
124
127
131
134
139
143
143
144
148
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
41263
Paragraph
Nos.
d. Notification to Applicable Regulatory Authorities or Governing Bodies Responsible for Retail Electric Service
Issues ................................................................................................................................................................................
2. Commission Determination ...................................................................................................................................................
a. Jurisdictional Issues ........................................................................................................................................................
b. Circumstances That Require Corrective Action Plans ..................................................................................................
c. Generation and Transmission Capacity Increase and Resource Adequacy Issues .....................................................
d. Notification to Applicable Regulatory Authorities or Governing Bodies Responsible for Retail Electric Service
Issues ................................................................................................................................................................................
I. Other Extreme Weather-Related Events and Issues .....................................................................................................................
1. Comments ...............................................................................................................................................................................
2. Commission Determination ...................................................................................................................................................
J. Reliability Standard Development and Implementation Timeline .............................................................................................
1. Comments ...............................................................................................................................................................................
2. Commission Determination ...................................................................................................................................................
V. Information Collection Statement .......................................................................................................................................................
VI. Environmental Analysis .....................................................................................................................................................................
VII. Regulatory Flexibility Act .................................................................................................................................................................
VIII. Document Availability .....................................................................................................................................................................
IX. Effective Date and Congressional Notification .................................................................................................................................
Appendix A: Commenter Names.
I. Introduction
1. Pursuant to section 215(d)(5) of the
Federal Power Act (FPA),1 the
Commission directs the North American
Electric Reliability Corporation (NERC),
the Commission-certified Electric
Reliability Organization (ERO), to
submit a new Reliability Standard or
modifications to Reliability Standard
TPL–001–5.1 that addresses concerns
pertaining to transmission system
planning for extreme heat and cold
weather events that impact the Reliable
Operation 2 of the Bulk-Power System.3
2. We take this action to address
challenges associated with planning for
extreme heat and cold weather events,
particularly those that occur during
periods when the Bulk-Power System
must meet unexpectedly high demand.4
Extreme heat and cold weather events
have occurred with greater frequency in
recent years, and are projected to occur
with even greater frequency in the
1 16
U.S.C. 824o(d)(5).
FPA defines ‘‘Reliable Operation’’ as
‘‘operating the elements of the Bulk-Power System
within equipment and electric system thermal,
voltage, and stability limits so that instability,
uncontrolled separation, or cascading failures of
such system will not occur as a result of a sudden
disturbance, including a cybersecurity incident, or
unanticipated failure of system elements.’’ 16
U.S.C. 824o(a)(4).
3 The Bulk-Power System is defined in the FPA
as ‘‘facilities and control systems necessary for
operating an interconnected electric energy
transmission network (or any portion thereof), and
electric energy from generating facilities needed to
maintain transmission system reliability. The term
does not include facilities used in the local
distribution of electric energy.’’ Id. 824o(a)(1).
4 Technical Conference June 1–2, 2021, Climate
Change, Extreme Weather, and Electric System
Reliability, Docket No. AD21–13–000 (June 1–2,
2021), June 1, 2021 Tr. 26: 3–7 (Derek Stenclik,
Founding Partner, Telos Energy, Inc.), 31:7–8 (Judy
Chang, Undersecretary of Energy, Massachusetts).
lotter on DSK11XQN23PROD with RULES3
2 The
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
future.5 These events have shown that
load shed during extreme temperature
result in unacceptable risk to life and
have extreme economic impact.6 As
such, the impact of concurrent failures
of Bulk-Power System generation and
transmission equipment and the
potential for cascading outages 7 that
may be caused by extreme heat and cold
weather events should be studied and
corrective actions should be identified
and implemented.
3. At the Commission’s June 1–2,
2021 technical conference on Climate
Change, Extreme Weather, and Electric
System Reliability, there was consensus
among panelists that planners cannot
simply project historical weather
patterns forward to effectively forecast
the future, since climate change has
made the use of historical weather
observations no longer representative of
5 See e.g., Environmental Protection Agency,
Climate Change Indicators: Weather and Climate
(May 12, 2021) (EPA Climate Change Indicators),
https://www.epa.gov/climate-indicators/weatherclimate (showing an upward trend in extreme heat
and cold weather events). NOAA, Adam Smith,
2022 U.S. Billion-dollar Weather and Climate
Disasters in Historical Context (Jan. 10, 2023),
https://www.climate.gov/news-features/blogs/2022us-billion-dollar-weather-and-climate-disastershistorical-context.
6 FERC, NERC, and Regional Entity Staff, The
February 2021 Cold Weather Outages in Texas and
the South Central United States, at 9, 192 (Nov. 16,
2021), https://www.ferc.gov/media/february-2021cold-weather-outages-texas-and-south-centralunited-states-ferc-nerc-and (2021 Cold Weather
Event Report).
7 NERC Glossary of Terms Used in Reliability
Standards (Updated Mar. 8, 2023) (NERC Glossary).
NERC defines ‘‘cascading’’ as, the ‘‘uncontrolled
successive loss of System Elements triggered by an
incident at any location. Cascading results in
widespread electric service interruption that cannot
be restrained from sequentially spreading beyond
an area predetermined by studies.’’
PO 00000
Frm 00003
Fmt 4701
Sfmt 4700
151
152
154
157
161
165
169
170
177
181
182
188
194
196
197
200
203
future conditions.8 For example,
extreme summer heat in regions like the
Pacific Northwest and extreme winter
cold in regions like Texas have
increased demand for electricity at
times when historically demand has
been low.9 As events such as these will
likely continue to present challenges in
the future, transmission planners and
planning coordinators must account for
this new reality in their planning
processes.10
4. Since 2011, the country has
experienced at least seven major
extreme heat and cold weather events,11
each of which put stress on the BulkPower System and resulted in some
degree of load shed. In some cases, these
events nearly caused system collapse
8 June 1, 2021 Tr. 30:2–3 (Chang), 31:12–18 (Lisa
Barton, Executive Vice President/Chief Operating
Officer, American Electric Power).
9 June 1, 2021 Tr. 31:1–6 (Chang); June 2, 2021 Tr.
72:8–10 (Amanda Frazier, Senior Vice President of
Regulatory Policy, Vista Corp.); 9:1–5 (Wesley
Yeomans, Vice President of Operations, New York
Independent System Operator, Inc. (NYISO))
(noting that in New York the majority of the
extreme conditions were cold weather related but
that there can be heat waves in New York City, and
more heat waves are expected).
10 June 1, 2021 Tr. 35:1–6 (Chang). See also US
News, Blackouts in US Northwest Due to Heat
Wave, Deaths Reported (June 29, 2021), https://
www.usnews.com/news/business/articles/2021-0629/rolling-blackouts-for-parts-of-us-northwestamid-heat-wave; Judah Cohen et al., Linking Arctic
Variability and Change With Extreme Winter
Weather in the United States, 373 Sci. 1116, 1120
(2021), (a study connecting the 2021 extreme cold
weather event in Texas and the South-central
United States to global warming-induced weather
anomalies that are likely to continue to produce
severe winter storm events).
11 See Transmission System Planning
Performance Requirements for Extreme Weather,
Notice of Proposed Rulemaking, 87 FR 38,020 (June
27, 2023), 179 FERC ¶ 61,195 at PP 24–36 (2022)
(NOPR) (discussing these prior events in detail).
E:\FR\FM\23JNR3.SGM
23JNR3
41264
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
lotter on DSK11XQN23PROD with RULES3
and uncontrolled blackouts, which were
avoided due to system operator actions.
5. Given the reliability risks
associated with extreme heat and cold
weather events, including the potential
for widespread blackouts, maintaining
the reliability of the Bulk-Power System
requires transmission system planning
to account for the potential impact of
extreme heat and cold weather over
wide geographical areas, and to consider
the changing resource mix. Reliability
Standard TPL–001–4 12 was developed
to establish transmission system
planning performance requirements that
ensure that the Bulk-Power System
operates reliably over a broad spectrum
of system conditions and following a
wide range of probable contingencies.13
Both it and its successor, TPL–001–5.1,
include provisions for transmission
planners and planning coordinators to
study system performance under
extreme events based on their
experience; 14 however, neither standard
specifically requires entities to conduct
performance analysis for extreme heat
and cold weather, despite the fact that
such conditions have clearly
demonstrated a risk to the Reliable
Operation of the Bulk-Power System,
thus leaving a reliability gap in system
planning.
6. To address this reliability gap, we
direct NERC to develop a new or
modified Reliability Standard that
requires the following: (1) the
development of benchmark planning
cases based on information such as
major prior extreme heat and cold
weather events and/or future
meteorological projections; (2) planning
for extreme heat and cold weather
events using steady state and transient
stability analyses expanded to cover a
range of extreme weather scenarios,
including expected availability of the
resource mix during extreme heat and
cold weather conditions, and including
the broad area impacts of extreme heat
and cold weather; and (3) the
development of corrective action plans
that mitigate specified instances where
performance requirements during
extreme heat and cold weather events
are not met. In directing NERC to
develop a new or modified Reliability
Standard, we are not proposing specific
requirements. Instead, we identify
concerns that should be addressed by
the proposed Reliability Standard.
12 Effective July 1, 2023, Reliability Standard
TPL–001–4 will be replaced by Reliability Standard
TPL–001–5.1. Unless otherwise specified, the use of
Reliability Standard TPL–001–5.1 in this final rule
also refers to its predecessor, Reliability Standard
TPL–001–4.
13 Reliability Standard TPL–001–5, at 1.
14 Id. at tbl. 1.
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
NERC may propose to develop a new or
modified Reliability Standard that
address our concerns in an equally
efficient and effective manner; however,
NERC’s proposal should explain how it
addresses the Commission’s concerns.15
7. We direct NERC to submit the
proposed new or modified Reliability
Standard no later than 18 months from
the publication of this final rule in the
Federal Register. We believe that an 18month deadline provides sufficient time
for NERC to develop a responsive
Standard in consideration of the issues
involved and the steps in NERC’s
standards development process.
Further, we direct NERC to ensure that
the proposed new or modified
Reliability Standard becomes mandatory
and enforceable beginning no later than
12 months from the effective date of
Commission approval of the new or
modified Reliability Standard.
II. Background
A. Legal Authority
8. Section 215 of the FPA provides
that the Commission may certify an
ERO, the purpose of which is to develop
mandatory and enforceable Reliability
Standards, subject to Commission
review and approval.16 Reliability
Standards may be enforced by the ERO,
subject to Commission oversight, or by
the Commission independently.17
Pursuant to section 215 of the FPA, the
Commission established a process to
select and certify an ERO,18 and
subsequently certified NERC.19
9. Pursuant to section 215(d)(5) of the
FPA, the Commission has the authority,
upon its own motion or upon
complaint, to order the ERO to submit
to the Commission a proposed
Reliability Standard or a modification to
a Reliability Standard that addresses a
specific matter if the Commission
15 See e.g., Mandatory Reliability Standards for
the Bulk-Power Sys., Order No. 693, 72 FR 16416
(Apr. 4, 2007), 118 FERC ¶ 61,218, at PP 186, 297,
order on reh’g, Order No. 693–A, 72 FR 40717 (July
25, 2007), 120 FERC ¶ 61,053 (2007) (‘‘where the
Final Rule identifies a concern and offers a specific
approach to address the concern, we will consider
an equivalent alternative approach provided that
the ERO demonstrates that the alternative will
address the Commission’s underlying concern or
goal as efficiently and effectively as the
Commission’s proposal’’).
16 16 U.S.C. 824o(c).
17 Id. 824o(e).
18 Rules Concerning Certification of the Elec.
Reliability Org. & Procedures for the Establishment,
Approval, & Enf’t. of Elec. Reliability Standards,
Order No. 672, 71 FR 8662 (Feb. 17, 2006), 114
FERC ¶ 61,104, order on reh’g, Order No. 672–A, 71
FR 19814 (Apr. 18, 2006), 114 FERC ¶ 61,328
(2006).
19 N. Am. Elec. Reliability Corp., 116 FERC
¶ 61,062, order on reh’g and compliance, 117 FERC
¶ 61,126 (2006), aff’d sub nom. Alcoa, Inc. v. FERC,
564 F.3d 1342 (D.C. Cir. 2009).
PO 00000
Frm 00004
Fmt 4701
Sfmt 4700
considers such a new or modified
Reliability Standard appropriate to carry
out section 215 of the FPA.20 Further,
pursuant to § 39.5(g) of the
Commission’s regulations, the
Commission may order a deadline by
which the ERO must submit a proposed
or modified Reliability Standard, or
when ordering the ERO to submit to the
Commission a proposed Reliability
Standard that addresses a specific
matter.21
B. Reliability Standard TPL–001–5.1
(Transmission System Planning
Performance Requirements)
10. Transmission system planning
refers to the evaluation of future
transmission system performance and
creation of corrective action plans that
include mitigation to remedy identified
deficiencies.22 The planning horizon
associated with transmission system
planning covers near term (one to five
years), long-term (six to ten years), and
beyond.23
11. Reliability Standard TPL–001–5.1
establishes minimum transmission
system planning performance
requirements to plan a Bulk-Power
System that will operate reliably over a
broad spectrum of system conditions
and following a wide range of probable
contingencies.24 Under Requirement R2
of Reliability Standard TPL–001–5.1,
each transmission planner and planning
coordinator must prepare an annual
planning assessment for its portion of
the Bulk-Power System.25 This planning
assessment is required for both nearterm and long-term transmission
planning horizons.26
12. Requirements R3 and R4 of
Reliability Standard TPL–001–5.1
20 16
U.S.C. 824o(d)(5).
CFR 39.5(g) (2022).
22 NERC Glossary (defining ‘‘Planning
Assessment’’ as ‘‘documented evaluation of future
Transmission System performance and Corrective
Action Plans to remedy identified deficiencies’’).
23 Id. (defining ‘‘Near-Term Transmission
Planning Horizon’’ and ‘‘Long-Term Transmission
Planning Horizon’’).
24 Reliability Standard TPL–001–5.1, Purpose.
25 Id., at Requirement 2. Further, steady-state
analyses are a snapshot in time where load and
system conditions (e.g., generators, lines, facilities)
are modeled as constant (not as changing over
time). The analysis will either solve (converge
numerically) or not solve (diverge numerically). See
IEEE, Transactions on Power Systems, Vol. 19, No.
2, (May 2004) (power system stability is the ability
of an electric power system, for a given initial
operating condition, to regain a state of operating
equilibrium after being subjected to a physical
disturbance, with most system variables bounded so
that practically the entire system remains intact);
see also, Kundur, Prabha, Power System Stability
and Control, McGraw Hill, at 26 (1994).
26 See Reliability Standard TPL–001–5.1, at
Requirement 2.1 (Near-Term Transmission Planning
Horizon) and Requirement R.2.2 (Long-Term
Transmission Planning Horizon).
21 18
E:\FR\FM\23JNR3.SGM
23JNR3
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
require in part that planning
coordinators and transmission planners
conduct steady state and stability
studies of pre-specified extreme events
and evaluate possible actions designed
to reduce the likelihood or mitigate the
consequences and adverse impacts of
the event(s), if the analysis concludes
that the pre-selected extreme events
cause cascading outages.
13. Table 1 of Reliability Standard
TPL–001–5.1 includes a list of examples
of planning events (i.e., Category P1
through P7) 27 for which specific studies
may be required based on the entity’s
own evaluation that such an event could
occur within its operating area. Section
3.a of Table-1 (Steady State & Stability
Performance Extreme Events) states that
steady state analysis should be
conducted for wide-area events affecting
the transmission system based on
system configuration and how it can be
affected by events such as wildfires and
severe weather (e.g., hurricanes and
tornadoes). In addition, section 3.b
serves as a catch-all provision, stating
that steady state analysis should be
performed for ‘‘other events based upon
operating experience that may result in
wide-area disturbances.’’
lotter on DSK11XQN23PROD with RULES3
C. Prior Commission Actions To
Address the Reliability Impacts of
Extreme Weather
14. On June 1 and 2, 2021, the
Commission convened a staff-led
technical conference on Climate
Change, Extreme Weather, and Electric
System Reliability.28 The Commission
sought to understand, among other
things, whether further action from the
Commission is needed to help achieve
an electric system that can withstand,
respond to, and recover from extreme
weather events.29
15. In the pre- and post-conference
comments, industry experts agreed that
extreme weather events are likely to
become more severe and frequent in the
future.30 They also acknowledged the
challenges associated with planning for
extreme events, including shifting
scheduled maintenance and canceling
or recalling transmission and generation
assets from scheduled maintenance to
meet demand under unexpected
27 Categories P1 through P7 are defined in TPL–
001–5.1 in Table 1—Steady State & Stability
Performance Planning Events.
28 Climate Change, Extreme Weather, and Electric
System Reliability, Notice of Technical Conference,
Docket No. AD21–13–000, at 1 (Mar. 5, 2021).
29 Id. at 2.
30 CAISO Pre-Conference Comments at 1–3;
California Public Utilities Commission PreConference Comments at 4; Oregon Public Utilities
Commission Pre-Conference Comments at 2–3;
NYISO Pre-Conference Comments at 4; AEP PreConference Comments at 5.
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
circumstances.31 Further, commenters
discussed potential changes to the
Reliability Standards to address
planning and operational preparedness
for energy adequacy risks,32
contingencies related to extreme
weather events, and wide-area
transmission planning and development
challenges, among others.33 Comments
also addressed more directly the
potential reliability gaps in the existing
set of Reliability Standards, including
Reliability Standard TPL–001–4, and
identified potential solutions.34
16. On August 24, 2021, and February
16, 2023, the Commission approved
revised Reliability Standards to address
some of the reliability risks posed by
extreme cold weather.35 These
Reliability Standards, among other
things, require generators to implement
plans for cold weather preparedness and
implement freeze protection measures
to mitigate the reliability impacts of
extreme cold weather on their
generating units. The new and revised
standards also require the balancing
authority, transmission operator, and
reliability coordinator to plan and
operate the grid reliably during cold
weather conditions by requiring the
exchange of certain information related
to the generator’s capability to operate
under such conditions.36
D. Notice of Proposed Rulemaking
17. On June 26, 2022, the Commission
issued the Notice of Proposed
Rulemaking (NOPR) proposing to direct
NERC to develop a new or modified
Reliability Standard to address a lack of
a long term planning requirement for
extreme heat and cold weather events.37
Specifically, the Commission proposed
to direct NERC to develop either
modifications to Reliability Standard
TPL–001–5.1 or a new Reliability
31 June 2, 2021, Tr. at 21–23 (Wesley Yeomans,
Vice President of Operations, NYISO).
32 ISO-New England Inc. Pre-Conference
Comments at 10.
33 Midcontinent Independent System Operator
(MISO) Pre-Conference Comments at 4–5, 14–17.
34 See e.g., NERC Pre-Conference Comments at 6;
MISO Post-Conference Comments at 20; Pacific Gas
& Electric Company Pre-Conference Comments at
19–20; PJM Post-Conference Comments at 21;
CAISO Post-Conference Comments at 10.
35 N. Am. Elec. Reliability Corp., 176 FERC
¶ 61,119 (2021). The Commission approved
proposed Reliability Standards EOP–011–2
(Emergency Preparedness and Operations); IRO–
010–4 (Reliability Coordinator Data Specification
and Collection); and TOP–003–5 (Operational
Reliability Data) (collectively, the Cold Weather
Reliability Standards) and Order Approving
Extreme Cold Weather Reliability Standards EOP–
011–3 and EOP–012–1 and Directing Modification
of Reliability Standard EOP–012–1, 182 FERC
¶ 61,094 (2023).
36 Id. P 3.
37 NOPR, 179 FERC ¶ 61,195 at P 47.
PO 00000
Frm 00005
Fmt 4701
Sfmt 4700
41265
Standard, to require the following: (1)
development of benchmark planning
cases based on major prior extreme heat
and cold weather events and/or
meteorological projections; (2) planning
for extreme heat and cold weather
events using steady state and transient
stability analyses expanded to cover a
range of extreme weather scenarios
including the expected resource mix’s
availability during extreme heat and
cold weather conditions, and including
the wide-area impacts of extreme heat
and cold weather; and (3) development
of corrective action plans that mitigate
any instances where performance
requirements for extreme heat and cold
weather events are not met.38
18. The NOPR preliminarily found
that, based on the wide geographic
impacts on the Bulk-Power System of
previous extreme heat and cold weather
events, the study criteria for extreme
heat and cold events should include a
consideration of wide-area conditions
affecting neighboring regions and their
impact on one planning area’s ability to
rely on the resources of another region
during the weather event.39
19. The NOPR sought comments on
all aspects of the proposed directives,
including among others: (1) the
development of benchmark planning
cases; (2) requiring transmission
planning studies of wide-area extreme
heat and cold events; (3) the study of
concurrent generator and transmission
outages; (4) the analysis of sensitivities;
(5) modifications to current
deterministic planning approaches; (6)
coordination among registered entities
and sharing of study results; (7)
requiring entities to implement
corrective action plans if performance
standards are not met; and (8) whether
the final rule should address other
extreme weather events beyond heat
and cold events. The comment period
for the NOPR ended on August 26, 2022,
and the Commission received 33 sets of
comments.40
III. The Need for Reform
20. Extreme weather-related events
that spread across large portions of the
country over the past decade
demonstrate the challenges to
transmission planning from extreme
heat and cold weather patterns. The
NOPR discussed seven major extreme
heat and cold weather events that had
38 Id.
P 51.
P 67.
40 A list of commenters to the NOPR and the
abbreviated names used in this final rule appear in
Appendix A.
39 Id.
E:\FR\FM\23JNR3.SGM
23JNR3
41266
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
lotter on DSK11XQN23PROD with RULES3
occurred since 2011.41 Of these, four
(2011, 2013, 2018, and 2021) were
extreme cold weather events that nearly
caused system collapse if the operators
had not acted to shed load.42 The
remaining three events (2014, 2020, and
2021) were extreme heat weather events
that resulted in generation losses and
varying degrees of load shedding.43
Since the issuance of the NOPR, another
extreme cold weather event indicated
reliability challenges faced by the BulkPower System. In December 2022,
Winter Storm Elliott caused extreme
cold conditions that significantly
stressed the Bulk-Power System, forcing
some utilities to deploy rolling
blackouts to preserve Bulk-Power
System reliability.44 These extreme heat
and cold events demonstrate a risk to
Reliable Operation of the Bulk-Power
System.
21. While wide-area extreme heat and
cold weather events may not occur
every year, their frequency and
magnitude are expected to increase. The
National Oceanic and Atmospheric
Administration’s (NOAA) data and
analyses show an increasing trend in
extreme heat and cold weather events,45
and the U.S. Environmental Protection
Agency climate change indicators also
show upward trends in heatwave
frequency, duration, and intensity.46
NOAA states that climate change is also
driving more compound events, i.e.,
multiple extreme events occurring
simultaneously or successively, such as
concurrent heat waves and droughts,
and more extreme heat conditions in
cities.47
22. These conditions have created an
urgency to address the negative impact
of extreme weather on the reliability of
the Bulk-Power System. To that end, the
41 For a full discussion of these extreme weather
events, see NOPR, 179 FERC ¶ 61,195 at PP 24–33.
42 See e.g., FERC and NERC Staff Report, Outages
and Curtailments During the Southwest Cold
Weather Event of February 1–5, 2011, at 7 (Aug.
2011), https://www.ferc.gov/sites/default/files/202005/ReportontheSouthwestColdWeatherEventfrom
February2011Report.pdf (impacting nearly 4.4
million electric customers in ERCOT); 2013 PJM
Heat Wave Analysis at 5 (impacting approximately
45,000 customers in PJM).
43 See, e.g., 2021 Cold Weather Event Report at
133.
44 FERC, FERC, NERC to Open Joint Inquiry into
Winter Storm Elliott (Dec. 2022), https://
www.ferc.gov/news-events/news/ferc-nerc-openjoint-inquiry-winter-storm-elliott.
45 See NOAA., Nat’l Centers for Envtl. Info., U.S.
Billion-Dollar Weather and Climate Disasters
(2023), https://www.ncei.noaa.gov/access/billions/.
46 U.S. EPA, Climate Change Indicators in the
United States (last updated May 2, 2023), https://
www.epa.gov/climate-indicators.
47 NOAA, 2022 U.S. Billion Dollar Weather and
Climate Disasters in Historical Context (2023),
https://www.climate.gov/news-features/blogs/2022us-billion-dollar-weather-and-climate-disastershistorical-context.
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
directives to NERC in this final rule aim
to improve system planning specifically
for extreme heat and cold weather
events. The potential impact of
widespread extreme heat and cold
events on the reliability of the BulkPower System can be modeled and
studied in advance as part of near-term
and long-term transmission system
planning. Responsible entities could
then use the studies to develop
transmission system operational
strategies or corrective action plans with
mitigations that could be deployed in
preparation for extreme heat and cold
events.
23. The current transmission planning
Reliability Standards, however, do not
obligate transmission planners and
planning coordinators to consider
extreme hot and cold weather in their
transmission assessments. In particular,
Reliability Standard TPL–001–5.1
requires steady state and stability
analyses to be performed for certain
extreme events but does not require
steady state and stability analyses for
extreme heat and cold conditions.48
Likewise, while Reliability Standard
TPL–001–5.1 Table 1, provisions 2.f
(stability) and 3.b (steady state), requires
responsible entities to study events
based on operating experience that may
result in a wide-area disturbance,49 the
Standard does not specify the study of
extreme heat or cold conditions.
24. System planning measures alone
will not eliminate the reliability risk
associated with extreme heat and cold
events. The directives to improve
transmission planning discussed in this
final rule will prepare the Bulk-Power
System for extreme weather events in
the long term and will work together
with the requirements in the Cold
Weather Reliability Standards to
mitigate the near-term reliability impact
of extreme weather events. Improved
system planning will limit the impact of
such events and reduce the risk to the
reliability of the Bulk-Power System,
which prior events demonstrate is
significant.
IV. Discussion
A. Directive to NERC To Develop New
or Modified Reliability Standard
25. Pursuant to FPA section 215(d)(5),
we adopt the NOPR proposal and direct
NERC to submit a new Reliability
Standard or modifications to Reliability
Standard TPL–001–5.1 requiring
transmission system planning for
extreme heat and cold weather events
that impact the Reliable Operation of
48 See Reliability Standard TPL–001–5.1, at
Requirements R3 and R4 and Table 1.
49 Id. at Table 1, provisions 2.f and 3.b.
PO 00000
Frm 00006
Fmt 4701
Sfmt 4700
the Bulk-Power System. For the reasons
discussed in section III above, we
conclude that it is necessary to update
the transmission planning Reliability
Standard to reflect the impact of
extreme heat and cold weather events
on the reliability of the Bulk-Power
System. Most commenters support the
NOPR proposal to develop mandatory
transmission system planning
requirements for extreme heat and cold
weather events.50 Commenters also
agree that Commission action is
necessary to address the reliability gaps
pertaining to the consideration of
extreme heat and cold weather events
that exist in current transmission
planning processes.51
26. Although supportive of the need
to consider extreme weather in the
transmission planning process, PJM
Interconnection, L.L.C. (PJM) is critical
of the Commission’s proposed
‘‘piecemeal’’ approach and suggests that
the Commission harmonize this
rulemaking with other Commission
actions on transmission planning.52
While we agree that it is important for
NERC and applicable planning entities
to consider how requirements
implemented pursuant to this
rulemaking may interact with processes
carried out pursuant to other
Commission actions on transmission
planning, we disagree with PJM’s
suggestion that this proceeding is not an
appropriate forum for directing changes
to the NERC Reliability Standards.
While there is undoubtedly a nexus
between the long-term planning for
expected changes in resources and
demand as contemplated in Docket No.
RM21–17–000 and Reliability Standards
for extreme weather, each set of reforms
is subject to differing statutory schemes
and other considerations, and each aims
at related but distinct challenges. The
Commission’s transmission planning
reform efforts require individual
consideration, as they each concern
different transmission planning
objectives, time horizons, and areas of
Commission jurisdiction. This
proceeding is conducted pursuant to the
Commission’s jurisdiction under section
215 of the FPA and contemplates
transmission planning entity actions
that may be needed in the planning
timeframe of six to ten years and beyond
to mitigate the impacts of extreme
weather, whereas the proceeding in
Docket No. RM21–17–000 was initiated
50 See, e.g., MISO Transmission Owners
Comments at 1–2; Indicated Trade Associations
Comments at 1–2; NYISO Comments at 1–2; AEP
Comments at 1; ACP Comments at 1; PIOs
Comments at 1.
51 See, e.g., EPRI Comments at P 4.
52 PJM Comments at 3–4, 7.
E:\FR\FM\23JNR3.SGM
23JNR3
lotter on DSK11XQN23PROD with RULES3
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
pursuant to the Commission’s
jurisdiction under section 206 of the
FPA, considers a more fulsome range of
practices that may be required to render
rates just and reasonable, and
contemplates a planning horizon of 20
years.53 While addressing these related
efforts in a single proceeding may have
benefits, it also would risk complicating
the development of solutions and
making the process more unwieldy. The
Commission has thus determined to
take this step to facilitate solutions to
one aspect of the extreme weather
challenge, as part of a series of actions
that build on each other by seeking to
address the many areas that affect
extreme weather reliability.
27. Accordingly, we adopt the NOPR
proposal and direct NERC to develop a
new or modified Reliability Standard to
require the following: (1) development
of benchmark planning cases based on
major prior extreme heat and cold
weather events and/or meteorological
projections; (2) planning for extreme
heat and cold weather events using
steady state and transient stability
analyses expanded to cover a range of
extreme weather scenarios including the
expected resource mix’s availability
during extreme heat and cold weather
conditions, and including the wide-area
impacts of extreme heat and cold
weather; and (3) development of
corrective action plans that mitigate
specified instances where performance
requirements for extreme heat and cold
weather events are not met.54 We also
direct NERC to identify the responsible
entities for developing benchmark
planning cases and conducting widearea studies under the new or modified
Reliability Standard.
28. Given the importance of timely
addressing the identified reliability gap,
we direct NERC to submit the
responsive new or modified Reliability
Standard within 18 months of the date
of publication of this final rule in the
Federal Register. We further direct
NERC to develop a phased-in
implementation timeline for the
different requirements of the new or
modified Reliability Standard (i.e.,
developing benchmark planning cases,
conducting studies, developing
corrective action plans) that shall begin
within 12 months of the effective date
of a Commission order approving the
proposed Reliability Standard.
29. We address below in further detail
issues raised in the NOPR and in
53 See Building for the Future Through Elec. Reg’l
Transmission Planning & Cost Allocation &
Generator Interconnection, Notice of Proposed
Rulemaking, 87 FR 26504, (May 4, 2022), 179 FERC
¶ 61,028 (2022).
54 NOPR, 179 FERC ¶ 61,195 at P 51.
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
41267
comments regarding: (1) development of
benchmark events and planning cases;
(2) definition of ‘‘wide-area;’’ (3) entities
responsible for developing benchmark
events and conducting transmission
planning studies of wide-area events; (4)
coordination among registered entities
and sharing of data and study results;
(5) concurrent/correlated generator and
transmission outages; (6) conducting
transmission system planning studies
for extreme heat and cold weather
events; (7) corrective action plans; (8)
other extreme weather events; and (9)
Reliability Standard development and
implementation timeline.
information to be applied to preparing
for possible comparable future events,
these events would also serve as a basis
for effectively using assets and
resources. Specifically, once developed,
responsible entities would use the
benchmark events to develop
benchmark planning cases to conduct
studies to assess the limitations of the
transmission system locally and over a
wide-area, and to understand resource
availability and potential firm load
shedding requirements under stressed
conditions.58 The NOPR sought
comments on all aspects of the proposed
directive.
B. Develop Benchmark Events and
Planning Cases Based on Major Prior
Extreme Heat and Cold Weather Events
and/or Meteorological Projections
30. In the NOPR, the Commission
proposed to direct NERC to include in
the new or modified Reliability
Standard benchmark events that
responsible entities must study.55 The
NOPR proposed basing such benchmark
events on prior events (e.g., the
February 2011 Southwest Cold Weather
Event and the January 2014 Polar Vortex
Cold Weather Event) and/or
meteorological projections. Recognizing
that extreme weather risks may vary
from region to region and change over
time, the NOPR proposed to direct
NERC to consider approaches that
would provide a uniform framework for
developing benchmark events while still
recognizing regional differences; for
example, NERC could define benchmark
events around a projected frequency
(e.g., 1-in-50-year event) or probability
distribution (95th percentile event).56
Although the NOPR did not specify how
these benchmark events should be
developed, the NOPR provided two
examples: (1) NERC could develop the
benchmark event or events during the
standard development process; or (2)
NERC could include in the new or
modified Reliability Standard a
framework establishing a common
design basis for the development of
benchmark events. The NOPR also
suggested including in the modified
standard the primary features of the
benchmark event(s) while designating
NERC or another entity to periodically
update benchmark events.57
31. The NOPR also proposed that
establishing one or more benchmark
planning cases, based on benchmark
events, should form the basis for
sensitivity analysis. In addition to
providing valuable case study
1. Comments
32. Commenters generally agree with
the NOPR proposal to direct NERC to
develop requirements that address the
types of extreme heat and cold weather
scenarios that responsible entities are
required to study.59 Indicated Trade
Associations caution, however, that
universal benchmark events would be
hard to implement given regional
differences.60 As such, and consistent
with the NOPR proposal, Indicated
Trade Associations, APS, Bonneville
Power Administration (BPA), and Idaho
Power, among others, agree that regional
differences (e.g., climate, topology,
electrical characteristics) should be
considered in developing benchmark
events.61
33. Regarding how benchmark events
should be developed, NERC notes that
significant work will be necessary to
develop a uniform planning approach
that properly accounts for regional
differences in climate and weather
patterns, among other considerations.
Accordingly, NERC asks for flexibility
in developing benchmark events,
including considering options beyond
those identified in the NOPR.62
Indicated Trade Associations
recommend that NERC consider all the
examples of benchmark events
identified in the NOPR.63 PJM indicates
that developing benchmark events will
require scientific and meteorological
expertise to ensure that NERC
guidelines and criteria reflect
statistically valid scenarios for the
meteorological projections and their
possible impacts on transmission
planning. As such, PJM recommends
that the Commission engage the national
55 Id.
56 Id.
57 Id.
PO 00000
P 52.
P 53.
Frm 00007
Fmt 4701
Sfmt 4700
58 Id.
59 See, e.g., NERC Comments at 7–8; AEP
Comments at 7; Indicated Trade Associations
Comments at 8; NARUC Comments at 5.
60 Indicated Trade Associations Comments at 8.
61 See id.; APS Comments at 3; BPA Comments
at 3; Idaho Comments at 2.
62 NERC Comments at 8–9.
63 Indicated Trade Associations Comments at 8.
E:\FR\FM\23JNR3.SGM
23JNR3
41268
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
labs, Regional Transmission
Organizations (RTO), NOAA, and other
agencies to develop extreme weather
‘‘design threshold’’ metrics, as well as
investigate targeted planning thresholds
(e.g., 1-in-50-year events).64 Other
commenters highlight the necessity of
ensuring that benchmark events are not
only developed using historical extreme
heat and cold event data, but more
importantly use future meteorological
projections in order to prepare for
plausible extremes in future years.65
34. All those who submitted
comments regarding the NOPR proposal
to require periodic updates to
benchmark events agree with the need
to do so. For example, Union for
Concerned Scientists (UCS) points to
the scientific consensus that climate
change is altering the intensity and
frequency of extreme weather
conditions as a reason to require the
periodic update of benchmark events.66
American Electric Power Service
Corporation (AEP) recommends
updating the benchmark events every
three years, consistent with the
Commission’s proposed planning cycle
for regional transmission planning,
based on the most up-to-date data.67 In
contrast, Midcontinent Independent
System Operator, Inc. (MISO) suggests
that, consistent with similar
requirements in Reliability Standard
TPL–007–4 (Transmission System
Planned Performance for Geomagnetic
Disturbance Events) and Reliability
Standard PRC–006–5 (Automatic
Underfrequency Load Shedding)
extreme heat and cold weather
benchmark events should be updated
every five years.68 Other commenters
recommend that the key aspects of the
benchmark be updated periodically,
without opining on the periodicity of
updates.69
2. Commission Determination
35. Pursuant to section 215(d)(5) of
the FPA, we adopt the NOPR proposal
and direct NERC to: (1) develop extreme
heat and cold weather benchmark
events, and (2) require the development
of benchmark planning cases based on
identified benchmark events. Without
specific requirements describing the
types of heat and cold scenarios that
responsible entities must study, the new
64 PJM
Comments at 9.
e.g., EPRI Comments at P 5; Entergy
Comments at 3.
66 UCS Comments at 7.
67 AEP Comments at 3–4 (citing Docket No.
RM21–17–000).
68 MISO Comments at 3.
69 See, e.g., APS Comments at 3; Entergy
Comments at 4; Indicated Trade Associations
Comments at 8.
or modified Reliability Standard may
not provide a significant improvement
upon the status quo. Benchmark events
will provide a defined event that will
form the basis for assessing system
performance during extreme heat and
cold weather events. Benchmark events
will also form the basis for a planner’s
benchmark planning case—i.e., the base
case representing system conditions
under the relevant benchmark event—
that will be used to study the potential
wide-area impacts of anticipated
extreme heat and cold weather events.
36. Although the NOPR outlined some
of the Commission’s expectations for the
development of benchmark events,
including that benchmark events be
based on prior extreme heat and cold
events and/or meteorological
projections,70 there is currently no
established guidance or set of tools in
place to facilitate the development of
extreme heat and cold benchmark
events for the purpose of informing
transmission system planning. As
recommended by commenters, NERC
should consider the examples of
approaches for defining benchmark
events identified in the NOPR (e.g., the
use of projected frequency or probability
distribution).71 NERC may also consider
other approaches that achieve the
objectives outlined in this final rule.
Further, as recommended by PJM, we
believe there is value in engaging with
national labs, RTOs, NOAA, and other
agencies and organizations in
developing benchmark events.
Considering NERC’s key role, technical
expertise, and experience assessing the
reliability impacts of various events and
conditions, we encourage NERC to
engage with national labs, RTOs,
NOAA, and other agencies and
organizations as needed. To that end, as
discussed in section IV.J below, we have
modified the NOPR proposal to allow
more time for NERC to consider these
complex issues and engage additional
expertise where necessary.
37. Because the impact of most
extreme heat and cold events spans
beyond the footprints of individual
planning entities, it is important that all
responsible entities likely to be
impacted by the same extreme weather
events use consistent benchmark events.
Doing so is important to ensuring that
neighboring planning regions are
assuming similar weather conditions
lotter on DSK11XQN23PROD with RULES3
65 See,
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
70 For instance, a benchmark event could be
constructed based on data from a major prior
extreme heat or cold event, with adjustments if
necessary to account for the fact that future
meteorological projections may estimate that
similar events in the future are likely to be more
extreme.
71 See supra P 33.
PO 00000
Frm 00008
Fmt 4701
Sfmt 4700
and are able to coordinate their
assumptions accordingly. As a result,
defining the benchmark event in a
manner that provides responsible
entities significant discretion to
determine the applicable meteorological
conditions would not meet the
objectives of this final rule.
