Columbia Gas Transmission, LLC; Notice of Request for Extension of Time, 40795 [2023-13267]
Download as PDF
Federal Register / Vol. 88, No. 119 / Thursday, June 22, 2023 / Notices
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Dated: June 15, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–13257 Filed 6–21–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP17–80–004]
ddrumheller on DSK120RN23PROD with NOTICES1
Columbia Gas Transmission, LLC;
Notice of Request for Extension of
Time
Take notice that on June 8, 2023,
Columbia Gas Transmission, LLC
(Columbia) requested that the Federal
Energy Regulatory Commission
(Commission) grant an extension of
time, until July 19, 2026, to construct
and operate its Eastern Panhandle
Expansion Project, originally authorized
in the July 19, 2018 Order Issuing
Certificate under section 7 of the
Natural Gas Act and part 157 of the
Commission’s regulations (July 19,
Order).1 Ordering Paragraph (B1) of the
July 19 Order provided a deadline of
July 19, 2020, to complete construction
of the facilities and making them
available for service.
In its original application, Columbia
requested authorization to construct and
operate approximately 3.37 miles of 8inch in diameter pipeline commencing
in Fulton County, Pennsylvania, and
extending through Washington County,
Maryland, to a point of delivery in
Morgan County, West Virginia. The
project was designed to meet
Mountaineer Gas’ request for 47,500
dekatherms per day (Dth/d) of capacity,
and Mountaineer Gas and Columbia
have a binding precedent agreement
executed for the entire capacity of the
project for a 20-year primary term.
On July 8, 2020, Columbia filed a
request for a three-year extension of
time, until July 19, 2023, to construct
the project and place it into service. In
that filing, Columbia stated that, due to
unforeseen delays in acquiring an
easement from the Government of
Maryland across the Western Maryland
1 See
Columbia Gas Transmission, LLC, 164 FERC
¶ 61,036 (2018) (July 19 Order), reh’g denied, 170
FERC ¶ 61,247 (2020).
VerDate Sep<11>2014
18:01 Jun 21, 2023
Jkt 259001
Rail Trail, additional time was required
in order to complete the construction of
the authorized project facilities. On
August 25, 2020, the Commission
granted Columbia’s request.2
In this latest request, Columbia states
that the easement in question is still the
subject of litigation pending before the
U.S. Court of Appeals for the Fourth
Circuit (Fourth Circuit). Columbia
reports that, due to this litigation,
Columbia is prevented from moving
forward with the construction of the
project.
This notice establishes a 15-calendar
day intervention and comment period
deadline. Any person wishing to
comment on the applicant’s request for
an extension of time may do so. No
reply comments or answers will be
considered. If you wish to obtain legal
status by becoming a party to the
proceedings for this request, you
should, on or before the comment date
stated below, file a motion to intervene
in accordance with the requirements of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the Natural
Gas Act (18 CFR 157.10).3
As a matter of practice, the
Commission itself generally acts on
requests for extensions of time to
complete construction for Natural Gas
Act facilities when such requests are
contested before order issuance. For
those extension requests that are
contested,4 the Commission will aim to
issue an order acting on the request
within 45 days.5 The Commission will
address all arguments relating to
whether the applicant has demonstrated
there is good cause to grant the
extension.6 The Commission will not
consider arguments that re-litigate the
issuance of the certificate order,
including whether the Commission
properly found the project to be in the
public convenience and necessity and
whether the Commission’s
environmental analysis for the
certificate complied with the National
Environmental Policy Act.7 At the time
2 Columbia Gas Transmission, LLC, Docket No.
CP18–116–003 (August 25, 2020) (delegated order).
3 Only motions to intervene from entities that
were party to the underlying proceeding will be
accepted. Algonquin Gas Transmission, LLC, 170
FERC ¶ 61,144, at P 39 (2020).
4 Contested proceedings are those where an
intervenor disputes any material issue of the filing.
18 CFR 385.2201(c)(1) (2019).
5 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
6 Id. at P 40.
7 Similarly, the Commission will not re-litigate
the issuance of an NGA section 3 authorization,
including whether a proposed project is not
inconsistent with the public interest and whether
the Commission’s environmental analysis for the
permit order complied with NEPA.
PO 00000
Frm 00021
Fmt 4703
Sfmt 9990
40795
a pipeline requests an extension of time,
orders on certificates of public
convenience and necessity are final and
the Commission will not re-litigate their
issuance.8 The OEP Director, or his or
her designee, will act on all of those
extension requests that are uncontested.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room. For assistance, contact
FERC at FERCOnlineSupport@ferc.gov
or call toll-free, (886) 208–3676 or TTY,
(202) 502–8659.
The Commission strongly encourages
electronic filings of comments in lieu of
paper using the ‘‘eFile’’ link at https://
www.ferc.gov. In lieu of electronic filing,
you may submit a paper copy.
Submissions sent via the U.S. Postal
Service must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Comment Date: 5:00 p.m. Eastern
Time on June 30, 2023.
