City of Sturgis, Michigan; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests, 40794-40795 [2023-13257]
Download as PDF
40794
Federal Register / Vol. 88, No. 119 / Thursday, June 22, 2023 / Notices
for improving the nation’s capacity for
teaching and learning foreign languages
through teacher training, research,
instructional materials development,
and dissemination projects. This
program responds to the ongoing
national need for individuals with
expertise and competence in world
languages; advance national security by
developing a pipeline of highly
proficient linguists; and contribute to
developing a globally competent
workforce able to engage with a
multilingual/multicultural clientele at
home and abroad.
This collection is being submitted
under the Streamlined Clearance
Process for Discretionary Grant
Information Collections (1894–0001).
Therefore, the 30-day public comment
period notice will be the only public
comment notice published for this
information collection.
Dated: June 15, 2023.
Kun Mullan,
PRA Coordinator, Strategic Collections and
Clearance, Governance and Strategy Division,
Office of Chief Data Officer, Office of
Planning, Evaluation and Policy
Development.
[FR Doc. 2023–13198 Filed 6–21–23; 8:45 am]
BILLING CODE 4000–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2964–045]
ddrumheller on DSK120RN23PROD with NOTICES1
City of Sturgis, Michigan; Notice of
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Request for
temporary variance of Article 401.
b. Project No.: 2964–045.
c. Date Filed: April 11, 2023.
d. Applicant: City of Sturgis,
Michigan (licensee).
e. Name of Project: Sturgis
Hydroelectric Project.
f. Location: The project is located on
the St. Joseph River in St. Joseph
County, Michigan, and does not occupy
federal lands.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Christopher J.
Jeter, PE, Lawson-Fisher Associates P.C.,
525 West Washington Avenue, South
Bend, IN 46601, (574) 234–3167, cjeter@
lawson-fisher.com.
VerDate Sep<11>2014
18:01 Jun 21, 2023
Jkt 259001
i. FERC Contact: Jeremy Jessup, (202)
502–6779, Jeremy.Jessup@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests: July
17, 2023.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, and protests using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. The first
page of any filing should include the
docket number P–2964–045. Comments
emailed to Commission staff are not
considered part of the Commission
record.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. Description of Request: The
licensee proposes a temporary variance
from the reservoir elevation
requirements of the Michigan
Department of Environment, Great
Lakes, and Energy’s water quality
certification condition 1.1 to facilitate a
scheduled drawdown of the project
impoundment. The purpose of the
drawdown is to mitigate risk during
construction of several dam safety
improvements. The licensee would
lower the impoundment approximately
3 feet to an elevation of 822.6 ±0.25 feet.
The drawdown is scheduled to begin
after Labor Day and continue through
April 30, 2024, in order to protect
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
hibernating wildlife along the
impoundment shoreline.
l. Locations of the Application: This
filing may be viewed on the
Commission’s website at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. You may
also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. Agencies may
obtain copies of the application directly
from the applicant.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214,
respectively. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
o. Filing and Service of Documents:
Any filing must (1) bear in all capital
letters the title ‘‘COMMENTS’’,
‘‘PROTEST’’, or ‘‘MOTION TO
INTERVENE’’ as applicable; (2) set forth
in the heading the name of the applicant
and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
commenting, protesting or intervening;
and (4) otherwise comply with the
requirements of 18 CFR 385.2001
through 385.2005. All comments,
motions to intervene, or protests must
set forth their evidentiary basis. Any
filing made by an intervenor must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
385.2010.
p. The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
E:\FR\FM\22JNN1.SGM
22JNN1
Federal Register / Vol. 88, No. 119 / Thursday, June 22, 2023 / Notices
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Dated: June 15, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–13257 Filed 6–21–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP17–80–004]
ddrumheller on DSK120RN23PROD with NOTICES1
Columbia Gas Transmission, LLC;
Notice of Request for Extension of
Time
Take notice that on June 8, 2023,
Columbia Gas Transmission, LLC
(Columbia) requested that the Federal
Energy Regulatory Commission
(Commission) grant an extension of
time, until July 19, 2026, to construct
and operate its Eastern Panhandle
Expansion Project, originally authorized
in the July 19, 2018 Order Issuing
Certificate under section 7 of the
Natural Gas Act and part 157 of the
Commission’s regulations (July 19,
Order).1 Ordering Paragraph (B1) of the
July 19 Order provided a deadline of
July 19, 2020, to complete construction
of the facilities and making them
available for service.