38. At the same time, because
different regions experience weather
conditions and their impacts differently,
a single benchmark event for the entire
Nation is unlikely to meet the objectives
of this final rule. Accordingly, in
developing extreme heat and cold
benchmark events, NERC shall ensure
that benchmark events reflect regional
differences in climate and weather
patterns.
39. We also direct NERC to include in
the Reliability Standard the framework
and criteria that responsible entities
shall use to develop from the relevant
benchmark event planning cases to
represent potential weather-related
contingencies (e.g., concurrent/
correlated generation and transmission
outages, derates) and expected future
conditions of the system such as
changes in load, transfers, and
generation resource mix, and impacts on
generators sensitive to extreme heat or
cold, due to the weather conditions
indicated in the benchmark events.
Developing such a framework would
provide a common design basis for
responsible entities to follow when
creating benchmark planning cases.
This would not only help establish a
clear set of expectations for responsible
entities to follow when developing
benchmark planning events, but also
facilitate auditing and enforcement of
the Standard.
40. We also direct NERC to ensure the
reliability standard contains appropriate
mechanisms for ensuring the benchmark
event reflects up-to-date meteorological
data. The increasing intensity,
frequency, and unpredictability of
extreme weather conditions requires
that key aspects of the benchmark
events be reviewed, and if necessary,
updated periodically to ensure the
corresponding benchmark planning
cases reflect updated meteorological
data. For example, a requirement that
defines a fixed benchmark event with
no provision for future updates (e.g.,
defining the benchmark event for a
responsible entity as the most severe
heat wave in the last twenty years
measured from the effective date of the
standard) may not provide an accurate
indicator of future risks. To the extent
NERC determines that the benchmark
event should be fixed or only updated
E:\FR\FM\23JNR3.SGM
23JNR3
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
periodically,72 we agree with MISO that
including a mechanism to update the
benchmark event at least every five
years would strike a reasonable balance
between the benefits of using the most
up-to-date meteorological data and
administrative the burdens of collecting
and analyzing such data.
C. Definition of ‘‘Wide-Area’’
41. In the NOPR, the Commission
proposed to direct NERC to require in a
new or modified Reliability Standard
that transmission planning studies
consider the wide-area impacts of
extreme heat and cold weather.73 The
NOPR explained that the impacts of
extreme weather events on the Reliable
Operation of the Bulk-Power System can
be widespread, potentially causing
simultaneous loss of generation and
increased transmission constraints
within and across regions.74 The NOPR
also pointed out that failure to study the
wide-area impact of extreme heat or
cold weather conditions in transmission
planning could result in reliability
issues affecting multiple regions or
multiple planning coordinator areas
remaining undetected in the long-term
planning horizon. This, in turn, could
lead to otherwise avoidable system
conditions that would be only one
contingency away from voltage collapse
and uncontrolled blackouts.75
42. The NOPR proposed that, based
on prior events, the study criteria for
extreme heat and cold weather events
should consider wide-area conditions
affecting neighboring regions and their
impact on one planning area’s ability to
rely on the resources of another region
during the weather event.
43. To identify opportunities for
improved wide-area planning studies
and coordination, the NOPR sought
comments on whether wide-area
planning studies should be defined
geographically or electrically.76
1. Comments
lotter on DSK11XQN23PROD with RULES3
44. AEP, MISO Transmission Owners,
and Tri-State Generation and
Transmission Association, Inc. (TriState) favor defining wide-area
72 See, e.g., Reliability Standard EOP–012–1
(Extreme Cold Weather Preparedness and
Operations), at Requirement 4 (requiring generator
owners to calculate the generator extreme cold
weather temperature every five years).
73 NOPR, 179 FERC ¶ 61,195 at P 64.
74 Id.
75 Id. P 66.
76 Id. P 67. The NOPR also solicited comment on
which entities should oversee and coordinate the
wide-area planning models and studies, as well as
addressing the results of the studies, and how they
should communicate those results among
transmission planners. Id. These comments are
addressed below in the sections D and E.
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
geographically.77 MISO Transmission
Owners assert that wide-area must be
defined by geography to address issues
in each region as best suited for that
region, given that extreme heat and cold
weather risks, and the appropriate
responses thereto, vary by geography.78
Tri-State explains that ‘‘wide-area’’
should be defined geographically,
because for a transmission planner to
evaluate a large area weather event, it
would need to be modeled within the
transmission planner’s area, as well as
neighboring entities.79
45. Although MISO Transmission
Owners support a geographic definition,
they also caution that RTO regions,
Order No. 1000 planning regions, and
NERC Regional Entities do not have
identical footprints. Therefore, MISO
Transmission Owners recommend that
the final rule direct NERC to propose
modifications to Reliability Standards to
provide appropriately flexible
provisions to address scenarios where
those inconsistent footprints may
introduce conflicts.80
46. Idaho Power, on the other hand,
comments that ‘‘wide-area’’ should be
defined electrically to better capture the
interdependency of systems.81
47. LCRA Transmission Services
Corporation (LCRA), Electric Power
Research Institute (EPRI), and PJM
prefer that ‘‘wide-area’’ be defined both
geographically and electrically. LCRA
explains that this is necessary to
represent the geographic correlation of
extreme weather events and the
electrical connectivity of the
transmission system.82 EPRI cautions
that ‘‘geographic definitions of wide
area events will need to be developed
for inclusion in resource adequacy or
production cost models’’ for purposes of
identifying the snapshot conditions that
should serve as the primary inputs to
the transmission planning
assessments.83 Further, EPRI explains
that ‘‘wide area events defined
electrically can be used to represent
acute switching events that occur over
much shorter timescales and can be
used to capture discrete impacts defined
as contingency events, which occur
concurrent with the extreme
temperature condition.’’ 84
48. Other commenters, while not
indicating a preference between
77 AEP
Comments at 16; MISO Transmission
Owners Comments at 4.
78 Id. at 4.
79 Tri-State Comments at 5–6.
80 MISO Transmission Owners Comments at 4.
81 Idaho Power Comments at 4.
82 LCRA Comments at 3; EPRI Comments at P 18;
PJM Comments at 10.
83 EPRI Comments at P 18.
84 Id. at 12.
PO 00000
Frm 00009
Fmt 4701
Sfmt 4700
41269
electrical or geographical definition,
highlight that extreme heat and cold
weather events are not bound by the
footprint of utilities or authorities that
separate planning and balancing areas.85
Indicated Trade Associations
recommend that the Commission invest
the NERC standard drafting team with
substantial discretion in addressing
whether and how wide-area planning
studies should be defined
geographically or electrically.86
49. Although also not stating a
preference as to whether to define
‘‘wide-area’’ electrically or
geographically, Entergy Services, LLC
(Entergy) cautions against expecting
transmission planners and coordinators
‘‘to overlap benchmark events between
regions’’ because ‘‘[s]uch overlapping
could result in modeling of extreme heat
and cold events over regions that are
much larger than the areas in which
such events are likely to occur.’’ 87
2. Commission Determination
50. Pursuant to section 215(d)(5) of
the FPA, we adopt the NOPR proposal
and direct NERC to require that
transmission planning studies under the
new or revised Reliability Standard
consider the wide-area impacts of
extreme heat and cold weather. We
direct NERC to clearly describe the
process that an entity must use to define
the wide-area boundaries. While
commenters provide various views in
favor of both a geographical approach
and electrical approach to defining
wide-area boundaries, we do not adopt
any one approach in this final rule.
Rather, we believe that this technical
matter deserves a more fulsome vetting
in the Reliability Standards
development process. NERC should
consider the comments in this
proceeding when developing a new or
modified reliability standard that
considers the broad area impacts of
extreme heat and cold weather.88
D. Entities Responsible for Developing
Benchmark Events and Planning Cases,
and for Conducting Transmission
Planning Studies of Wide-Area Events
51. The NOPR proposed to direct
NERC to develop requirements that
address the types of extreme heat and
85 UCS Comments at 8; Entergy Comments at 5;
EDF at Comments 23; MISO Transmission Owners
Comments at 4.
86 Indicated Trade Associations at 10.
87 Entergy Comments at 5–6.
88 Cf., Order No. 693, 118 FERC ¶ 61,218 at P 188
(directing NERC to address NOPR comments
suggesting specific new improvements to the
Reliability Standards in the standards development
process, noting that it ‘‘does not direct any outcome
other than that the comments receive
consideration.’’).
E:\FR\FM\23JNR3.SGM
23JNR3
41270
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
cold scenarios responsible entities are
required to study, including the
development of benchmark events and
benchmark planning cases.89 The NOPR
solicited feedback on which entities
should be responsible for updating
benchmark events and whether, and to
what extent, it may be appropriate to
allow designated entities to periodically
update key aspects of the benchmark
events.90
52. As a separate matter, the NOPR
proposed to require that transmission
planning studies that consider the widearea impacts of extreme heat and cold
weather.91 To inform this directive, the
NOPR solicited comment on which
entities should oversee and coordinate
the wide-area planning models and
studies, as well as which entities should
have responsibility to address the
results of the studies.92
1. Comments
a. Entity Responsible for Development
of Benchmark Events
53. There is no consensus among the
commenters regarding which entities
should be tasked with developing the
benchmark events. Indicated Trade
Associations suggest that the subject
matter experts on the NERC standard
drafting team should develop the
benchmark events.93 Entergy also
suggests that the NERC develop the
benchmark events, as NERC will be able
to tailor the benchmark events to reflect
regional variations in extreme weather
risk.94 All other commenters on this
issue proposed that other entities be
responsible for benchmark event
development.95 For example, New York
Independent System Operator, Inc.
(NYISO) and MISO Transmission
Owners posit that entities registered
with NERC as planning coordinators or
transmission planners should be given
the latitude to develop the benchmark
events.96 AEP recommends that each
planning coordinator should develop
individualized benchmark events for its
planning area, except in regions that
lack the necessary resources or
expertise, in which case the Regional
Entities should coordinate and review
the benchmark event process in
collaboration with these smaller
planning coordinators in that region.97
179 FERC ¶ 61,195 at PP 50–51.
P 53.
91 Id. P 64.
92 Id. P 67.
93 Indicated Trade Associations Comments at 8.
94 Entergy Comments at 4.
95 See. e.g., EDF Comments at 8.
96 NYISO Comments at 13; MISO Transmission
Owners Comments at 5.
97 AEP Comments at 9.
American Clean Power Association
(ACP) suggests that the Regional Entities
should develop the benchmark events
that will be evaluated by all
transmission planners and planning
coordinators in a given region.98
b. Entity Responsible for Development
of Planning Cases and Conducting
Transmission Planning Studies of WideArea Events
54. Regarding development of
benchmark planning cases, beyond
existing registered entities, Arizona
Public Service Company (APS)
recommends ‘‘that a regional planning
entity would be the appropriate entity to
determine the benchmark planning
cases and develop the scenarios that
constitute an extreme event in their
region.’’ 99
55. Further, commenters suggest a
variety of entities to perform the wide
area studies. NERC suggests that a
registered entity subject to the
Reliability Standard, such as a planning
coordinator or transmission planner,
should be responsible for performing
the wide-area studies.100 AEP asserts
that the planning coordinators should
oversee and coordinate the wide-area
planning models and studies,
communicate the results, and work to
mitigate issues that require corrective
action.101
56. APS and MISO Transmission
Owners express concern that an
individual transmission planner or
planning coordinator would not be
positioned to perform a wide-area
assessment of extreme weather
conditions because of its limited
geographical visibility.102 Similarly,
Entergy also questions whether a single
transmission planner would be able to
model a wide-area event on its own.
Entergy believes that the responsibility
for performing the analysis should lie
with the RTOs or Regional Entities, with
input provided by member transmission
owners and transmission planners.103
Alternatively, APS suggested a regional
planning entity, such as those created
under Order No. 1000, would be
appropriate to oversee and coordinate
wide-area planning models and
studies.104 Idaho Power Company
(Idaho Power) asserts that regional
planning groups such as Western Power
Pool are the ones best positioned to
89 NOPR,
lotter on DSK11XQN23PROD with RULES3
90 Id.
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
98 ACP
Comments at 3.
99 APS Comments at 3.
100 AEP Comments at 20; NERC Comments at 9–
10.
101 AEP Comments at 16.
102 APS Comments at 4; MISO Transmission
Owners Comments at 4.
103 Entergy Comments at 6.
104 APS Comments at 4.
PO 00000
Frm 00010
Fmt 4701
Sfmt 4700
coordinate and perform the wide-area
planning studies.105
57. Environmental Defense Fund
(EDF), Tri-State, and Eversource Energy
Service Company (Eversource) propose
that reliability coordinators should have
the responsibility to perform wide-area
planning and coordination in
collaboration with other impacted
reliability coordinators.106
2. Commission Determination
a. Entity Responsible for Establishing
Benchmark Events
58. Pursuant to section 215(d)(5) of
the FPA, we adopt the NOPR proposal
and direct NERC to develop benchmark
events for extreme heat and cold
weather events through the Reliability
Standards development process. We
agree with Indicated Trade Associations
that the development of adequate
benchmark events is critical and should
be committed to the subject matter
experts on the standards drafting team.
We also agree with Entergy that NERC
will be able to tailor benchmark events
to capture regional differences and the
different risks that each region faces
during extreme heat and cold weather
events. While Regional Entities and
reliability coordinators are encouraged
to participate in the NERC Reliability
Standards development process to
develop the benchmark events, we
disagree with AEP and other
commenters who recommend that
entities other than NERC take the lead
in the development of benchmark
events.
59. Further, requiring NERC to
develop the new or modified Reliability
Standard’s benchmark events is
consistent with the approach the
Commission took in Order No. 779,
when the Commission directed NERC to
develop benchmark events for
geomagnetic disturbance analyses.107
For the same reasons, we also conclude
that NERC is best positioned to define
mechanisms to periodically update
extreme heat and cold weather
benchmark events, as discussed
above.108
b. Entities Responsible for Development
of Planning Cases and Conducting
Transmission Planning Studies of WideArea Events
60. We also direct NERC to designate
the type(s) of entities responsible for
105 Idaho
Power Comments at 4.
Comments at 23; Tri-State Comments at
6; Eversource Comments at 5.
107 Reliability Standards for Geomagnetic
Disturbances, Order No. 779, 143 FERC ¶ 61,147, at
P 2 (2013).
108 See supra P 40.
106 EDF
E:\FR\FM\23JNR3.SGM
23JNR3
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
lotter on DSK11XQN23PROD with RULES3
developing benchmark planning cases
and conducting wide-area studies under
the new or modified Reliability
Standard. The scope of extreme weather
event studies will likely cover large
geographical areas far exceeding the
smaller individual transmission planner
or planning coordinator planning areas.
Accordingly, we agree with APS that the
benchmark planning cases should be
developed by registered entities such as
large planning coordinators, or groups
of planning coordinators, with the
capability of planning on a regional
scope.109
61. We also disagree with assertions
that reliability coordinators should be
responsible for developing benchmark
planning cases or conducting wide-area
studies. We believe the designated
responsible entities should have certain
characteristics, including having a widearea view of the Bulk-Power System and
the ability to conduct long-term
planning studies across a wide
geographic area. The responsible
entities should also have the planning
tools, expertise, processes, and
procedures to develop benchmark
planning cases and analyze extreme
weather events in the long-term
planning horizon. Under the NERC
functional model, however, reliability
coordinators have responsibility for the
real-time operation of the bulk-power
system. Accordingly, we conclude that
reliability coordinators are not well
suited for developing benchmark
planning cases or conducting wide-area
studies.
62. To comply with this directive,
NERC may designate the tasks of
developing benchmark planning cases
and conducting wide-area studies to an
existing functional entity or a group of
functional entities (e.g., a group of
planning coordinators). NERC may also
establish a new functional entity
registration to undertake these tasks. In
the petition accompanying the proposed
Reliability Standard NERC should
explain how the applicable registered
entity or entities meet the objectives
outlined above.
109 According to the NERC Registration Matrix,
there are currently 211 transmission planners and
66 planning coordinators in the United States.
While some of these entities operate over large
geographic areas—for example, PJM and MISO are
the only planning coordinators in the Reliability
First footprint—the majority operate on a much
smaller scale—WECC and SERC have 59 planning
coordinators, some of which are small cities and
counties. NERC, NCR Active Entities List, (last
visited Apr. 7, 2023) https://www.nerc.com/pa/
comp/Registration%20and%20Certification%20DL/
NERC_Compliance_Registry_Matrix_Excel.xlsx.
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
E. Coordination Among Registered
Entities and Sharing of Data and Study
Results
63. The NOPR explained that
Reliability Standard TPL–001–5.1 crossreferences Reliability Standard MOD–
032–1 (Data for Power System Modeling
Analysis), which establishes consistent
modeling data requirements and
reporting procedures for the
development of planning horizon cases
necessary to support analysis of the
reliability of the interconnected
system.110 Reliability Standard MOD–
032–1 ensures an adequate means of
data collection for transmission
planning. It requires applicable
registered entities to provide steadystate, dynamic, and short circuit
modeling data to their transmission
planner(s) and planning coordinator(s).
The modeling data is then shared
pursuant to the data requirements and
reporting procedures developed by the
transmission planner and planning
coordinator as set forth in Reliability
Standard TPL–001–5.1, Requirement
R1.
64. The NOPR stated that, while
balancing authorities and other entities
must share system information and
study results with their transmission
planner and planning coordinator
pursuant to Reliability Standards MOD–
032–1 and TPL–001–5.1, there is no
required sharing of such information
related to extreme heat or cold weather
events—or required coordination—
among planning coordinators and
transmission planners with
transmission operators, transmission
owners, and generator owners.111
Sharing system information and study
results and enhancing coordination
among these entities for extreme heat
and cold weather events could result in
more representative planning models by
better integrating and including
operations concerns (e.g., lessons
learned from past issues including
corrective actions and projected
outcomes from these actions, evolving
issues concerning extreme heat/cold) in
planning models; and conveying
reliability concerns from planning
studies (e.g., potential widespread
cascading, islanding, significant loss of
load, blackout, etc.) as they pertain to
extreme heat or cold.112
65. The NOPR proposed to direct
NERC to require system information and
study results sharing and coordination
among planning coordinators and
transmission planners with
transmission operators, transmission
110 NOPR,
111 Id.
179 FERC ¶ 61,195 at P 80.
P 81.
112 Id.
PO 00000
Frm 00011
Fmt 4701
Sfmt 4700
41271
owners, and generator owners for
extreme heat and cold weather
events.113 The NOPR solicited
comments on whether existing
Reliability Standards are sufficient to
ensure that responsible entities
performing studies of extreme heat and
cold weather events have the necessary
data, and/or whether the Commission
should direct additional changes
pursuant to FPA section 215(d)(5) to
address the issue.114 The NOPR also
sought comments on the following: (1)
the parameters and timing of
coordination and sharing; (2) specific
protocols that may need to be
established for efficient coordination
practices; and (3) potential impediments
to the proposed coordination efforts.
1. Comments
66. There is no consensus among
commenters on whether Reliability
Standards TPL–001.5.1 and MOD–032–
1 are adequate means of data collection
for transmission planning, with some
commenters raising concerns about the
types of data that will be needed to
conduct extreme heat and cold weather
studies under the new or modified
Reliability Standard and whether such
data can be obtained through existing
processes.
67. For example, NERC and Idaho
Power believes that the existing
standards are sufficient.115 According to
NERC, the Commission does not need to
direct revisions to Reliability Standard
MOD–032–1 to account for new data
required for extreme heat and cold
weather studies because the standard
requires functional entities to provide
‘‘other information requested by the
Planning Coordinator or Transmission
Planner necessary for modeling
purposes’’ for each of the three types of
data required (steady-state, dynamics,
and short circuit).116 Thus, NERC
asserts that planning coordinators and
transmission planners are empowered to
request any specific data needed for
studies of extreme heat and cold
conditions. According to Idaho Power,
because (1) utilities currently share
contingencies to be studied with
neighboring entities to get feedback and
make updates as needed and (2) utilities
share TPL–001 reports with other
utilities subject to the execution of a
non-disclosure agreement, the
Commission proposal would be
redundant of current practice.117
113 Id.
P 82.
P 63.
115 NERC Comments at 13; Idaho Power
Comments at 5.
116 NERC Comments at 13.
117 Idaho Power Comments at 5.
114 Id.
E:\FR\FM\23JNR3.SGM
23JNR3
41272
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
lotter on DSK11XQN23PROD with RULES3
68. In contrast, Tri-State indicates that
there is no requirement for transmission
customers to provide data for extreme
heat and cold weather conditions such
as load forecast data.118 AEP asserts that
planning coordinators and transmission
planners have limited insight into a
generator’s likelihood of availability
during extreme weather events,
particularly limited for inverter-based
resources.119 EPRI states that there is
limited modeling of protection systems
in dynamic assessments currently, and
any dynamic simulation of extreme
events would require significant
modeling of protection systems to
provide for convergence of the
numerical simulation.120 NYISO notes
that Reliability Standard TPL–001
currently limits transmission planners
or planning coordinators to requesting
data pertaining to their own planning
area.121
69. Other commenters suggest that it
will be necessary to define the data
needed by responsible entities to
perform studies under the new or
modified Reliability Standard. AEP
proposes that the Commission hold a
technical conference to help define the
data needed to perform the extreme
weather assessments and the avenue
through which information will be
shared.122 Indicated Trade Associations
recommend that, although Reliability
Standard MOD–032–1 might be
adequate as a data source, the
Commission should recognize in any
final rule that the standard drafting team
should be tasked with identifying what
data is already collected and specifying
what new data is needed to perform the
assessments for extreme heat and
cold.123
70. Regarding the sharing of study
results and coordination among entities,
Tri-State suggests that the balancing
authority should address the results of
the studies and how they should
communicate those results among the
transmission planners. Tri-State also
asserts that the balancing authority is
responsible for resource adequacy and
should communicate resource needs for
the area with the responsible
transmission planners who can evaluate
system needs and ‘‘provide access to
remove’’ resource needs.124 EPRI does
not opine on who should do the widearea coordination, but states that some
level of coordination will be required to
118 Tri-State
Comments at 4–5.
Comments at 15.
120 EPRI Comments at P 11.
121 NYISO Comments at 14.
122 AEP Comments at 4.
123 Indicated Trade Associations Comments at 9–
10.
124 Tri-State Comments at 6.
119 AEP
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
ensure accurate assessments of wide
area events that impact geographic
footprints across multiple planning
entities.125 UCS suggests that the final
rule should direct the sharing of
modeling information between planning
areas regarding extreme weather
benchmark events, because ensuring
reliability will depend on the extent to
which neighboring regions cooperate.126
71. NERC asserts that while wide-area
studies should be coordinated as
appropriate for the area, the specific
procedural details for coordination on
wide-area studies do not need to be
mandated in a Reliability Standard.
NERC adds that other coordination
requirements, such as those related to
sharing of study results and
coordination for corrective actions
across multiple transmission planner
areas, can be addressed through the
standard development process with
consideration of any factors identified
by the commenters in this
proceeding.127 Similarly, Indicated
Trade Associations recommend that the
Commission empower the standards
drafting team to consider whether
coordination between a variety of
functional entities, and across regions,
would be the most effective means of
addressing certain identified extreme
heat and cold weather events.128
2. Commission Determination
72. Pursuant to section 215(d)(5) of
the FPA, we adopt and modify the
NOPR proposal and direct NERC to
require functional entities to share with
the entities responsible for developing
benchmark planning cases and
conducting wide-area studies the system
information necessary to develop
benchmark planning cases and conduct
wide-area studies. Further, responsible
entities must share the study results
with affected transmission operators,
transmission owners, generator owners,
and other functional entities with a
reliability need for the studies.129
73. We agree with commenters that
Reliability Standard MOD–032–1 allows
for data collection for extreme heat and
125 EPRI
Comments at P 19.
Comments at 8.
127 NERC Comments at 10.
128 Indicated Trade Associations Comments at 5.
129 The NOPR proposed to direct NERC to ensure
that functional entities share necessary system
information with planning coordinators and
transmission planners, as these entities conduct
current transmission planning studies under TPL–
001–5.1. Because this final rule directs NERC to
determine the entities that will be responsible for
conducting studies under the new or modified
Reliability Standard, we modify the NOPR
accordingly to ensure the selected responsible
entity has the means to request and receive
necessary system information.
126 UCS
PO 00000
Frm 00012
Fmt 4701
Sfmt 4700
cold weather events. However, only
planning coordinators and transmission
planners can request data from other
entities through Reliability Standard
MOD–032–1 processes. Because in this
final rule we direct NERC to determine
the responsible entities that will be
developing benchmark planning cases
and conducting wide-area studies, it is
possible that the selected responsible
entities under the new or modified
Reliability Standard will not be able to
request and receive needed data
pursuant to MOD–032–1, absent
modification to that Standard.
74. Regarding EPRI’s statement of
insufficiency of dynamic modeling of
protection systems, we consider the
insufficiency of protection system
modeling to be an ongoing deficiency in
the modeling process. The dynamics
databases used for transient stability
simulations by various interconnections
typically do not include comprehensive
dynamic models of relays installed in
the interconnection. Thus, in addressing
our directive above, NERC should
evaluate this deficiency during the
standard development process.
75. We disagree with UCS’s
recommendation that the final rule
should direct the sharing of modeling
information between planning areas
regarding extreme weather benchmark
events. We expect that the existing
practice (e.g., MOD–032–1) of
responsible entities sharing modeling
information between planning areas will
continue, without the need for us to
specifically direct that in this final rule.
76. Rather than predetermine each
aspect of the coordination process, we
believe the decision of which entities
are best positioned for wide-area
coordination should be left to NERC. We
therefore direct NERC to address the
requirement for wide-area coordination
through the standard development
process, giving due consideration to
relevant factors identified by
commenters in this proceeding.
77. We agree with NERC and
Indicated Trade Associations that
coordination requirements, such as
those related to the sharing of study
results and corrective actions across
multiple transmission planner areas, are
best addressed through the standard
development process, which we expect
will consider relevant factors identified
by the commenters in this proceeding.
Although this final rule does not specify
how study results must be shared, we
believe that the new or modified
Reliability Standard must require
responsible entities to share these
studies with affected functional entities.
The sharing of study results will alert
entities of reliability concerns identified
E:\FR\FM\23JNR3.SGM
23JNR3
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
in wide-area studies.130 Further,
requiring responsible entities to share
study results with functional entities
with a reliability related need for the
study is consistent with existing
planning assessment sharing
requirements under Reliability Standard
TPL–001–5.1.131 Therefore, we direct
NERC to require in the new or modified
Reliability Standard that responsible
entities share the results of their widearea studies with other registered
entities such as transmission operators,
transmission owners, and generator
owners that have a reliability related
need for the studies.
lotter on DSK11XQN23PROD with RULES3
F. Concurrent/Correlated Generator and
Transmission Outages
78. The NOPR stated that generation
resources that are sensitive to severe
weather conditions may cease operation
during extreme heat and cold events,
thus contributing to wide-area
concurrent outages. In addition, the
NOPR indicated that extreme heat could
lead to significant derating, reduced
lifetime, or failure of power
transformers, while extreme cold could
lead to at least temporary transmission
facility outages.132
79. As such, the NOPR posited that
modeling the loss of these generators
and transmission equipment during
extreme heat and cold weather events
would allow planners to assess the
effects of potential concurrent
transmission and generator outages and
study the feasibility (i.e., availability
and deliverability) of external
generation resources that could possibly
be imported to serve load during such
events, thereby minimizing the potential
impact of extreme heat and cold events
on customers.133 In addition, the NOPR
indicated that modeling concurrent
generator and transmission outages
would also allow planners to better
identify appropriate solutions to be
incorporated into corrective action
plans.134
80. The NOPR also proposed that
accounting for concurrent outages
including modeling the derating and
possible loss of wind and solar
generators, as well as natural gas
generators sensitive to extreme heat and
cold conditions in planning studies
would provide a more realistic
assessment of system conditions (i.e.,
updated conditions based on historic
benchmarked performance) during
potential extreme heat and cold events
and will help better assess the
probability of potential occurrences of
cascading outages, uncontrolled
separation, or instability. Thus, the
NOPR suggested that requiring
transmission planners and planning
coordinators to study concurrent
generator and transmission failures
under extreme heat and cold events to
account for the expected resource mix’s
availability during these extreme
conditions is one way to address the
reliability gap in Reliability Standard
TPL–001–5.1.135
81. To identify the scope of these
planning studies, the NOPR sought
comments on the following: (1) the
assumptions (e.g., weather forecast, load
forecast, transmission voltage levels,
generator types, multi-day low wind,
and solar events) used in modeling of
concurrent outages due to extreme heat
and cold weather events; (2) what
assumptions should be included when
performing modeling and planning for
generators sensitive to extreme heat and
cold; (3) how the impact of loss of
generators sensitive to extreme heat and
cold should be factored into long-term
planning; (4) the extent of neighboring
systems’ or planning areas’ outages that
should be modeled in transmission
planning studies; and (5) whether a
certain threshold penetration of wind,
solar, and natural gas generation should
trigger additional analyses.136
pipeline into a region or multiple
regions that have significant gas-fired
generation, the standard could be
modified to include the impact of
renewable energy resource response due
to extreme weather as well.139 While
agreeing with the NOPR proposal,
Public Interest Organizations (PIOs) and
ACP argue that any requirement to
study concurrent or correlated
generation outages should be extended
to conventional generators to account
for the reliability risk and to eliminate
undue discrimination caused by
overstating the reliability contributions
of conventional generators relative to
renewable and storage resources.140
83. Some commenters assert that the
NOPR proposal on modeling the effects
of potential concurrent transmission
and generator outages might be
unnecessary. ISO New England Inc.
(ISO–NE) takes issue with including the
expected resource mix’s availability
during extreme weather conditions as
part of extreme weather scenarios. ISO–
NE asserts that resource mix availability
should not be addressed in a
transmission planning standard because
it is addressed as part of resource
adequacy assessment and other
Reliability Standards, such as the Cold
Weather Reliability Standards. Further,
ISO–NE argues that transmission
planning Reliability Standards need to
consider resource availability in
planning cases, because generators will
be required to be ready to perform in
1. Comments
extreme weather events under those
82. Commenters mostly agree with the
other standards.141 EPRI asks if the
NOPR that responsible entities should
Commission intends for the concurrent
evaluate the risk of correlated or
outages of generation and transmission
concurrent outages and derates of all
assets to be modeled as an acute event,
types of generation resources (i.e.,
conventional and renewables) as well as and if so, requests clarification as to
transmission facilities related to extreme how it differs from the P3 category of
contingency events from TPL–001–
weather events.137 For example, the
5.1.142
Federal Energy Advocate for the Public
84. NYISO recommends that, as the
Utilities Commission of Ohio (Ohio
extreme
events in Reliability Standard
FEA) recommends that the Standard
TPL–001–5.1 are analogous to extreme
incorporate asset correlations and
contingencies rather than extreme
interdependencies, and consider the
system conditions such as heatwaves,
extent to which they can be obviated or
cold snaps, droughts, etc., NERC
mitigated because asset performance or
planning events should be expanded to
failure is highly correlated with their
include the weather-related loss of
dependency on weather conditions and
generation across areas of the system in
on the performance of nearby or related
138
infrastructure.
Idaho Power notes that the design-basis contingencies rather
143
while Reliability Standard TPL–001–5.1 than as an extreme contingency.
already addresses the loss of multiple
139 Idaho Power Comments at 4.
generating stations resulting from
140 PIOs Comments at 23–24.
conditions such as the loss of a large gas
141 ISO–NE Comments at 2–4.
135 Id.
130 NOPR,
179 FERC ¶ 61,195 at P 81.
131 See Reliability Standard TPL–001–5.1,
Requirement R8.
132 NOPR, 179 FERC ¶ 61,195 at P 68.
133 Id. P 69.
134 Id.
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
41273
P 72.
136 Id.
137 EDF Comments at 22; ACP Comments at 5;
PIOs Comments at 9; AEP Comments at 4; UCS
Comments at 12; and Americans for Clean Energy
Grid Comments at 6 (ACEG Comments).
138 Ohio FEA Comments at 5.
PO 00000
Frm 00013
Fmt 4701
Sfmt 4700
142 EPRI Comments at PP 20–21. Category P3
requires the study of the loss of a generator unit
followed by system adjustments, followed by a loss
of one of the following: generator or transmission
circuit or transformer or shunt device or single pole
of a DC line as stated in Reliability Standard TPL–
001.5.1, Table 1.
143 NYISO Comments at 13.
E:\FR\FM\23JNR3.SGM
23JNR3
41274
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
85. Regarding modeling assumptions,
LCRA asserts that the Standard should
not be prescriptive regarding the
modeling assumptions, particularly
concerning generation availability,
beyond developing the study base case
when available generation is insufficient
to meet the load with respect to extreme
weather events.144 LCRA also cautions
that modeling too many outages will
result in an unsolvable case that cannot
be analyzed.145
86. While no comments
recommended any specific threshold of
penetration of renewable resources that
would trigger additional analysis, PJM
notes that special studies may be
needed as greater numbers of renewable,
inverter-based resources (IBR), connect
to the Bulk-Power System. With a much
higher IBR penetration level, a more
material change to dynamic and steady
state assessment will likely be needed to
capture the impacts of higher
penetration levels of IBRs and much
reduced conventional generation
support.146 APS, however, suggests that
the Commission should not set a
penetration threshold, arguing that the
entity performing the study should
determine the threshold, which likely
would differ depending on the
characteristics of the particular
system.147
87. Electric Power Supply Association
(EPSA) suggests that the Commission
direct NERC to examine how it defines
and measures its resource adequacy
benchmarks, including the impacts of
non-dispatchable resources with
increasing penetration in the system and
the availability of dispatchable, flexible
resources which are increasingly being
replaced by new, less flexible resources
or technologies.148
lotter on DSK11XQN23PROD with RULES3
2. Commission Determination
88. Pursuant to section 215(d)(5) of
the FPA, we adopt the NOPR proposal
and direct NERC to require under the
new or revised Reliability Standard the
study of concurrent/correlated generator
and transmission outages due to
extreme heat and cold events in
benchmark events as described in more
detail below.
89. We disagree with comments
suggesting that the modeling of
concurrent/correlated generator and
transmission outages is unnecessary.149
As discussed in the NOPR, and
reinforced by commenters, the failures
144 LCRA
Comments at 3.
146 PJM
Comments at 11.
Comments at 5.
148 EPSA Comments at 3.
149 See, e.g., ISO–NE Comments at 2–4.
147 APS
19:38 Jun 22, 2023
150 NOPR,
179 FERC ¶ 61,195 at P 70.
PP 70–71.
152 See supra P 82.
153 This understanding is consistent with section
215(a)(1) of the FPA, 16 U.S.C. 824o(a)(1), which
defines Bulk-Power System to include ‘‘electric
energy from generation facilities needed to maintain
transmission system reliability.’’
151 Id.
145 Id.
VerDate Sep<11>2014
of individual generators during extreme
weather events are not independent.150
Previous extreme weather events have
demonstrated that there is a high
correlation between generator outages
and cold temperatures, indicating that
as temperatures decrease, unplanned
generator outages and derates
increase.151 Because of this correlation,
it is necessary that responsible entities
evaluate the risk of correlated or
concurrent outages and derates of all
types of generation resources and
transmission facilities as a result of
extreme heat and cold events, as
commenters suggest.152
90. Further, we disagree with ISO–NE
that resource mix availability should not
be considered here because it is
considered in resource adequacy
planning and in other Reliability
Standards. Although resource outages
are an important input into the resource
adequacy studies, they are also an
important determinant in assessing the
adequacy of the transmission system.153
Therefore, it will be necessary to
consider the impact of extreme weather
events on generators anticipated to be
connected to the subject transmission
system during the study period.
Similarly, although the Cold Weather
Reliability Standards require generators
to be prepared to be available and
perform at or above their extreme cold
weather temperature during extreme
weather events, generator availability is
not guaranteed by any Reliability
Standard, and outages occur for many
reasons. Accordingly, some generators
may still be unavailable under extreme
heat or cold conditions and thus their
potential outages must be considered in
extreme heat and cold weather planning
scenarios.
91. Although several commenters ask
for flexibility as to modeling
assumptions, we believe that it is
necessary for the Reliability Standard to
strike a balance between allowing
responsible entities discretion to ensure
the study incorporates their operating
experience and the need to create a
robust framework that ensures extreme
heat and cold events are adequately
studied. Thus, while generation and
transmission availability and concurrent
outages must be included in the
benchmark planning case, we defer to
NERC to develop the framework and
criteria that responsible entities shall
Jkt 259001
PO 00000
Frm 00014
Fmt 4701
Sfmt 4700
use to represent potential weatherrelated contingencies (e.g., concurrent/
correlated generation and transmission
outages, derates) in the relevant
benchmark event planning cases.154
92. Regarding the comments of NYISO
and EPRI on the difference between
extreme events and contingencies
covered under Reliability Standard
TPL–001–5.1, we clarify that all
contingencies included in benchmark
planning cases under the new or
modified Reliability Standard will
represent initial conditions for extreme
weather event planning and analysis.
These contingencies (i.e., correlated/
concurrent, temperature sensitive
outages, and derates) shall be identified
based on similar contingencies that
occurred in recent extreme weather
events or expected to occur in future
forecasted events.
93. Regarding PJM’s comment
regarding the likely need for additional
studies to capture the impacts of higher
penetration levels of renewables and
much reduced conventional generation
support, we note that the benchmark
planning case will include this
information pursuant to our directive
above regarding benchmarking planning
cases. Accordingly, we do not foresee
the need for the additional studies
suggested by PJM.
94. Lastly, regarding EPSA’s comment
requesting that we direct NERC to
examine how it defines and measures its
resource adequacy benchmarks, we note
that resource adequacy benchmarks are
outside the scope of this proceeding.
G. Conduct Transmission System
Planning Studies for Extreme Heat and
Cold Weather Events
1. Steady State and Transient Stability
Analyses
95. The Commission proposed in the
NOPR to require both steady state and
transient stability analyses be conducted
for extreme heat and cold weather
events as part of transmission planning
studies.155 Consistent with Reliability
Standard TPL–001–5.1, the NOPR stated
that steady state and stability analyses
of study cases modeled to reflect past
and forecasted extreme heat and cold
conditions would better prepare
transmission operators for such
154 See supra P 39. Reliability Standard TPL–001–
5.1 Requirement 1.1.5 requires responsible entities
to maintain system models that represent projected
system conditions, including resources required for
load. Because drought conditions may impact the
availability of certain supply resources, we expect
that the new or revised Reliability Standard will
include a similar requirement that accounts for the
impact of drought conditions on generation where
appropriate.