Dated: June 15, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–13267 Filed 6–21–23; 8:45 am]
BILLING CODE 6717–01–P
8 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
E:\FR\FM\22JNN1.SGM
22JNN1
Agencies
[Federal Register Volume 88, Number 119 (Thursday, June 22, 2023)]
[Notices]
[Page 40795]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-13267]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP17-80-004]
Columbia Gas Transmission, LLC; Notice of Request for Extension
of Time
Take notice that on June 8, 2023, Columbia Gas Transmission, LLC
(Columbia) requested that the Federal Energy Regulatory Commission
(Commission) grant an extension of time, until July 19, 2026, to
construct and operate its Eastern Panhandle Expansion Project,
originally authorized in the July 19, 2018 Order Issuing Certificate
under section 7 of the Natural Gas Act and part 157 of the Commission's
regulations (July 19, Order).\1\ Ordering Paragraph (B1) of the July 19
Order provided a deadline of July 19, 2020, to complete construction of
the facilities and making them available for service.
---------------------------------------------------------------------------
\1\ See Columbia Gas Transmission, LLC, 164 FERC ] 61,036 (2018)
(July 19 Order), reh'g denied, 170 FERC ] 61,247 (2020).
---------------------------------------------------------------------------
In its original application, Columbia requested authorization to
construct and operate approximately 3.37 miles of 8-inch in diameter
pipeline commencing in Fulton County, Pennsylvania, and extending
through Washington County, Maryland, to a point of delivery in Morgan
County, West Virginia. The project was designed to meet Mountaineer
Gas' request for 47,500 dekatherms per day (Dth/d) of capacity, and
Mountaineer Gas and Columbia have a binding precedent agreement
executed for the entire capacity of the project for a 20-year primary
term.
On July 8, 2020, Columbia filed a request for a three-year
extension of time, until July 19, 2023, to construct the project and
place it into service. In that filing, Columbia stated that, due to
unforeseen delays in acquiring an easement from the Government of
Maryland across the Western Maryland Rail Trail, additional time was
required in order to complete the construction of the authorized
project facilities. On August 25, 2020, the Commission granted
Columbia's request.\2\
---------------------------------------------------------------------------
\2\ Columbia Gas Transmission, LLC, Docket No. CP18-116-003
(August 25, 2020) (delegated order).
---------------------------------------------------------------------------
In this latest request, Columbia states that the easement in
question is still the subject of litigation pending before the U.S.
Court of Appeals for the Fourth Circuit (Fourth Circuit). Columbia
reports that, due to this litigation, Columbia is prevented from moving
forward with the construction of the project.
This notice establishes a 15-calendar day intervention and comment
period deadline. Any person wishing to comment on the applicant's
request for an extension of time may do so. No reply comments or
answers will be considered. If you wish to obtain legal status by
becoming a party to the proceedings for this request, you should, on or
before the comment date stated below, file a motion to intervene in
accordance with the requirements of the Commission's Rules of Practice
and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the
Natural Gas Act (18 CFR 157.10).\3\
---------------------------------------------------------------------------
\3\ Only motions to intervene from entities that were party to
the underlying proceeding will be accepted. Algonquin Gas
Transmission, LLC, 170 FERC ] 61,144, at P 39 (2020).
---------------------------------------------------------------------------
As a matter of practice, the Commission itself generally acts on
requests for extensions of time to complete construction for Natural
Gas Act facilities when such requests are contested before order
issuance. For those extension requests that are contested,\4\ the
Commission will aim to issue an order acting on the request within 45
days.\5\ The Commission will address all arguments relating to whether
the applicant has demonstrated there is good cause to grant the
extension.\6\ The Commission will not consider arguments that re-
litigate the issuance of the certificate order, including whether the
Commission properly found the project to be in the public convenience
and necessity and whether the Commission's environmental analysis for
the certificate complied with the National Environmental Policy Act.\7\
At the time a pipeline requests an extension of time, orders on
certificates of public convenience and necessity are final and the
Commission will not re-litigate their issuance.\8\ The OEP Director, or
his or her designee, will act on all of those extension requests that
are uncontested.
---------------------------------------------------------------------------
\4\ Contested proceedings are those where an intervenor disputes
any material issue of the filing. 18 CFR 385.2201(c)(1) (2019).
\5\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40
(2020).
\6\ Id. at P 40.
\7\ Similarly, the Commission will not re-litigate the issuance
of an NGA section 3 authorization, including whether a proposed
project is not inconsistent with the public interest and whether the
Commission's environmental analysis for the permit order complied
with NEPA.
\8\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40
(2020).
---------------------------------------------------------------------------
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (https://www.ferc.gov) using
the ``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to the Commission's Public
Reference Room. For assistance, contact FERC at
[email protected] or call toll-free, (886) 208-3676 or TTY,
(202) 502-8659.
The Commission strongly encourages electronic filings of comments
in lieu of paper using the ``eFile'' link at https://www.ferc.gov. In
lieu of electronic filing, you may submit a paper copy. Submissions
sent via the U.S. Postal Service must be addressed to: Kimberly D.
Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street
NE, Room 1A, Washington, DC 20426. Submissions sent via any other
carrier must be addressed to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland
20852.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
Comment Date: 5:00 p.m. Eastern Time on June 30, 2023.
Dated: June 15, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-13267 Filed 6-21-23; 8:45 am]
BILLING CODE 6717-01-P