In its original application, Columbia
requested authorization to construct and
operate approximately 3.37 miles of 8inch in diameter pipeline commencing
in Fulton County, Pennsylvania, and
extending through Washington County,
Maryland, to a point of delivery in
Morgan County, West Virginia. The
project was designed to meet
Mountaineer Gas’ request for 47,500
dekatherms per day (Dth/d) of capacity,
and Mountaineer Gas and Columbia
have a binding precedent agreement
executed for the entire capacity of the
project for a 20-year primary term.
On July 8, 2020, Columbia filed a
request for a three-year extension of
time, until July 19, 2023, to construct
the project and place it into service. In
that filing, Columbia stated that, due to
unforeseen delays in acquiring an
easement from the Government of
Maryland across the Western Maryland
1 See
Columbia Gas Transmission, LLC, 164 FERC
¶ 61,036 (2018) (July 19 Order), reh’g denied, 170
FERC ¶ 61,247 (2020).
VerDate Sep<11>2014
18:01 Jun 21, 2023
Jkt 259001
Rail Trail, additional time was required
in order to complete the construction of
the authorized project facilities. On
August 25, 2020, the Commission
granted Columbia’s request.2
In this latest request, Columbia states
that the easement in question is still the
subject of litigation pending before the
U.S. Court of Appeals for the Fourth
Circuit (Fourth Circuit). Columbia
reports that, due to this litigation,
Columbia is prevented from moving
forward with the construction of the
project.
This notice establishes a 15-calendar
day intervention and comment period
deadline. Any person wishing to
comment on the applicant’s request for
an extension of time may do so. No
reply comments or answers will be
considered. If you wish to obtain legal
status by becoming a party to the
proceedings for this request, you
should, on or before the comment date
stated below, file a motion to intervene
in accordance with the requirements of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the Natural
Gas Act (18 CFR 157.10).3
As a matter of practice, the
Commission itself generally acts on
requests for extensions of time to
complete construction for Natural Gas
Act facilities when such requests are
contested before order issuance. For
those extension requests that are
contested,4 the Commission will aim to
issue an order acting on the request
within 45 days.5 The Commission will
address all arguments relating to
whether the applicant has demonstrated
there is good cause to grant the
extension.6 The Commission will not
consider arguments that re-litigate the
issuance of the certificate order,
including whether the Commission
properly found the project to be in the
public convenience and necessity and
whether the Commission’s
environmental analysis for the
certificate complied with the National
Environmental Policy Act.7 At the time
2 Columbia Gas Transmission, LLC, Docket No.
CP18–116–003 (August 25, 2020) (delegated order).
3 Only motions to intervene from entities that
were party to the underlying proceeding will be
accepted. Algonquin Gas Transmission, LLC, 170
FERC ¶ 61,144, at P 39 (2020).
4 Contested proceedings are those where an
intervenor disputes any material issue of the filing.
18 CFR 385.2201(c)(1) (2019).
5 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
6 Id. at P 40.
7 Similarly, the Commission will not re-litigate
the issuance of an NGA section 3 authorization,
including whether a proposed project is not
inconsistent with the public interest and whether
the Commission’s environmental analysis for the
permit order complied with NEPA.
PO 00000
Frm 00021
Fmt 4703
Sfmt 9990
40795
a pipeline requests an extension of time,
orders on certificates of public
convenience and necessity are final and
the Commission will not re-litigate their
issuance.8 The OEP Director, or his or
her designee, will act on all of those
extension requests that are uncontested.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room. For assistance, contact
FERC at FERCOnlineSupport@ferc.gov
or call toll-free, (886) 208–3676 or TTY,
(202) 502–8659.
The Commission strongly encourages
electronic filings of comments in lieu of
paper using the ‘‘eFile’’ link at https://
www.ferc.gov. In lieu of electronic filing,
you may submit a paper copy.
Submissions sent via the U.S. Postal
Service must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
The Commission’s Office of Public
Participation (OPP) supports meaningful
public engagement and participation in
Commission proceedings. OPP can help
members of the public, including
landowners, environmental justice
communities, Tribal members and
others, access publicly available
information and navigate Commission
processes. For public inquiries and
assistance with making filings such as
interventions, comments, or requests for
rehearing, the public is encouraged to
contact OPP at (202) 502–6595 or OPP@
ferc.gov.