155 NOPR, 179 FERC ¶ 61,195 at P 69.
E:\FR\FM\23JNR3.SGM
23JNR3
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
conditions.156 The NOPR explained that
a steady-state analysis is based on a
snapshot in time where the bulk electric
system facilities such as generators,
transmission lines, transformers etc. are
modeled as fixed and load is modeled
as a constant.157 On the other hand,
transient stability or dynamic analyses
simulate the time-varying characteristics
of the system during a disturbance that
occurs during an extreme heat or cold
event.158 The NOPR further stated that
performing these studies in the longterm planning horizon period (i.e., six to
ten years and beyond) will provide an
adequate lead time for entities to
develop and implement corrective
action plans to reduce the likelihood or
mitigate the consequences and adverse
impacts of such events.159
96. The NOPR noted that the use of
dynamic studies is particularly
important given the changing resource
mix and the need to understand the
dynamic behavior of both traditional
generators and variable energy resources
(VERs) (i.e., wind and solar
photovoltaic).160
97. The NOPR sought comments on
all aspects of the proposal, and
specifically, on whether responsible
entities should include contingencies
based on their planning area and
perform both steady state and transient
stability (dynamic) analyses using
extreme heat and cold cases. In
addition, the NOPR invited comments
on the following topics: (1) the set of
contingencies responsible entities must
consider; (2) required analyses to assess
voltage stability, frequency excursions
and angular deviations caused as a
result of near simultaneous outages or
common mode failures of VERs; and (3)
the role of demand response under such
scenarios.161
a. Comments
98. All those who commented on the
NOPR proposal to require both steady
state and transient stability analyses
agree with the NOPR that both steady
state and transient stability analyses
should be performed in order to
understand the potential impacts of
extreme heat and cold weather
156 Id.
P 70.
P 59.
158 Id. P 60.
159 Id. P 58.
160 Id. P 61.
161 Id. P 62. The NOPR also sought comment on
whether existing Reliability Standards are sufficient
to ensure that responsible entities performing
studies of extreme heat and cold weather conditions
have the necessary data, and/or whether the
Commission should direct additional modifications
pursuant to FPA section 215(d)(5) to address this
issue. Id. P 63. This question is discussed in section
IV.E of this final rule.
lotter on DSK11XQN23PROD with RULES3
157 Id.
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
events.162 Below, we discuss comments
received on the following topics: (i)
required contingencies; (ii) analyses of
common mode failures; and (iii)
demand response.
i. Required Set of Contingencies
99. Idaho Power supports the
inclusion of contingencies listed in
Table 1 of Reliability Standard TPL–
001–4 such as the loss of two generating
stations resulting from, among other
events, severe weather, as it currently
applies these contingencies in its severe
weather studies.163
100. AEP recommends that the
Commission direct NERC to revise and
reclassify the contingency lists in
Reliability Standard TPL–001–5.1 to
‘‘reflect the unique challenges posed by
extreme weather events’’ and to ensure
that the bulk electric system is operated
to withstand N–1–1 contingencies
‘‘without interruption of firm
transmission service or nonconsequential load loss.’’ 164 NYISO
recommends expanding NERC planning
events to include the weather-related
loss of generation across areas of the
system in the design-basis contingencies
rather than as an extreme
contingency.165 Southern California
Edison Company (SCE) suggests that
NERC determine whether additional
contingencies should be developed to
evaluate potential reliability risks from
events occurring at the same or
sequential times in the same region that
have the potential to pose an aggregate
impact on electricity assets, operations,
and services, e.g., an extreme heat event
that reduces grid capacity while
increasing demand for cooling.166 LCRA
suggests that performing contingency
analyses similar to what is required
under Reliability Standard CIP–014–3
(Physical Security) may be useful.167
LCRA states, for example, that the
analysis could study the outage of
medium impact facilities (e.g., single
circuit, common tower). If the result of
the analysis identifies instability,
cascading, uncontrolled islanding, or
excessive load shed, these facilities
162 See, e.g., NERC Comments at 9; PJM
Comments at 10; Tri-State Comments at 4;
Eversource Comments at 5; WE ACT for
Environmental Justice Comments at 4; LCRA
Comments at 3; UCS Comments at 7.
163 Idaho Power Comments at 3.
164 AEP Comments at 4.
165 NYISO Comments at 14.
166 SCE Comments at 4.
167 Reliability Standard CIP–014–3 requires
entities to assess their transmission facilities to
determine whether, if rendered inoperable or
damaged, they could result in widespread
instability, uncontrolled separation, or cascading.
Reliability Standard CIP–014–3 (Physical Security),
at 1.
PO 00000
Frm 00015
Fmt 4701
Sfmt 4700
41275
could be identified as ‘‘weather critical’’
and targeted for hardening as part of a
corrective action plan.168
101. Other commenters state that
responsible entities should be able to
consider contingencies beyond those in
Table 1 of Reliability Standard TPL–
001.5.1 that will affect their study
area.169 For example, PJM emphasizes
the need for regional variance for
unique contingencies to be studied.170
Eversource recommends that the
Commission avoid prescription and
allow details such as the types of
required contingencies to be determined
during the standard development
process.171
102. EPRI asserts that clarification is
needed to differentiate between events
that impact the initial conditions of the
benchmark scenario for which the
contingency events will be analyzed,
and the actual contingencies meant to
be captured as acute impacts to the
system that occur over a wide area and
can be studied through the steady state
and transient stability processes.172
ii. Analyses for Common Mode Failures
103. NERC and ACP agree that
Reliability Standard TPL–001–5.1
should better address the risk posed by
extreme heat and cold weather events
and the associated common mode
failure impacting resource availability
and the transmission system.173
104. EPRI states that the benchmark
planning cases, which serve as the basis
for steady state and transient stability
assessments, historically have not been
developed to include the correlated
impacts of common mode events based
on the impact of extreme temperature
on load and the availability of derated
generation and transmission capacity.
EPRI asserts that capturing extreme
temperature conditions for both heat
and cold would require a new approach
that directly accounts for the correlated
temperature-related impacts to supply
and demand.174 EPRI agrees with the
Commission’s proposal that dynamic
models of VERs need to be included in
the studies but states they would need
to be sufficiently robust to accurately
capture system performance under
extreme weather conditions.175
168 LCRA
Comments at 2.
Comments at 4; Idaho Power Comments
at 3; Tri-State Comments at 4, PJM Comments at 11.
170 AEP Comments at 4; Idaho Power Comments
at 3; Tri-State Comments at 4, PJM comments at 11.
171 Eversource Comments at 4.
172 EPRI Comments at P 21.
173 NERC Comments at 6; ACP Comments at 9
n.23.
174 EPRI Comments at PP 3–4.
175 Id. P 11.
169 AEP
E:\FR\FM\23JNR3.SGM
23JNR3
41276
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
105. Indicated Trade Associations
state that in any case modeling these
scenarios will likely require additional
resources in time, expertise, and
enhanced software capabilities.176
Indicated Trade Associations ask that
the standard drafting team recognize the
range and quantity of complexities
layered into the modeling process, e.g.,
whether concurrent generators must be
in a single or multiple balancing
authority area, how many generators are
needed for a given study, and if there is
a particular combination of generators
needed for modeling.177
lotter on DSK11XQN23PROD with RULES3
iii. Demand Response
106. EDF and UCS suggest that when
evaluating relevant distribution system
impacts, responsible entities should
focus on the impacts of the extreme
weather event on both electric demand
and on the capability of the distribution
system assets, including demand
response, distributed storage and
generation, and utility-scale storage, to
mitigate reliability risks.178
107. APS comments that demand
response should be used as a tool to
resolve issues and only studied when it
is relied on as a mitigation action.179
108. Eversource states that the
Commission should encourage regional
flexibility in any consideration of
demand response. Eversource further
comments that the Commission should
not impose a ‘‘one size fits all’’
approach for resources that may
significantly differ based on location. It
is also concerned that during extreme
weather events, demand response with
heating or cooling-based load reduction
may not be achievable due to safety
concerns.180
109. EPRI asserts that steady state
simulation cannot sufficiently capture
demand response, and that there is
limited capability to capture the
aggregated dynamic response of demand
in the load models used in positive
sequence platforms. EPRI adds that ‘‘the
impacts of demand response are better
represented through appropriate
temporal and diurnal patterns that
would inform the load and demand
profile under a given extreme
temperature condition. This information
is best represented in operational
assessments such as resource adequacy
or production cost modeling.’’ 181
110. LCRA notes that while the role
of demand response in its portion of the
176 Indicated
Trade Associations at 9.
177 Id.
178 EDF
Comments at 22–23; UCS Comments at 7–
8.
179 APS
Comments at 4.
Comments at 6.
181 EPRI Comments at P 12.
180 Eversource
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
Bulk-Power System is negligible today,
this could change in the future as
additional large loads (e.g.,
cryptocurrency mining and data centers)
are energized. LCRA states that this
trend should be observed for further
consideration in the future.182
b. Commission Determination
111. Pursuant to section 215(d)(5) of
the FPA, we adopt the NOPR proposal
and direct NERC to require in the
proposed new or modified Reliability
Standard that responsible entities
perform both steady state and transient
stability (dynamic) analyses in the
extreme heat and cold weather planning
studies. In a steady state analysis, the
system components are modeled as
either in-service or out-of-service and
the result is a single point-in-time
snapshot of the system in a state of
operating equilibrium. A transient
stability (dynamic) analysis examines
the system from the start to the end of
a disturbance to determine if the system
regains a state of operating
equilibrium.183 Performing both
analyses ensures that the system has
been thoroughly assessed for instability,
uncontrolled separation, and cascading
failures in both the steady state and the
transient stability realms.
112. We also adopt the NOPR
proposal and direct NERC to define a set
of contingencies that responsible
entities will be required to consider
when conducting wide-area studies of
extreme heat and cold weather events
under the new or modified Reliability
Standard. We believe that it is necessary
to establish a set of common
contingencies for all responsible entities
to analyze. Required contingencies,
such as those listed in Table 1 of
Reliability Standard TPL–001–5.1 (i.e.,
category P1 through P7), establish
common planning events that set the
starting point for transmission system
planning assessments. Requiring the
study of predefined contingencies will
ensure a level of uniformity across
planning regions—a feature that will be
necessary in the new or revised
Reliability Standard considering that
extreme heat and cold weather events
often exceed the geographic boundaries
of most existing planning footprints.
113. Additionally, establishing a set of
required contingencies will aide in the
auditing and enforcement of the new or
revised Reliability Standard. While we
do not require in this final rule the
182 LCRA
Comments at 2–3.
are created during the dynamic
simulation from pre to post disturbance and are
then examined for voltage, frequency, and rotor
angle stability, which cannot be assessed using only
a steady state analysis.
183 Plots
PO 00000
Frm 00016
Fmt 4701
Sfmt 4700
inclusion of any particular contingency,
we agree with commenters that the
contingencies required in the new or
revised Reliability Standard should
reflect the complexities of transmission
system planning studies for extreme
heat and cold weather events. As such,
NERC may determine whether
contingencies P1 through P7 should also
apply to the new or modified Reliability
Standard, or whether a new set of
contingencies should be developed.
114. Regarding the request for
clarification from EPRI as to what
outages should be included in the
benchmark planning case versus
modeled as contingencies, we believe
the standard drafting team is best
positioned to consider that specific
question. By definition, the benchmark
planning case will already include
certain weather-related contingencies
that therefore will not be studied as
additional contingencies when
conducting extreme weather studies.184
For example, baseline drought
conditions will be present in the
benchmark planning case as part of the
system models representing projected
system conditions,185 whereas the
impacts of more severe droughts could
be studied during sensitivity analysis as
a variation to the benchmark planning
case’s generation assumptions.186 As
discussed in section IV.F above, we
direct NERC to develop specific criteria
for determining which outages should
be considered in the benchmark
planning case.
115. Regarding the study of common
mode failures, we reiterate our above
directives concerning the study of
concurrent/correlated generator and
transmission outages. We believe that,
as suggested by Indicated Trade
Associations, the standard development
process will provide an adequate
platform to address the concerns raised
by commenters regarding common
mode failures.
116. We also direct NERC to require
in the new or modified Reliability
Standard that responsible entities model
demand load response in their extreme
weather event planning area. As
indicated by several commenters,
because demand load response is
generally a mitigating action that
involves reducing distribution load
during periods of stress to stabilize the
Bulk-Power System, its effect during an
extreme weather event should be
modeled.
117. Regarding EPRI’s comment that
steady state simulation cannot
184 See
supra P 39.
supra note 155.
186 See infra P 124.
185 See
E:\FR\FM\23JNR3.SGM
23JNR3
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
sufficiently capture demand load
response, we believe EPRI’s comments
are accurate for modeling in the
operational timeframe for temporal and
diurnal studies. However, we recognize
that it is possible that the loads used to
represent extreme heat and cold events
will include the effects of demand load
response because entities’ load data
obtained from historical data during
these past extreme events will reflect
the effects of demand load response. If
that is the case, demand load response
will be automatically factored into the
benchmark planning case. Thus, in
addressing this directive, we expect
NERC to determine whether responsible
entities will need to take additional
steps to ensure that the impacts of
demand load response are accurately
modeled in extreme weather studies,
such as by analyzing demand load
response as a sensitivity, as is currently
the case under Reliability Standard
TPL–001–5.1.187
lotter on DSK11XQN23PROD with RULES3
2. Sensitivity Analysis
118. In the NOPR, the Commission
proposed directing NERC to establish a
requirement for responsible entities to
consider system models and sensitivity
cases when assessing extreme heat and
extreme cold weather.188 The NOPR
explained that, while Reliability
Standard TPL–001–5.1 requires the use
of sensitivity power flow cases, the
Standard does not require responsible
entities to model the simultaneous
variation of load, generation, and
transfers necessary to account for the
impacts of extreme heat and cold
weather events. This, in turn, could
result in failure to detect in the planning
horizon potential reliability issues such
as widespread outages and cascading
failures.189
119. The NOPR further stated that to
accurately model the impacts of extreme
heat and cold weather events it would
be necessary to define and model in
sensitivity analyses demand probability
scenario cases, generators that are
affected by these events (i.e., wind
tripping off, solar dropping off, gas
plants not being operational due to gas
restrictions/freeze-offs, etc.) and transfer
levels.190
120. The NOPR requested comment
on: (1) whether to require transmission
planners and planning coordinators to
assess reliability in the planning
horizon for sensitivity cases in which
187 Reliability Standard TPL–001–5.1, at
Requirement 2.1.3.
188 NOPR, 179 FERC ¶ 61,195 at P 73. Sensitivity
analyses consider the impact on a base case by
altering discrete variables.
189 Id.
190 Id.
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
multiple inputs (e.g., load and generator
failures) change simultaneously during
extreme heat and cold events; and (2)
the range of factors and the number of
sensitivity cases that should be
considered to ensure reliable
planning.191
a. Comments
121. Some commenters support
requiring the consideration of certain
sensitivities. For example, AEP
recommends that a baseline set of
sensitivities should be defined by the
NERC standard drafting team and there
should be flexibility for planning
coordinators to introduce further
sensitivities if deemed necessary.192
EPRI suggests that multiple hours may
need to be studied over the course of the
extreme temperature window to capture
sensitivities related to generation and
demand that can lead to differing steady
state and dynamic stability impacts.
EPRI also recommends that in addition
to the sensitivities driven by the
operational performance of the system,
the standard should include other
external drivers that may compound
system conditions during the extreme
temperature events, such as a
concurrent lull in wind speeds that
would limit wind generation outputs.193
122. Other commenters suggest
reasons why it may not be necessary for
the Commission to direct the study of
additional sensitivities. NYISO and
LCRA explain that extreme heat and
cold weather impacts and unavailability
of natural gas fuel are already studied as
sensitivities under Reliability Standard
TPL–001–5.1.194 Similarly, Indicated
Trade Associations assert that the
extreme weather base case should
already represent system conditions at
or near possible seasonal extreme
weather limits and that, as such, many
additional sensitivities may not be
necessary.195 LCRA adds that the effect
of changing inputs (e.g., load and
generation, including generation
retirements and forced generation
outages) should be captured in the
contingency definitions, performance
requirements, and analysis for the given
region and extreme weather case.196
123. Idaho Power, APS, and Indicated
Trade Associations indicate that given
the diversity among utilities with
respect to load profiles, geographic
footprint, resource mix, particular
utility, its resource mix, and geographic
191 Id.
P 74.
Comments at 12.
193 EPRI Comments at P 22.
194 NYISO Comments at 13; LCRA Comments at
41277
footprint, and available resources and
needs, the Commission should allow
entities to select the sensitivities they
will study.197
b. Commission Determination
124. Pursuant to section 215(d)(5) of
the FPA, we adopt the NOPR proposal
and direct NERC to require the use of
sensitivity cases to demonstrate the
impact of changes to the assumptions
used in the benchmark planning case.
Sensitivity analyses help a transmission
planner to determine if the results of the
base case are sensitive to changes in the
inputs. The use of sensitivity analyses is
particularly necessary when studying
extreme heat and cold events because
some of the assumptions made when
developing a base case may change if
temperatures change—for example,
during extreme cold events, load may
increase as temperatures decrease, while
a decrease in temperature may result in
a decrease in generation. We agree with
AEP, and we direct NERC to define
during the Reliability Standard
development process a baseline set of
sensitivities for the new or modified
Reliability Standard. While we do not
require the inclusion of any specific
sensitivity in this final rule, NERC
should consider including conditions
that vary with temperature such as load,
generation, and system transfers.198
125. We do not agree with Idaho
Power, APS, and Indicated Trade
Associations that responsible entities
alone should determine the sensitivity
cases that must be considered in the
responsible entity’s study. Failure to
consider variations in conditions
necessary to reflect extreme heat or cold
weather events could result in major
reliability risks being overlooked and
undetected in the planning horizon.199
We do, however, believe that
responsible entities should be free to
study additional sensitivities relevant to
their planning areas. Because wide-area
studies conducted under the new or
modified Reliability Standard will be
likely based on footprints significantly
larger than those typically concerned
under Reliability Standard TPL–001.5.1,
cooperation will be necessary between
responsible entities conducting extreme
heat and cold weather studies and other
registered entities within their extreme
weather study footprints to ensure the
selection of appropriate sensitivities.
EPRI’s comment further highlights the
need for coordination between
192 AEP
3.
195 Indicated
196 LCRA
PO 00000
Trade Associations Comments at 10.
Comments at 3.
Frm 00017
Fmt 4701
Sfmt 4700
197 Indicated Trade Associations Comments at 11;
Idaho Power Comments at 4–5; APS Comments at
7.
198 NOPR, 179 FERC ¶ 61,195 at P 73.
199 See id.
E:\FR\FM\23JNR3.SGM
23JNR3
41278
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
lotter on DSK11XQN23PROD with RULES3
registered entities to capture
sensitivities related to variable energy
resources and demand.
126. We disagree with NYISO and
LCRA that extreme heat and cold
weather impacts are already studied as
sensitivities under Reliability Standard
TPL–001–5.1. Although TPL–001–5.1
mandates sensitivity analysis by varying
one or more conditions specified in the
standard such as load, generation, and
transfers, this analysis alone cannot
capture the complexities of extreme heat
and cold weather conditions. Sensitivity
analyses consider the impact on a base
case of the variability of discrete
variables. Extreme heat and cold
weather impacts, on the other hand,
may include numerous concurrent
outages and derates which cannot be
studied as part of a single-variable
sensitivity analysis. Under the new or
modified Reliability Standard, however,
these outages will be captured in the
benchmark planning case upon which
sensitivity analyses will be performed.
3. Modifications to the Traditional
Planning Approach
127. In the NOPR, the Commission
proposed to direct NERC to consider
alternative planning methods and
techniques that diverge from past
Reliability Standard requirements to
better capture the challenges posed by
extreme heat and cold events.200
128. The NOPR stated that Reliability
Standard TPL–001–5.1 is based on a
deterministic approach, which uses
planned contingencies and specific
performance criteria to study system
response to various conditions. This
approach yields accurate planning when
the power supply is highly
dispatchable, weather is predictable,
and near-record peak demand is reached
only a few days a year.201 However, as
noted in the NOPR, the current planning
approach applied in Reliability
Standard TPL–001–5.1 likely is not
sufficient to accurately characterize the
reliability risk from extreme heat and
cold weather given the high degree of
uncertainty inherent in predicting
severe weather and its impact on
generation resources, transmission, and
load.202
129. The NOPR explained the value of
establishing a new or modified planning
approach to better capture the impacts
of, and ensure reliable planning and
operation in response to, extreme heat
and cold events.203 Specifically, the
NOPR mentioned as an option
200 Id.
P 75.
201 Id.
202 Id.
203 Id.
P 78.
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
expanding current deterministic studies
to include probabilistically developed
scenarios as an option to better account
for uncertainties during extreme heat
and cold weather conditions, since
probabilistic tools can capture ‘‘random
uncertainties in power system planning,
including those in load forecasting,
generator performance, and failures of
system equipment.’’ 204
130. Finally, the NOPR sought
comments on combining or layering
probabilistic and deterministic
approaches when planning for extreme
heat and cold weather conditions in the
context of Reliability Standard TPL–
001–5.1. Specifically, the NOPR sought
comments on the use of a hybrid
deterministic/probabilistic planning
approach and the following: (1) the
assumptions from the deterministic and
probabilistic approaches that should be
applied to study extreme heat and cold
weather events; (2) the potential
planning challenges from combining the
two planning approaches; (3) the costs
associated with adjustments to the
currently applied deterministic
approach; (4) the implementation period
necessary for proposed changes; and (5)
the reliability benefits that could
result.205
a. Comments
131. Many commenters support the
use of probabilistic methods in
transmission planning to account for
uncertainty in availability of
transmission and generation in extreme
weather conditions.206 For example,
PJM states that the use of probabilistic
modeling ‘‘would help establish the
baseline and sensitivity system
conditions upon which deterministic
approaches for go/no-go corrective
action transmission build decisions
would be made.’’ 207 EPRI discusses
potential deficiencies in traditional
deterministic approaches in planning
studies in cases where uncertainty and
variability will increase on both the
generation and demand side across a
variety of temperature extremes. EPRI
raises concerns that scenarios or system
conditions that result in consequential
stability implications may not be
adequately captured in the planning
models using the traditional
deterministic approach.208 ACP states
that there is precedent for using
probabilistic tools in assessing electric
reliability, as these methods are widely
used by utilities and RTOs to assess
resource adequacy and loss of load
risk.209
132. Other commenters do not
support a requirement to use
probabilistic methods. For example,
while AEP recognizes the value of
probabilistic methods, it warns that the
industry is not yet ready because the
necessary methods, frameworks, and
tools are not yet available to
transmission planners.210 Several other
commenters warn that it would be
premature to require the use of
probabilistic methods.211 Trade
Associations express concern that
probabilistic planning based on
extremely low probability events is
highly speculative and dependent on
the judgment of planners, which
increases the complexity and risk
associated with the development of
transmission projects, hampering the
construction of needed transmission.212
Idaho Power also does not think
converting to a probabilistic approach is
necessary as sensitivities with
appropriate inputs will capture the
impacts of extreme weather using
deterministic techniques.213 LCRA
comments that probabilistic analysis
requires large samples (i.e., number of
events), but given the infrequent
occurrence of extreme weather events, it
would be challenging to layer
probabilistic assumptions into
transmission planning analyses.214
133. Supporters of the use of
probabilistic methods acknowledge that
implementation poses challenges. For
example, EPRI comments that
implementation of probabilistic
methods would require new processes
to link and communicate data across
models, such as linking generation and
transmission expansion assessments,
resource adequacy, production cost
models, and transmission planning
assessments.215 Further, new statistical
methods and processes will be needed
to inform the selection of powerflow
cases for planning assessments.216 PJM
states that the benefits of applying
probabilistic methods would require
knowing in advance pre-established
bounded parameter ranges, so
209 ACP
Comments at 16.
Comments at 22.
211 APS Comments at 7 (requesting that the
Commission hold ‘‘robust industry-wide
discussions to discuss probabilistic approaches’’);
Tri-State Comments at 8.
212 Trade Associations Comments at 11.
213 Idaho Power Comments at 5.
214 LCRA Comments at 3–4.
215 EPRI Comments at P 25.
216 Id.
210 AEP
204 Id.
P 79.
205 Id.
206 See, e.g., NESCOE Comments at 9; EPRI
Comments at P 24; PJM Comments at 11; EDF
Comments at 20; PIOs Comments at 7; ACEG
Comments at 7; NARUC Comments at 5–6; ACP
Comments at 15; Entergy Comments at 6.
207 PJM Comments at 11.
208 EPRI Comments at P 24.
PO 00000
Frm 00018
Fmt 4701
Sfmt 4700
E:\FR\FM\23JNR3.SGM
23JNR3
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
lotter on DSK11XQN23PROD with RULES3
reasonable selection of probabilistic
method assumptions lead to benchmark
planning cases that reflect statistically
credible scenarios.217 PJM further states
that this should be the result of
coordinated analysis among RTOs,
NOAA, DOE Labs, and NERC.218
Entergy asserts that the probabilistic
approach is significantly more
complicated than deterministic
planning and cautions that any
requirement for probabilistic planning
must have requirements that reasonably
can be performed, are assessable, and
are auditable for compliance.219 Because
of the potential challenges associated
with implementing probabilistic
planning requirements, Tri-State
recommends the further study of and
development of best practices for
probabilistic planning.220
b. Commission Determination
134. Pursuant to section 215(d)(5) of
the FPA, the Commission adopts and
modifies the NOPR proposal and directs
NERC to require in the new or modified
Reliability Standard the use of planning
methods that ensure adequate
consideration of the broad
characteristics of extreme heat and cold
weather conditions. We further direct
NERC to determine during the standard
development process whether
probabilistic elements can be
incorporated into the new or modified
Reliability Standard and implemented
presently by responsible entities. If
NERC identifies probabilistic elements
which responsible entities can feasibly
implement and that would improve
upon existing planning practices, we
expect the inclusion of those methods in
the proposed Reliability Standard.
135. Including probabilistic scenarios
in the planning process could result in
a planning approach that better captures
the uncertainties of extreme weather
events, thus better preparing responsible
entities to ensure Reliable Operation
under stressed conditions.221 Further,
we agree with commenters that the use
of probabilistic methods by responsible
entities would help ensure Reliable
Operation of the Bulk-Power System as
probabilistic methods better
characterize multi-day wide-area events
such as extreme heat and cold events.222
136. However, we recognize, as
certain commenters point out, that a
prescriptive requirement to add
probabilistic planning methods to better
217 PJM
Comments at 11.
218 Id.
219 Entergy
Comments at 9.
Comments at 8.
221 NOPR, 179 FERC ¶ 61,195 at P 76.
222 EPRI Comments at 4.
understand reliability implications
could be met by significant challenges.
Some of the challenges identified by
commenters include lack of
commercially available tools required
for probabilistic modeling and lack of
planning staff trained in the use of these
tools and in carrying out probabilistic
studies. Further, there may be a need to
develop and maintain probabilistic
databases that include, for example,
outage data from extreme weatherdependent grid components and
generation resources.
137. Because of these implementation
concerns, we believe that the best
course of action is to allow NERC to use
its expertise and the standard
development process to address the
concerns identified by commenters and
develop proposed modifications to
existing planning methods that address
the Commission’s directive to use
transmission planning methods that
adequately characterize the effects of
extreme heat and cold weather
conditions on the transmission system,
including incorporating probabilistic
elements where possible. The standard
development process will also provide
an adequate forum in which to evaluate
the many recommendations that
commenters have presented in response
to the NOPR.
138. We also direct NERC to identify
during the standard development
process any probabilistic planning
methods that would improve upon
existing planning practices, but that
NERC deems infeasible to include in the
proposed Reliability Standard at this
time. If any such methods are identified,
NERC shall describe in its petition for
approval of the proposed Reliability
Standard the barriers preventing the
implementation of those probabilistic
elements. We intend to use this
information to determine whether and
what next steps may be warranted to
facilitate the use of probabilistic
methods in transmission system
planning practices.
H. Implement a Corrective Action Plan
if Performance Standards Are Not Met
139. The NOPR noted that under the
currently effective Reliability Standard
TPL–001–5.1, planning coordinators
and transmission planners are required
to evaluate possible actions to reduce
the likelihood or mitigate the
consequences of extreme weather
events, but are not obligated to develop
corrective action plans, even if such
events are found to cause cascading
outages.223 Because of the potential
220 Tri-State
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
223 NOPR, 179 FERC ¶ 61,195 at P 83. Reliability
Standard TPL–001–5.1, Requirements R3.3.5 and
PO 00000
Frm 00019
Fmt 4701
Sfmt 4700
41279
severity of extreme heat and cold
weather events and their likelihood to
cause system instability, uncontrolled
separation, or cascading failures as a
result of a sudden disturbance or
unanticipated failure of system
elements, the NOPR proposed to direct
NERC to require corrective action plans
that include mitigation for any instances
where performance requirements for
extreme heat and cold events are not
met.224
140. Consistent with the existing
requirements of Reliability Standard
TPL–001–5.1, the NOPR proposed to
provide responsible entities with the
flexibility to determine the actions to
include in their corrective action plans
to remedy identified deficiencies in
performance. The NOPR included
several examples of actions that could
be included in a corrective action plan:
planning for additional contingency
reserves or implementing new energy
efficiency programs to decrease load,
increasing intra- and inter-regional
transfer capabilities, transmission
switching, or adjusting transmission and
generation maintenance outages based
on longer-lead forecasts. The NOPR
observed that well-planned mitigation
and corrective actions that account for
some of these contingencies will
minimize loss of load and improve
resilience during extreme heat and cold
weather events.225
141. The NOPR explained that
increases in interregional transfer
capability could be considered as one
option to address potential reliability
issues during extreme weather
events.226 The NOPR noted that such
transfer capability would allow an
entity in one region with available
energy to assist one or more entities in
another region that is experiencing an
energy shortfall due to the extreme
weather event.227 Increasing
interregional transfer capability may be
a particularly robust option for planning
entities attempting to mitigate the risks
associated with concurrent generator
outages over a wide area.228
R4.4.5 require computer simulation analyses of
extreme events listed in Table 1 of the standard
(some listed are examples and are not definitive),
and if the analysis concludes there is cascading
caused by the occurrence of extreme events, an
evaluation of possible actions designed to reduce
the likelihood or mitigate the consequences and
adverse impacts of the event(s) shall be conducted.
224 Id.
225 Id. P 84.
226 Id. P 85.
227 Id.
228 Id. In this proceeding, we refer to interregional
transfer capability strictly in the context of
improving the reliability of the Bulk-Power System
through improved transmission system planning
E:\FR\FM\23JNR3.SGM
Continued
23JNR3
41280
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
142. To ensure the timely
development and implementation of
corrective action plans, the NOPR
sought comments on the timeframe for
developing such corrective action plans
and sharing of the corrective actions
with other interconnected planning
entities.229 In addition, to identify
opportunities for improved wide-area
planning studies and coordination, the
NOPR requested comment on how to
develop corrective action plans that
mitigate issues that require corrective
action by, and coordination among,
multiple transmission owners.230
1. Comments
a. Jurisdictional Issues
143. Several commenters raise
jurisdictional concerns regarding
corrective action plans.231 While
Indicated Trade Associations support
the NOPR proposal to require corrective
action plans addressing vulnerabilities
identified in the study process, they also
urge that the Commission ‘‘remain
mindful’’ of the statutory limitation set
forth in FPA section 215(i) that NERC
and the Commission do not have
authority ‘‘to order the construction of
additional generation or transmission
capacity or to set or enforce compliance
with standards for adequacy or safety of
electric facilities or services.’’ 232 In
particular, Indicated Trade Associations
express concern that certain examples of
potential corrective action plans
mentioned in the NOPR, including
‘‘planning for additional contingency
reserves . . . or increasing intra- and
inter-regional transfer capabilities,’’
exceed the Commission’s authority
under section 215 of the FPA.233
Similarly, Electric Reliability Council of
Texas, Inc. (ERCOT) opines that
‘‘[r]equiring transmission planners to
address what is fundamentally a
resource adequacy concern through the
transmission planning process would
usurp the authority of the states, which
are responsible for ensuring the
adequacy of the generation supply.’’ 234
lotter on DSK11XQN23PROD with RULES3
b. Corrective Action Plans
144. Most commenters agree that
corrective action plans should be
required to address system performance
issues identified in studies under
extreme heat and cold weather
and associated modifications to NERC’s Reliability
Standards.
229 Id.
230 Id. P 67.
231 Indicated Trade Associations Comments at
11–12; ERCOT Comments at 5.
232 Indicated Trade Association Comments at 12
(citing 16 U.S.C. 824o(i)).
233 Id. at 11–12; ERCOT Comments at 5.
234 ERCOT Comments at 5.
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
conditions.235 NERC agrees that any
revised Reliability Standard directed
under a final rule issued in this
proceeding should require that entities
develop corrective action plans for
instances where performance
requirements for selected extreme
weather and environmental conditions
are not met for at least some of the
planning scenarios.
145. BPA asserts that several of the
corrective action plan examples listed in
the NOPR, such as transmission
switching/reconfiguration, or adjusting
transmission and generation
maintenance outages, would likely be
covered by Reliability Standard EOP–
011–2, requiring transmission operators
and balancing authorities to have
operating plans to mitigate operating
emergencies including determining the
reliability impacts of extreme weather
conditions. Therefore, BPA cautioned,
any modifications to Reliability
Standard TPL–001–5.1 should be
careful not to encroach upon the
authority and discretion of transmission
operators and balancing authorities.236
146. Some commenters do not
support the NOPR proposal to require
the development and implementation of
corrective action plans for all instances
where performance requirements for
extreme heat and cold events are not
met. APS asserts that ‘‘corrective action
plans should be focused on the most
likely and impactful events, which may
not include extreme weather scenarios,’’
and that as such, it disagrees that
corrective action plans ‘‘should be
required for results that come out of
sensitivity analysis, which includes
extreme weather scenarios.’’
147. With regard to costs, National
Association of Regulatory Utility
Commissioners (NARUC) asserts that
mitigation and corrective actions to
minimize loss of load and improve
resilience should be subjected to a cost/
benefit analysis.237 Entergy suggests that
the Commission ‘‘provide additional
guidance regarding the level of
performance it expects during extreme
heat and cold events,’’ including
consideration of ‘‘the cost effects on
customers relative to the potential risks
and the time-frame in which those risks
are likely to arise.’’ 238
235 See, e.g., NERC Comments at 10; NARUC
Comments at 6; NESCOE Comments at 3; MISO
Comments at 4.; PJM Comments at 12.
236 BPA Comments at 4.
237 NARUC Comments at 6.
238 Entergy Comments at 2.
PO 00000
Frm 00020
Fmt 4701
Sfmt 4700
c. Generation and Transmission
Capacity Increase and Resource
Adequacy Issues
148. Most commenters agree that the
responsible entities developing
corrective action plans should evaluate
a range of solutions, including
transmission upgrades to increase
interregional transfer capability and/or
building generation to address
generation deficiency under extreme
weather events.239 Some commenters,
however, question the efficacy of
corrective action plans and suggest that
alternative approaches are preferable.
149. With regards to transmission
capacity, and specifically interregional
transfer capabilities, many commenters
agree that adequate interregional
transfer capability would help address
reliability challenges posed by extreme
heat and cold weather conditions.240
Some commenters urge the Commission
to set a minimum interregional transfer
capability requirement.241 However,
most commenters addressing this topic
opine that interregional transfer
requirements, including setting
necessary or minimum transfer levels
and direction, should be addressed
outside of the Reliability Standard TPL–
001–5.1 planning process.242 For
example, MISO Transmission Owners
suggest that interregional transfers could
be better dealt with under Order No.
1000 Regional Transmission Planning
processes.243 MISO recommends that
corrective action plans require
meaningful mitigation, such as
investment in transmission solutions, to
address issues identified in an extreme
weather event study.244 Conversely,
Idaho Power states that if regional
transmission facilities are to be
considered as corrective actions, Idaho
Power would have concerns with the
efficacy of those corrective actions given
the amount of time necessary to build
new transmission.245
150. Most commenters who disagree
with the NOPR proposal to allow
entities to consider additional
generation capacity as a corrective
action plan measure disagree on the
239 See, e.g., NARUC Comments at 6; UCS
Comments at 9; PIOs Comments at 15; AEP
Comments at 5; ACEG Comments at 8; ACP
Comments at 11; Entergy Comments at 8.
240 AEP Comments at 2; ACP Comments at 19;
ACEG Comments at 9; PJM Comments at 12; see
MISO Transmission Owners Comments at 5–6.
241 EDF Comments at 27; AEP Comments at 2;
ACP Comments at 19; ACEG Comments at 9; PJM
Comments at 12.
242 MISO Transmission Owners Comments at 5–
6; ACP Comments at 19; ACEG Comments at 9; AEP
Comments at 2.
243 MISO Transmission Owners Comments at 5.
244 MISO Comments at 4.
245 Idaho Power Comments at 4, 6.
E:\FR\FM\23JNR3.SGM
23JNR3
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
basis that resource adequacy is not a
matter that should be dealt with within
the transmission planning process.246
For example, ISO–NE asserts that the
purpose of Reliability Standard TPL–
001–5.1 is not to ensure resource
adequacy, but to ensure that load can be
served.247 ACP and PIOs question the
efficacy of building new generation as
part of a corrective action plan because
such new generation may be subject to
the same issues as existing generation—
for example, if an extreme cold event
leads to the outage of weather-sensitive
generators, adding more weathersensitive generators will not resolve the
resource deficiency.248
d. Notification to Applicable Regulatory
Authorities or Governing Bodies
Responsible for Retail Electric Service
Issues
151. ACP, New England States
Committee on Electricity (NESCOE),
and Entergy comment that entities must
coordinate with state and local
authorities in the development of
corrective action plans involving
generation and transmission capacity.249
For example, NESCOE suggests that
corrective action plans be informed by
state officials’ perspectives, consider a
variety of mitigation options, and
include a detailed explanation of how
the entity weighed the various
options.250 Additionally, NESCOE
points out that given the likelihood that
corrective action plans will include load
shed, state officials should be involved
in the corrective action plan process.251
NESCOE proposes that responsible
entities seek input from state regulators
during their planning process.
Alternatively, NESCOE recommends the
adoption of the Joint Federal-State Task
Force on Electric Transmission model to
create a similar task force focusing on
extreme weather and grid reliability.252
lotter on DSK11XQN23PROD with RULES3
2. Commission Determination
152. Pursuant to section 215(d)(5) of
the FPA, the Commission adopts and
modifies the NOPR proposal and directs
NERC to require in the new or modified
Reliability Standard the development of
extreme weather corrective action plans
246 See, e.g., PJM Comments at 12; ERCOT
Comments at 5; ISO–NE Comments at 4.
247 ISO–NE Comments at 4.
248 ACP Comments at 6; PIOs Comments at 16.
249 See ACP Comments at 18; NESCOE Comments
at 3; see also Entergy Comments at 9 (stating in the
context of the development of corrective action
plans that ‘‘[t]he Commission also should ensure
that the relevant retail regulators have input into
the level of risks versus costs a transmission owner
should accept.’’).
250 NESCOE Comments at 3.
251 Id. at 5.
252 Id. at 6.
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
for specified instances when
performance standards are not met. In
addition, as explained below, we direct
NERC to develop certain processes to
facilitate interaction and coordination
with applicable regulatory authorities or
governing bodies responsible for retail
electric service as appropriate in
implementing a corrective action plan.
153. We adopt our rationale set forth
in the NOPR and conclude that the
directive to require the development of
corrective action plans is needed for
Reliable Operation of the Bulk-Power
System. Under the currently effective
Reliability Standard TPL–001–5.1,
planning coordinators and transmission
planners are required to evaluate
possible actions to reduce the likelihood
or mitigate the consequences of extreme
weather events, but are not obligated to
develop corrective action plans, even if
such events are found to cause
cascading outages. Experience over the
past decade has demonstrated that the
potential severity of extreme heat and
cold weather events exacerbates the
likelihood to cause system instability,
uncontrolled separation, or cascading
failures as a result of a sudden
disturbance or unanticipated failure of
system elements. Thus, we conclude
that entities should proactively address
known system vulnerabilities by
developing corrective action plans that
include mitigation for specified
instances where performance
requirements for extreme heat and cold
events are not met.
a. Jurisdictional Issues
154. We reject the arguments that our
directive to require responsible entities
to develop corrective action plans may
exceed the Commission’s jurisdiction.
