Pyrites Hydro, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions, 39841-39842 [2023-13079]

Download as PDF Federal Register / Vol. 88, No. 117 / Tuesday, June 20, 2023 / Notices process plan and schedule for pre-filing activity that incorporates the time frames provided for in part 5 of the Commission’s regulations and, to the extent possible, maximizes coordination of Federal, State, and Tribal permitting and certification processes; and (5) discuss the potential of any Federal or State agency or Native American Tribe to act as a cooperating agency for development of an environmental document. Meeting participants should come prepared to discuss their issues and/or concerns. Please review the PAD in preparation for the scoping meetings. Directions on how to obtain a copy of the PAD and SD1 are included in item n of this document. Meeting Procedures The meetings will be recorded by a court reporter and become part of the Commission’s formal record on the project. Agencies, Native American Tribes, NGOs, and individuals with environmental expertise and concerns are encouraged to attend the meetings and to assist Commission staff in defining and clarifying the issues to be addressed in the NEPA document. Dated: June 13, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–13072 Filed 6–16–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 6115–016] lotter on DSK11XQN23PROD with NOTICES1 Pyrites Hydro, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: New Major License. b. Project No.: 6115–016. c. Date filed: August 31, 2021. d. Applicant: Pyrites Hydro, LLC (Pyrites Hydro). e. Name of Project: Pyrites Hydroelectric Project (Pyrites Project or project). f. Location: On the Grass River near the Town of Canton, St. Lawrence County, New York. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)–825(r). VerDate Sep<11>2014 16:52 Jun 16, 2023 Jkt 259001 h. Applicant Contact: Curtis Mooney, Manager, Regulatory Affairs, Patriot Hydro, LLC, 59 Ayers Island Road, Bristol, New Hampshire 03222; (603) 744–0846 or cmooney@ patriothydro.com. i. FERC Contact: Josh Dub at (202) 502–8138, or email at joshua.dub@ ferc.gov. j. Deadline for filing comments, recommendations, terms and conditions, and prescriptions: 60 days from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice. The Commission strongly encourages electronic filing. Please file comments, recommendations, terms and conditions, and prescriptions using the Commission’s eFiling system at https:// ferconline.ferc.gov/FERCOnline.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://ferconline.ferc.gov/ QuickComment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. All filings must clearly identify the project name and docket number on the first page: Pyrites Hydroelectric Project P–6115–016. The Commission’s Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application has been accepted and is now ready for environmental analysis. The Council on Environmental Quality (CEQ) issued a final rule on April 20, 2022, revising the regulations under 40 CFR parts 1502, 1507, and 1508 that Federal agencies use to implement the National Environmental Policy Act (NEPA) (see National PO 00000 Frm 00023 Fmt 4703 Sfmt 4703 39841 Environmental Policy Act Implementing Regulations Revisions, 87 FR 23,453– 70). The final rule became effective on May 20, 2022. Commission staff intends to conduct its NEPA review in accordance with CEQ’s new regulations. l. The Pyrites Project consists of: (1) a 170-foot-long and 12-foot-high concrete Ambursen overflow spillway with 1.5foot-high flashboards, a 115-foot-long concrete auxiliary spillway, and a 208foot-long non-overflow dam, which includes a 50-foot-wide intake structure; (2) a 6-foot-diameter, 700-foot-long steel penstock running from the intake structure to an upper powerhouse and a 10-foot-diameter, 2,160-foot-long penstock running from the intake structure to a lower powerhouse; (3) a 21-foot by 31-foot upper powerhouse located 700 feet downstream of the intake structure containing one 1.2megawatt (MW) turbine/generator unit operating under a rated head of 76 feet and a 50-foot by 53-foot lower powerhouse located 1,200 feet downstream of the tailrace containing two 3.5–MW turbine/generator units operating under a rated head of 111 feet; (4) a 50-foot by 97-foot, 115/4.16/2.3kilovolt (kV) switchyard and substation for use by both powerhouses; (5) a 470foot-long 2.3-kV transmission line connecting the upper powerhouse to the switchyard; (6) a 1,150-foot-long 4.16kV transmission line connecting the lower powerhouse to the switchyard; and (7) appurtenant facilities. The Pyrites Project is operated in a run-of-river mode with an average annual generation of 27,865 megawatthours. Pyrites Hydro proposes to continue to operate the project in a run-of-river mode and maintain a continuous minimum flow to the bypassed reach of 45 cubic feet per second or inflow to the impoundment, whichever is less. m. A copy of the application can be viewed on the Commission’s website at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. At this time, the Commission has suspended access to the Commission’s Public Reference Room. For assistance, contact FERC at FERCOnline Support@ferc.gov or call toll-free, (886) 208–3676 or TTY, (202) 502–8659. All filings must (1) bear in