Comment Date: 5:00 p.m. Eastern
Time on June 30, 2023.
Dated: June 15, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–13267 Filed 6–21–23; 8:45 am]
BILLING CODE 6717–01–P
8 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
E:\FR\FM\22JNN1.SGM
22JNN1
Agencies
[Federal Register Volume 88, Number 119 (Thursday, June 22, 2023)]
[Notices]
[Pages 40794-40795]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-13257]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2964-045]
City of Sturgis, Michigan; Notice of Application Accepted for
Filing and Soliciting Comments, Motions To Intervene, and Protests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Application Type: Request for temporary variance of Article 401.
b. Project No.: 2964-045.
c. Date Filed: April 11, 2023.
d. Applicant: City of Sturgis, Michigan (licensee).
e. Name of Project: Sturgis Hydroelectric Project.
f. Location: The project is located on the St. Joseph River in St.
Joseph County, Michigan, and does not occupy federal lands.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
h. Applicant Contact: Christopher J. Jeter, PE, Lawson-Fisher
Associates P.C., 525 West Washington Avenue, South Bend, IN 46601,
(574) 234-3167, fisher.com">[email protected]fisher.com.
i. FERC Contact: Jeremy Jessup, (202) 502-6779,
[email protected].
j. Deadline for filing comments, motions to intervene, and
protests: July 17, 2023.
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, and protests using the Commission's
eFiling system at https://www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments up to 6,000 characters, without
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact
information at the end of your comments. For assistance, please contact
FERC Online Support at [email protected], (866) 208-3676 (toll
free), or (202) 502-8659 (TTY). In lieu of electronic filing, you may
submit a paper copy. Submissions sent via the U.S. Postal Service must
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852. The first page of any filing should
include the docket number P-2964-045. Comments emailed to Commission
staff are not considered part of the Commission record.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person whose name appears on the official service
list for the project. Further, if an intervenor files comments or
documents with the Commission relating to the merits of an issue that
may affect the responsibilities of a particular resource agency, they
must also serve a copy of the document on that resource agency.
k. Description of Request: The licensee proposes a temporary
variance from the reservoir elevation requirements of the Michigan
Department of Environment, Great Lakes, and Energy's water quality
certification condition 1.1 to facilitate a scheduled drawdown of the
project impoundment. The purpose of the drawdown is to mitigate risk
during construction of several dam safety improvements. The licensee
would lower the impoundment approximately 3 feet to an elevation of
822.6 0.25 feet. The drawdown is scheduled to begin after
Labor Day and continue through April 30, 2024, in order to protect
hibernating wildlife along the impoundment shoreline.
l. Locations of the Application: This filing may be viewed on the
Commission's website at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. You may also register
online at https://www.ferc.gov/docs-filing/esubscription.asp to be
notified via email of new filings and issuances related to this or
other pending projects. For assistance, call 1-866-208-3676 or email
[email protected], for TTY, call (202) 502-8659. Agencies may
obtain copies of the application directly from the applicant.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214, respectively. In determining the appropriate action to take, the
Commission will consider all protests or other comments filed, but only
those who file a motion to intervene in accordance with the
Commission's Rules may become a party to the proceeding. Any comments,
protests, or motions to intervene must be received on or before the
specified comment date for the particular application.
o. Filing and Service of Documents: Any filing must (1) bear in all
capital letters the title ``COMMENTS'', ``PROTEST'', or ``MOTION TO
INTERVENE'' as applicable; (2) set forth in the heading the name of the
applicant and the project number of the application to which the filing
responds; (3) furnish the name, address, and telephone number of the
person commenting, protesting or intervening; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, motions to intervene, or protests must set forth their
evidentiary basis. Any filing made by an intervenor must be accompanied
by proof of service on all persons listed in the service list prepared
by the Commission in this proceeding, in accordance with 18 CFR
385.2010.
p. The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and
[[Page 40795]]
others, access publicly available information and navigate Commission
processes. For public inquiries and assistance with making filings such
as interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
Dated: June 15, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-13257 Filed 6-21-23; 8:45 am]