Section 215(i)(2) of the FPA states that
the Commission and ERO are not
authorized to order the construction of
additional generation or transmission
capacity as part of a Reliability
Standard.253 Consistent with this
limitation, the final rule does not
require any responsible entity to engage
in the construction of additional
generation or transmission capacity.
Moreover, while the final rule directs
NERC to include in a new or modified
Reliability Standard a requirement for
entities to develop a corrective action
plan to address extreme heat and cold
weather events during the transmission
planning process, the final rule does not
mandate the use of any specific
mitigation measure.254
253 16
U.S.C. 824o(i)(2).
179 FERC ¶ 61,195 at P 84 (‘‘we believe
it is appropriate to provide responsible entities with
the flexibility to determine the best actions to
254 NOPR,
PO 00000
Frm 00021
Fmt 4701
Sfmt 4700
41281
155. As noted by commenters, the
NOPR provided examples of various
activities that may be appropriate under
a corrective action plan, some of which
may require state or local authorizations
(e.g., generation or transmission
development).255 Other examples
mentioned in the NOPR include
‘‘implementing new energy efficiency
programs to decrease load, . . .
transmission switching, or adjusting
transmission and generation
maintenance outages based on longerlead forecasts,’’ 256 none of which
involve the construction of generation
or transmission capacity. In addition,
responsible entities have the option to
use controlled load shed as a mitigation
measure. In sum, while responsible
entities would have the obligation to
develop and implement a corrective
action plan, the Commission is not
directing any specific result or content
of the corrective action plan. In such
circumstances, the Commission’s
directive does not exceed the
jurisdictional limits set forth in section
215(i) of the FPA.257
156. In response to ERCOT and other
commenters, the Commission’s action
does not usurp state authority with
regard to resource adequacy. As
explained above, the directive that
responsible entities develop corrective
action plans in certain circumstances
does not require the construction of
additional generation or transmission
capacity. Further, as discussed below,
responsible entities that elect mitigation
activities that involve increased
transmission or generation capacity will
of course be subject to the authority of
such state agencies or others with legal
jurisdiction over the construction of
transmission or generation facilities.
b. Circumstances That Require
Corrective Action Plans
157. As stated above, we adopt and
modify the NOPR proposal and direct
NERC to require in the new or modified
Reliability Standard the development of
corrective action plans that include
mitigation for specified instances where
performance requirements for extreme
heat and cold events are not met—i.e.,
when certain studies conducted under
the Standard show that an extreme heat
or cold event would result in cascading
outages, uncontrolled separation, or
instability.258 We agree with APS that
include in their corrective action plan to remedy
any identified deficiencies in performance’’).
255 Id.
256 Id.
257 S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 80
(D.C. Cir. 2014).
258 NOPR, 179 FERC ¶ 61,195 at P 83.
E:\FR\FM\23JNR3.SGM
23JNR3
41282
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
lotter on DSK11XQN23PROD with RULES3
neither version 4 nor 5.1 of Reliability
Standard TPL–001–5.1 require
corrective action plans for extreme heat
and cold weather events. Extreme heat
and cold weather events, which pose a
serious risk to the Reliable Operation of
the Bulk-Power System, are increasing
in frequency and intensity. We believe
that in taking steps to avoid occurrences
of cascading outages, uncontrolled
separation, or instability under extreme
heat and cold, corrective action plans
would also minimize the extent and
duration of loss of load and improve
Bulk-Power System resilience during
extreme heat and cold weather
events.259
158. Although the NOPR proposed
requiring the development of corrective
action plans for any instance where
performance requirements for extreme
heat and cold events are not met, we
give NERC in this final rule the
flexibility to specify the circumstances
that require the development of a
corrective action plan. For example,
NERC should determine whether
corrective action plans should be
required for single or multiple
sensitivity cases, and whether corrective
action plans should be developed if a
contingency event that is not already
included in benchmark planning case
would result in cascading outages,
uncontrolled separation, or
instability.260 Because we also direct
NERC to establish required study
contingencies and baseline
sensitivities,261 we believe it is
necessary for NERC to develop those
aspects of the Standard prior to
determining the instances under which
corrective action plans must be
developed.
159. With regard to BPA’s suggestion
that Reliability Standard EOP–011–2
already addresses certain mitigation
measures listed in the NOPR as
examples, we clarify that nothing in the
final rule affects the responsibilities or
obligations of registered entities under
that Reliability Standard and note that
there are important differences in the
scope and intent of EOP–011–2 and the
Reliability Standard we are directing be
developed here. Specifically, while
Reliability Standard EOP–011–2
includes provisions to determine
reliability impacts of extreme cold
conditions and extreme weather
conditions,262 it does not require the
transmission operator to mitigate the
259 Id.
P 84.
Reliability Standard TPL–001–5.1,
corrective action plans are not required for single
sensitivity cases.
261 See supra PP 111, 124.
262 Reliability Standard EOP–011–2, Requirement
1.2.6.
260 Under
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
condition. In addition, Reliability
Standard EOP–011–2 addresses the
issues within the operating time frame.
Corrective action plans, as proposed in
the NOPR, would be developed in the
planning horizon to address the issues
in the long-term planning time frame.
Simultaneously, such issues would be
addressed by Reliability Standard EOP–
011–2 in the operating time frame
should the studied extreme weather
condition occur. As such, there would
not be any encroachment or conflict
between the two standards.
160. With respect to arguments from
NARUC and Entergy that the
Commission should require cost-benefit
analysis for corrective action plans or
otherwise provide additional guidance
as to the cost impacts on customers, we
decline to do so. FPA section 215 does
not require the use of cost-benefit
analysis and, given the flexibility
allowed to responsible entities in
crafting a corrective action plan, we are
not persuaded such a requirement
would be warranted in this instance.
Regarding the cost impact on customers
more generally, we believe that NERC
should have an opportunity in the first
instance to balance such impacts and
present a new or modified Reliability
Standard for Commission approval. As
articulated in Order No. 672, the cost of
compliance is but one factor in
determining whether to approve a
proposed Reliability Standard and we
will consider the potential cost impacts
in the context of the larger record.263
c. Generation and Transmission
Capacity Increase and Resource
Adequacy Issues
161. As discussed above, corrective
action plans are not required to use any
specific mitigation measure and
responsible entities are not required to
build transmission or generation.
Nevertheless, some entities may choose
to include additional transmission or
generation capacity as a mitigation
measure in their corrective action plan,
subject to the approval of relevant
regulatory authorities.
162. With respect to the use of
transmission as a mitigation measure, as
stated in the NOPR and echoed by
commenters, interregional transfer
capability can be a solution to some
extreme weather-related reliability
concerns. We recognize that a proposal
by a planning entity to increase its
interregional transfer capability to
address the impact of extreme heat and
cold conditions on its portion of the
Bulk-Power System may be acceptable
263 See
d. Notification to Applicable Regulatory
Authorities or Governing Bodies
Responsible for Retail Electric Service
Issues
165. We direct NERC to require in the
new or modified Reliability Standard
that responsible entities share their
corrective action plans with, and solicit
feedback from, applicable regulatory
authorities or governing bodies
responsible for retail electric service
issues. We agree with commenters that
relevant state entities should have the
opportunity to provide input during the
Order No. 672, 114 FERC ¶ 61,104 at P
264 Idaho
330.
PO 00000
in a corrective action plan, and we
expect that the benchmark planning
cases developed, and wide-area studies
conducted under this Standard could be
beneficial for purposes of determining
interregional transfer needs. However,
we decline to set a minimum
interregional transfer capability
requirement in this proceeding and note
the Commission’s ongoing pending
proceeding addressing such a
requirement in Docket No. AD23–3.
163. Regarding Idaho Power’s concern
given the amount of time necessary to
build new transmission,264 we note that
corrective action plans address
deficiencies identified in a long-term
transmission planning timeframe (i.e.,
six to ten years and beyond). The period
associated with a transmission project
will inform whether and when that
project may be included in an extreme
weather corrective action plan. For
example, a transmission project that is
not expected to be operational in the
six-to-ten-year long-term horizon may
not be relied upon in an extreme
weather corrective action plan to
mitigate identified system deficiencies
within that time horizon. In that
circumstance, the responsible entity
will have to develop an extreme weather
corrective action plan that includes
other measures that can be implemented
to ensure Reliable Operation of its
portion of the Bulk-Power System.
164. With respect to concerns that
generation capacity is not appropriately
included in corrective because it should
be addressed through resource adequacy
processes, we reiterate our findings
above in section IV.F that the purpose
of the new or modified Standard is to
address transmission system
deliverability and not to supplant or
duplicate resource adequacy processes.
With respect to concerns from PIOs and
ACP that generation may be ineffective
as a mitigation measure, we note that
responsible entities have the flexibility
to determine the appropriate mitigation
measure for their circumstances.
Frm 00022
Fmt 4701
Sfmt 4700
E:\FR\FM\23JNR3.SGM
Power Comments at 4, 6.
23JNR3
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
lotter on DSK11XQN23PROD with RULES3
development of corrective action plans.
Just as this final rule seeks to ensure
Reliable Operation of the Bulk-Power
System during extreme heat and cold
weather events, regulatory authorities
and governing bodies responsible for
retail electric service are taking actions
to ensure reliability for local
stakeholders. As such, we believe that
requiring responsible entities to seek
input from applicable regulatory
authorities or governing bodies
responsible for retail electric service
issues when developing corrective
action plans could help ensure that
shared opportunities to increase system
reliability are not missed. Further, as
NESCOE points out, such consultation
may allow these entities to better
understand ‘‘the cost implications of
various approaches’’ and, therefore,
provide ‘‘better insight into the
considerations and tradeoffs inherent in
the options available.’’ 265
166. We also agree with NESCOE that
sharing corrective action plans with
applicable regulatory authorities or
governing bodies responsible for retail
electric service is necessary given the
possibility that corrective action plans
could include load shedding.266 As the
Commission has stated in the past, we
believe that the public should have
notice and understanding of a
responsible entity’s plans to shed nonconsequential load.267 Therefore, just as
Reliability Standard TPL–001–5.1
requires planning coordinators and
transmission planners to notify
stakeholders, including applicable
regulatory authorities or governing
bodies responsible for retail electric
service, of their intent to include nonconsequential load loss in corrective
action plans for certain singlecontingency events,268 the new or
modified Reliability Standard must also
require responsible entities to similarly
communicate their intent to use nonconsequential load shed in their
extreme weather corrective action plans.
167. Further, because an important
goal of transmission planning is to avoid
load shed,269 any responsible entity that
includes non-consequential load loss in
its corrective action plan should also
identify and share with applicable
regulatory authorities or governing
bodies responsible for retail electric
service alternative corrective actions
that would, if approved and
implemented, avoid the use of load
265 NESCOE
266 Id.
Comments at 4.
at 5.
267 Transmission
Planning Reliability Standards,
Order No. 762, 77 FR 26686 (May 7, 2012), 139
FERC ¶ 61,060, at P 65 (2012).
268 Reliability Standard TPL–001–5.1, at attach. 1.
269 Order No. 693, 118 FERC ¶ 61,218 at P 1,795.
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
shedding. Examples could include
building additional generation and/or
transmission capacity, energy efficiency
programs, and demand load response
programs.270
168. While we direct NERC to require
registered entities to communicate the
results of their studies and share their
extreme weather corrective action plans
with applicable regulatory authorities or
governing bodies responsible for retail
electric service, NERC should not
attempt to mandate that entities which
are not under the Commission’s
jurisdiction participate in the
development of corrective action plans.
I. Other Extreme Weather-Related
Events and Issues
169. While the NOPR focused on
extreme heat and cold weather events,
the NOPR recognized that long-term
drought, particularly when occurring in
conjunction with high temperatures,
could also pose a serious risk to BulkPower System reliability over a wide
geographical area. In the NOPR, the
Commission raised a concern that
drought may cause or contribute to
conditions that affect reliable operation
of the Bulk-Power System such as
transmission outages, reduced plant
efficiency, and reduced generation
capacity. The Commission sought
comment on whether drought should be
included along with extreme heat and
cold weather events within the scope of
the Reliability Standard.271
Additionally, the Commission invited
comment on whether other extreme
events with significant impact on the
reliability of the Bulk-Power System
could also be considered and modeled
in the future.272
1. Comments
170. Indicated Trade Associations,
EDF, and ACP support including the
consideration of drought with extreme
heat and cold weather events within the
scope of the new or modified Reliability
Standard.273 NERC agrees, suggesting
that drought conditions be studied in
drought-prone areas of the country.274
EDF notes that drought events can
significantly impact the capacity and
operation of water-cooled fossil and
nuclear generators and other watercooled assets, as well as hydroelectric
generators. EDF also asserts that drought
270 To be clear, responsible entities may also
pursue such mitigating actions in the first instance,
subject to the approval of relevant regulatory
authorities. See supra P 161.
271 NOPR, 179 FERC ¶ 61,195 at P 92.
272 Id. P 93.
273 Indicated Trade Associations Comments at 13;
EDF Comments at 19; ACP Comments at 18–19.
274 NERC Comments at 12.
PO 00000
Frm 00023
Fmt 4701
Sfmt 4700
41283
events are also highly correlated with
high temperature and wildfires.
Therefore, according to EDF, a failure to
consider drought impacts could result
in an overestimation of generation
availability during an extreme heat
weather event and understate the risks
of that event.275
171. Similarly, Indicated Trade
Associations note that they support the
study of long-term drought impacts on
relevant generation (e.g., hydro-electric,
geothermal, and nuclear generation) in
regions where drought has been, or may
plausibly become, an issue. They add
that droughts are sustained long-term
conditions that may be fundamentally
studied and addressed differently—for
example, as a fuel supply sensitivity—
than a short-term extreme heat or cold
weather event.276 However, Indicated
Trade Associations believe that the
Commission should not attempt to
address all types of extreme weather
events at once in the Reliability
Standard, but rather take a phased
approach.277
172. ACP states ‘‘[b]ecause drought
events are already widespread across all
regions, and climate change will make
them even more frequent and
widespread, it would be prudent for the
Commission and NERC to require all
regions to include drought in their
analysis of severe weather benchmark
events under TPL–001.’’ 278
173. Tri-State notes that drought is
already sufficiently included in the
resource forecasts developed by
Resource Planners.279
174. Certain commenters support the
inclusion of extreme weather events
beyond heat, cold and drought. For
example, NERC identifies extreme
weather conditions for inclusion in
required studies, such as high winds,
diminished winds, dust, smoke, fog, and
increased cloud cover.280 According to
NERC, such long-term, widespread
weather and environmental conditions
can impact resource availability and the
transmission system. Other commenters
suggest the inclusion of other extreme
weather events such as wildfires,
hurricanes, and tornadoes; 281 rain and
wind (including derechos), and ice
storms; 282 debris flow (landslide risk
following wildfire scars and heavy
275 EDF
Comments at 24.
Trade Associations Comments at 13.
276 Indicated
277 Id.
278 ACP
Comments at 10.
Comments at 8.
280 NERC Comments at 12.
281 EDF Comments at 25.
282 AEP Comments at 5.
279 Tri-State
E:\FR\FM\23JNR3.SGM
23JNR3
41284
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
precipitation) and rain-on-snow events
that may lead to dam overtopping.283
175. EPRI points out that certain
extreme weather events such as
hurricanes or flooding can and do often
occur independent of extreme heat and
cold events. As such, EPRI states that
the standard should identify climate
and weather-related threats that occur
concurrently or independently based on
the planning area’s local footprint and
develop scenarios accordingly.284
176. In contrast, MISO and LCRA
comment that the Reliability Standard
should be limited to extreme heat and
cold events. MISO also comments that
there is a fundamental difference
between extreme heat and cold events
and other extreme weather events:
extreme temperature events would
likely result in the load increasing and
continuing to stay online, while other
extreme weather events such as
hurricanes or tornados create the
possibility of load loss. MISO also
points out that the operation horizon
will continue to prepare for situations
like hurricanes, tornados, or ice
storms.285 Likewise, LCRA adds that
drought and other extreme weather
events beyond extreme temperature are
already modeled by existing extreme
event contingencies.286
lotter on DSK11XQN23PROD with RULES3
2. Commission Determination
177. We decline to direct NERC to
create or modify a Reliability Standard
to specifically require the assessment of
the impacts of drought conditions as
part of extreme heat and cold
transmission system planning. As
explained above, the type of long-term
meteorological study involved in
extreme heat and cold event
transmission planning necessarily
includes examining the extreme weather
impact on base climate conditions over
the study period, conditions that would
have to include anticipated drought
conditions in relevant planning areas.287
178. We agree with various
commenters that drought conditions
may impact reliability,288 and drought
impacts on generation are already
studied in the resource forecasts
developed by resource planners and
mitigated by operating procedures.
Additionally, droughts that may occur
concurrently with extreme heat and
cold events will be included in the
benchmark planning case, as drought
conditions would be present in the
283 SCE
Comments at 6–7.
Comments at P 29.
285 MISO Comments at 2.
286 LCRA Comments at 4.
287 See supra P 114
288 See e.g., EDF Comments at 24.
meteorological data that feeds the
benchmark planning case,289 and the
possibility of more severe drought could
be reflected as part of a sensitivity
analysis.290
179. Regarding other extreme weather
events such as NERC’s concern with
high winds, diminished winds, dust,
smoke, smog fog, extreme snowstorms,
flooding and increased cloud cover, and
extreme snowstorms, or other
commenters recommendations to
include hurricanes, tornados, heavy rain
and wind, and ice storms; and adjacent
events such as wildfires, debris flow,
and flooding, we agree that these
conditions may affect the Bulk-Power
System. However, we are not persuaded
that a directive to address these events
in the new or modified Reliability
Standard is warranted at this time.
180. As MISO indicates, there are
fundamental differences between
extreme heat and cold events and other
extreme weather events that cast doubt
as to whether this Reliability Standard
is the correct vehicle for addressing
their impacts.291 For instance, extreme
heat and cold events generally affect
large geographic areas, while other
extreme weather and adjacent events
such as tornadoes, hurricanes, storms,
floods, and wildfires tend to have more
localized impacts. Moreover, as MISO
points out, extreme heat and cold
weather events are typically
characterized by potential sustained
load increases, while other extreme
weather events typically result in load
losses.
J. Reliability Standard Development and
Implementation Timeline
181. The Commission proposed to
direct NERC to develop a new or
modified Reliability Standard within
one year of the effective date of a final
rule in this proceeding, with
compliance obligations beginning no
later than 12 months from Commission
approval of the proposed Reliability
Standard.292
1. Comments
182. NERC raises no concerns with
the proposed 12-month proposal to
create a new or modified Reliability
Standard; however, NERC requests that
the Commission consider coordinating
the timing of this final rule to allow
NERC to benefit from the informational
filings in Docket Nos. RM22–16–000
and AD21–13–000, as information
obtained from these reports ‘‘may prove
284 EPRI
VerDate Sep<11>2014
19:38 Jun 22, 2023
289 See
supra note 155.
supra P 114 and note 155.
291 MISO Comments at 2.
292 NOPR, 179 FERC ¶ 61,195 at P 48.
290 See
Jkt 259001
PO 00000
Frm 00024
Fmt 4701
Sfmt 4700
useful to the NERC standard
development process.’’ 293
183. PJM and MISO Transmission
Owners state that one year will not be
enough time to develop the proposed
Reliability Standard.294 PJM states that
such a short timeframe will hamper
stakeholder input.295 PJM further
comments that the NOPR’s proposed
timeline for standard development is
not ‘‘sequenced with any of the other
activities associated with ensuring
enhanced reliability planning’’ and will
thus ‘‘divert resources from the more
comprehensive work that is needed in
this area.’’ 296 MISO Transmission
Owners agree that ‘‘one year’s time is
not long enough’’ to modify or create a
new Reliability Standard, and the
Commission should give NERC ‘‘more
time.’’ 297
184. Regarding the effective date of
any resulting Reliability Standard,
NERC requests that the Commission
clarify the proposed implementation
schedule, i.e., ‘‘whether entities must
begin to comply with all new study
requirements within one year of
Commission approval (i.e., completed
studies with Corrective Action Plans
developed), or whether a phased-in
approach beginning no later than one
year is permitted for entities to
coordinate on the development of new
models, collect new data, and perform
the necessary coordination to study
wide area impacts before completing
studies and developing any associated
Corrective Action Plans.’’ 298
185. PJM also states that one year is
not enough time for responsible entities
to implement the new or revised
Reliability Standard, because after
Commission approval ‘‘Transmission
Providers like PJM will have
responsibility to translate it into
workable planning process
methodologies and related stakeholderapproved manual language.’’ 299
186. PJM further calls for flexibility
on setting start dates for the
implementation period for different
293 NERC Comments at 14. In Docket Nos. RM22–
16–000 and AD21–13–000, the Commission
proposes directing transmission providers to submit
one-time informational reports describing their
current or planned policies and processes for
conducting extreme weather vulnerability
assessments. One-Time Informational Reports on
Extreme Weather Vulnerability Assessments;
Climate Change, Extreme Weather, & Elec. Sys.
Reliability, Notice of Proposed Rulemaking, 87 FR
39414 (July 1, 2022), 179 FERC ¶ 61,196 (2022)
(Informational Reports NOPR).
294 PJM Comments at 14; MISO Transmission
Owners Comments at 7.
295 PJM Comments at 14.
296 Id.
297 MISO Transmission Owners Comments at 7.
298 NERC Comments at 14–15.
299 PJM Comments at 14–15.
E:\FR\FM\23JNR3.SGM
23JNR3
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
entities given variances in regional
planning cycles.300 APS echoes the call
for flexibility as to the timeframe for
developing a corrective action plan as
the potential mitigation strategies may
vary or include neighboring entities.301
187. AEP proposes that the
Commission provide responsible
entities ‘‘at least two years to implement
stability analysis’’ after the proposed
Reliability Standard takes effect, and
that corrective action plans be
developed ‘‘within one year of the
assessment of reliability deficiency.’’ 302
2. Commission Determination
lotter on DSK11XQN23PROD with RULES3
188. We direct NERC to submit a new
or modified Reliability Standard within
18 months of the date of publication of
this final rule in the Federal Register.
Further, we direct NERC to propose an
implementation timeline for the new or
modified Reliability Standard, with
implementation beginning no later than
12 months after the effective date of a
Commission order approving the
proposed Reliability Standard.
189. We agree with NERC that it is
important to coordinate the timeline for
the development of a Reliability
Standard under this proceeding with
that of the extreme weather one-time
informational reports required under
Docket Nos. RM22–16–000 and AD21–
13–000.303 The Informational Reports
Final Rule, which is being issued
concurrently with this final rule, directs
responsible entities to develop and file
with the Commission within 120 days of
that order’s publication in the Federal
Register a one-time informational report
‘‘describing their current or planned
policies and processes for conducting
extreme weather vulnerability
assessments.’’ 304 The Informational
Reports Final Rule further states that
public comments will be due 60 days
after the reports are filed.305 These
informational reports may assist the
standard drafting team’s efforts in
developing the proposed Reliability
Standard, as they will be helpful for
determining whether and to what extent
transmission providers are already
considering the impacts of extreme
weather events. We believe that
extending the NOPR’s proposed
standard development timeline is
appropriate to ensure that NERC can
benefit from the information obtained
300 Id.
301 APS
Comments at 8.
Comments at 13, 24.
303 Final Rule, Order No. 897, 183 FERC ¶ 61,192
(2023) (‘‘Informational Reports Final Rule’’).
304 Id. PP 1, 3.
305 Id. P 104.
302 AEP
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
from these reports, as well as from
public comments on the reports.
190. With regards to PJM and MISO
Transmission Owners’ comments, we
recognize that the NOPR proposed an
ambitious development timeline for the
proposed Reliability Standard. As we
indicated in the NOPR, the negative
impact of extreme weather on the
reliability of the Bulk-Power System
demands an urgent response. Further,
we note that NERC, the entity
responsible for the development of the
Reliability Standard, did not raise
concerns about the NOPR’s proposed
development timeline. As such, we are
not persuaded that there is a present
need to extend the deadline to submit
a proposed Reliability Standard further
than what is necessary to ensure that
NERC can benefit from the data
obtained as a result of the one-time
informational reports.
191. Accordingly, we direct NERC to
submit a proposed Reliability Standard
within 18 months of the date of
publication of this final rule in the
Federal Register. We believe that
extending the development timeline by
six months should be sufficient to
ensure that the standard drafting team
will be able to take advantage of the
one-time reports required by the
Commission under Docket Nos. RM22–
16–000 and AD21–13–000.
192. We decline to direct NERC to
ensure that entities fully comply with
all new requirements within one year of
Commission approval (i.e., completed
studies with corrective action plans
developed). As AEP and PJM note in
their comments, the new or modified
Reliability Standard will require
significant implementation efforts.
Given the complexities and multiple
stages of activity that would be involved
in compliance with the directives in this
final rule, we believe that a more
flexible implementation approach is
appropriate.
193. We therefore direct NERC to
establish an implementation timeline
for the proposed Reliability Standard. In
complying with this directive, NERC
will have discretion to develop a
phased-in implementation timeline for
the different requirements of the
proposed Reliability Standard (i.e.,
developing benchmark cases,
conducting studies, developing
corrective action plans). However, this
phased-in implementation must begin
within 12 months of the effective date
of a Commission order approving the
proposed Reliability Standard and must
include a clear deadline for
implementation of all requirements.
PO 00000
Frm 00025
Fmt 4701
Sfmt 4700
41285
V. Information Collection Statement
194. The information collection
requirements contained in this final rule
are subject to review by the Office of
Management and Budget (OMB) under
section 3507(d) of the Paperwork
Reduction Act of 1995.306 OMB’s
regulations require approval of certain
information collection requirements
imposed by agency rules.307 Upon
approval of a collection of information,
OMB will assign an OMB control
number and expiration date.
Respondents subject to the filing
requirements of this rule will not be
penalized for failing to respond to this
collection of information unless the
collection of information displays a
valid OMB control number.
195. The directives to NERC to
develop a new Reliability Standard or
modify existing Reliability Standard
TPL–001 (Transmission System
Planning Performance Requirements),
are covered by, and already included in,
the existing OMB-approved information
collection FERC–725 (Certification of
Electric Reliability Organization;
Procedures for Electric Reliability
Standards; OMB Control No. 1902–
0225), under Reliability Standards
Development.308 The reporting
requirements in FERC–725 include the
ERO’s overall responsibility for
developing Reliability Standards, such
as the TPL–001 Reliability Standard,
which is designed to ensure the BulkPower System will operate reliably over
a broad spectrum of system conditions
and following a wide range of probable
contingencies.309 The Commission will
submit to OMB a request for a nonsubstantive revision of FERC–725 in
connection with this final rule.
VI. Environmental Analysis
196. The Commission is required to
prepare an Environmental Assessment
or an Environmental Impact Statement
for any action that may have a
significant adverse effect on the human
306 44
U.S.C. 3507(d).
CFR 1320.11.
308 Reliability Standards Development as
described in FERC–725 covers standards
development initiated by NERC, the Regional
Entities, and industry, as well as standards the
Commission may direct NERC to develop or
modify. The information collection associated with
this final rule ordinarily would be a non-material
addition to FERC–725. However, an information
collection request unrelated to this final rule is
pending review under FERC–725 at the Office of
Management and Budget. To submit this final rule
timely to OMB, we will submit this to OMB as a
temporary placeholder under FERC–725(1A), OMB
Control No. 1902–0289.
309 Reliability Standard TPL–001–4, Purpose.
307 5
E:\FR\FM\23JNR3.SGM
23JNR3
41286
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
environment.310 The Commission has
categorically excluded certain actions
from this requirement as not having a
significant effect on the human
environment. Included in the exclusion
are rules that are clarifying, corrective,
or procedural or that do not
substantially change the effect of the
regulations being amended.311 The
actions directed here fall within this
categorical exclusion in the
Commission’s regulations.
VII. Regulatory Flexibility Act
197. The Regulatory Flexibility Act of
1980 (RFA) 312 generally requires a
description and analysis of final rules
that will have significant economic
impact on a substantial number of small
entities.
198. This final rule directs NERC, the
Commission-certified ERO, to develop a
new or modified Reliability Standard
that requires long-term transmission
system planning designed to prepare for
extreme heat and cold weather events.
Therefore, this final rule will not have
a significant or substantial impact on
entities other than NERC. Consequently,
the Commission certifies that this final
rule will not have a significant
economic impact on a substantial
number of small entities.
199. Any Reliability Standards
proposed by NERC in compliance with
VIII. Document Availability
200. In addition to publishing the full
text of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov). At this time, the
Commission has suspended access to
the Commission’s Public Reference
Room due to the President’s March 13,
2020 proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19).
201. From FERC’s Home Page on the
internet, this information is available on
eLibrary. The full text of this document
is available on eLibrary in PDF and
Microsoft Word format for viewing,
printing, and/or downloading. To access
this document in eLibrary, type the
docket number excluding the last three
digits of this document in the docket
number field.
202. User assistance is available for
eLibrary and the FERC’s website during
normal business hours from FERC
Online Support at (202) 502–6652 (toll
free at 1–866–208–3676) or email at
ferconlinesupport@ferc.gov, or the
Public Reference Room at (202) 502–
8371, TTY (202) 502–8659. Email the
Public Reference Room at
public.referenceroom@ferc.gov.
IX. Effective Date and Congressional
Notification
203. This rule will become effective
September 21, 2023. The Commission
has determined, with the concurrence of
the Administrator of the Office of
Information and Regulatory Affairs of
OMB, that this rule is not a ‘‘major rule’’
as defined in section 351 of the Small
Business Regulatory Enforcement
Fairness Act of 1996.
By the Commission. Commissioner Danly is
concurring in part.
Issued: June 15, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
The following appendix will not
appear in the Code of Federal
Regulations.
Appendix A: Commenter Names
Acronyms
Commenter name
ACP ..............................................
ACEG ...........................................
AEP ..............................................
Ampjack ........................................
APS ..............................................
BPA ..............................................
EDF ..............................................
Indicated Trade Associations .......
American Clean Power Association.
Americans for a Clean Energy Grid.
American Electric Power Service Corporation.
Ampjack Industries Ltd.
Arizona Public Service Company.
Bonneville Power Administration.
Environmental Defense Fund.
The Edison Electric Institute (EEI), the American Public Power Association (APPA), the Large Public Power
Council (LPPC), the National Rural Electric Cooperative Association (NRECA), and the Transmission Access Policy Study Group (TAPS).
Entergy Services, LLC.
Electric Power Research Institute.
Electric Power Supply Association.
Electric Reliability Council of Texas, Inc.
Eversource Energy Service Company.
Idaho Power Company.
ISO New England Inc.
LCRA Transmission Services Corporation.
Louisiana Public Service Commission.
Midcontinent Independent System Operator, Inc.
Entergy .........................................
EPRI .............................................
EPSA ............................................
ERCOT .........................................
Eversource ...................................
Idaho Power .................................
ISO–NE ........................................
LCRA ............................................
Louisiana PSC ..............................
MISO ............................................
lotter on DSK11XQN23PROD with RULES3
this rulemaking will be considered by
the Commission in future proceedings.
As part of any future proceedings, the
Commission will make determinations
pertaining to the Regulatory Flexibility
Act based on the content of the
Reliability Standards proposed by
NERC.
310 Regul. Implementing the Nat’l Env’t Pol’y Act,
Order No. 486, 52 FR 47897 (Dec. 17, 1987), FERC
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
Stats. & Regs. ¶ 30,783 (1987) (cross-referenced at 41
FERC ¶ 61,284).
PO 00000
Frm 00026
Fmt 4701
Sfmt 4700
311 18
312 5
E:\FR\FM\23JNR3.SGM
CFR 380.4(a)(2)(ii) (2022).
U.S.C. 601–612.
23JNR3
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules and Regulations
Acronyms
Commenter name
MISO Transmission Owners ........
Ameren Services Company, as agent for Union Electric Company d/b/a Ameren Missouri, Ameren Illinois
Company d/b/a Ameren Illinois and Ameren Transmission Company of Illinois; American Transmission
Company LLC; Big Rivers Electric Corporation; Central Minnesota Municipal Power Agency; City Water,
Light & Power (Springfield, IL); Cleco Power LLC; Cooperative Energy; Dairyland Power Cooperative;
Duke Energy Business Services, LLC for Duke Energy Indiana, LLC; East Texas Electric Cooperative;
Entergy Arkansas, LLC; Entergy Louisiana, LLC; Entergy Mississippi, LLC; Entergy New Orleans, LLC;
Entergy Texas, Inc.; Great River Energy; GridLiance Heartland LLC; Hoosier Energy Rural Electric Cooperative, Inc.; Indiana Municipal Power Agency; Indianapolis Power & Light Company; International Transmission Company d/b/a ITCTransmission; ITC Midwest LLC; Lafayette Utilities System; Michigan Electric
Transmission Company, LLC; MidAmerican Energy Company; Minnesota Power (and its subsidiary Superior Water, L&P); Missouri River Energy Services; Montana-Dakota Utilities Co.; Northern Indiana Public
Service Company LLC; Northern States Power Company, a Minnesota corporation, and Northern States
Power Company, a Wisconsin corporation, subsidiaries of Xcel Energy Inc.; Northwestern Wisconsin Electric Company; Otter Tail Power Company; Prairie Power, Inc.; Republic Transmission, LLC; Southern Illinois Power Cooperative; Southern Indiana Gas & Electric Company (d/b/a CenterPoint Energy Indiana
South); Southern Minnesota Municipal Power Agency; Wabash Valley Power Association, Inc.; and Wolverine Power Supply Cooperative, Inc.
National Association of Regulatory Utility Commissioners.
North American Electric Reliability Corporation.
New England States Committee on Electricity.
National Mining Association.
New York Independent System Operator, Inc.
New York State Reliability Council.
Federal Energy Advocate for the Public Utilities Commission of Ohio.
Pacific Gas and Electric Company.
Public Interest Organizations (Sustainable FERC Project, Natural Resources Defense Council, American
Council on Renewable Energy, Sierra Club, Southern Environmental Law Center, Western Resource Advocates).
PJM Interconnection, L.L.C.
Southern California Edison Company.
Sunflower Electric Power Corporation.
Tri-State Generation and Transmission Association, Inc.
Union of Concerned Scientists.
Working for Advanced Transmission Technologies.
WE ACT for Environmental Justice.
NARUC .........................................
NERC ...........................................
NESCOE ......................................
NMA ..............................................
NYISO ..........................................
NYSRC .........................................
Ohio FEA ......................................
PG&E ............................................
PIOs ..............................................
PJM ..............................................
SCE ..............................................
Sunflower ......................................
Tri-State ........................................
UCS ..............................................
WATT ...........................................
WE ACT .......................................
[FR Doc. 2023–13286 Filed 6–22–23; 8:45 am]
BILLING CODE 6717–01–P
lotter on DSK11XQN23PROD with RULES3
41287
VerDate Sep<11>2014
19:38 Jun 22, 2023
Jkt 259001
PO 00000
Frm 00027
Fmt 4701
Sfmt 9990
E:\FR\FM\23JNR3.SGM
23JNR3
Agencies
[Federal Register Volume 88, Number 120 (Friday, June 23, 2023)]
[Rules and Regulations]
[Pages 41262-41287]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-13286]
[[Page 41261]]
Vol. 88
Friday,
No. 120
June 23, 2023
Part IV
Department of Energy
-----------------------------------------------------------------------
Federal Energy Regulatory Commission
-----------------------------------------------------------------------
18 CFR Part 40
Transmission System Planning Performance Requirements for Extreme
Weather; Final Rule
Federal Register / Vol. 88, No. 120 / Friday, June 23, 2023 / Rules
and Regulations
[[Page 41262]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
18 CFR Part 40
[Docket No. RM22-10-000; Order No. 896]
Transmission System Planning Performance Requirements for Extreme
Weather
AGENCY: Federal Energy Regulatory Commission, Department of Energy.
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: The Federal Energy Regulatory Commission directs the North
American Electric Reliability Corporation, the Commission-certified
Electric Reliability Organization, to develop a new or modified
Reliability Standard no later than 18 months of the date of publication
of this final rule in the Federal Register to address reliability
concerns pertaining to transmission system planning for extreme heat
and cold weather events that impact the Reliable Operation of the Bulk-
Power System. Specifically, we direct the North American Electric
Reliability Corporation to develop a new or modified Reliability
Standard that requires the following: development of benchmark planning
cases based on prior extreme heat and cold weather events and/or future
meteorological projections; planning for extreme heat and cold events
using steady state and transient stability analyses that cover a range
of extreme weather scenarios, including the expected resource mix's
availability during extreme weather conditions and the broad area
impacts of extreme weather; and corrective action plans that include
mitigation activities for specified instances where performance
requirements during extreme heat and cold events are not met.
DATES: This rule is effective September 21, 2023.
FOR FURTHER INFORMATION CONTACT:
Mahmood Mirheydar (Technical Information), Office of Electric
Reliability, Federal Energy Regulatory Commission, 888 First Street NE,
Washington, DC 20426, (202) 502-8034, [email protected]
Gonzalo E. Rodriguez (Legal Information), Office of the General
Counsel, Federal Energy Regulatory Commission, 888 First Street NE,
Washington, DC 20426, (202) 502-8568, [email protected]
SUPPLEMENTARY INFORMATION:
Table of Contents
Paragraph
Nos.
Introduction................................................ 1
II. Background.............................................. 8
A. Legal Authority...................................... 8
B. Reliability Standard TPL-001-5.1 (Transmission System 10
Planning Performance Requirements).....................
C. Prior Commission Actions To Address the Reliability 14
Impacts of Extreme Weather.............................
D. Notice of Proposed Rulemaking........................ 17
III. The Need for Reform.................................... 20
IV. Discussion.............................................. 25
A. Directive to NERC To Develop New or Modified 25
Reliability Standard...................................
B. Develop Benchmark Events and Planning Cases Based on 30
Major Prior Extreme Heat and Cold Weather Events and/or
Meteorological Projections.............................
1. Comments......................................... 32
2. Commission Determination......................... 35
C. Definition of ``Wide-Area''.......................... 41
1. Comments......................................... 44
2. Commission Determination......................... 50
D. Entities Responsible for Developing Benchmark Events 51
and Planning Cases, and for Conducting Transmission
Planning Studies of Wide-Area Events...................
1. Comments......................................... 53
a. Entity Responsible for Development of 53
Benchmark Events...............................
b. Entity Responsible for Development of 54
Planning Cases and Conducting Transmission
Planning Studies of Wide-Area Events...........
2. Commission Determination......................... 58
a. Entity Responsible for Establishing Benchmark 58
Events.........................................
b. Entities Responsible for Development of 60
Planning Cases and Conducting Transmission
Planning Studies of Wide-Area Events...........
E. Coordination Among Registered Entities and Sharing of 63
Data and Study Results.................................
1. Comments......................................... 66
2. Commission Determination......................... 72
F. Concurrent/Correlated Generator and Transmission 78
Outages................................................
1. Comments......................................... 82
2. Commission Determination......................... 88
G. Conduct Transmission System Planning Studies for 95
Extreme Heat and Cold Weather Events...................
1. Steady State and Transient Stability Analyses.... 95
a. Comments..................................... 98
b. Commission Determination..................... 111
2. Sensitivity Analysis............................. 118
a. Comments..................................... 121
b. Commission Determination..................... 124
3. Modifications to the Traditional Planning 127
Approach...........................................
a. Comments..................................... 131
b. Commission Determination..................... 134
H. Implement a Corrective Action Plan if Performance 139
Standards Are Not Met..................................
1. Comments......................................... 143
a. Jurisdictional Issues........................ 143
b. Corrective Action Plans...................... 144
c. Generation and Transmission Capacity Increase 148
and Resource Adequacy Issues...................
[[Page 41263]]
d. Notification to Applicable Regulatory 151
Authorities or Governing Bodies Responsible for
Retail Electric Service Issues.................
2. Commission Determination......................... 152
a. Jurisdictional Issues........................ 154
b. Circumstances That Require Corrective Action 157
Plans..........................................
c. Generation and Transmission Capacity Increase 161
and Resource Adequacy Issues...................
d. Notification to Applicable Regulatory 165
Authorities or Governing Bodies Responsible for
Retail Electric Service Issues.................
I. Other Extreme Weather-Related Events and Issues...... 169
1. Comments......................................... 170
2. Commission Determination......................... 177
J. Reliability Standard Development and Implementation 181
Timeline...............................................
1. Comments......................................... 182
2. Commission Determination......................... 188
V. Information Collection Statement......................... 194
VI. Environmental Analysis.................................. 196
VII. Regulatory Flexibility Act............................. 197
VIII. Document Availability................................. 200
IX. Effective Date and Congressional Notification........... 203
Appendix A: Commenter Names.................................
I. Introduction
1. Pursuant to section 215(d)(5) of the Federal Power Act (FPA),\1\
the Commission directs the North American Electric Reliability
Corporation (NERC), the Commission-certified Electric Reliability
Organization (ERO), to submit a new Reliability Standard or
modifications to Reliability Standard TPL-001-5.1 that addresses
concerns pertaining to transmission system planning for extreme heat
and cold weather events that impact the Reliable Operation \2\ of the
Bulk-Power System.\3\
---------------------------------------------------------------------------
\1\ 16 U.S.C. 824o(d)(5).
\2\ The FPA defines ``Reliable Operation'' as ``operating the
elements of the Bulk-Power System within equipment and electric
system thermal, voltage, and stability limits so that instability,
uncontrolled separation, or cascading failures of such system will
not occur as a result of a sudden disturbance, including a
cybersecurity incident, or unanticipated failure of system
elements.'' 16 U.S.C. 824o(a)(4).
\3\ The Bulk-Power System is defined in the FPA as ``facilities
and control systems necessary for operating an interconnected
electric energy transmission network (or any portion thereof), and
electric energy from generating facilities needed to maintain
transmission system reliability. The term does not include
facilities used in the local distribution of electric energy.'' Id.
824o(a)(1).
---------------------------------------------------------------------------
2. We take this action to address challenges associated with
planning for extreme heat and cold weather events, particularly those
that occur during periods when the Bulk-Power System must meet
unexpectedly high demand.\4\ Extreme heat and cold weather events have
occurred with greater frequency in recent years, and are projected to
occur with even greater frequency in the future.\5\ These events have
shown that load shed during extreme temperature result in unacceptable
risk to life and have extreme economic impact.\6\ As such, the impact
of concurrent failures of Bulk-Power System generation and transmission
equipment and the potential for cascading outages \7\ that may be
caused by extreme heat and cold weather events should be studied and
corrective actions should be identified and implemented.
---------------------------------------------------------------------------
\4\ Technical Conference June 1-2, 2021, Climate Change, Extreme
Weather, and Electric System Reliability, Docket No. AD21-13-000
(June 1-2, 2021), June 1, 2021 Tr. 26: 3-7 (Derek Stenclik, Founding
Partner, Telos Energy, Inc.), 31:7-8 (Judy Chang, Undersecretary of
Energy, Massachusetts).
\5\ See e.g., Environmental Protection Agency, Climate Change
Indicators: Weather and Climate (May 12, 2021) (EPA Climate Change
Indicators), https://www.epa.gov/climate-indicators/weather-climate
(showing an upward trend in extreme heat and cold weather events).
NOAA, Adam Smith, 2022 U.S. Billion-dollar Weather and Climate
Disasters in Historical Context (Jan. 10, 2023), https://www.climate.gov/news-features/blogs/2022-us-billion-dollar-weather-and-climate-disasters-historical-context.
\6\ FERC, NERC, and Regional Entity Staff, The February 2021
Cold Weather Outages in Texas and the South Central United States,
at 9, 192 (Nov. 16, 2021), https://www.ferc.gov/media/february-2021-cold-weather-outages-texas-and-south-central-united-states-ferc-nerc-and (2021 Cold Weather Event Report).
\7\ NERC Glossary of Terms Used in Reliability Standards
(Updated Mar. 8, 2023) (NERC Glossary). NERC defines ``cascading''
as, the ``uncontrolled successive loss of System Elements triggered
by an incident at any location. Cascading results in widespread
electric service interruption that cannot be restrained from
sequentially spreading beyond an area predetermined by studies.''
---------------------------------------------------------------------------
3. At the Commission's June 1-2, 2021 technical conference on
Climate Change, Extreme Weather, and Electric System Reliability, there
was consensus among panelists that planners cannot simply project
historical weather patterns forward to effectively forecast the future,
since climate change has made the use of historical weather
observations no longer representative of future conditions.\8\ For
example, extreme summer heat in regions like the Pacific Northwest and
extreme winter cold in regions like Texas have increased demand for
electricity at times when historically demand has been low.\9\ As
events such as these will likely continue to present challenges in the
future, transmission planners and planning coordinators must account
for this new reality in their planning processes.\10\
---------------------------------------------------------------------------
\8\ June 1, 2021 Tr. 30:2-3 (Chang), 31:12-18 (Lisa Barton,
Executive Vice President/Chief Operating Officer, American Electric
Power).
\9\ June 1, 2021 Tr. 31:1-6 (Chang); June 2, 2021 Tr. 72:8-10
(Amanda Frazier, Senior Vice President of Regulatory Policy, Vista
Corp.); 9:1-5 (Wesley Yeomans, Vice President of Operations, New
York Independent System Operator, Inc. (NYISO)) (noting that in New
York the majority of the extreme conditions were cold weather
related but that there can be heat waves in New York City, and more
heat waves are expected).
\10\ June 1, 2021 Tr. 35:1-6 (Chang). See also US News,
Blackouts in US Northwest Due to Heat Wave, Deaths Reported (June
29, 2021), https://www.usnews.com/news/business/articles/2021-06-29/rolling-blackouts-for-parts-of-us-northwest-amid-heat-wave; Judah
Cohen et al., Linking Arctic Variability and Change With Extreme
Winter Weather in the United States, 373 Sci. 1116, 1120 (2021), (a
study connecting the 2021 extreme cold weather event in Texas and
the South-central United States to global warming-induced weather
anomalies that are likely to continue to produce severe winter storm
events).
---------------------------------------------------------------------------
4. Since 2011, the country has experienced at least seven major
extreme heat and cold weather events,\11\ each of which put stress on
the Bulk-Power System and resulted in some degree of load shed. In some
cases, these events nearly caused system collapse
[[Page 41264]]
and uncontrolled blackouts, which were avoided due to system operator
actions.
---------------------------------------------------------------------------
\11\ See Transmission System Planning Performance Requirements
for Extreme Weather, Notice of Proposed Rulemaking, 87 FR 38,020
(June 27, 2023), 179 FERC ] 61,195 at PP 24-36 (2022) (NOPR)
(discussing these prior events in detail).
---------------------------------------------------------------------------
5. Given the reliability risks associated with extreme heat and
cold weather events, including the potential for widespread blackouts,
maintaining the reliability of the Bulk-Power System requires
transmission system planning to account for the potential impact of
extreme heat and cold weather over wide geographical areas, and to
consider the changing resource mix. Reliability Standard TPL-001-4 \12\
was developed to establish transmission system planning performance
requirements that ensure that the Bulk-Power System operates reliably
over a broad spectrum of system conditions and following a wide range
of probable contingencies.\13\ Both it and its successor, TPL-001-5.1,
include provisions for transmission planners and planning coordinators
to study system performance under extreme events based on their
experience; \14\ however, neither standard specifically requires
entities to conduct performance analysis for extreme heat and cold
weather, despite the fact that such conditions have clearly
demonstrated a risk to the Reliable Operation of the Bulk-Power System,
thus leaving a reliability gap in system planning.
---------------------------------------------------------------------------
\12\ Effective July 1, 2023, Reliability Standard TPL-001-4 will
be replaced by Reliability Standard TPL-001-5.1. Unless otherwise
specified, the use of Reliability Standard TPL-001-5.1 in this final
rule also refers to its predecessor, Reliability Standard TPL-001-4.
\13\ Reliability Standard TPL-001-5, at 1.
\14\ Id. at tbl. 1.
---------------------------------------------------------------------------
6. To address this reliability gap, we direct NERC to develop a new
or modified Reliability Standard that requires the following: (1) the
development of benchmark planning cases based on information such as
major prior extreme heat and cold weather events and/or future
meteorological projections; (2) planning for extreme heat and cold
weather events using steady state and transient stability analyses
expanded to cover a range of extreme weather scenarios, including
expected availability of the resource mix during extreme heat and cold
weather conditions, and including the broad area impacts of extreme
heat and cold weather; and (3) the development of corrective action
plans that mitigate specified instances where performance requirements
during extreme heat and cold weather events are not met. In directing
NERC to develop a new or modified Reliability Standard, we are not
proposing specific requirements. Instead, we identify concerns that
should be addressed by the proposed Reliability Standard. NERC may
propose to develop a new or modified Reliability Standard that address
our concerns in an equally efficient and effective manner; however,
NERC's proposal should explain how it addresses the Commission's
concerns.\15\
---------------------------------------------------------------------------
\15\ See e.g., Mandatory Reliability Standards for the Bulk-
Power Sys., Order No. 693, 72 FR 16416 (Apr. 4, 2007), 118 FERC ]
61,218, at PP 186, 297, order on reh'g, Order No. 693-A, 72 FR 40717
(July 25, 2007), 120 FERC ] 61,053 (2007) (``where the Final Rule
identifies a concern and offers a specific approach to address the
concern, we will consider an equivalent alternative approach
provided that the ERO demonstrates that the alternative will address
the Commission's underlying concern or goal as efficiently and
effectively as the Commission's proposal'').
---------------------------------------------------------------------------
7. We direct NERC to submit the proposed new or modified
Reliability Standard no later than 18 months from the publication of
this final rule in the Federal Register. We believe that an 18-month
deadline provides sufficient time for NERC to develop a responsive
Standard in consideration of the issues involved and the steps in
NERC's standards development process. Further, we direct NERC to ensure
that the proposed new or modified Reliability Standard becomes
mandatory and enforceable beginning no later than 12 months from the
effective date of Commission approval of the new or modified
Reliability Standard.
II. Background
A. Legal Authority
8. Section 215 of the FPA provides that the Commission may certify
an ERO, the purpose of which is to develop mandatory and enforceable
Reliability Standards, subject to Commission review and approval.\16\
Reliability Standards may be enforced by the ERO, subject to Commission
oversight, or by the Commission independently.\17\ Pursuant to section
215 of the FPA, the Commission established a process to select and
certify an ERO,\18\ and subsequently certified NERC.\19\
---------------------------------------------------------------------------
\16\ 16 U.S.C. 824o(c).
\17\ Id. 824o(e).
\18\ Rules Concerning Certification of the Elec. Reliability
Org. & Procedures for the Establishment, Approval, & Enf't. of Elec.
Reliability Standards, Order No. 672, 71 FR 8662 (Feb. 17, 2006),
114 FERC ] 61,104, order on reh'g, Order No. 672-A, 71 FR 19814
(Apr. 18, 2006), 114 FERC ] 61,328 (2006).
\19\ N. Am. Elec. Reliability Corp., 116 FERC ] 61,062, order on
reh'g and compliance, 117 FERC ] 61,126 (2006), aff'd sub nom.
Alcoa, Inc. v. FERC, 564 F.3d 1342 (D.C. Cir. 2009).
---------------------------------------------------------------------------
9. Pursuant to section 215(d)(5) of the FPA, the Commission has the
authority, upon its own motion or upon complaint, to order the ERO to
submit to the Commission a proposed Reliability Standard or a
modification to a Reliability Standard that addresses a specific matter
if the Commission considers such a new or modified Reliability Standard
appropriate to carry out section 215 of the FPA.\20\ Further, pursuant
to Sec. 39.5(g) of the Commission's regulations, the Commission may
order a deadline by which the ERO must submit a proposed or modified
Reliability Standard, or when ordering the ERO to submit to the
Commission a proposed Reliability Standard that addresses a specific
matter.\21\
---------------------------------------------------------------------------
\20\ 16 U.S.C. 824o(d)(5).
\21\ 18 CFR 39.5(g) (2022).
---------------------------------------------------------------------------
B. Reliability Standard TPL-001-5.1 (Transmission System Planning
Performance Requirements)
10. Transmission system planning refers to the evaluation of future
transmission system performance and creation of corrective action plans
that include mitigation to remedy identified deficiencies.\22\ The
planning horizon associated with transmission system planning covers
near term (one to five years), long-term (six to ten years), and
beyond.\23\
---------------------------------------------------------------------------
\22\ NERC Glossary (defining ``Planning Assessment'' as
``documented evaluation of future Transmission System performance
and Corrective Action Plans to remedy identified deficiencies'').
\23\ Id. (defining ``Near-Term Transmission Planning Horizon''
and ``Long-Term Transmission Planning Horizon'').
---------------------------------------------------------------------------
11. Reliability Standard TPL-001-5.1 establishes minimum
transmission system planning performance requirements to plan a Bulk-
Power System that will operate reliably over a broad spectrum of system
conditions and following a wide range of probable contingencies.\24\
Under Requirement R2 of Reliability Standard TPL-001-5.1, each
transmission planner and planning coordinator must prepare an annual
planning assessment for its portion of the Bulk-Power System.\25\ This
planning assessment is required for both near-term and long-term
transmission planning horizons.\26\
---------------------------------------------------------------------------
\24\ Reliability Standard TPL-001-5.1, Purpose.
\25\ Id., at Requirement 2. Further, steady-state analyses are a
snapshot in time where load and system conditions (e.g., generators,
lines, facilities) are modeled as constant (not as changing over
time). The analysis will either solve (converge numerically) or not
solve (diverge numerically). See IEEE, Transactions on Power
Systems, Vol. 19, No. 2, (May 2004) (power system stability is the
ability of an electric power system, for a given initial operating
condition, to regain a state of operating equilibrium after being
subjected to a physical disturbance, with most system variables
bounded so that practically the entire system remains intact); see
also, Kundur, Prabha, Power System Stability and Control, McGraw
Hill, at 26 (1994).
\26\ See Reliability Standard TPL-001-5.1, at Requirement 2.1
(Near-Term Transmission Planning Horizon) and Requirement R.2.2
(Long-Term Transmission Planning Horizon).
---------------------------------------------------------------------------
12. Requirements R3 and R4 of Reliability Standard TPL-001-5.1
[[Page 41265]]
require in part that planning coordinators and transmission planners
conduct steady state and stability studies of pre-specified extreme
events and evaluate possible actions designed to reduce the likelihood
or mitigate the consequences and adverse impacts of the event(s), if
the analysis concludes that the pre-selected extreme events cause
cascading outages.
13. Table 1 of Reliability Standard TPL-001-5.1 includes a list of
examples of planning events (i.e., Category P1 through P7) \27\ for
which specific studies may be required based on the entity's own
evaluation that such an event could occur within its operating area.
Section 3.a of Table-1 (Steady State & Stability Performance Extreme
Events) states that steady state analysis should be conducted for wide-
area events affecting the transmission system based on system
configuration and how it can be affected by events such as wildfires
and severe weather (e.g., hurricanes and tornadoes). In addition,
section 3.b serves as a catch-all provision, stating that steady state
analysis should be performed for ``other events based upon operating
experience that may result in wide-area disturbances.''
---------------------------------------------------------------------------
\27\ Categories P1 through P7 are defined in TPL-001-5.1 in
Table 1--Steady State & Stability Performance Planning Events.
---------------------------------------------------------------------------
C. Prior Commission Actions To Address the Reliability Impacts of
Extreme Weather
14. On June 1 and 2, 2021, the Commission convened a staff-led
technical conference on Climate Change, Extreme Weather, and Electric
System Reliability.\28\ The Commission sought to understand, among
other things, whether further action from the Commission is needed to
help achieve an electric system that can withstand, respond to, and
recover from extreme weather events.\29\
---------------------------------------------------------------------------
\28\ Climate Change, Extreme Weather, and Electric System
Reliability, Notice of Technical Conference, Docket No. AD21-13-000,
at 1 (Mar. 5, 2021).
\29\ Id. at 2.
---------------------------------------------------------------------------
15. In the pre- and post-conference comments, industry experts
agreed that extreme weather events are likely to become more severe and
frequent in the future.\30\ They also acknowledged the challenges
associated with planning for extreme events, including shifting
scheduled maintenance and canceling or recalling transmission and
generation assets from scheduled maintenance to meet demand under
unexpected circumstances.\31\ Further, commenters discussed potential
changes to the Reliability Standards to address planning and
operational preparedness for energy adequacy risks,\32\ contingencies
related to extreme weather events, and wide-area transmission planning
and development challenges, among others.\33\ Comments also addressed
more directly the potential reliability gaps in the existing set of
Reliability Standards, including Reliability Standard TPL-001-4, and
identified potential solutions.\34\
---------------------------------------------------------------------------
\30\ CAISO Pre-Conference Comments at 1-3; California Public
Utilities Commission Pre-Conference Comments at 4; Oregon Public
Utilities Commission Pre-Conference Comments at 2-3; NYISO Pre-
Conference Comments at 4; AEP Pre-Conference Comments at 5.
\31\ June 2, 2021, Tr. at 21-23 (Wesley Yeomans, Vice President
of Operations, NYISO).
\32\ ISO-New England Inc. Pre-Conference Comments at 10.
\33\ Midcontinent Independent System Operator (MISO) Pre-
Conference Comments at 4-5, 14-17.
\34\ See e.g., NERC Pre-Conference Comments at 6; MISO Post-
Conference Comments at 20; Pacific Gas & Electric Company Pre-
Conference Comments at 19-20; PJM Post-Conference Comments at 21;
CAISO Post-Conference Comments at 10.
---------------------------------------------------------------------------
16. On August 24, 2021, and February 16, 2023, the Commission
approved revised Reliability Standards to address some of the
reliability risks posed by extreme cold weather.\35\ These Reliability
Standards, among other things, require generators to implement plans
for cold weather preparedness and implement freeze protection measures
to mitigate the reliability impacts of extreme cold weather on their
generating units. The new and revised standards also require the
balancing authority, transmission operator, and reliability coordinator
to plan and operate the grid reliably during cold weather conditions by
requiring the exchange of certain information related to the
generator's capability to operate under such conditions.\36\
---------------------------------------------------------------------------
\35\ N. Am. Elec. Reliability Corp., 176 FERC ] 61,119 (2021).
The Commission approved proposed Reliability Standards EOP-011-2
(Emergency Preparedness and Operations); IRO-010-4 (Reliability
Coordinator Data Specification and Collection); and TOP-003-5
(Operational Reliability Data) (collectively, the Cold Weather
Reliability Standards) and Order Approving Extreme Cold Weather
Reliability Standards EOP-011-3 and EOP-012-1 and Directing
Modification of Reliability Standard EOP-012-1, 182 FERC ] 61,094
(2023).
\36\ Id. P 3.
---------------------------------------------------------------------------
D. Notice of Proposed Rulemaking
17. On June 26, 2022, the Commission issued the Notice of Proposed
Rulemaking (NOPR) proposing to direct NERC to develop a new or modified
Reliability Standard to address a lack of a long term planning
requirement for extreme heat and cold weather events.\37\ Specifically,
the Commission proposed to direct NERC to develop either modifications
to Reliability Standard TPL-001-5.1 or a new Reliability Standard, to
require the following: (1) development of benchmark planning cases
based on major prior extreme heat and cold weather events and/or
meteorological projections; (2) planning for extreme heat and cold
weather events using steady state and transient stability analyses
expanded to cover a range of extreme weather scenarios including the
expected resource mix's availability during extreme heat and cold
weather conditions, and including the wide-area impacts of extreme heat
and cold weather; and (3) development of corrective action plans that
mitigate any instances where performance requirements for extreme heat
and cold weather events are not met.\38\
---------------------------------------------------------------------------
\37\ NOPR, 179 FERC ] 61,195 at P 47.
\38\ Id. P 51.
---------------------------------------------------------------------------
18. The NOPR preliminarily found that, based on the wide geographic
impacts on the Bulk-Power System of previous extreme heat and cold
weather events, the study criteria for extreme heat and cold events
should include a consideration of wide-area conditions affecting
neighboring regions and their impact on one planning area's ability to
rely on the resources of another region during the weather event.\39\
---------------------------------------------------------------------------
\39\ Id. P 67.
---------------------------------------------------------------------------
19. The NOPR sought comments on all aspects of the proposed
directives, including among others: (1) the development of benchmark
planning cases; (2) requiring transmission planning studies of wide-
area extreme heat and cold events; (3) the study of concurrent
generator and transmission outages; (4) the analysis of sensitivities;
(5) modifications to current deterministic planning approaches; (6)
coordination among registered entities and sharing of study results;
(7) requiring entities to implement corrective action plans if
performance standards are not met; and (8) whether the final rule
should address other extreme weather events beyond heat and cold
events. The comment period for the NOPR ended on August 26, 2022, and
the Commission received 33 sets of comments.\40\
---------------------------------------------------------------------------
\40\ A list of commenters to the NOPR and the abbreviated names
used in this final rule appear in Appendix A.
---------------------------------------------------------------------------
III. The Need for Reform
20. Extreme weather-related events that spread across large
portions of the country over the past decade demonstrate the challenges
to transmission planning from extreme heat and cold weather patterns.
The NOPR discussed seven major extreme heat and cold weather events
that had
[[Page 41266]]
occurred since 2011.\41\ Of these, four (2011, 2013, 2018, and 2021)
were extreme cold weather events that nearly caused system collapse if
the operators had not acted to shed load.\42\ The remaining three
events (2014, 2020, and 2021) were extreme heat weather events that
resulted in generation losses and varying degrees of load shedding.\43\
Since the issuance of the NOPR, another extreme cold weather event
indicated reliability challenges faced by the Bulk-Power System. In
December 2022, Winter Storm Elliott caused extreme cold conditions that
significantly stressed the Bulk-Power System, forcing some utilities to
deploy rolling blackouts to preserve Bulk-Power System reliability.\44\
These extreme heat and cold events demonstrate a risk to Reliable
Operation of the Bulk-Power System.
---------------------------------------------------------------------------
\41\ For a full discussion of these extreme weather events, see
NOPR, 179 FERC ] 61,195 at PP 24-33.
\42\ See e.g., FERC and NERC Staff Report, Outages and
Curtailments During the Southwest Cold Weather Event of February 1-
5, 2011, at 7 (Aug. 2011), https://www.ferc.gov/sites/default/files/2020-05/ReportontheSouthwestColdWeatherEventfromFebruary2011Report.pdf
(impacting nearly 4.4 million electric customers in ERCOT); 2013 PJM
Heat Wave Analysis at 5 (impacting approximately 45,000 customers in
PJM).
\43\ See, e.g., 2021 Cold Weather Event Report at 133.
\44\ FERC, FERC, NERC to Open Joint Inquiry into Winter Storm
Elliott (Dec. 2022), https://www.ferc.gov/news-events/news/ferc-nerc-open-joint-inquiry-winter-storm-elliott.
---------------------------------------------------------------------------
21. While wide-area extreme heat and cold weather events may not
occur every year, their frequency and magnitude are expected to
increase. The National Oceanic and Atmospheric Administration's (NOAA)
data and analyses show an increasing trend in extreme heat and cold
weather events,\45\ and the U.S. Environmental Protection Agency
climate change indicators also show upward trends in heatwave
frequency, duration, and intensity.\46\ NOAA states that climate change
is also driving more compound events, i.e., multiple extreme events
occurring simultaneously or successively, such as concurrent heat waves
and droughts, and more extreme heat conditions in cities.\47\
---------------------------------------------------------------------------
\45\ See NOAA., Nat'l Centers for Envtl. Info., U.S. Billion-
Dollar Weather and Climate Disasters (2023), https://www.ncei.noaa.gov/access/billions/.
\46\ U.S. EPA, Climate Change Indicators in the United States
(last updated May 2, 2023), https://www.epa.gov/climate-indicators.
\47\ NOAA, 2022 U.S. Billion Dollar Weather and Climate
Disasters in Historical Context (2023), https://www.climate.gov/news-features/blogs/2022-us-billion-dollar-weather-and-climate-disasters-historical-context.
---------------------------------------------------------------------------
22. These conditions have created an urgency to address the
negative impact of extreme weather on the reliability of the Bulk-Power
System. To that end, the directives to NERC in this final rule aim to
improve system planning specifically for extreme heat and cold weather
events. The potential impact of widespread extreme heat and cold events
on the reliability of the Bulk-Power System can be modeled and studied
in advance as part of near-term and long-term transmission system
planning. Responsible entities could then use the studies to develop
transmission system operational strategies or corrective action plans
with mitigations that could be deployed in preparation for extreme heat
and cold events.
23. The current transmission planning Reliability Standards,
however, do not obligate transmission planners and planning
coordinators to consider extreme hot and cold weather in their
transmission assessments. In particular, Reliability Standard TPL-001-
5.1 requires steady state and stability analyses to be performed for
certain extreme events but does not require steady state and stability
analyses for extreme heat and cold conditions.\48\ Likewise, while
Reliability Standard TPL-001-5.1 Table 1, provisions 2.f (stability)
and 3.b (steady state), requires responsible entities to study events
based on operating experience that may result in a wide-area
disturbance,\49\ the Standard does not specify the study of extreme
heat or cold conditions.
---------------------------------------------------------------------------
\48\ See Reliability Standard TPL-001-5.1, at Requirements R3
and R4 and Table 1.
\49\ Id. at Table 1, provisions 2.f and 3.b.
---------------------------------------------------------------------------
24. System planning measures alone will not eliminate the
reliability risk associated with extreme heat and cold events. The
directives to improve transmission planning discussed in this final
rule will prepare the Bulk-Power System for extreme weather events in
the long term and will work together with the requirements in the Cold
Weather Reliability Standards to mitigate the near-term reliability
impact of extreme weather events. Improved system planning will limit
the impact of such events and reduce the risk to the reliability of the
Bulk-Power System, which prior events demonstrate is significant.
IV. Discussion
A. Directive to NERC To Develop New or Modified Reliability Standard
25. Pursuant to FPA section 215(d)(5), we adopt the NOPR proposal
and direct NERC to submit a new Reliability Standard or modifications
to Reliability Standard TPL-001-5.1 requiring transmission system
planning for extreme heat and cold weather events that impact the
Reliable Operation of the Bulk-Power System. For the reasons discussed
in section III above, we conclude that it is necessary to update the
transmission planning Reliability Standard to reflect the impact of
extreme heat and cold weather events on the reliability of the Bulk-
Power System. Most commenters support the NOPR proposal to develop
mandatory transmission system planning requirements for extreme heat
and cold weather events.\50\ Commenters also agree that Commission
action is necessary to address the reliability gaps pertaining to the
consideration of extreme heat and cold weather events that exist in
current transmission planning processes.\51\
---------------------------------------------------------------------------
\50\ See, e.g., MISO Transmission Owners Comments at 1-2;
Indicated Trade Associations Comments at 1-2; NYISO Comments at 1-2;
AEP Comments at 1; ACP Comments at 1; PIOs Comments at 1.
\51\ See, e.g., EPRI Comments at P 4.
---------------------------------------------------------------------------
26. Although supportive of the need to consider extreme weather in
the transmission planning process, PJM Interconnection, L.L.C. (PJM) is
critical of the Commission's proposed ``piecemeal'' approach and
suggests that the Commission harmonize this rulemaking with other
Commission actions on transmission planning.\52\ While we agree that it
is important for NERC and applicable planning entities to consider how
requirements implemented pursuant to this rulemaking may interact with
processes carried out pursuant to other Commission actions on
transmission planning, we disagree with PJM's suggestion that this
proceeding is not an appropriate forum for directing changes to the
NERC Reliability Standards. While there is undoubtedly a nexus between
the long-term planning for expected changes in resources and demand as
contemplated in Docket No. RM21-17-000 and Reliability Standards for
extreme weather, each set of reforms is subject to differing statutory
schemes and other considerations, and each aims at related but distinct
challenges. The Commission's transmission planning reform efforts
require individual consideration, as they each concern different
transmission planning objectives, time horizons, and areas of
Commission jurisdiction. This proceeding is conducted pursuant to the
Commission's jurisdiction under section 215 of the FPA and contemplates
transmission planning entity actions that may be needed in the planning
timeframe of six to ten years and beyond to mitigate the impacts of
extreme weather, whereas the proceeding in Docket No. RM21-17-000 was
initiated
[[Page 41267]]
pursuant to the Commission's jurisdiction under section 206 of the FPA,
considers a more fulsome range of practices that may be required to
render rates just and reasonable, and contemplates a planning horizon
of 20 years.\53\ While addressing these related efforts in a single
proceeding may have benefits, it also would risk complicating the
development of solutions and making the process more unwieldy. The
Commission has thus determined to take this step to facilitate
solutions to one aspect of the extreme weather challenge, as part of a
series of actions that build on each other by seeking to address the
many areas that affect extreme weather reliability.
---------------------------------------------------------------------------
\52\ PJM Comments at 3-4, 7.
\53\ See Building for the Future Through Elec. Reg'l
Transmission Planning & Cost Allocation & Generator Interconnection,
Notice of Proposed Rulemaking, 87 FR 26504, (May 4, 2022), 179 FERC
] 61,028 (2022).
---------------------------------------------------------------------------
27. Accordingly, we adopt the NOPR proposal and direct NERC to
develop a new or modified Reliability Standard to require the
following: (1) development of benchmark planning cases based on major
prior extreme heat and cold weather events and/or meteorological
projections; (2) planning for extreme heat and cold weather events
using steady state and transient stability analyses expanded to cover a
range of extreme weather scenarios including the expected resource
mix's availability during extreme heat and cold weather conditions, and
including the wide-area impacts of extreme heat and cold weather; and
(3) development of corrective action plans that mitigate specified
instances where performance requirements for extreme heat and cold
weather events are not met.\54\ We also direct NERC to identify the
responsible entities for developing benchmark planning cases and
conducting wide-area studies under the new or modified Reliability
Standard.
---------------------------------------------------------------------------
\54\ NOPR, 179 FERC ] 61,195 at P 51.
---------------------------------------------------------------------------
28. Given the importance of timely addressing the identified
reliability gap, we direct NERC to submit the responsive new or
modified Reliability Standard within 18 months of the date of
publication of this final rule in the Federal Register. We further
direct NERC to develop a phased-in implementation timeline for the
different requirements of the new or modified Reliability Standard
(i.e., developing benchmark planning cases, conducting studies,
developing corrective action plans) that shall begin within 12 months
of the effective date of a Commission order approving the proposed
Reliability Standard.
29. We address below in further detail issues raised in the NOPR
and in comments regarding: (1) development of benchmark events and
planning cases; (2) definition of ``wide-area;'' (3) entities
responsible for developing benchmark events and conducting transmission
planning studies of wide-area events; (4) coordination among registered
entities and sharing of data and study results; (5) concurrent/
correlated generator and transmission outages; (6) conducting
transmission system planning studies for extreme heat and cold weather
events; (7) corrective action plans; (8) other extreme weather events;
and (9) Reliability Standard development and implementation timeline.
B. Develop Benchmark Events and Planning Cases Based on Major Prior
Extreme Heat and Cold Weather Events and/or Meteorological Projections
30. In the NOPR, the Commission proposed to direct NERC to include
in the new or modified Reliability Standard benchmark events that
responsible entities must study.\55\ The NOPR proposed basing such
benchmark events on prior events (e.g., the February 2011 Southwest
Cold Weather Event and the January 2014 Polar Vortex Cold Weather
Event) and/or meteorological projections. Recognizing that extreme
weather risks may vary from region to region and change over time, the
NOPR proposed to direct NERC to consider approaches that would provide
a uniform framework for developing benchmark events while still
recognizing regional differences; for example, NERC could define
benchmark events around a projected frequency (e.g., 1-in-50-year
event) or probability distribution (95th percentile event).\56\
Although the NOPR did not specify how these benchmark events should be
developed, the NOPR provided two examples: (1) NERC could develop the
benchmark event or events during the standard development process; or
(2) NERC could include in the new or modified Reliability Standard a
framework establishing a common design basis for the development of
benchmark events. The NOPR also suggested including in the modified
standard the primary features of the benchmark event(s) while
designating NERC or another entity to periodically update benchmark
events.\57\
---------------------------------------------------------------------------
\55\ Id.
\56\ Id. P 52.
\57\ Id. P 53.
---------------------------------------------------------------------------
31. The NOPR also proposed that establishing one or more benchmark
planning cases, based on benchmark events, should form the basis for
sensitivity analysis. In addition to providing valuable case study
information to be applied to preparing for possible comparable future
events, these events would also serve as a basis for effectively using
assets and resources. Specifically, once developed, responsible
entities would use the benchmark events to develop benchmark planning
cases to conduct studies to assess the limitations of the transmission
system locally and over a wide-area, and to understand resource
availability and potential firm load shedding requirements under
stressed conditions.\58\ The NOPR sought comments on all aspects of the
proposed directive.
---------------------------------------------------------------------------
\58\ Id.
---------------------------------------------------------------------------
1. Comments
32. Commenters generally agree with the NOPR proposal to direct
NERC to develop requirements that address the types of extreme heat and
cold weather scenarios that responsible entities are required to
study.\59\ Indicated Trade Associations caution, however, that
universal benchmark events would be hard to implement given regional
differences.\60\ As such, and consistent with the NOPR proposal,
Indicated Trade Associations, APS, Bonneville Power Administration
(BPA), and Idaho Power, among others, agree that regional differences
(e.g., climate, topology, electrical characteristics) should be
considered in developing benchmark events.\61\
---------------------------------------------------------------------------
\59\ See, e.g., NERC Comments at 7-8; AEP Comments at 7;
Indicated Trade Associations Comments at 8; NARUC Comments at 5.
\60\ Indicated Trade Associations Comments at 8.
\61\ See id.; APS Comments at 3; BPA Comments at 3; Idaho
Comments at 2.
---------------------------------------------------------------------------
33. Regarding how benchmark events should be developed, NERC notes
that significant work will be necessary to develop a uniform planning
approach that properly accounts for regional differences in climate and
weather patterns, among other considerations. Accordingly, NERC asks
for flexibility in developing benchmark events, including considering
options beyond those identified in the NOPR.\62\ Indicated Trade
Associations recommend that NERC consider all the examples of benchmark
events identified in the NOPR.\63\ PJM indicates that developing
benchmark events will require scientific and meteorological expertise
to ensure that NERC guidelines and criteria reflect statistically valid
scenarios for the meteorological projections and their possible impacts
on transmission planning. As such, PJM recommends that the Commission
engage the national
[[Page 41268]]
labs, Regional Transmission Organizations (RTO), NOAA, and other
agencies to develop extreme weather ``design threshold'' metrics, as
well as investigate targeted planning thresholds (e.g., 1-in-50-year
events).\64\ Other commenters highlight the necessity of ensuring that
benchmark events are not only developed using historical extreme heat
and cold event data, but more importantly use future meteorological
projections in order to prepare for plausible extremes in future
years.\65\
---------------------------------------------------------------------------
\62\ NERC Comments at 8-9.
\63\ Indicated Trade Associations Comments at 8.
\64\ PJM Comments at 9.
\65\ See, e.g., EPRI Comments at P 5; Entergy Comments at 3.
---------------------------------------------------------------------------
34. All those who submitted comments regarding the NOPR proposal to
require periodic updates to benchmark events agree with the need to do
so. For example, Union for Concerned Scientists (UCS) points to the
scientific consensus that climate change is altering the intensity and
frequency of extreme weather conditions as a reason to require the
periodic update of benchmark events.\66\ American Electric Power
Service Corporation (AEP) recommends updating the benchmark events
every three years, consistent with the Commission's proposed planning
cycle for regional transmission planning, based on the most up-to-date
data.\67\ In contrast, Midcontinent Independent System Operator, Inc.
(MISO) suggests that, consistent with similar requirements in
Reliability Standard TPL-007-4 (Transmission System Planned Performance
for Geomagnetic Disturbance Events) and Reliability Standard PRC-006-5
(Automatic Underfrequency Load Shedding) extreme heat and cold weather
benchmark events should be updated every five years.\68\ Other
commenters recommend that the key aspects of the benchmark be updated
periodically, without opining on the periodicity of updates.\69\
---------------------------------------------------------------------------
\66\ UCS Comments at 7.
\67\ AEP Comments at 3-4 (citing Docket No. RM21-17-000).
\68\ MISO Comments at 3.
\69\ See, e.g., APS Comments at 3; Entergy Comments at 4;
Indicated Trade Associations Comments at 8.
---------------------------------------------------------------------------
2. Commission Determination
35. Pursuant to section 215(d)(5) of the FPA, we adopt the NOPR
proposal and direct NERC to: (1) develop extreme heat and cold weather
benchmark events, and (2) require the development of benchmark planning
cases based on identified benchmark events. Without specific
requirements describing the types of heat and cold scenarios that
responsible entities must study, the new or modified Reliability
Standard may not provide a significant improvement upon the status quo.
Benchmark events will provide a defined event that will form the basis
for assessing system performance during extreme heat and cold weather
events. Benchmark events will also form the basis for a planner's
benchmark planning case--i.e., the base case representing system
conditions under the relevant benchmark event--that will be used to
study the potential wide-area impacts of anticipated extreme heat and
cold weather events.
36. Although the NOPR outlined some of the Commission's
expectations for the development of benchmark events, including that
benchmark events be based on prior extreme heat and cold events and/or
meteorological projections,\70\ there is currently no established
guidance or set of tools in place to facilitate the development of
extreme heat and cold benchmark events for the purpose of informing
transmission system planning. As recommended by commenters, NERC should
consider the examples of approaches for defining benchmark events
identified in the NOPR (e.g., the use of projected frequency or
probability distribution).\71\ NERC may also consider other approaches
that achieve the objectives outlined in this final rule. Further, as
recommended by PJM, we believe there is value in engaging with national
labs, RTOs, NOAA, and other agencies and organizations in developing
benchmark events. Considering NERC's key role, technical expertise, and
experience assessing the reliability impacts of various events and
conditions, we encourage NERC to engage with national labs, RTOs, NOAA,
and other agencies and organizations as needed. To that end, as
discussed in section IV.J below, we have modified the NOPR proposal to
allow more time for NERC to consider these complex issues and engage
additional expertise where necessary.
---------------------------------------------------------------------------
\70\ For instance, a benchmark event could be constructed based
on data from a major prior extreme heat or cold event, with
adjustments if necessary to account for the fact that future
meteorological projections may estimate that similar events in the
future are likely to be more extreme.
\71\ See supra P 33.
---------------------------------------------------------------------------
37. Because the impact of most extreme heat and cold events spans
beyond the footprints of individual planning entities, it is important
that all responsible entities likely to be impacted by the same extreme
weather events use consistent benchmark events. Doing so is important
to ensuring that neighboring planning regions are assuming similar
weather conditions and are able to coordinate their assumptions
accordingly. As a result, defining the benchmark event in a manner that
provides responsible entities significant discretion to determine the
applicable meteorological conditions would not meet the objectives of
this final rule.
38. At the same time, because different regions experience weather
conditions and their impacts differently, a single benchmark event for
the entire Nation is unlikely to meet the objectives of this final
rule. Accordingly, in developing extreme heat and cold benchmark
events, NERC shall ensure that benchmark events reflect regional
differences in climate and weather patterns.
39. We also direct NERC to include in the Reliability Standard the
framework and criteria that responsible entities shall use to develop
from the relevant benchmark event planning cases to represent potential
weather-related contingencies (e.g., concurrent/correlated generation
and transmission outages, derates) and expected future conditions of
the system such as changes in load, transfers, and generation resource
mix, and impacts on generators sensitive to extreme heat or cold, due
to the weather conditions indicated in the benchmark events. Developing
such a framework would provide a common design basis for responsible
entities to follow when creating benchmark planning cases. This would
not only help establish a clear set of expectations for responsible
entities to follow when developing benchmark planning events, but also
facilitate auditing and enforcement of the Standard.
40. We also direct NERC to ensure the reliability standard contains
appropriate mechanisms for ensuring the benchmark event reflects up-to-
date meteorological data. The increasing intensity, frequency, and
unpredictability of extreme weather conditions requires that key
aspects of the benchmark events be reviewed, and if necessary, updated
periodically to ensure the corresponding benchmark planning cases
reflect updated meteorological data. For example, a requirement that
defines a fixed benchmark event with no provision for future updates
(e.g., defining the benchmark event for a responsible entity as the
most severe heat wave in the last twenty years measured from the
effective date of the standard) may not provide an accurate indicator
of future risks. To the extent NERC determines that the benchmark event
should be fixed or only updated
[[Page 41269]]
periodically,\72\ we agree with MISO that including a mechanism to
update the benchmark event at least every five years would strike a
reasonable balance between the benefits of using the most up-to-date
meteorological data and administrative the burdens of collecting and
analyzing such data.
---------------------------------------------------------------------------
\72\ See, e.g., Reliability Standard EOP-012-1 (Extreme Cold
Weather Preparedness and Operations), at Requirement 4 (requiring
generator owners to calculate the generator extreme cold weather
temperature every five years).
---------------------------------------------------------------------------
C. Definition of ``Wide-Area''
41. In the NOPR, the Commission proposed to direct NERC to require
in a new or modified Reliability Standard that transmission planning
studies consider the wide-area impacts of extreme heat and cold
weather.\73\ The NOPR explained that the impacts of extreme weather
events on the Reliable Operation of the Bulk-Power System can be
widespread, potentially causing simultaneous loss of generation and
increased transmission constraints within and across regions.\74\ The
NOPR also pointed out that failure to study the wide-area impact of
extreme heat or cold weather conditions in transmission planning could
result in reliability issues affecting multiple regions or multiple
planning coordinator areas remaining undetected in the long-term
planning horizon. This, in turn, could lead to otherwise avoidable
system conditions that would be only one contingency away from voltage
collapse and uncontrolled blackouts.\75\
---------------------------------------------------------------------------
\73\ NOPR, 179 FERC ] 61,195 at P 64.
\74\ Id.
\75\ Id. P 66.
---------------------------------------------------------------------------
42. The NOPR proposed that, based on prior events, the study
criteria for extreme heat and cold weather events should consider wide-
area conditions affecting neighboring regions and their impact on one
planning area's ability to rely on the resources of another region
during the weather event.
43. To identify opportunities for improved wide-area planning
studies and coordination, the NOPR sought comments on whether wide-area
planning studies should be defined geographically or electrically.\76\
---------------------------------------------------------------------------
\76\ Id. P 67. The NOPR also solicited comment on which entities
should oversee and coordinate the wide-area planning models and
studies, as well as addressing the results of the studies, and how
they should communicate those results among transmission planners.
Id. These comments are addressed below in the sections D and E.
---------------------------------------------------------------------------
1. Comments
44. AEP, MISO Transmission Owners, and Tri-State Generation and
Transmission Association, Inc. (Tri-State) favor defining wide-area
geographically.\77\ MISO Transmission Owners assert that wide-area must
be defined by geography to address issues in each region as best suited
for that region, given that extreme heat and cold weather risks, and
the appropriate responses thereto, vary by geography.\78\ Tri-State
explains that ``wide-area'' should be defined geographically, because
for a transmission planner to evaluate a large area weather event, it
would need to be modeled within the transmission planner's area, as
well as neighboring entities.\79\
---------------------------------------------------------------------------
\77\ AEP Comments at 16; MISO Transmission Owners Comments at 4.
\78\ Id. at 4.
\79\ Tri-State Comments at 5-6.
---------------------------------------------------------------------------
45. Although MISO Transmission Owners support a geographic
definition, they also caution that RTO regions, Order No. 1000 planning
regions, and NERC Regional Entities do not have identical footprints.
Therefore, MISO Transmission Owners recommend that the final rule
direct NERC to propose modifications to Reliability Standards to
provide appropriately flexible provisions to address scenarios where
those inconsistent footprints may introduce conflicts.\80\
---------------------------------------------------------------------------
\80\ MISO Transmission Owners Comments at 4.
---------------------------------------------------------------------------
46. Idaho Power, on the other hand, comments that ``wide-area''
should be defined electrically to better capture the interdependency of
systems.\81\
---------------------------------------------------------------------------
\81\ Idaho Power Comments at 4.
---------------------------------------------------------------------------
47. LCRA Transmission Services Corporation (LCRA), Electric Power
Research Institute (EPRI), and PJM prefer that ``wide-area'' be defined
both geographically and electrically. LCRA explains that this is
necessary to represent the geographic correlation of extreme weather
events and the electrical connectivity of the transmission system.\82\
EPRI cautions that ``geographic definitions of wide area events will
need to be developed for inclusion in resource adequacy or production
cost models'' for purposes of identifying the snapshot conditions that
should serve as the primary inputs to the transmission planning
assessments.\83\ Further, EPRI explains that ``wide area events defined
electrically can be used to represent acute switching events that occur
over much shorter timescales and can be used to capture discrete
impacts defined as contingency events, which occur concurrent with the
extreme temperature condition.'' \84\
---------------------------------------------------------------------------
\82\ LCRA Comments at 3; EPRI Comments at P 18; PJM Comments at
10.
\83\ EPRI Comments at P 18.
\84\ Id. at 12.
---------------------------------------------------------------------------
48. Other commenters, while not indicating a preference between
electrical or geographical definition, highlight that extreme heat and
cold weather events are not bound by the footprint of utilities or
authorities that separate planning and balancing areas.\85\ Indicated
Trade Associations recommend that the Commission invest the NERC
standard drafting team with substantial discretion in addressing
whether and how wide-area planning studies should be defined
geographically or electrically.\86\
---------------------------------------------------------------------------
\85\ UCS Comments at 8; Entergy Comments at 5; EDF at Comments
23; MISO Transmission Owners Comments at 4.
\86\ Indicated Trade Associations at 10.
---------------------------------------------------------------------------
49. Although also not stating a preference as to whether to define
``wide-area'' electrically or geographically, Entergy Services, LLC
(Entergy) cautions against expecting transmission planners and
coordinators ``to overlap benchmark events between regions'' because
``[s]uch overlapping could result in modeling of extreme heat and cold
events over regions that are much larger than the areas in which such
events are likely to occur.'' \87\
---------------------------------------------------------------------------
\87\ Entergy Comments at 5-6.
---------------------------------------------------------------------------
2. Commission Determination
50. Pursuant to section 215(d)(5) of the FPA, we adopt the NOPR
proposal and direct NERC to require that transmission planning studies
under the new or revised Reliability Standard consider the wide-area
impacts of extreme heat and cold weather. We direct NERC to clearly
describe the process that an entity must use to define the wide-area
boundaries. While commenters provide various views in favor of both a
geographical approach and electrical approach to defining wide-area
boundaries, we do not adopt any one approach in this final rule.
Rather, we believe that this technical matter deserves a more fulsome
vetting in the Reliability Standards development process. NERC should
consider the comments in this proceeding when developing a new or
modified reliability standard that considers the broad area impacts of
extreme heat and cold weather.\88\
---------------------------------------------------------------------------
\88\ Cf., Order No. 693, 118 FERC ] 61,218 at P 188 (directing
NERC to address NOPR comments suggesting specific new improvements
to the Reliability Standards in the standards development process,
noting that it ``does not direct any outcome other than that the
comments receive consideration.'').
---------------------------------------------------------------------------
D. Entities Responsible for Developing Benchmark Events and Planning
Cases, and for Conducting Transmission Planning Studies of Wide-Area
Events
51. The NOPR proposed to direct NERC to develop requirements that
address the types of extreme heat and
[[Page 41270]]
cold scenarios responsible entities are required to study, including
the development of benchmark events and benchmark planning cases.\89\
The NOPR solicited feedback on which entities should be responsible for
updating benchmark events and whether, and to what extent, it may be
appropriate to allow designated entities to periodically update key
aspects of the benchmark events.\90\
---------------------------------------------------------------------------
\89\ NOPR, 179 FERC ] 61,195 at PP 50-51.
\90\ Id. P 53.
---------------------------------------------------------------------------
52. As a separate matter, the NOPR proposed to require that
transmission planning studies that consider the wide-area impacts of
extreme heat and cold weather.\91\ To inform this directive, the NOPR
solicited comment on which entities should oversee and coordinate the
wide-area planning models and studies, as well as which entities should
have responsibility to address the results of the studies.\92\
---------------------------------------------------------------------------
\91\ Id. P 64.
\92\ Id. P 67.
---------------------------------------------------------------------------
1. Comments
a. Entity Responsible for Development of Benchmark Events
53. There is no consensus among the commenters regarding which
entities should be tasked with developing the benchmark events.
Indicated Trade Associations suggest that the subject matter experts on
the NERC standard drafting team should develop the benchmark
events.\93\ Entergy also suggests that the NERC develop the benchmark
events, as NERC will be able to tailor the benchmark events to reflect
regional variations in extreme weather risk.\94\ All other commenters
on this issue proposed that other entities be responsible for benchmark
event development.\95\ For example, New York Independent System
Operator, Inc. (NYISO) and MISO Transmission Owners posit that entities
registered with NERC as planning coordinators or transmission planners
should be given the latitude to develop the benchmark events.\96\ AEP
recommends that each planning coordinator should develop individualized
benchmark events for its planning area, except in regions that lack the
necessary resources or expertise, in which case the Regional Entities
should coordinate and review the benchmark event process in
collaboration with these smaller planning coordinators in that
region.\97\ American Clean Power Association (ACP) suggests that the
Regional Entities should develop the benchmark events that will be
evaluated by all transmission planners and planning coordinators in a
given region.\98\
---------------------------------------------------------------------------
\93\ Indicated Trade Associations Comments at 8.
\94\ Entergy Comments at 4.
\95\ See. e.g., EDF Comments at 8.
\96\ NYISO Comments at 13; MISO Transmission Owners Comments at
5.
\97\ AEP Comments at 9.
\98\ ACP Comments at 3.
---------------------------------------------------------------------------
b. Entity Responsible for Development of Planning Cases and Conducting
Transmission Planning Studies of Wide-Area Events
54. Regarding development of benchmark planning cases, beyond
existing registered entities, Arizona Public Service Company (APS)
recommends ``that a regional planning entity would be the appropriate
entity to determine the benchmark planning cases and develop the
scenarios that constitute an extreme event in their region.'' \99\
---------------------------------------------------------------------------
\99\ APS Comments at 3.
---------------------------------------------------------------------------
55. Further, commenters suggest a variety of entities to perform
the wide area studies. NERC suggests that a registered entity subject
to the Reliability Standard, such as a planning coordinator or
transmission planner, should be responsible for performing the wide-
area studies.\100\ AEP asserts that the planning coordinators should
oversee and coordinate the wide-area planning models and studies,
communicate the results, and work to mitigate issues that require
corrective action.\101\
---------------------------------------------------------------------------
\100\ AEP Comments at 20; NERC Comments at 9-10.
\101\ AEP Comments at 16.
---------------------------------------------------------------------------
56. APS and MISO Transmission Owners express concern that an
individual transmission planner or planning coordinator would not be
positioned to perform a wide-area assessment of extreme weather
conditions because of its limited geographical visibility.\102\
Similarly, Entergy also questions whether a single transmission planner
would be able to model a wide-area event on its own. Entergy believes
that the responsibility for performing the analysis should lie with the
RTOs or Regional Entities, with input provided by member transmission
owners and transmission planners.\103\ Alternatively, APS suggested a
regional planning entity, such as those created under Order No. 1000,
would be appropriate to oversee and coordinate wide-area planning
models and studies.\104\ Idaho Power Company (Idaho Power) asserts that
regional planning groups such as Western Power Pool are the ones best
positioned to coordinate and perform the wide-area planning
studies.\105\
---------------------------------------------------------------------------
\102\ APS Comments at 4; MISO Transmission Owners Comments at 4.
\103\ Entergy Comments at 6.
\104\ APS Comments at 4.
\105\ Idaho Power Comments at 4.
---------------------------------------------------------------------------
57. Environmental Defense Fund (EDF), Tri-State, and Eversource
Energy Service Company (Eversource) propose that reliability
coordinators should have the responsibility to perform wide-area
planning and coordination in collaboration with other impacted
reliability coordinators.\106\
---------------------------------------------------------------------------
\106\ EDF Comments at 23; Tri-State Comments at 6; Eversource
Comments at 5.
---------------------------------------------------------------------------
2. Commission Determination
a. Entity Responsible for Establishing Benchmark Events
58. Pursuant to section 215(d)(5) of the FPA, we adopt the NOPR
proposal and direct NERC to develop benchmark events for extreme heat
and cold weather events through the Reliability Standards development
process. We agree with Indicated Trade Associations that the
development of adequate benchmark events is critical and should be
committed to the subject matter experts on the standards drafting team.
We also agree with Entergy that NERC will be able to tailor benchmark
events to capture regional differences and the different risks that
each region faces during extreme heat and cold weather events. While
Regional Entities and reliability coordinators are encouraged to
participate in the NERC Reliability Standards development process to
develop the benchmark events, we disagree with AEP and other commenters
who recommend that entities other than NERC take the lead in the
development of benchmark events.
59. Further, requiring NERC to develop the new or modified
Reliability Standard's benchmark events is consistent with the approach
the Commission took in Order No. 779, when the Commission directed NERC
to develop benchmark events for geomagnetic disturbance analyses.\107\
For the same reasons, we also conclude that NERC is best positioned to
define mechanisms to periodically update extreme heat and cold weather
benchmark events, as discussed above.\108\
---------------------------------------------------------------------------
\107\ Reliability Standards for Geomagnetic Disturbances, Order
No. 779, 143 FERC ] 61,147, at P 2 (2013).
\108\ See supra P 40.
---------------------------------------------------------------------------
b. Entities Responsible for Development of Planning Cases and
Conducting Transmission Planning Studies of Wide-Area Events
60. We also direct NERC to designate the type(s) of entities
responsible for
[[Page 41271]]
developing benchmark planning cases and conducting wide-area studies
under the new or modified Reliability Standard. The scope of extreme
weather event studies will likely cover large geographical areas far
exceeding the smaller individual transmission planner or planning
coordinator planning areas. Accordingly, we agree with APS that the
benchmark planning cases should be developed by registered entities
such as large planning coordinators, or groups of planning
coordinators, with the capability of planning on a regional scope.\109\
---------------------------------------------------------------------------
\109\ According to the NERC Registration Matrix, there are
currently 211 transmission planners and 66 planning coordinators in
the United States. While some of these entities operate over large
geographic areas--for example, PJM and MISO are the only planning
coordinators in the Reliability First footprint--the majority
operate on a much smaller scale--WECC and SERC have 59 planning
coordinators, some of which are small cities and counties. NERC, NCR
Active Entities List, (last visited Apr. 7, 2023) https://www.nerc.com/pa/comp/Registration%20and%20Certification%20DL/NERC_Compliance_Registry_Matrix_Excel.xlsx.
---------------------------------------------------------------------------
61. We also disagree with assertions that reliability coordinators
should be responsible for developing benchmark planning cases or
conducting wide-area studies. We believe the designated responsible
entities should have certain characteristics, including having a wide-
area view of the Bulk-Power System and the ability to conduct long-term
planning studies across a wide geographic area. The responsible
entities should also have the planning tools, expertise, processes, and
procedures to develop benchmark planning cases and analyze extreme
weather events in the long-term planning horizon. Under the NERC
functional model, however, reliability coordinators have responsibility
for the real-time operation of the bulk-power system. Accordingly, we
conclude that reliability coordinators are not well suited for
developing benchmark planning cases or conducting wide-area studies.
62. To comply with this directive, NERC may designate the tasks of
developing benchmark planning cases and conducting wide-area studies to
an existing functional entity or a group of functional entities (e.g.,
a group of planning coordinators). NERC may also establish a new
functional entity registration to undertake these tasks. In the
petition accompanying the proposed Reliability Standard NERC should
explain how the applicable registered entity or entities meet the
objectives outlined above.
E. Coordination Among Registered Entities and Sharing of Data and Study
Results
63. The NOPR explained that Reliability Standard TPL-001-5.1 cross-
references Reliability Standard MOD-032-1 (Data for Power System
Modeling Analysis), which establishes consistent modeling data
requirements and reporting procedures for the development of planning
horizon cases necessary to support analysis of the reliability of the
interconnected system.\110\ Reliability Standard MOD-032-1 ensures an
adequate means of data collection for transmission planning. It
requires applicable registered entities to provide steady-state,
dynamic, and short circuit modeling data to their transmission
planner(s) and planning coordinator(s). The modeling data is then
shared pursuant to the data requirements and reporting procedures
developed by the transmission planner and planning coordinator as set
forth in Reliability Standard TPL-001-5.1, Requirement R1.
---------------------------------------------------------------------------
\110\ NOPR, 179 FERC ] 61,195 at P 80.
---------------------------------------------------------------------------
64. The NOPR stated that, while balancing authorities and other
entities must share system information and study results with their
transmission planner and planning coordinator pursuant to Reliability
Standards MOD-032-1 and TPL-001-5.1, there is no required sharing of
such information related to extreme heat or cold weather events--or
required coordination--among planning coordinators and transmission
planners with transmission operators, transmission owners, and
generator owners.\111\ Sharing system information and study results and
enhancing coordination among these entities for extreme heat and cold
weather events could result in more representative planning models by
better integrating and including operations concerns (e.g., lessons
learned from past issues including corrective actions and projected
outcomes from these actions, evolving issues concerning extreme heat/
cold) in planning models; and conveying reliability concerns from
planning studies (e.g., potential widespread cascading, islanding,
significant loss of load, blackout, etc.) as they pertain to extreme
heat or cold.\112\
---------------------------------------------------------------------------
\111\ Id. P 81.
\112\ Id.
---------------------------------------------------------------------------
65. The NOPR proposed to direct NERC to require system information
and study results sharing and coordination among planning coordinators
and transmission planners with transmission operators, transmission
owners, and generator owners for extreme heat and cold weather
events.\113\ The NOPR solicited comments on whether existing
Reliability Standards are sufficient to ensure that responsible
entities performing studies of extreme heat and cold weather events
have the necessary data, and/or whether the Commission should direct
additional changes pursuant to FPA section 215(d)(5) to address the
issue.\114\ The NOPR also sought comments on the following: (1) the
parameters and timing of coordination and sharing; (2) specific
protocols that may need to be established for efficient coordination
practices; and (3) potential impediments to the proposed coordination
efforts.
---------------------------------------------------------------------------
\113\ Id. P 82.
\114\ Id. P 63.
---------------------------------------------------------------------------
1. Comments
66. There is no consensus among commenters on whether Reliability
Standards TPL-001.5.1 and MOD-032-1 are adequate means of data
collection for transmission planning, with some commenters raising
concerns about the types of data that will be needed to conduct extreme
heat and cold weather studies under the new or modified Reliability
Standard and whether such data can be obtained through existing
processes.
67. For example, NERC and Idaho Power believes that the existing
standards are sufficient.\115\ According to NERC, the Commission does
not need to direct revisions to Reliability Standard MOD-032-1 to
account for new data required for extreme heat and cold weather studies
because the standard requires functional entities to provide ``other
information requested by the Planning Coordinator or Transmission
Planner necessary for modeling purposes'' for each of the three types
of data required (steady-state, dynamics, and short circuit).\116\
Thus, NERC asserts that planning coordinators and transmission planners
are empowered to request any specific data needed for studies of
extreme heat and cold conditions. According to Idaho Power, because (1)
utilities currently share contingencies to be studied with neighboring
entities to get feedback and make updates as needed and (2) utilities
share TPL-001 reports with other utilities subject to the execution of
a non-disclosure agreement, the Commission proposal would be redundant
of current practice.\117\
---------------------------------------------------------------------------
\115\ NERC Comments at 13; Idaho Power Comments at 5.
\116\ NERC Comments at 13.
\117\ Idaho Power Comments at 5.
---------------------------------------------------------------------------
[[Page 41272]]
68. In contrast, Tri-State indicates that there is no requirement
for transmission customers to provide data for extreme heat and cold
weather conditions such as load forecast data.\118\ AEP asserts that
planning coordinators and transmission planners have limited insight
into a generator's likelihood of availability during extreme weather
events, particularly limited for inverter-based resources.\119\ EPRI
states that there is limited modeling of protection systems in dynamic
assessments currently, and any dynamic simulation of extreme events
would require significant modeling of protection systems to provide for
convergence of the numerical simulation.\120\ NYISO notes that
Reliability Standard TPL-001 currently limits transmission planners or
planning coordinators to requesting data pertaining to their own
planning area.\121\
---------------------------------------------------------------------------
\118\ Tri-State Comments at 4-5.
\119\ AEP Comments at 15.
\120\ EPRI Comments at P 11.
\121\ NYISO Comments at 14.
---------------------------------------------------------------------------
69. Other commenters suggest that it will be necessary to define
the data needed by responsible entities to perform studies under the
new or modified Reliability Standard. AEP proposes that the Commission
hold a technical conference to help define the data needed to perform
the extreme weather assessments and the avenue through which
information will be shared.\122\ Indicated Trade Associations recommend
that, although Reliability Standard MOD-032-1 might be adequate as a
data source, the Commission should recognize in any final rule that the
standard drafting team should be tasked with identifying what data is
already collected and specifying what new data is needed to perform the
assessments for extreme heat and cold.\123\
---------------------------------------------------------------------------
\122\ AEP Comments at 4.
\123\ Indicated Trade Associations Comments at 9-10.
---------------------------------------------------------------------------
70. Regarding the sharing of study results and coordination among
entities, Tri-State suggests that the balancing authority should
address the results of the studies and how they should communicate
those results among the transmission planners. Tri-State also asserts
that the balancing authority is responsible for resource adequacy and
should communicate resource needs for the area with the responsible
transmission planners who can evaluate system needs and ``provide
access to remove'' resource needs.\124\ EPRI does not opine on who
should do the wide-area coordination, but states that some level of
coordination will be required to ensure accurate assessments of wide
area events that impact geographic footprints across multiple planning
entities.\125\ UCS suggests that the final rule should direct the
sharing of modeling information between planning areas regarding
extreme weather benchmark events, because ensuring reliability will
depend on the extent to which neighboring regions cooperate.\126\
---------------------------------------------------------------------------
\124\ Tri-State Comments at 6.
\125\ EPRI Comments at P 19.
\126\ UCS Comments at 8.
---------------------------------------------------------------------------
71. NERC asserts that while wide-area studies should be coordinated
as appropriate for the area, the specific procedural details for
coordination on wide-area studies do not need to be mandated in a
Reliability Standard. NERC adds that other coordination requirements,
such as those related to sharing of study results and coordination for
corrective actions across multiple transmission planner areas, can be
addressed through the standard development process with consideration
of any factors identified by the commenters in this proceeding.\127\
Similarly, Indicated Trade Associations recommend that the Commission
empower the standards drafting team to consider whether coordination
between a variety of functional entities, and across regions, would be
the most effective means of addressing certain identified extreme heat
and cold weather events.\128\
---------------------------------------------------------------------------
\127\ NERC Comments at 10.
\128\ Indicated Trade Associations Comments at 5.
---------------------------------------------------------------------------
2. Commission Determination
72. Pursuant to section 215(d)(5) of the FPA, we adopt and modify
the NOPR proposal and direct NERC to require functional entities to
share with the entities responsible for developing benchmark planning
cases and conducting wide-area studies the system information necessary
to develop benchmark planning cases and conduct wide-area studies.
Further, responsible entities must share the study results with
affected transmission operators, transmission owners, generator owners,
and other functional entities with a reliability need for the
studies.\129\
---------------------------------------------------------------------------
\129\ The NOPR proposed to direct NERC to ensure that functional
entities share necessary system information with planning
coordinators and transmission planners, as these entities conduct
current transmission planning studies under TPL-001-5.1. Because
this final rule directs NERC to determine the entities that will be
responsible for conducting studies under the new or modified
Reliability Standard, we modify the NOPR accordingly to ensure the
selected responsible entity has the means to request and receive
necessary system information.
---------------------------------------------------------------------------
73. We agree with commenters that Reliability Standard MOD-032-1
allows for data collection for extreme heat and cold weather events.
However, only planning coordinators and transmission planners can
request data from other entities through Reliability Standard MOD-032-1
processes. Because in this final rule we direct NERC to determine the
responsible entities that will be developing benchmark planning cases
and conducting wide-area studies, it is possible that the selected
responsible entities under the new or modified Reliability Standard
will not be able to request and receive needed data pursuant to MOD-
032-1, absent modification to that Standard.
74. Regarding EPRI's statement of insufficiency of dynamic modeling
of protection systems, we consider the insufficiency of protection
system modeling to be an ongoing deficiency in the modeling process.
The dynamics databases used for transient stability simulations by
various interconnections typically do not include comprehensive dynamic
models of relays installed in the interconnection. Thus, in addressing
our directive above, NERC should evaluate this deficiency during the
standard development process.
75. We disagree with UCS's recommendation that the final rule
should direct the sharing of modeling information between planning
areas regarding extreme weather benchmark events. We expect that the
existing practice (e.g., MOD-032-1) of responsible entities sharing
modeling information between planning areas will continue, without the
need for us to specifically direct that in this final rule.
76. Rather than predetermine each aspect of the coordination
process, we believe the decision of which entities are best positioned
for wide-area coordination should be left to NERC. We therefore direct
NERC to address the requirement for wide-area coordination through the
standard development process, giving due consideration to relevant
factors identified by commenters in this proceeding.
77. We agree with NERC and Indicated Trade Associations that
coordination requirements, such as those related to the sharing of
study results and corrective actions across multiple transmission
planner areas, are best addressed through the standard development
process, which we expect will consider relevant factors identified by
the commenters in this proceeding. Although this final rule does not
specify how study results must be shared, we believe that the new or
modified Reliability Standard must require responsible entities to
share these studies with affected functional entities. The sharing of
study results will alert entities of reliability concerns identified
[[Page 41273]]
in wide-area studies.\130\ Further, requiring responsible entities to
share study results with functional entities with a reliability related
need for the study is consistent with existing planning assessment
sharing requirements under Reliability Standard TPL-001-5.1.\131\
Therefore, we direct NERC to require in the new or modified Reliability
Standard that responsible entities share the results of their wide-area
studies with other registered entities such as transmission operators,
transmission owners, and generator owners that have a reliability
related need for the studies.
---------------------------------------------------------------------------
\130\ NOPR, 179 FERC ] 61,195 at P 81.
\131\ See Reliability Standard TPL-001-5.1, Requirement R8.
---------------------------------------------------------------------------
F. Concurrent/Correlated Generator and Transmission Outages
78. The NOPR stated that generation resources that are sensitive to
severe weather conditions may cease operation during extreme heat and
cold events, thus contributing to wide-area concurrent outages. In
addition, the NOPR indicated that extreme heat could lead to
significant derating, reduced lifetime, or failure of power
transformers, while extreme cold could lead to at least temporary
transmission facility outages.\132\
---------------------------------------------------------------------------
\132\ NOPR, 179 FERC ] 61,195 at P 68.
---------------------------------------------------------------------------
79. As such, the NOPR posited that modeling the loss of these
generators and transmission equipment during extreme heat and cold
weather events would allow planners to assess the effects of potential
concurrent transmission and generator outages and study the feasibility
(i.e., availability and deliverability) of external generation
resources that could possibly be imported to serve load during such
events, thereby minimizing the potential impact of extreme heat and
cold events on customers.\133\ In addition, the NOPR indicated that
modeling concurrent generator and transmission outages would also allow
planners to better identify appropriate solutions to be incorporated
into corrective action plans.\134\
---------------------------------------------------------------------------
\133\ Id. P 69.
\134\ Id.
---------------------------------------------------------------------------
80. The NOPR also proposed that accounting for concurrent outages
including modeling the derating and possible loss of wind and solar
generators, as well as natural gas generators sensitive to extreme heat
and cold conditions in planning studies would provide a more realistic
assessment of system conditions (i.e., updated conditions based on
historic benchmarked performance) during potential extreme heat and
cold events and will help better assess the probability of potential
occurrences of cascading outages, uncontrolled separation, or
instability. Thus, the NOPR suggested that requiring transmission
planners and planning coordinators to study concurrent generator and
transmission failures under extreme heat and cold events to account for
the expected resource mix's availability during these extreme
conditions is one way to address the reliability gap in Reliability
Standard TPL-001-5.1.\135\
---------------------------------------------------------------------------
\135\ Id. P 72.
---------------------------------------------------------------------------
81. To identify the scope of these planning studies, the NOPR
sought comments on the following: (1) the assumptions (e.g., weather
forecast, load forecast, transmission voltage levels, generator types,
multi-day low wind, and solar events) used in modeling of concurrent
outages due to extreme heat and cold weather events; (2) what
assumptions should be included when performing modeling and planning
for generators sensitive to extreme heat and cold; (3) how the impact
of loss of generators sensitive to extreme heat and cold should be
factored into long-term planning; (4) the extent of neighboring
systems' or planning areas' outages that should be modeled in
transmission planning studies; and (5) whether a certain threshold
penetration of wind, solar, and natural gas generation should trigger
additional analyses.\136\
---------------------------------------------------------------------------
\136\ Id.
---------------------------------------------------------------------------
1. Comments
82. Commenters mostly agree with the NOPR that responsible entities
should evaluate the risk of correlated or concurrent outages and
derates of all types of generation resources (i.e., conventional and
renewables) as well as transmission facilities related to extreme
weather events.\137\ For example, the Federal Energy Advocate for the
Public Utilities Commission of Ohio (Ohio FEA) recommends that the
Standard incorporate asset correlations and interdependencies, and
consider the extent to which they can be obviated or mitigated because
asset performance or failure is highly correlated with their dependency
on weather conditions and on the performance of nearby or related
infrastructure.\138\ Idaho Power notes that while Reliability Standard
TPL-001-5.1 already addresses the loss of multiple generating stations
resulting from conditions such as the loss of a large gas pipeline into
a region or multiple regions that have significant gas-fired
generation, the standard could be modified to include the impact of
renewable energy resource response due to extreme weather as well.\139\
While agreeing with the NOPR proposal, Public Interest Organizations
(PIOs) and ACP argue that any requirement to study concurrent or
correlated generation outages should be extended to conventional
generators to account for the reliability risk and to eliminate undue
discrimination caused by overstating the reliability contributions of
conventional generators relative to renewable and storage
resources.\140\
---------------------------------------------------------------------------
\137\ EDF Comments at 22; ACP Comments at 5; PIOs Comments at 9;
AEP Comments at 4; UCS Comments at 12; and Americans for Clean
Energy Grid Comments at 6 (ACEG Comments).
\138\ Ohio FEA Comments at 5.
\139\ Idaho Power Comments at 4.
\140\ PIOs Comments at 23-24.
---------------------------------------------------------------------------
83. Some commenters assert that the NOPR proposal on modeling the
effects of potential concurrent transmission and generator outages
might be unnecessary. ISO New England Inc. (ISO-NE) takes issue with
including the expected resource mix's availability during extreme
weather conditions as part of extreme weather scenarios. ISO-NE asserts
that resource mix availability should not be addressed in a
transmission planning standard because it is addressed as part of
resource adequacy assessment and other Reliability Standards, such as
the Cold Weather Reliability Standards. Further, ISO-NE argues that
transmission planning Reliability Standards need to consider resource
availability in planning cases, because generators will be required to
be ready to perform in extreme weather events under those other
standards.\141\ EPRI asks if the Commission intends for the concurrent
outages of generation and transmission assets to be modeled as an acute
event, and if so, requests clarification as to how it differs from the
P3 category of contingency events from TPL-001-5.1.\142\
---------------------------------------------------------------------------
\141\ ISO-NE Comments at 2-4.
\142\ EPRI Comments at PP 20-21. Category P3 requires the study
of the loss of a generator unit followed by system adjustments,
followed by a loss of one of the following: generator or
transmission circuit or transformer or shunt device or single pole
of a DC line as stated in Reliability Standard TPL-001.5.1, Table 1.
---------------------------------------------------------------------------
84. NYISO recommends that, as the extreme events in Reliability
Standard TPL-001-5.1 are analogous to extreme contingencies rather than
extreme system conditions such as heatwaves, cold snaps, droughts,
etc., NERC planning events should be expanded to include the weather-
related loss of generation across areas of the system in the design-
basis contingencies rather than as an extreme contingency.\143\
---------------------------------------------------------------------------
\143\ NYISO Comments at 13.
---------------------------------------------------------------------------
[[Page 41274]]
85. Regarding modeling assumptions, LCRA asserts that the Standard
should not be prescriptive regarding the modeling assumptions,
particularly concerning generation availability, beyond developing the
study base case when available generation is insufficient to meet the
load with respect to extreme weather events.\144\ LCRA also cautions
that modeling too many outages will result in an unsolvable case that
cannot be analyzed.\145\
---------------------------------------------------------------------------
\144\ LCRA Comments at 3.
\145\ Id.
---------------------------------------------------------------------------
86. While no comments recommended any specific threshold of
penetration of renewable resources that would trigger additional
analysis, PJM notes that special studies may be needed as greater
numbers of renewable, inverter-based resources (IBR), connect to the
Bulk-Power System. With a much higher IBR penetration level, a more
material change to dynamic and steady state assessment will likely be
needed to capture the impacts of higher penetration levels of IBRs and
much reduced conventional generation support.\146\ APS, however,
suggests that the Commission should not set a penetration threshold,
arguing that the entity performing the study should determine the
threshold, which likely would differ depending on the characteristics
of the particular system.\147\
---------------------------------------------------------------------------
\146\ PJM Comments at 11.
\147\ APS Comments at 5.
---------------------------------------------------------------------------
87. Electric Power Supply Association (EPSA) suggests that the
Commission direct NERC to examine how it defines and measures its
resource adequacy benchmarks, including the impacts of non-dispatchable
resources with increasing penetration in the system and the
availability of dispatchable, flexible resources which are increasingly
being replaced by new, less flexible resources or technologies.\148\
---------------------------------------------------------------------------
\148\ EPSA Comments at 3.
---------------------------------------------------------------------------
2. Commission Determination
88. Pursuant to section 215(d)(5) of the FPA, we adopt the NOPR
proposal and direct NERC to require under the new or revised
Reliability Standard the study of concurrent/correlated generator and
transmission outages due to extreme heat and cold events in benchmark
events as described in more detail below.
89. We disagree with comments suggesting that the modeling of
concurrent/correlated generator and transmission outages is
unnecessary.\149\ As discussed in the NOPR, and reinforced by
commenters, the failures of individual generators during extreme
weather events are not independent.\150\ Previous extreme weather
events have demonstrated that there is a high correlation between
generator outages and cold temperatures, indicating that as
temperatures decrease, unplanned generator outages and derates
increase.\151\ Because of this correlation, it is necessary that
responsible entities evaluate the risk of correlated or concurrent
outages and derates of all types of generation resources and
transmission facilities as a result of extreme heat and cold events, as
commenters suggest.\152\
---------------------------------------------------------------------------
\149\ See, e.g., ISO-NE Comments at 2-4.
\150\ NOPR, 179 FERC ] 61,195 at P 70.
\151\ Id. PP 70-71.
\152\ See supra P 82.
---------------------------------------------------------------------------
90. Further, we disagree with ISO-NE that resource mix availability
should not be considered here because it is considered in resource
adequacy planning and in other Reliability Standards. Although resource
outages are an important input into the resource adequacy studies, they
are also an important determinant in assessing the adequacy of the
transmission system.\153\ Therefore, it will be necessary to consider
the impact of extreme weather events on generators anticipated to be
connected to the subject transmission system during the study period.
Similarly, although the Cold Weather Reliability Standards require
generators to be prepared to be available and perform at or above their
extreme cold weather temperature during extreme weather events,
generator availability is not guaranteed by any Reliability Standard,
and outages occur for many reasons. Accordingly, some generators may
still be unavailable under extreme heat or cold conditions and thus
their potential outages must be considered in extreme heat and cold
weather planning scenarios.
---------------------------------------------------------------------------
\153\ This understanding is consistent with section 215(a)(1) of
the FPA, 16 U.S.C. 824o(a)(1), which defines Bulk-Power System to
include ``electric energy from generation facilities needed to
maintain transmission system reliability.''
---------------------------------------------------------------------------
91. Although several commenters ask for flexibility as to modeling
assumptions, we believe that it is necessary for the Reliability
Standard to strike a balance between allowing responsible entities
discretion to ensure the study incorporates their operating experience
and the need to create a robust framework that ensures extreme heat and
cold events are adequately studied. Thus, while generation and
transmission availability and concurrent outages must be included in
the benchmark planning case, we defer to NERC to develop the framework
and criteria that responsible entities shall use to represent potential
weather-related contingencies (e.g., concurrent/correlated generation
and transmission outages, derates) in the relevant benchmark event
planning cases.\154\
---------------------------------------------------------------------------
\154\ See supra P 39. Reliability Standard TPL-001-5.1
Requirement 1.1.5 requires responsible entities to maintain system
models that represent projected system conditions, including
resources required for load. Because drought conditions may impact
the availability of certain supply resources, we expect that the new
or revised Reliability Standard will include a similar requirement
that accounts for the impact of drought conditions on generation
where appropriate.
---------------------------------------------------------------------------
92. Regarding the comments of NYISO and EPRI on the difference
between extreme events and contingencies covered under Reliability
Standard TPL-001-5.1, we clarify that all contingencies included in
benchmark planning cases under the new or modified Reliability Standard
will represent initial conditions for extreme weather event planning
and analysis. These contingencies (i.e., correlated/concurrent,
temperature sensitive outages, and derates) shall be identified based
on similar contingencies that occurred in recent extreme weather events
or expected to occur in future forecasted events.
93. Regarding PJM's comment regarding the likely need for
additional studies to capture the impacts of higher penetration levels
of renewables and much reduced conventional generation support, we note
that the benchmark planning case will include this information pursuant
to our directive above regarding benchmarking planning cases.
Accordingly, we do not foresee the need for the additional studies
suggested by PJM.
94. Lastly, regarding EPSA's comment requesting that we direct NERC
to examine how it defines and measures its resource adequacy
benchmarks, we note that resource adequacy benchmarks are outside the
scope of this proceeding.
G. Conduct Transmission System Planning Studies for Extreme Heat and
Cold Weather Events
1. Steady State and Transient Stability Analyses
95. The Commission proposed in the NOPR to require both steady
state and transient stability analyses be conducted for extreme heat
and cold weather events as part of transmission planning studies.\155\
Consistent with Reliability Standard TPL-001-5.1, the NOPR stated that
steady state and stability analyses of study cases modeled to reflect
past and forecasted extreme heat and cold conditions would better
prepare transmission operators for such
[[Page 41275]]
conditions.\156\ The NOPR explained that a steady-state analysis is
based on a snapshot in time where the bulk electric system facilities
such as generators, transmission lines, transformers etc. are modeled
as fixed and load is modeled as a constant.\157\ On the other hand,
transient stability or dynamic analyses simulate the time-varying
characteristics of the system during a disturbance that occurs during
an extreme heat or cold event.\158\ The NOPR further stated that
performing these studies in the long-term planning horizon period
(i.e., six to ten years and beyond) will provide an adequate lead time
for entities to develop and implement corrective action plans to reduce
the likelihood or mitigate the consequences and adverse impacts of such
events.\159\
---------------------------------------------------------------------------
\155\ NOPR, 179 FERC ] 61,195 at P 69.
\156\ Id. P 70.
\157\ Id. P 59.
\158\ Id. P 60.
\159\ Id. P 58.
---------------------------------------------------------------------------
96. The NOPR noted that the use of dynamic studies is particularly
important given the changing resource mix and the need to understand
the dynamic behavior of both traditional generators and variable energy
resources (VERs) (i.e., wind and solar photovoltaic).\160\
---------------------------------------------------------------------------
\160\ Id. P 61.
---------------------------------------------------------------------------
97. The NOPR sought comments on all aspects of the proposal, and
specifically, on whether responsible entities should include
contingencies based on their planning area and perform both steady
state and transient stability (dynamic) analyses using extreme heat and
cold cases. In addition, the NOPR invited comments on the following
topics: (1) the set of contingencies responsible entities must
consider; (2) required analyses to assess voltage stability, frequency
excursions and angular deviations caused as a result of near
simultaneous outages or common mode failures of VERs; and (3) the role
of demand response under such scenarios.\161\
---------------------------------------------------------------------------
\161\ Id. P 62. The NOPR also sought comment on whether existing
Reliability Standards are sufficient to ensure that responsible
entities performing studies of extreme heat and cold weather
conditions have the necessary data, and/or whether the Commission
should direct additional modifications pursuant to FPA section
215(d)(5) to address this issue. Id. P 63. This question is
discussed in section IV.E of this final rule.
---------------------------------------------------------------------------
a. Comments
98. All those who commented on the NOPR proposal to require both
steady state and transient stability analyses agree with the NOPR that
both steady state and transient stability analyses should be performed
in order to understand the potential impacts of extreme heat and cold
weather events.\162\ Below, we discuss comments received on the
following topics: (i) required contingencies; (ii) analyses of common
mode failures; and (iii) demand response.
---------------------------------------------------------------------------
\162\ See, e.g., NERC Comments at 9; PJM Comments at 10; Tri-
State Comments at 4; Eversource Comments at 5; WE ACT for
Environmental Justice Comments at 4; LCRA Comments at 3; UCS
Comments at 7.
---------------------------------------------------------------------------
i. Required Set of Contingencies
99. Idaho Power supports the inclusion of contingencies listed in
Table 1 of Reliability Standard TPL-001-4 such as the loss of two
generating stations resulting from, among other events, severe weather,
as it currently applies these contingencies in its severe weather
studies.\163\
---------------------------------------------------------------------------
\163\ Idaho Power Comments at 3.
---------------------------------------------------------------------------
100. AEP recommends that the Commission direct NERC to revise and
reclassify the contingency lists in Reliability Standard TPL-001-5.1 to
``reflect the unique challenges posed by extreme weather events'' and
to ensure that the bulk electric system is operated to withstand N-1-1
contingencies ``without interruption of firm transmission service or
non-consequential load loss.'' \164\ NYISO recommends expanding NERC
planning events to include the weather-related loss of generation
across areas of the system in the design-basis contingencies rather
than as an extreme contingency.\165\ Southern California Edison Company
(SCE) suggests that NERC determine whether additional contingencies
should be developed to evaluate potential reliability risks from events
occurring at the same or sequential times in the same region that have
the potential to pose an aggregate impact on electricity assets,
operations, and services, e.g., an extreme heat event that reduces grid
capacity while increasing demand for cooling.\166\ LCRA suggests that
performing contingency analyses similar to what is required under
Reliability Standard CIP-014-3 (Physical Security) may be useful.\167\
LCRA states, for example, that the analysis could study the outage of
medium impact facilities (e.g., single circuit, common tower). If the
result of the analysis identifies instability, cascading, uncontrolled
islanding, or excessive load shed, these facilities could be identified
as ``weather critical'' and targeted for hardening as part of a
corrective action plan.\168\
---------------------------------------------------------------------------
\164\ AEP Comments at 4.
\165\ NYISO Comments at 14.
\166\ SCE Comments at 4.
\167\ Reliability Standard CIP-014-3 requires entities to assess
their transmission facilities to determine whether, if rendered
inoperable or damaged, they could result in widespread instability,
uncontrolled separation, or cascading. Reliability Standard CIP-014-
3 (Physical Security), at 1.
\168\ LCRA Comments at 2.
---------------------------------------------------------------------------
101. Other commenters state that responsible entities should be
able to consider contingencies beyond those in Table 1 of Reliability
Standard TPL-001.5.1 that will affect their study area.\169\ For
example, PJM emphasizes the need for regional variance for unique
contingencies to be studied.\170\ Eversource recommends that the
Commission avoid prescription and allow details such as the types of
required contingencies to be determined during the standard development
process.\171\
---------------------------------------------------------------------------
\169\ AEP Comments at 4; Idaho Power Comments at 3; Tri-State
Comments at 4, PJM Comments at 11.
\170\ AEP Comments at 4; Idaho Power Comments at 3; Tri-State
Comments at 4, PJM comments at 11.
\171\ Eversource Comments at 4.
---------------------------------------------------------------------------
102. EPRI asserts that clarification is needed to differentiate
between events that impact the initial conditions of the benchmark
scenario for which the contingency events will be analyzed, and the
actual contingencies meant to be captured as acute impacts to the
system that occur over a wide area and can be studied through the
steady state and transient stability processes.\172\
---------------------------------------------------------------------------
\172\ EPRI Comments at P 21.
---------------------------------------------------------------------------
ii. Analyses for Common Mode Failures
103. NERC and ACP agree that Reliability Standard TPL-001-5.1
should better address the risk posed by extreme heat and cold weather
events and the associated common mode failure impacting resource
availability and the transmission system.\173\
---------------------------------------------------------------------------
\173\ NERC Comments at 6; ACP Comments at 9 n.23.
---------------------------------------------------------------------------
104. EPRI states that the benchmark planning cases, which serve as
the basis for steady state and transient stability assessments,
historically have not been developed to include the correlated impacts
of common mode events based on the impact of extreme temperature on
load and the availability of derated generation and transmission
capacity. EPRI asserts that capturing extreme temperature conditions
for both heat and cold would require a new approach that directly
accounts for the correlated temperature-related impacts to supply and
demand.\174\ EPRI agrees with the Commission's proposal that dynamic
models of VERs need to be included in the studies but states they would
need to be sufficiently robust to accurately capture system performance
under extreme weather conditions.\175\
---------------------------------------------------------------------------
\174\ EPRI Comments at PP 3-4.
\175\ Id. P 11.
---------------------------------------------------------------------------
[[Page 41276]]
105. Indicated Trade Associations state that in any case modeling
these scenarios will likely require additional resources in time,
expertise, and enhanced software capabilities.\176\ Indicated Trade
Associations ask that the standard drafting team recognize the range
and quantity of complexities layered into the modeling process, e.g.,
whether concurrent generators must be in a single or multiple balancing
authority area, how many generators are needed for a given study, and
if there is a particular combination of generators needed for
modeling.\177\
---------------------------------------------------------------------------
\176\ Indicated Trade Associations at 9.
\177\ Id.
---------------------------------------------------------------------------
iii. Demand Response
106. EDF and UCS suggest that when evaluating relevant distribution
system impacts, responsible entities should focus on the impacts of the
extreme weather event on both electric demand and on the capability of
the distribution system assets, including demand response, distributed
storage and generation, and utility-scale storage, to mitigate
reliability risks.\178\
---------------------------------------------------------------------------
\178\ EDF Comments at 22-23; UCS Comments at 7-8.
---------------------------------------------------------------------------
107. APS comments that demand response should be used as a tool to
resolve issues and only studied when it is relied on as a mitigation
action.\179\
---------------------------------------------------------------------------
\179\ APS Comments at 4.
---------------------------------------------------------------------------
108. Eversource states that the Commission should encourage
regional flexibility in any consideration of demand response.
Eversource further comments that the Commission should not impose a
``one size fits all'' approach for resources that may significantly
differ based on location. It is also concerned that during extreme
weather events, demand response with heating or cooling-based load
reduction may not be achievable due to safety concerns.\180\
---------------------------------------------------------------------------
\180\ Eversource Comments at 6.
---------------------------------------------------------------------------
109. EPRI asserts that steady state simulation cannot sufficiently
capture demand response, and that there is limited capability to
capture the aggregated dynamic response of demand in the load models
used in positive sequence platforms. EPRI adds that ``the impacts of
demand response are better represented through appropriate temporal and
diurnal patterns that would inform the load and demand profile under a
given extreme temperature condition. This information is best
represented in operational assessments such as resource adequacy or
production cost modeling.'' \181\
---------------------------------------------------------------------------
\181\ EPRI Comments at P 12.
---------------------------------------------------------------------------
110. LCRA notes that while the role of demand response in its
portion of the Bulk-Power System is negligible today, this could change
in the future as additional large loads (e.g., cryptocurrency mining
and data centers) are energized. LCRA states that this trend should be
observed for further consideration in the future.\182\
---------------------------------------------------------------------------
\182\ LCRA Comments at 2-3.
---------------------------------------------------------------------------
b. Commission Determination
111. Pursuant to section 215(d)(5) of the FPA, we adopt the NOPR
proposal and direct NERC to require in the proposed new or modified
Reliability Standard that responsible entities perform both steady
state and transient stability (dynamic) analyses in the extreme heat
and cold weather planning studies. In a steady state analysis, the
system components are modeled as either in-service or out-of-service
and the result is a single point-in-time snapshot of the system in a
state of operating equilibrium. A transient stability (dynamic)
analysis examines the system from the start to the end of a disturbance
to determine if the system regains a state of operating
equilibrium.\183\ Performing both analyses ensures that the system has
been thoroughly assessed for instability, uncontrolled separation, and
cascading failures in both the steady state and the transient stability
realms.
---------------------------------------------------------------------------
\183\ Plots are created during the dynamic simulation from pre
to post disturbance and are then examined for voltage, frequency,
and rotor angle stability, which cannot be assessed using only a
steady state analysis.
---------------------------------------------------------------------------
112. We also adopt the NOPR proposal and direct NERC to define a
set of contingencies that responsible entities will be required to
consider when conducting wide-area studies of extreme heat and cold
weather events under the new or modified Reliability Standard. We
believe that it is necessary to establish a set of common contingencies
for all responsible entities to analyze. Required contingencies, such
as those listed in Table 1 of Reliability Standard TPL-001-5.1 (i.e.,
category P1 through P7), establish common planning events that set the
starting point for transmission system planning assessments. Requiring
the study of predefined contingencies will ensure a level of uniformity
across planning regions--a feature that will be necessary in the new or
revised Reliability Standard considering that extreme heat and cold
weather events often exceed the geographic boundaries of most existing
planning footprints.
113. Additionally, establishing a set of required contingencies
will aide in the auditing and enforcement of the new or revised
Reliability Standard. While we do not require in this final rule the
inclusion of any particular contingency, we agree with commenters that
the contingencies required in the new or revised Reliability Standard
should reflect the complexities of transmission system planning studies
for extreme heat and cold weather events. As such, NERC may determine
whether contingencies P1 through P7 should also apply to the new or
modified Reliability Standard, or whether a new set of contingencies
should be developed.
114. Regarding the request for clarification from EPRI as to what
outages should be included in the benchmark planning case versus
modeled as contingencies, we believe the standard drafting team is best
positioned to consider that specific question. By definition, the
benchmark planning case will already include certain weather-related
contingencies that therefore will not be studied as additional
contingencies when conducting extreme weather studies.\184\ For
example, baseline drought conditions will be present in the benchmark
planning case as part of the system models representing projected
system conditions,\185\ whereas the impacts of more severe droughts
could be studied during sensitivity analysis as a variation to the
benchmark planning case's generation assumptions.\186\ As discussed in
section IV.F above, we direct NERC to develop specific criteria for
determining which outages should be considered in the benchmark
planning case.
---------------------------------------------------------------------------
\184\ See supra P 39.
\185\ See supra note 155.
\186\ See infra P 124.
---------------------------------------------------------------------------
115. Regarding the study of common mode failures, we reiterate our
above directives concerning the study of concurrent/correlated
generator and transmission outages. We believe that, as suggested by
Indicated Trade Associations, the standard development process will
provide an adequate platform to address the concerns raised by
commenters regarding common mode failures.
116. We also direct NERC to require in the new or modified
Reliability Standard that responsible entities model demand load
response in their extreme weather event planning area. As indicated by
several commenters, because demand load response is generally a
mitigating action that involves reducing distribution load during
periods of stress to stabilize the Bulk-Power System, its effect during
an extreme weather event should be modeled.
117. Regarding EPRI's comment that steady state simulation cannot
[[Page 41277]]
sufficiently capture demand load response, we believe EPRI's comments
are accurate for modeling in the operational timeframe for temporal and
diurnal studies. However, we recognize that it is possible that the
loads used to represent extreme heat and cold events will include the
effects of demand load response because entities' load data obtained
from historical data during these past extreme events will reflect the
effects of demand load response. If that is the case, demand load
response will be automatically factored into the benchmark planning
case. Thus, in addressing this directive, we expect NERC to determine
whether responsible entities will need to take additional steps to
ensure that the impacts of demand load response are accurately modeled
in extreme weather studies, such as by analyzing demand load response
as a sensitivity, as is currently the case under Reliability Standard
TPL-001-5.1.\187\
---------------------------------------------------------------------------
\187\ Reliability Standard TPL-001-5.1, at Requirement 2.1.3.
---------------------------------------------------------------------------
2. Sensitivity Analysis
118. In the NOPR, the Commission proposed directing NERC to
establish a requirement for responsible entities to consider system
models and sensitivity cases when assessing extreme heat and extreme
cold weather.\188\ The NOPR explained that, while Reliability Standard
TPL-001-5.1 requires the use of sensitivity power flow cases, the
Standard does not require responsible entities to model the
simultaneous variation of load, generation, and transfers necessary to
account for the impacts of extreme heat and cold weather events. This,
in turn, could result in failure to detect in the planning horizon
potential reliability issues such as widespread outages and cascading
failures.\189\
---------------------------------------------------------------------------
\188\ NOPR, 179 FERC ] 61,195 at P 73. Sensitivity analyses
consider the impact on a base case by altering discrete variables.
\189\ Id.
---------------------------------------------------------------------------
119. The NOPR further stated that to accurately model the impacts
of extreme heat and cold weather events it would be necessary to define
and model in sensitivity analyses demand probability scenario cases,
generators that are affected by these events (i.e., wind tripping off,
solar dropping off, gas plants not being operational due to gas
restrictions/freeze-offs, etc.) and transfer levels.\190\
---------------------------------------------------------------------------
\190\ Id.
---------------------------------------------------------------------------
120. The NOPR requested comment on: (1) whether to require
transmission planners and planning coordinators to assess reliability
in the planning horizon for sensitivity cases in which multiple inputs
(e.g., load and generator failures) change simultaneously during
extreme heat and cold events; and (2) the range of factors and the
number of sensitivity cases that should be considered to ensure
reliable planning.\191\
---------------------------------------------------------------------------
\191\ Id. P 74.
---------------------------------------------------------------------------
a. Comments
121. Some commenters support requiring the consideration of certain
sensitivities. For example, AEP recommends that a baseline set of
sensitivities should be defined by the NERC standard drafting team and
there should be flexibility for planning coordinators to introduce
further sensitivities if deemed necessary.\192\ EPRI suggests that
multiple hours may need to be studied over the course of the extreme
temperature window to capture sensitivities related to generation and
demand that can lead to differing steady state and dynamic stability
impacts. EPRI also recommends that in addition to the sensitivities
driven by the operational performance of the system, the standard
should include other external drivers that may compound system
conditions during the extreme temperature events, such as a concurrent
lull in wind speeds that would limit wind generation outputs.\193\
---------------------------------------------------------------------------
\192\ AEP Comments at 12.
\193\ EPRI Comments at P 22.
---------------------------------------------------------------------------
122. Other commenters suggest reasons why it may not be necessary
for the Commission to direct the study of additional sensitivities.
NYISO and LCRA explain that extreme heat and cold weather impacts and
unavailability of natural gas fuel are already studied as sensitivities
under Reliability Standard TPL-001-5.1.\194\ Similarly, Indicated Trade
Associations assert that the extreme weather base case should already
represent system conditions at or near possible seasonal extreme
weather limits and that, as such, many additional sensitivities may not
be necessary.\195\ LCRA adds that the effect of changing inputs (e.g.,
load and generation, including generation retirements and forced
generation outages) should be captured in the contingency definitions,
performance requirements, and analysis for the given region and extreme
weather case.\196\
---------------------------------------------------------------------------
\194\ NYISO Comments at 13; LCRA Comments at 3.
\195\ Indicated Trade Associations Comments at 10.
\196\ LCRA Comments at 3.
---------------------------------------------------------------------------
123. Idaho Power, APS, and Indicated Trade Associations indicate
that given the diversity among utilities with respect to load profiles,
geographic footprint, resource mix, particular utility, its resource
mix, and geographic footprint, and available resources and needs, the
Commission should allow entities to select the sensitivities they will
study.\197\
---------------------------------------------------------------------------
\197\ Indicated Trade Associations Comments at 11; Idaho Power
Comments at 4-5; APS Comments at 7.
---------------------------------------------------------------------------
b. Commission Determination
124. Pursuant to section 215(d)(5) of the FPA, we adopt the NOPR
proposal and direct NERC to require the use of sensitivity cases to
demonstrate the impact of changes to the assumptions used in the
benchmark planning case. Sensitivity analyses help a transmission
planner to determine if the results of the base case are sensitive to
changes in the inputs. The use of sensitivity analyses is particularly
necessary when studying extreme heat and cold events because some of
the assumptions made when developing a base case may change if
temperatures change--for example, during extreme cold events, load may
increase as temperatures decrease, while a decrease in temperature may
result in a decrease in generation. We agree with AEP, and we direct
NERC to define during the Reliability Standard development process a
baseline set of sensitivities for the new or modified Reliability
Standard. While we do not require the inclusion of any specific
sensitivity in this final rule, NERC should consider including
conditions that vary with temperature such as load, generation, and
system transfers.\198\
---------------------------------------------------------------------------
\198\ NOPR, 179 FERC ] 61,195 at P 73.
---------------------------------------------------------------------------
125. We do not agree with Idaho Power, APS, and Indicated Trade
Associations that responsible entities alone should determine the
sensitivity cases that must be considered in the responsible entity's
study. Failure to consider variations in conditions necessary to
reflect extreme heat or cold weather events could result in major
reliability risks being overlooked and undetected in the planning
horizon.\199\ We do, however, believe that responsible entities should
be free to study additional sensitivities relevant to their planning
areas. Because wide-area studies conducted under the new or modified
Reliability Standard will be likely based on footprints significantly
larger than those typically concerned under Reliability Standard TPL-
001.5.1, cooperation will be necessary between responsible entities
conducting extreme heat and cold weather studies and other registered
entities within their extreme weather study footprints to ensure the
selection of appropriate sensitivities. EPRI's comment further
highlights the need for coordination between
[[Page 41278]]
registered entities to capture sensitivities related to variable energy
resources and demand.
---------------------------------------------------------------------------
\199\ See id.
---------------------------------------------------------------------------
126. We disagree with NYISO and LCRA that extreme heat and cold
weather impacts are already studied as sensitivities under Reliability
Standard TPL-001-5.1. Although TPL-001-5.1 mandates sensitivity
analysis by varying one or more conditions specified in the standard
such as load, generation, and transfers, this analysis alone cannot
capture the complexities of extreme heat and cold weather conditions.
Sensitivity analyses consider the impact on a base case of the
variability of discrete variables. Extreme heat and cold weather
impacts, on the other hand, may include numerous concurrent outages and
derates which cannot be studied as part of a single-variable
sensitivity analysis. Under the new or modified Reliability Standard,
however, these outages will be captured in the benchmark planning case
upon which sensitivity analyses will be performed.
3. Modifications to the Traditional Planning Approach
127. In the NOPR, the Commission proposed to direct NERC to
consider alternative planning methods and techniques that diverge from
past Reliability Standard requirements to better capture the challenges
posed by extreme heat and cold events.\200\
---------------------------------------------------------------------------
\200\ Id. P 75.
---------------------------------------------------------------------------
128. The NOPR stated that Reliability Standard TPL-001-5.1 is based
on a deterministic approach, which uses planned contingencies and
specific performance criteria to study system response to various
conditions. This approach yields accurate planning when the power
supply is highly dispatchable, weather is predictable, and near-record
peak demand is reached only a few days a year.\201\ However, as noted
in the NOPR, the current planning approach applied in Reliability
Standard TPL-001-5.1 likely is not sufficient to accurately
characterize the reliability risk from extreme heat and cold weather
given the high degree of uncertainty inherent in predicting severe
weather and its impact on generation resources, transmission, and
load.\202\
---------------------------------------------------------------------------
\201\ Id.
\202\ Id.
---------------------------------------------------------------------------
129. The NOPR explained the value of establishing a new or modified
planning approach to better capture the impacts of, and ensure reliable
planning and operation in response to, extreme heat and cold
events.\203\ Specifically, the NOPR mentioned as an option expanding
current deterministic studies to include probabilistically developed
scenarios as an option to better account for uncertainties during
extreme heat and cold weather conditions, since probabilistic tools can
capture ``random uncertainties in power system planning, including
those in load forecasting, generator performance, and failures of
system equipment.'' \204\
---------------------------------------------------------------------------
\203\ Id. P 78.
\204\ Id. P 79.
---------------------------------------------------------------------------
130. Finally, the NOPR sought comments on combining or layering
probabilistic and deterministic approaches when planning for extreme
heat and cold weather conditions in the context of Reliability Standard
TPL-001-5.1. Specifically, the NOPR sought comments on the use of a
hybrid deterministic/probabilistic planning approach and the following:
(1) the assumptions from the deterministic and probabilistic approaches
that should be applied to study extreme heat and cold weather events;
(2) the potential planning challenges from combining the two planning
approaches; (3) the costs associated with adjustments to the currently
applied deterministic approach; (4) the implementation period necessary
for proposed changes; and (5) the reliability benefits that could
result.\205\
---------------------------------------------------------------------------
\205\ Id.
---------------------------------------------------------------------------
a. Comments
131. Many commenters support the use of probabilistic methods in
transmission planning to account for uncertainty in availability of
transmission and generation in extreme weather conditions.\206\ For
example, PJM states that the use of probabilistic modeling ``would help
establish the baseline and sensitivity system conditions upon which
deterministic approaches for go/no-go corrective action transmission
build decisions would be made.'' \207\ EPRI discusses potential
deficiencies in traditional deterministic approaches in planning
studies in cases where uncertainty and variability will increase on
both the generation and demand side across a variety of temperature
extremes. EPRI raises concerns that scenarios or system conditions that
result in consequential stability implications may not be adequately
captured in the planning models using the traditional deterministic
approach.\208\ ACP states that there is precedent for using
probabilistic tools in assessing electric reliability, as these methods
are widely used by utilities and RTOs to assess resource adequacy and
loss of load risk.\209\
---------------------------------------------------------------------------
\206\ See, e.g., NESCOE Comments at 9; EPRI Comments at P 24;
PJM Comments at 11; EDF Comments at 20; PIOs Comments at 7; ACEG
Comments at 7; NARUC Comments at 5-6; ACP Comments at 15; Entergy
Comments at 6.
\207\ PJM Comments at 11.
\208\ EPRI Comments at P 24.
\209\ ACP Comments at 16.
---------------------------------------------------------------------------
132. Other commenters do not support a requirement to use
probabilistic methods. For example, while AEP recognizes the value of
probabilistic methods, it warns that the industry is not yet ready
because the necessary methods, frameworks, and tools are not yet
available to transmission planners.\210\ Several other commenters warn
that it would be premature to require the use of probabilistic
methods.\211\ Trade Associations express concern that probabilistic
planning based on extremely low probability events is highly
speculative and dependent on the judgment of planners, which increases
the complexity and risk associated with the development of transmission
projects, hampering the construction of needed transmission.\212\ Idaho
Power also does not think converting to a probabilistic approach is
necessary as sensitivities with appropriate inputs will capture the
impacts of extreme weather using deterministic techniques.\213\ LCRA
comments that probabilistic analysis requires large samples (i.e.,
number of events), but given the infrequent occurrence of extreme
weather events, it would be challenging to layer probabilistic
assumptions into transmission planning analyses.\214\
---------------------------------------------------------------------------
\210\ AEP Comments at 22.
\211\ APS Comments at 7 (requesting that the Commission hold
``robust industry-wide discussions to discuss probabilistic
approaches''); Tri-State Comments at 8.
\212\ Trade Associations Comments at 11.
\213\ Idaho Power Comments at 5.
\214\ LCRA Comments at 3-4.
---------------------------------------------------------------------------
133. Supporters of the use of probabilistic methods acknowledge
that implementation poses challenges. For example, EPRI comments that
implementation of probabilistic methods would require new processes to
link and communicate data across models, such as linking generation and
transmission expansion assessments, resource adequacy, production cost
models, and transmission planning assessments.\215\ Further, new
statistical methods and processes will be needed to inform the
selection of powerflow cases for planning assessments.\216\ PJM states
that the benefits of applying probabilistic methods would require
knowing in advance pre-established bounded parameter ranges, so
[[Page 41279]]
reasonable selection of probabilistic method assumptions lead to
benchmark planning cases that reflect statistically credible
scenarios.\217\ PJM further states that this should be the result of
coordinated analysis among RTOs, NOAA, DOE Labs, and NERC.\218\ Entergy
asserts that the probabilistic approach is significantly more
complicated than deterministic planning and cautions that any
requirement for probabilistic planning must have requirements that
reasonably can be performed, are assessable, and are auditable for
compliance.\219\ Because of the potential challenges associated with
implementing probabilistic planning requirements, Tri-State recommends
the further study of and development of best practices for
probabilistic planning.\220\
---------------------------------------------------------------------------
\215\ EPRI Comments at P 25.
\216\ Id.
\217\ PJM Comments at 11.
\218\ Id.
\219\ Entergy Comments at 9.
\220\ Tri-State Comments at 8.
---------------------------------------------------------------------------
b. Commission Determination
134. Pursuant to section 215(d)(5) of the FPA, the Commission
adopts and modifies the NOPR proposal and directs NERC to require in
the new or modified Reliability Standard the use of planning methods
that ensure adequate consideration of the broad characteristics of
extreme heat and cold weather conditions. We further direct NERC to
determine during the standard development process whether probabilistic
elements can be incorporated into the new or modified Reliability
Standard and implemented presently by responsible entities. If NERC
identifies probabilistic elements which responsible entities can
feasibly implement and that would improve upon existing planning
practices, we expect the inclusion of those methods in the proposed
Reliability Standard.
135. Including probabilistic scenarios in the planning process
could result in a planning approach that better captures the
uncertainties of extreme weather events, thus better preparing
responsible entities to ensure Reliable Operation under stressed
conditions.\221\ Further, we agree with commenters that the use of
probabilistic methods by responsible entities would help ensure
Reliable Operation of the Bulk-Power System as probabilistic methods
better characterize multi-day wide-area events such as extreme heat and
cold events.\222\
---------------------------------------------------------------------------
\221\ NOPR, 179 FERC ] 61,195 at P 76.
\222\ EPRI Comments at 4.
---------------------------------------------------------------------------
136. However, we recognize, as certain commenters point out, that a
prescriptive requirement to add probabilistic planning methods to
better understand reliability implications could be met by significant
challenges. Some of the challenges identified by commenters include
lack of commercially available tools required for probabilistic
modeling and lack of planning staff trained in the use of these tools
and in carrying out probabilistic studies. Further, there may be a need
to develop and maintain probabilistic databases that include, for
example, outage data from extreme weather-dependent grid components and
generation resources.
137. Because of these implementation concerns, we believe that the
best course of action is to allow NERC to use its expertise and the
standard development process to address the concerns identified by
commenters and develop proposed modifications to existing planning
methods that address the Commission's directive to use transmission
planning methods that adequately characterize the effects of extreme
heat and cold weather conditions on the transmission system, including
incorporating probabilistic elements where possible. The standard
development process will also provide an adequate forum in which to
evaluate the many recommendations that commenters have presented in
response to the NOPR.
138. We also direct NERC to identify during the standard
development process any probabilistic planning methods that would
improve upon existing planning practices, but that NERC deems
infeasible to include in the proposed Reliability Standard at this
time. If any such methods are identified, NERC shall describe in its
petition for approval of the proposed Reliability Standard the barriers
preventing the implementation of those probabilistic elements. We
intend to use this information to determine whether and what next steps
may be warranted to facilitate the use of probabilistic methods in
transmission system planning practices.
H. Implement a Corrective Action Plan if Performance Standards Are Not
Met
139. The NOPR noted that under the currently effective Reliability
Standard TPL-001-5.1, planning coordinators and transmission planners
are required to evaluate possible actions to reduce the likelihood or
mitigate the consequences of extreme weather events, but are not
obligated to develop corrective action plans, even if such events are
found to cause cascading outages.\223\ Because of the potential
severity of extreme heat and cold weather events and their likelihood
to cause system instability, uncontrolled separation, or cascading
failures as a result of a sudden disturbance or unanticipated failure
of system elements, the NOPR proposed to direct NERC to require
corrective action plans that include mitigation for any instances where
performance requirements for extreme heat and cold events are not
met.\224\
---------------------------------------------------------------------------
\223\ NOPR, 179 FERC ] 61,195 at P 83. Reliability Standard TPL-
001-5.1, Requirements R3.3.5 and R4.4.5 require computer simulation
analyses of extreme events listed in Table 1 of the standard (some
listed are examples and are not definitive), and if the analysis
concludes there is cascading caused by the occurrence of extreme
events, an evaluation of possible actions designed to reduce the
likelihood or mitigate the consequences and adverse impacts of the
event(s) shall be conducted.
\224\ Id.
---------------------------------------------------------------------------
140. Consistent with the existing requirements of Reliability
Standard TPL-001-5.1, the NOPR proposed to provide responsible entities
with the flexibility to determine the actions to include in their
corrective action plans to remedy identified deficiencies in
performance. The NOPR included several examples of actions that could
be included in a corrective action plan: planning for additional
contingency reserves or implementing new energy efficiency programs to
decrease load, increasing intra- and inter-regional transfer
capabilities, transmission switching, or adjusting transmission and
generation maintenance outages based on longer-lead forecasts. The NOPR
observed that well-planned mitigation and corrective actions that
account for some of these contingencies will minimize loss of load and
improve resilience during extreme heat and cold weather events.\225\
---------------------------------------------------------------------------
\225\ Id. P 84.
---------------------------------------------------------------------------
141. The NOPR explained that increases in interregional transfer
capability could be considered as one option to address potential
reliability issues during extreme weather events.\226\ The NOPR noted
that such transfer capability would allow an entity in one region with
available energy to assist one or more entities in another region that
is experiencing an energy shortfall due to the extreme weather
event.\227\ Increasing interregional transfer capability may be a
particularly robust option for planning entities attempting to mitigate
the risks associated with concurrent generator outages over a wide
area.\228\
---------------------------------------------------------------------------
\226\ Id. P 85.
\227\ Id.
\228\ Id. In this proceeding, we refer to interregional transfer
capability strictly in the context of improving the reliability of
the Bulk-Power System through improved transmission system planning
and associated modifications to NERC's Reliability Standards.
---------------------------------------------------------------------------
[[Page 41280]]
142. To ensure the timely development and implementation of
corrective action plans, the NOPR sought comments on the timeframe for
developing such corrective action plans and sharing of the corrective
actions with other interconnected planning entities.\229\ In addition,
to identify opportunities for improved wide-area planning studies and
coordination, the NOPR requested comment on how to develop corrective
action plans that mitigate issues that require corrective action by,
and coordination among, multiple transmission owners.\230\
---------------------------------------------------------------------------
\229\ Id.
\230\ Id. P 67.
---------------------------------------------------------------------------
1. Comments
a. Jurisdictional Issues
143. Several commenters raise jurisdictional concerns regarding
corrective action plans.\231\ While Indicated Trade Associations
support the NOPR proposal to require corrective action plans addressing
vulnerabilities identified in the study process, they also urge that
the Commission ``remain mindful'' of the statutory limitation set forth
in FPA section 215(i) that NERC and the Commission do not have
authority ``to order the construction of additional generation or
transmission capacity or to set or enforce compliance with standards
for adequacy or safety of electric facilities or services.'' \232\ In
particular, Indicated Trade Associations express concern that certain
examples of potential corrective action plans mentioned in the NOPR,
including ``planning for additional contingency reserves . . . or
increasing intra- and inter-regional transfer capabilities,'' exceed
the Commission's authority under section 215 of the FPA.\233\
Similarly, Electric Reliability Council of Texas, Inc. (ERCOT) opines
that ``[r]equiring transmission planners to address what is
fundamentally a resource adequacy concern through the transmission
planning process would usurp the authority of the states, which are
responsible for ensuring the adequacy of the generation supply.'' \234\
---------------------------------------------------------------------------
\231\ Indicated Trade Associations Comments at 11-12; ERCOT
Comments at 5.
\232\ Indicated Trade Association Comments at 12 (citing 16
U.S.C. 824o(i)).
\233\ Id. at 11-12; ERCOT Comments at 5.
\234\ ERCOT Comments at 5.
---------------------------------------------------------------------------
b. Corrective Action Plans
144. Most commenters agree that corrective action plans should be
required to address system performance issues identified in studies
under extreme heat and cold weather conditions.\235\ NERC agrees that
any revised Reliability Standard directed under a final rule issued in
this proceeding should require that entities develop corrective action
plans for instances where performance requirements for selected extreme
weather and environmental conditions are not met for at least some of
the planning scenarios.
---------------------------------------------------------------------------
\235\ See, e.g., NERC Comments at 10; NARUC Comments at 6;
NESCOE Comments at 3; MISO Comments at 4.; PJM Comments at 12.
---------------------------------------------------------------------------
145. BPA asserts that several of the corrective action plan
examples listed in the NOPR, such as transmission switching/
reconfiguration, or adjusting transmission and generation maintenance
outages, would likely be covered by Reliability Standard EOP-011-2,
requiring transmission operators and balancing authorities to have
operating plans to mitigate operating emergencies including determining
the reliability impacts of extreme weather conditions. Therefore, BPA
cautioned, any modifications to Reliability Standard TPL-001-5.1 should
be careful not to encroach upon the authority and discretion of
transmission operators and balancing authorities.\236\
---------------------------------------------------------------------------
\236\ BPA Comments at 4.
---------------------------------------------------------------------------
146. Some commenters do not support the NOPR proposal to require
the development and implementation of corrective action plans for all
instances where performance requirements for extreme heat and cold
events are not met. APS asserts that ``corrective action plans should
be focused on the most likely and impactful events, which may not
include extreme weather scenarios,'' and that as such, it disagrees
that corrective action plans ``should be required for results that come
out of sensitivity analysis, which includes extreme weather
scenarios.''
147. With regard to costs, National Association of Regulatory
Utility Commissioners (NARUC) asserts that mitigation and corrective
actions to minimize loss of load and improve resilience should be
subjected to a cost/benefit analysis.\237\ Entergy suggests that the
Commission ``provide additional guidance regarding the level of
performance it expects during extreme heat and cold events,'' including
consideration of ``the cost effects on customers relative to the
potential risks and the time-frame in which those risks are likely to
arise.'' \238\
---------------------------------------------------------------------------
\237\ NARUC Comments at 6.
\238\ Entergy Comments at 2.
---------------------------------------------------------------------------
c. Generation and Transmission Capacity Increase and Resource Adequacy
Issues
148. Most commenters agree that the responsible entities developing
corrective action plans should evaluate a range of solutions, including
transmission upgrades to increase interregional transfer capability
and/or building generation to address generation deficiency under
extreme weather events.\239\ Some commenters, however, question the
efficacy of corrective action plans and suggest that alternative
approaches are preferable.
---------------------------------------------------------------------------
\239\ See, e.g., NARUC Comments at 6; UCS Comments at 9; PIOs
Comments at 15; AEP Comments at 5; ACEG Comments at 8; ACP Comments
at 11; Entergy Comments at 8.
---------------------------------------------------------------------------
149. With regards to transmission capacity, and specifically
interregional transfer capabilities, many commenters agree that
adequate interregional transfer capability would help address
reliability challenges posed by extreme heat and cold weather
conditions.\240\ Some commenters urge the Commission to set a minimum
interregional transfer capability requirement.\241\ However, most
commenters addressing this topic opine that interregional transfer
requirements, including setting necessary or minimum transfer levels
and direction, should be addressed outside of the Reliability Standard
TPL-001-5.1 planning process.\242\ For example, MISO Transmission
Owners suggest that interregional transfers could be better dealt with
under Order No. 1000 Regional Transmission Planning processes.\243\
MISO recommends that corrective action plans require meaningful
mitigation, such as investment in transmission solutions, to address
issues identified in an extreme weather event study.\244\ Conversely,
Idaho Power states that if regional transmission facilities are to be
considered as corrective actions, Idaho Power would have concerns with
the efficacy of those corrective actions given the amount of time
necessary to build new transmission.\245\
---------------------------------------------------------------------------
\240\ AEP Comments at 2; ACP Comments at 19; ACEG Comments at 9;
PJM Comments at 12; see MISO Transmission Owners Comments at 5-6.
\241\ EDF Comments at 27; AEP Comments at 2; ACP Comments at 19;
ACEG Comments at 9; PJM Comments at 12.
\242\ MISO Transmission Owners Comments at 5-6; ACP Comments at
19; ACEG Comments at 9; AEP Comments at 2.
\243\ MISO Transmission Owners Comments at 5.
\244\ MISO Comments at 4.
\245\ Idaho Power Comments at 4, 6.
---------------------------------------------------------------------------
150. Most commenters who disagree with the NOPR proposal to allow
entities to consider additional generation capacity as a corrective
action plan measure disagree on the
[[Page 41281]]
basis that resource adequacy is not a matter that should be dealt with
within the transmission planning process.\246\ For example, ISO-NE
asserts that the purpose of Reliability Standard TPL-001-5.1 is not to
ensure resource adequacy, but to ensure that load can be served.\247\
ACP and PIOs question the efficacy of building new generation as part
of a corrective action plan because such new generation may be subject
to the same issues as existing generation--for example, if an extreme
cold event leads to the outage of weather-sensitive generators, adding
more weather-sensitive generators will not resolve the resource
deficiency.\248\
---------------------------------------------------------------------------
\246\ See, e.g., PJM Comments at 12; ERCOT Comments at 5; ISO-NE
Comments at 4.
\247\ ISO-NE Comments at 4.
\248\ ACP Comments at 6; PIOs Comments at 16.
---------------------------------------------------------------------------
d. Notification to Applicable Regulatory Authorities or Governing
Bodies Responsible for Retail Electric Service Issues
151. ACP, New England States Committee on Electricity (NESCOE), and
Entergy comment that entities must coordinate with state and local
authorities in the development of corrective action plans involving
generation and transmission capacity.\249\ For example, NESCOE suggests
that corrective action plans be informed by state officials'
perspectives, consider a variety of mitigation options, and include a
detailed explanation of how the entity weighed the various
options.\250\ Additionally, NESCOE points out that given the likelihood
that corrective action plans will include load shed, state officials
should be involved in the corrective action plan process.\251\ NESCOE
proposes that responsible entities seek input from state regulators
during their planning process. Alternatively, NESCOE recommends the
adoption of the Joint Federal-State Task Force on Electric Transmission
model to create a similar task force focusing on extreme weather and
grid reliability.\252\
---------------------------------------------------------------------------
\249\ See ACP Comments at 18; NESCOE Comments at 3; see also
Entergy Comments at 9 (stating in the context of the development of
corrective action plans that ``[t]he Commission also should ensure
that the relevant retail regulators have input into the level of
risks versus costs a transmission owner should accept.'').
\250\ NESCOE Comments at 3.
\251\ Id. at 5.
\252\ Id. at 6.
---------------------------------------------------------------------------
2. Commission Determination
152. Pursuant to section 215(d)(5) of the FPA, the Commission
adopts and modifies the NOPR proposal and directs NERC to require in
the new or modified Reliability Standard the development of extreme
weather corrective action plans for specified instances when
performance standards are not met. In addition, as explained below, we
direct NERC to develop certain processes to facilitate interaction and
coordination with applicable regulatory authorities or governing bodies
responsible for retail electric service as appropriate in implementing
a corrective action plan.
153. We adopt our rationale set forth in the NOPR and conclude that
the directive to require the development of corrective action plans is
needed for Reliable Operation of the Bulk-Power System. Under the
currently effective Reliability Standard TPL-001-5.1, planning
coordinators and transmission planners are required to evaluate
possible actions to reduce the likelihood or mitigate the consequences
of extreme weather events, but are not obligated to develop corrective
action plans, even if such events are found to cause cascading outages.
Experience over the past decade has demonstrated that the potential
severity of extreme heat and cold weather events exacerbates the
likelihood to cause system instability, uncontrolled separation, or
cascading failures as a result of a sudden disturbance or unanticipated
failure of system elements. Thus, we conclude that entities should
proactively address known system vulnerabilities by developing
corrective action plans that include mitigation for specified instances
where performance requirements for extreme heat and cold events are not
met.
a. Jurisdictional Issues
154. We reject the arguments that our directive to require
responsible entities to develop corrective action plans may exceed the
Commission's jurisdiction. Section 215(i)(2) of the FPA states that the
Commission and ERO are not authorized to order the construction of
additional generation or transmission capacity as part of a Reliability
Standard.\253\ Consistent with this limitation, the final rule does not
require any responsible entity to engage in the construction of
additional generation or transmission capacity. Moreover, while the
final rule directs NERC to include in a new or modified Reliability
Standard a requirement for entities to develop a corrective action plan
to address extreme heat and cold weather events during the transmission
planning process, the final rule does not mandate the use of any
specific mitigation measure.\254\
---------------------------------------------------------------------------
\253\ 16 U.S.C. 824o(i)(2).
\254\ NOPR, 179 FERC ] 61,195 at P 84 (``we believe it is
appropriate to provide responsible entities with the flexibility to
determine the best actions to include in their corrective action
plan to remedy any identified deficiencies in performance'').
---------------------------------------------------------------------------
155. As noted by commenters, the NOPR provided examples of various
activities that may be appropriate under a corrective action plan, some
of which may require state or local authorizations (e.g., generation or
transmission development).\255\ Other examples mentioned in the NOPR
include ``implementing new energy efficiency programs to decrease load,
. . . transmission switching, or adjusting transmission and generation
maintenance outages based on longer-lead forecasts,'' \256\ none of
which involve the construction of generation or transmission capacity.
In addition, responsible entities have the option to use controlled
load shed as a mitigation measure. In sum, while responsible entities
would have the obligation to develop and implement a corrective action
plan, the Commission is not directing any specific result or content of
the corrective action plan. In such circumstances, the Commission's
directive does not exceed the jurisdictional limits set forth in
section 215(i) of the FPA.\257\
---------------------------------------------------------------------------
\255\ Id.
\256\ Id.
\257\ S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 80 (D.C. Cir.
2014).
---------------------------------------------------------------------------
156. In response to ERCOT and other commenters, the Commission's
action does not usurp state authority with regard to resource adequacy.
As explained above, the directive that responsible entities develop
corrective action plans in certain circumstances does not require the
construction of additional generation or transmission capacity.
Further, as discussed below, responsible entities that elect mitigation
activities that involve increased transmission or generation capacity
will of course be subject to the authority of such state agencies or
others with legal jurisdiction over the construction of transmission or
generation facilities.
b. Circumstances That Require Corrective Action Plans
157. As stated above, we adopt and modify the NOPR proposal and
direct NERC to require in the new or modified Reliability Standard the
development of corrective action plans that include mitigation for
specified instances where performance requirements for extreme heat and
cold events are not met--i.e., when certain studies conducted under the
Standard show that an extreme heat or cold event would result in
cascading outages, uncontrolled separation, or instability.\258\ We
agree with APS that
[[Page 41282]]
neither version 4 nor 5.1 of Reliability Standard TPL-001-5.1 require
corrective action plans for extreme heat and cold weather events.
Extreme heat and cold weather events, which pose a serious risk to the
Reliable Operation of the Bulk-Power System, are increasing in
frequency and intensity. We believe that in taking steps to avoid
occurrences of cascading outages, uncontrolled separation, or
instability under extreme heat and cold, corrective action plans would
also minimize the extent and duration of loss of load and improve Bulk-
Power System resilience during extreme heat and cold weather
events.\259\
---------------------------------------------------------------------------
\258\ NOPR, 179 FERC ] 61,195 at P 83.
\259\ Id. P 84.
---------------------------------------------------------------------------
158. Although the NOPR proposed requiring the development of
corrective action plans for any instance where performance requirements
for extreme heat and cold events are not met, we give NERC in this
final rule the flexibility to specify the circumstances that require
the development of a corrective action plan. For example, NERC should
determine whether corrective action plans should be required for single
or multiple sensitivity cases, and whether corrective action plans
should be developed if a contingency event that is not already included
in benchmark planning case would result in cascading outages,
uncontrolled separation, or instability.\260\ Because we also direct
NERC to establish required study contingencies and baseline
sensitivities,\261\ we believe it is necessary for NERC to develop
those aspects of the Standard prior to determining the instances under
which corrective action plans must be developed.
---------------------------------------------------------------------------
\260\ Under Reliability Standard TPL-001-5.1, corrective action
plans are not required for single sensitivity cases.
\261\ See supra PP 111, 124.
---------------------------------------------------------------------------
159. With regard to BPA's suggestion that Reliability Standard EOP-
011-2 already addresses certain mitigation measures listed in the NOPR
as examples, we clarify that nothing in the final rule affects the
responsibilities or obligations of registered entities under that
Reliability Standard and note that there are important differences in
the scope and intent of EOP-011-2 and the Reliability Standard we are
directing be developed here. Specifically, while Reliability Standard
EOP-011-2 includes provisions to determine reliability impacts of
extreme cold conditions and extreme weather conditions,\262\ it does
not require the transmission operator to mitigate the condition. In
addition, Reliability Standard EOP-011-2 addresses the issues within
the operating time frame. Corrective action plans, as proposed in the
NOPR, would be developed in the planning horizon to address the issues
in the long-term planning time frame. Simultaneously, such issues would
be addressed by Reliability Standard EOP-011-2 in the operating time
frame should the studied extreme weather condition occur. As such,
there would not be any encroachment or conflict between the two
standards.
---------------------------------------------------------------------------
\262\ Reliability Standard EOP-011-2, Requirement 1.2.6.
---------------------------------------------------------------------------
160. With respect to arguments from NARUC and Entergy that the
Commission should require cost-benefit analysis for corrective action
plans or otherwise provide additional guidance as to the cost impacts
on customers, we decline to do so. FPA section 215 does not require the
use of cost-benefit analysis and, given the flexibility allowed to
responsible entities in crafting a corrective action plan, we are not
persuaded such a requirement would be warranted in this instance.
Regarding the cost impact on customers more generally, we believe that
NERC should have an opportunity in the first instance to balance such
impacts and present a new or modified Reliability Standard for
Commission approval. As articulated in Order No. 672, the cost of
compliance is but one factor in determining whether to approve a
proposed Reliability Standard and we will consider the potential cost
impacts in the context of the larger record.\263\
---------------------------------------------------------------------------
\263\ See Order No. 672, 114 FERC ] 61,104 at P 330.
---------------------------------------------------------------------------
c. Generation and Transmission Capacity Increase and Resource Adequacy
Issues
161. As discussed above, corrective action plans are not required
to use any specific mitigation measure and responsible entities are not
required to build transmission or generation. Nevertheless, some
entities may choose to include additional transmission or generation
capacity as a mitigation measure in their corrective action plan,
subject to the approval of relevant regulatory authorities.
162. With respect to the use of transmission as a mitigation
measure, as stated in the NOPR and echoed by commenters, interregional
transfer capability can be a solution to some extreme weather-related
reliability concerns. We recognize that a proposal by a planning entity
to increase its interregional transfer capability to address the impact
of extreme heat and cold conditions on its portion of the Bulk-Power
System may be acceptable in a corrective action plan, and we expect
that the benchmark planning cases developed, and wide-area studies
conducted under this Standard could be beneficial for purposes of
determining interregional transfer needs. However, we decline to set a
minimum interregional transfer capability requirement in this
proceeding and note the Commission's ongoing pending proceeding
addressing such a requirement in Docket No. AD23-3.
163. Regarding Idaho Power's concern given the amount of time
necessary to build new transmission,\264\ we note that corrective
action plans address deficiencies identified in a long-term
transmission planning timeframe (i.e., six to ten years and beyond).
The period associated with a transmission project will inform whether
and when that project may be included in an extreme weather corrective
action plan. For example, a transmission project that is not expected
to be operational in the six-to-ten-year long-term horizon may not be
relied upon in an extreme weather corrective action plan to mitigate
identified system deficiencies within that time horizon. In that
circumstance, the responsible entity will have to develop an extreme
weather corrective action plan that includes other measures that can be
implemented to ensure Reliable Operation of its portion of the Bulk-
Power System.
---------------------------------------------------------------------------
\264\ Idaho Power Comments at 4, 6.
---------------------------------------------------------------------------
164. With respect to concerns that generation capacity is not
appropriately included in corrective because it should be addressed
through resource adequacy processes, we reiterate our findings above in
section IV.F that the purpose of the new or modified Standard is to
address transmission system deliverability and not to supplant or
duplicate resource adequacy processes. With respect to concerns from
PIOs and ACP that generation may be ineffective as a mitigation
measure, we note that responsible entities have the flexibility to
determine the appropriate mitigation measure for their circumstances.
d. Notification to Applicable Regulatory Authorities or Governing
Bodies Responsible for Retail Electric Service Issues
165. We direct NERC to require in the new or modified Reliability
Standard that responsible entities share their corrective action plans
with, and solicit feedback from, applicable regulatory authorities or
governing bodies responsible for retail electric service issues. We
agree with commenters that relevant state entities should have the
opportunity to provide input during the
[[Page 41283]]
development of corrective action plans. Just as this final rule seeks
to ensure Reliable Operation of the Bulk-Power System during extreme
heat and cold weather events, regulatory authorities and governing
bodies responsible for retail electric service are taking actions to
ensure reliability for local stakeholders. As such, we believe that
requiring responsible entities to seek input from applicable regulatory
authorities or governing bodies responsible for retail electric service
issues when developing corrective action plans could help ensure that
shared opportunities to increase system reliability are not missed.
Further, as NESCOE points out, such consultation may allow these
entities to better understand ``the cost implications of various
approaches'' and, therefore, provide ``better insight into the
considerations and tradeoffs inherent in the options available.'' \265\
---------------------------------------------------------------------------
\265\ NESCOE Comments at 4.
---------------------------------------------------------------------------
166. We also agree with NESCOE that sharing corrective action plans
with applicable regulatory authorities or governing bodies responsible
for retail electric service is necessary given the possibility that
corrective action plans could include load shedding.\266\ As the
Commission has stated in the past, we believe that the public should
have notice and understanding of a responsible entity's plans to shed
non-consequential load.\267\ Therefore, just as Reliability Standard
TPL-001-5.1 requires planning coordinators and transmission planners to
notify stakeholders, including applicable regulatory authorities or
governing bodies responsible for retail electric service, of their
intent to include non-consequential load loss in corrective action
plans for certain single-contingency events,\268\ the new or modified
Reliability Standard must also require responsible entities to
similarly communicate their intent to use non-consequential load shed
in their extreme weather corrective action plans.
---------------------------------------------------------------------------
\266\ Id. at 5.
\267\ Transmission Planning Reliability Standards, Order No.
762, 77 FR 26686 (May 7, 2012), 139 FERC ] 61,060, at P 65 (2012).
\268\ Reliability Standard TPL-001-5.1, at attach. 1.
---------------------------------------------------------------------------
167. Further, because an important goal of transmission planning is
to avoid load shed,\269\ any responsible entity that includes non-
consequential load loss in its corrective action plan should also
identify and share with applicable regulatory authorities or governing
bodies responsible for retail electric service alternative corrective
actions that would, if approved and implemented, avoid the use of load
shedding. Examples could include building additional generation and/or
transmission capacity, energy efficiency programs, and demand load
response programs.\270\
---------------------------------------------------------------------------
\269\ Order No. 693, 118 FERC ] 61,218 at P 1,795.
\270\ To be clear, responsible entities may also pursue such
mitigating actions in the first instance, subject to the approval of
relevant regulatory authorities. See supra P 161.
---------------------------------------------------------------------------
168. While we direct NERC to require registered entities to
communicate the results of their studies and share their extreme
weather corrective action plans with applicable regulatory authorities
or governing bodies responsible for retail electric service, NERC
should not attempt to mandate that entities which are not under the
Commission's jurisdiction participate in the development of corrective
action plans.
I. Other Extreme Weather-Related Events and Issues
169. While the NOPR focused on extreme heat and cold weather
events, the NOPR recognized that long-term drought, particularly when
occurring in conjunction with high temperatures, could also pose a
serious risk to Bulk-Power System reliability over a wide geographical
area. In the NOPR, the Commission raised a concern that drought may
cause or contribute to conditions that affect reliable operation of the
Bulk-Power System such as transmission outages, reduced plant
efficiency, and reduced generation capacity. The Commission sought
comment on whether drought should be included along with extreme heat
and cold weather events within the scope of the Reliability
Standard.\271\ Additionally, the Commission invited comment on whether
other extreme events with significant impact on the reliability of the
Bulk-Power System could also be considered and modeled in the
future.\272\
---------------------------------------------------------------------------
\271\ NOPR, 179 FERC ] 61,195 at P 92.
\272\ Id. P 93.
---------------------------------------------------------------------------
1. Comments
170. Indicated Trade Associations, EDF, and ACP support including
the consideration of drought with extreme heat and cold weather events
within the scope of the new or modified Reliability Standard.\273\ NERC
agrees, suggesting that drought conditions be studied in drought-prone
areas of the country.\274\ EDF notes that drought events can
significantly impact the capacity and operation of water-cooled fossil
and nuclear generators and other water-cooled assets, as well as
hydroelectric generators. EDF also asserts that drought events are also
highly correlated with high temperature and wildfires. Therefore,
according to EDF, a failure to consider drought impacts could result in
an overestimation of generation availability during an extreme heat
weather event and understate the risks of that event.\275\
---------------------------------------------------------------------------
\273\ Indicated Trade Associations Comments at 13; EDF Comments
at 19; ACP Comments at 18-19.
\274\ NERC Comments at 12.
\275\ EDF Comments at 24.
---------------------------------------------------------------------------
171. Similarly, Indicated Trade Associations note that they support
the study of long-term drought impacts on relevant generation (e.g.,
hydro-electric, geothermal, and nuclear generation) in regions where
drought has been, or may plausibly become, an issue. They add that
droughts are sustained long-term conditions that may be fundamentally
studied and addressed differently--for example, as a fuel supply
sensitivity--than a short-term extreme heat or cold weather event.\276\
However, Indicated Trade Associations believe that the Commission
should not attempt to address all types of extreme weather events at
once in the Reliability Standard, but rather take a phased
approach.\277\
---------------------------------------------------------------------------
\276\ Indicated Trade Associations Comments at 13.
\277\ Id.
---------------------------------------------------------------------------
172. ACP states ``[b]ecause drought events are already widespread
across all regions, and climate change will make them even more
frequent and widespread, it would be prudent for the Commission and
NERC to require all regions to include drought in their analysis of
severe weather benchmark events under TPL-001.'' \278\
---------------------------------------------------------------------------
\278\ ACP Comments at 10.
---------------------------------------------------------------------------
173. Tri-State notes that drought is already sufficiently included
in the resource forecasts developed by Resource Planners.\279\
---------------------------------------------------------------------------
\279\ Tri-State Comments at 8.
---------------------------------------------------------------------------
174. Certain commenters support the inclusion of extreme weather
events beyond heat, cold and drought. For example, NERC identifies
extreme weather conditions for inclusion in required studies, such as
high winds, diminished winds, dust, smoke, fog, and increased cloud
cover.\280\ According to NERC, such long-term, widespread weather and
environmental conditions can impact resource availability and the
transmission system. Other commenters suggest the inclusion of other
extreme weather events such as wildfires, hurricanes, and tornadoes;
\281\ rain and wind (including derechos), and ice storms; \282\ debris
flow (landslide risk following wildfire scars and heavy
[[Page 41284]]
precipitation) and rain-on-snow events that may lead to dam
overtopping.\283\
---------------------------------------------------------------------------
\280\ NERC Comments at 12.
\281\ EDF Comments at 25.
\282\ AEP Comments at 5.
\283\ SCE Comments at 6-7.
---------------------------------------------------------------------------
175. EPRI points out that certain extreme weather events such as
hurricanes or flooding can and do often occur independent of extreme
heat and cold events. As such, EPRI states that the standard should
identify climate and weather-related threats that occur concurrently or
independently based on the planning area's local footprint and develop
scenarios accordingly.\284\
---------------------------------------------------------------------------
\284\ EPRI Comments at P 29.
---------------------------------------------------------------------------
176. In contrast, MISO and LCRA comment that the Reliability
Standard should be limited to extreme heat and cold events. MISO also
comments that there is a fundamental difference between extreme heat
and cold events and other extreme weather events: extreme temperature
events would likely result in the load increasing and continuing to
stay online, while other extreme weather events such as hurricanes or
tornados create the possibility of load loss. MISO also points out that
the operation horizon will continue to prepare for situations like
hurricanes, tornados, or ice storms.\285\ Likewise, LCRA adds that
drought and other extreme weather events beyond extreme temperature are
already modeled by existing extreme event contingencies.\286\
---------------------------------------------------------------------------
\285\ MISO Comments at 2.
\286\ LCRA Comments at 4.
---------------------------------------------------------------------------
2. Commission Determination
177. We decline to direct NERC to create or modify a Reliability
Standard to specifically require the assessment of the impacts of
drought conditions as part of extreme heat and cold transmission system
planning. As explained above, the type of long-term meteorological
study involved in extreme heat and cold event transmission planning
necessarily includes examining the extreme weather impact on base
climate conditions over the study period, conditions that would have to
include anticipated drought conditions in relevant planning areas.\287\
---------------------------------------------------------------------------
\287\ See supra P 114
---------------------------------------------------------------------------
178. We agree with various commenters that drought conditions may
impact reliability,\288\ and drought impacts on generation are already
studied in the resource forecasts developed by resource planners and
mitigated by operating procedures. Additionally, droughts that may
occur concurrently with extreme heat and cold events will be included
in the benchmark planning case, as drought conditions would be present
in the meteorological data that feeds the benchmark planning case,\289\
and the possibility of more severe drought could be reflected as part
of a sensitivity analysis.\290\
---------------------------------------------------------------------------
\288\ See e.g., EDF Comments at 24.
\289\ See supra note 155.
\290\ See supra P 114 and note 155.
---------------------------------------------------------------------------
179. Regarding other extreme weather events such as NERC's concern
with high winds, diminished winds, dust, smoke, smog fog, extreme
snowstorms, flooding and increased cloud cover, and extreme snowstorms,
or other commenters recommendations to include hurricanes, tornados,
heavy rain and wind, and ice storms; and adjacent events such as
wildfires, debris flow, and flooding, we agree that these conditions
may affect the Bulk-Power System. However, we are not persuaded that a
directive to address these events in the new or modified Reliability
Standard is warranted at this time.
180. As MISO indicates, there are fundamental differences between
extreme heat and cold events and other extreme weather events that cast
doubt as to whether this Reliability Standard is the correct vehicle
for addressing their impacts.\291\ For instance, extreme heat and cold
events generally affect large geographic areas, while other extreme
weather and adjacent events such as tornadoes, hurricanes, storms,
floods, and wildfires tend to have more localized impacts. Moreover, as
MISO points out, extreme heat and cold weather events are typically
characterized by potential sustained load increases, while other
extreme weather events typically result in load losses.
---------------------------------------------------------------------------
\291\ MISO Comments at 2.
---------------------------------------------------------------------------
J. Reliability Standard Development and Implementation Timeline
181. The Commission proposed to direct NERC to develop a new or
modified Reliability Standard within one year of the effective date of
a final rule in this proceeding, with compliance obligations beginning
no later than 12 months from Commission approval of the proposed
Reliability Standard.\292\
---------------------------------------------------------------------------
\292\ NOPR, 179 FERC ] 61,195 at P 48.
---------------------------------------------------------------------------
1. Comments
182. NERC raises no concerns with the proposed 12-month proposal to
create a new or modified Reliability Standard; however, NERC requests
that the Commission consider coordinating the timing of this final rule
to allow NERC to benefit from the informational filings in Docket Nos.
RM22-16-000 and AD21-13-000, as information obtained from these reports
``may prove useful to the NERC standard development process.'' \293\
---------------------------------------------------------------------------
\293\ NERC Comments at 14. In Docket Nos. RM22-16-000 and AD21-
13-000, the Commission proposes directing transmission providers to
submit one-time informational reports describing their current or
planned policies and processes for conducting extreme weather
vulnerability assessments. One-Time Informational Reports on Extreme
Weather Vulnerability Assessments; Climate Change, Extreme Weather,
& Elec. Sys. Reliability, Notice of Proposed Rulemaking, 87 FR 39414
(July 1, 2022), 179 FERC ] 61,196 (2022) (Informational Reports
NOPR).
---------------------------------------------------------------------------
183. PJM and MISO Transmission Owners state that one year will not
be enough time to develop the proposed Reliability Standard.\294\ PJM
states that such a short timeframe will hamper stakeholder input.\295\
PJM further comments that the NOPR's proposed timeline for standard
development is not ``sequenced with any of the other activities
associated with ensuring enhanced reliability planning'' and will thus
``divert resources from the more comprehensive work that is needed in
this area.'' \296\ MISO Transmission Owners agree that ``one year's
time is not long enough'' to modify or create a new Reliability
Standard, and the Commission should give NERC ``more time.'' \297\
---------------------------------------------------------------------------
\294\ PJM Comments at 14; MISO Transmission Owners Comments at
7.
\295\ PJM Comments at 14.
\296\ Id.
\297\ MISO Transmission Owners Comments at 7.
---------------------------------------------------------------------------
184. Regarding the effective date of any resulting Reliability
Standard, NERC requests that the Commission clarify the proposed
implementation schedule, i.e., ``whether entities must begin to comply
with all new study requirements within one year of Commission approval
(i.e., completed studies with Corrective Action Plans developed), or
whether a phased-in approach beginning no later than one year is
permitted for entities to coordinate on the development of new models,
collect new data, and perform the necessary coordination to study wide
area impacts before completing studies and developing any associated
Corrective Action Plans.'' \298\
---------------------------------------------------------------------------
\298\ NERC Comments at 14-15.
---------------------------------------------------------------------------
185. PJM also states that one year is not enough time for
responsible entities to implement the new or revised Reliability
Standard, because after Commission approval ``Transmission Providers
like PJM will have responsibility to translate it into workable
planning process methodologies and related stakeholder-approved manual
language.'' \299\
---------------------------------------------------------------------------
\299\ PJM Comments at 14-15.
---------------------------------------------------------------------------
186. PJM further calls for flexibility on setting start dates for
the implementation period for different
[[Page 41285]]
entities given variances in regional planning cycles.\300\ APS echoes
the call for flexibility as to the timeframe for developing a
corrective action plan as the potential mitigation strategies may vary
or include neighboring entities.\301\
---------------------------------------------------------------------------
\300\ Id.
\301\ APS Comments at 8.
---------------------------------------------------------------------------
187. AEP proposes that the Commission provide responsible entities
``at least two years to implement stability analysis'' after the
proposed Reliability Standard takes effect, and that corrective action
plans be developed ``within one year of the assessment of reliability
deficiency.'' \302\
---------------------------------------------------------------------------
\302\ AEP Comments at 13, 24.
---------------------------------------------------------------------------
2. Commission Determination
188. We direct NERC to submit a new or modified Reliability
Standard within 18 months of the date of publication of this final rule
in the Federal Register. Further, we direct NERC to propose an
implementation timeline for the new or modified Reliability Standard,
with implementation beginning no later than 12 months after the
effective date of a Commission order approving the proposed Reliability
Standard.
189. We agree with NERC that it is important to coordinate the
timeline for the development of a Reliability Standard under this
proceeding with that of the extreme weather one-time informational
reports required under Docket Nos. RM22-16-000 and AD21-13-000.\303\
The Informational Reports Final Rule, which is being issued
concurrently with this final rule, directs responsible entities to
develop and file with the Commission within 120 days of that order's
publication in the Federal Register a one-time informational report
``describing their current or planned policies and processes for
conducting extreme weather vulnerability assessments.'' \304\ The
Informational Reports Final Rule further states that public comments
will be due 60 days after the reports are filed.\305\ These
informational reports may assist the standard drafting team's efforts
in developing the proposed Reliability Standard, as they will be
helpful for determining whether and to what extent transmission
providers are already considering the impacts of extreme weather
events. We believe that extending the NOPR's proposed standard
development timeline is appropriate to ensure that NERC can benefit
from the information obtained from these reports, as well as from
public comments on the reports.
---------------------------------------------------------------------------
\303\ Final Rule, Order No. 897, 183 FERC ] 61,192 (2023)
(``Informational Reports Final Rule'').
\304\ Id. PP 1, 3.
\305\ Id. P 104.
---------------------------------------------------------------------------
190. With regards to PJM and MISO Transmission Owners' comments, we
recognize that the NOPR proposed an ambitious development timeline for
the proposed Reliability Standard. As we indicated in the NOPR, the
negative impact of extreme weather on the reliability of the Bulk-Power
System demands an urgent response. Further, we note that NERC, the
entity responsible for the development of the Reliability Standard, did
not raise concerns about the NOPR's proposed development timeline. As
such, we are not persuaded that there is a present need to extend the
deadline to submit a proposed Reliability Standard further than what is
necessary to ensure that NERC can benefit from the data obtained as a
result of the one-time informational reports.
191. Accordingly, we direct NERC to submit a proposed Reliability
Standard within 18 months of the date of publication of this final rule
in the Federal Register. We believe that extending the development
timeline by six months should be sufficient to ensure that the standard
drafting team will be able to take advantage of the one-time reports
required by the Commission under Docket Nos. RM22-16-000 and AD21-13-
000.
192. We decline to direct NERC to ensure that entities fully comply
with all new requirements within one year of Commission approval (i.e.,
completed studies with corrective action plans developed). As AEP and
PJM note in their comments, the new or modified Reliability Standard
will require significant implementation efforts. Given the complexities
and multiple stages of activity that would be involved in compliance
with the directives in this final rule, we believe that a more flexible
implementation approach is appropriate.
193. We therefore direct NERC to establish an implementation
timeline for the proposed Reliability Standard. In complying with this
directive, NERC will have discretion to develop a phased-in
implementation timeline for the different requirements of the proposed
Reliability Standard (i.e., developing benchmark cases, conducting
studies, developing corrective action plans). However, this phased-in
implementation must begin within 12 months of the effective date of a
Commission order approving the proposed Reliability Standard and must
include a clear deadline for implementation of all requirements.
V. Information Collection Statement
194. The information collection requirements contained in this
final rule are subject to review by the Office of Management and Budget
(OMB) under section 3507(d) of the Paperwork Reduction Act of
1995.\306\ OMB's regulations require approval of certain information
collection requirements imposed by agency rules.\307\ Upon approval of
a collection of information, OMB will assign an OMB control number and
expiration date. Respondents subject to the filing requirements of this
rule will not be penalized for failing to respond to this collection of
information unless the collection of information displays a valid OMB
control number.
---------------------------------------------------------------------------
\306\ 44 U.S.C. 3507(d).
\307\ 5 CFR 1320.11.
---------------------------------------------------------------------------
195. The directives to NERC to develop a new Reliability Standard
or modify existing Reliability Standard TPL-001 (Transmission System
Planning Performance Requirements), are covered by, and already
included in, the existing OMB-approved information collection FERC-725
(Certification of Electric Reliability Organization; Procedures for
Electric Reliability Standards; OMB Control No. 1902-0225), under
Reliability Standards Development.\308\ The reporting requirements in
FERC-725 include the ERO's overall responsibility for developing
Reliability Standards, such as the TPL-001 Reliability Standard, which
is designed to ensure the Bulk-Power System will operate reliably over
a broad spectrum of system conditions and following a wide range of
probable contingencies.\309\ The Commission will submit to OMB a
request for a non-substantive revision of FERC-725 in connection with
this final rule.
---------------------------------------------------------------------------
\308\ Reliability Standards Development as described in FERC-725
covers standards development initiated by NERC, the Regional
Entities, and industry, as well as standards the Commission may
direct NERC to develop or modify. The information collection
associated with this final rule ordinarily would be a non-material
addition to FERC-725. However, an information collection request
unrelated to this final rule is pending review under FERC-725 at the
Office of Management and Budget. To submit this final rule timely to
OMB, we will submit this to OMB as a temporary placeholder under
FERC-725(1A), OMB Control No. 1902-0289.
\309\ Reliability Standard TPL-001-4, Purpose.
---------------------------------------------------------------------------
VI. Environmental Analysis
196. The Commission is required to prepare an Environmental
Assessment or an Environmental Impact Statement for any action that may
have a significant adverse effect on the human
[[Page 41286]]
environment.\310\ The Commission has categorically excluded certain
actions from this requirement as not having a significant effect on the
human environment. Included in the exclusion are rules that are
clarifying, corrective, or procedural or that do not substantially
change the effect of the regulations being amended.\311\ The actions
directed here fall within this categorical exclusion in the
Commission's regulations.
---------------------------------------------------------------------------
\310\ Regul. Implementing the Nat'l Env't Pol'y Act, Order No.
486, 52 FR 47897 (Dec. 17, 1987), FERC Stats. & Regs. ] 30,783
(1987) (cross-referenced at 41 FERC ] 61,284).
\311\ 18 CFR 380.4(a)(2)(ii) (2022).
---------------------------------------------------------------------------
VII. Regulatory Flexibility Act
197. The Regulatory Flexibility Act of 1980 (RFA) \312\ generally
requires a description and analysis of final rules that will have
significant economic impact on a substantial number of small entities.
---------------------------------------------------------------------------
\312\ 5 U.S.C. 601-612.
---------------------------------------------------------------------------
198. This final rule directs NERC, the Commission-certified ERO, to
develop a new or modified Reliability Standard that requires long-term
transmission system planning designed to prepare for extreme heat and
cold weather events. Therefore, this final rule will not have a
significant or substantial impact on entities other than NERC.
Consequently, the Commission certifies that this final rule will not
have a significant economic impact on a substantial number of small
entities.
199. Any Reliability Standards proposed by NERC in compliance with
this rulemaking will be considered by the Commission in future
proceedings. As part of any future proceedings, the Commission will
make determinations pertaining to the Regulatory Flexibility Act based
on the content of the Reliability Standards proposed by NERC.
VIII. Document Availability
200. In addition to publishing the full text of this document in
the Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (https://www.ferc.gov). At
this time, the Commission has suspended access to the Commission's
Public Reference Room due to the President's March 13, 2020
proclamation declaring a National Emergency concerning the Novel
Coronavirus Disease (COVID-19).
201. From FERC's Home Page on the internet, this information is
available on eLibrary. The full text of this document is available on
eLibrary in PDF and Microsoft Word format for viewing, printing, and/or
downloading. To access this document in eLibrary, type the docket
number excluding the last three digits of this document in the docket
number field.
202. User assistance is available for eLibrary and the FERC's
website during normal business hours from FERC Online Support at (202)
502-6652 (toll free at 1-866-208-3676) or email at
[email protected], or the Public Reference Room at (202) 502-
8371, TTY (202) 502-8659. Email the Public Reference Room at
[email protected].
IX. Effective Date and Congressional Notification
203. This rule will become effective September 21, 2023. The
Commission has determined, with the concurrence of the Administrator of
the Office of Information and Regulatory Affairs of OMB, that this rule
is not a ``major rule'' as defined in section 351 of the Small Business
Regulatory Enforcement Fairness Act of 1996.
By the Commission. Commissioner Danly is concurring in part.
Issued: June 15, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
The following appendix will not appear in the Code of Federal
Regulations.
Appendix A: Commenter Names
----------------------------------------------------------------------------------------------------------------
Acronyms Commenter name
----------------------------------------------------------------------------------------------------------------
ACP......................................... American Clean Power Association.
ACEG........................................ Americans for a Clean Energy Grid.
AEP......................................... American Electric Power Service Corporation.
Ampjack..................................... Ampjack Industries Ltd.
APS......................................... Arizona Public Service Company.
BPA......................................... Bonneville Power Administration.
EDF......................................... Environmental Defense Fund.
Indicated Trade Associations................ The Edison Electric Institute (EEI), the American Public Power
Association (APPA), the Large Public Power Council (LPPC), the
National Rural Electric Cooperative Association (NRECA), and the
Transmission Access Policy Study Group (TAPS).
Entergy..................................... Entergy Services, LLC.
EPRI........................................ Electric Power Research Institute.
EPSA........................................ Electric Power Supply Association.
ERCOT....................................... Electric Reliability Council of Texas, Inc.
Eversource.................................. Eversource Energy Service Company.
Idaho Power................................. Idaho Power Company.
ISO-NE...................................... ISO New England Inc.
LCRA........................................ LCRA Transmission Services Corporation.
Louisiana PSC............................... Louisiana Public Service Commission.
MISO........................................ Midcontinent Independent System Operator, Inc.
[[Page 41287]]
MISO Transmission Owners.................... Ameren Services Company, as agent for Union Electric Company d/b/a
Ameren Missouri, Ameren Illinois Company d/b/a Ameren Illinois
and Ameren Transmission Company of Illinois; American
Transmission Company LLC; Big Rivers Electric Corporation;
Central Minnesota Municipal Power Agency; City Water, Light &
Power (Springfield, IL); Cleco Power LLC; Cooperative Energy;
Dairyland Power Cooperative; Duke Energy Business Services, LLC
for Duke Energy Indiana, LLC; East Texas Electric Cooperative;
Entergy Arkansas, LLC; Entergy Louisiana, LLC; Entergy
Mississippi, LLC; Entergy New Orleans, LLC; Entergy Texas, Inc.;
Great River Energy; GridLiance Heartland LLC; Hoosier Energy
Rural Electric Cooperative, Inc.; Indiana Municipal Power Agency;
Indianapolis Power & Light Company; International Transmission
Company d/b/a ITCTransmission; ITC Midwest LLC; Lafayette
Utilities System; Michigan Electric Transmission Company, LLC;
MidAmerican Energy Company; Minnesota Power (and its subsidiary
Superior Water, L&P); Missouri River Energy Services; Montana-
Dakota Utilities Co.; Northern Indiana Public Service Company
LLC; Northern States Power Company, a Minnesota corporation, and
Northern States Power Company, a Wisconsin corporation,
subsidiaries of Xcel Energy Inc.; Northwestern Wisconsin Electric
Company; Otter Tail Power Company; Prairie Power, Inc.; Republic
Transmission, LLC; Southern Illinois Power Cooperative; Southern
Indiana Gas & Electric Company (d/b/a CenterPoint Energy Indiana
South); Southern Minnesota Municipal Power Agency; Wabash Valley
Power Association, Inc.; and Wolverine Power Supply Cooperative,
Inc.
NARUC....................................... National Association of Regulatory Utility Commissioners.
NERC........................................ North American Electric Reliability Corporation.
NESCOE...................................... New England States Committee on Electricity.
NMA......................................... National Mining Association.
NYISO....................................... New York Independent System Operator, Inc.
NYSRC....................................... New York State Reliability Council.
Ohio FEA.................................... Federal Energy Advocate for the Public Utilities Commission of
Ohio.
PG&E........................................ Pacific Gas and Electric Company.
PIOs........................................ Public Interest Organizations (Sustainable FERC Project, Natural
Resources Defense Council, American Council on Renewable Energy,
Sierra Club, Southern Environmental Law Center, Western Resource
Advocates).
PJM......................................... PJM Interconnection, L.L.C.
SCE......................................... Southern California Edison Company.
Sunflower................................... Sunflower Electric Power Corporation.
Tri-State................................... Tri-State Generation and Transmission Association, Inc.
UCS......................................... Union of Concerned Scientists.
WATT........................................ Working for Advanced Transmission Technologies.
WE ACT...................................... WE ACT for Environmental Justice.
----------------------------------------------------------------------------------------------------------------
[FR Doc. 2023-13286 Filed 6-22-23; 8:45 am]
BILLING CODE 6717-01-P