all capital letters the title ‘‘COMMENTS,’’ ‘‘REPLY COMMENTS,’’ ‘‘RECOMMENDATIONS,’’ ‘‘TERMS AND CONDITIONS,’’ or ‘‘PRESCRIPTIONS;’’ (2) set forth in the heading the name of the applicant and E:\FR\FM\20JNN1.SGM 20JNN1 39842 Federal Register / Vol. 88, No. 117 / Tuesday, June 20, 2023 / Notices the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person submitting the filing; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions or prescriptions must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicant. Each filing must be accompanied by proof of service on all persons listed on the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. You may also register online at https:// www.ferc.gov/docs-filing/esubscription. asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. The applicant must file no later than 60 days following the date of issuance of this notice: (1) a copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification. Please note that the certification request must comply with 40 CFR 121.5(b), including documentation that a pre-filing meeting request was submitted to the certifying authority at least 30 days prior to submitting the certification request. Please also note that the certification request must be sent to the certifying authority and to the Commission concurrently. o. Procedural schedule: The application will be processed according to the following schedule. Revisions to the schedule will be made as appropriate. Target date Milestone lotter on DSK11XQN23PROD with NOTICES1 Filing of Comments, Recommendations, Terms and Conditions, and Prescriptions. Filing of Reply Comments .......... August 2023. September 2023 p. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as VerDate Sep<11>2014 16:52 Jun 16, 2023 Jkt 259001 interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Dated: June 13, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–13079 Filed 6–16–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. AC23–125–000] Western Power Pool; Notice of Petition for Waiver Take notice that on June 9, 2023, Northwest Power Pool d/b/a Western Power Pool (WPP or Petitioner), filed a petition for waiver of the Federal Energy Regulatory Commission’s (Commission) requirement to provide its FERC Form No. 3–Qs for 2023 on the basis that WPP was not a public utility until January 1, 2023 and requires additional time to align its accounting with the Commission’s Uniform System of Accounts, all as more fully explained in the petition. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. Anyone filing a motion to intervene, or protest must serve a copy of that document on the Petitioner. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this PO 00000 Frm 00024 Fmt 4703 Sfmt 4703 document via the internet through the Commission’s Home Page (https:// ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. The Commission’s Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502–6595 or OPP@ ferc.gov. Comments: 5:00 p.m. Eastern Time on July 13, 2023. Dated: June 13, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–13075 Filed 6–16–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 3211–010] Power Authority of the State of New York; Notice of Waiver Period for Water Quality Certification Application On June 1, 2023, the Power Authority of the State of New York submitted to the Federal Energy Regulatory Commission (Commission) a copy of its application for a Clean Water Act section 401(a)(1) water quality certification filed with the New York State Department of Environmental Conservation (New York DEC), in conjunction with the above captioned project. Pursuant to 40 CFR 121.6 and section 5.23(b) of the Commission’s regulations,1 we hereby notify the New York DEC of the following: Date of Receipt of the Certification Request: May 26, 2023. Reasonable Period of Time to Act on the Certification Request: One year (May 26, 2024). If New York DEC fails or refuses to act on the water quality certification request 1 18 E:\FR\FM\20JNN1.SGM CFR 5.23(b). 20JNN1

Agencies

[Federal Register Volume 88, Number 117 (Tuesday, June 20, 2023)]
[Notices]
[Pages 39841-39842]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-13079]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 6115-016]


Pyrites Hydro, LLC; Notice of Application Ready for Environmental 
Analysis and Soliciting Comments, Recommendations, Terms and 
Conditions, and Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: New Major License.
    b. Project No.: 6115-016.
    c. Date filed: August 31, 2021.
    d. Applicant: Pyrites Hydro, LLC (Pyrites Hydro).
    e. Name of Project: Pyrites Hydroelectric Project (Pyrites Project 
or project).
    f. Location: On the Grass River near the Town of Canton, St. 
Lawrence County, New York.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Curtis Mooney, Manager, Regulatory Affairs, 
Patriot Hydro, LLC, 59 Ayers Island Road, Bristol, New Hampshire 03222; 
(603) 744-0846 or [email protected].
    i. FERC Contact: Josh Dub at (202) 502-8138, or email at 
[email protected].
    j. Deadline for filing comments, recommendations, terms and 
conditions, and prescriptions: 60 days from the issuance date of this 
notice; reply comments are due 105 days from the issuance date of this 
notice.
    The Commission strongly encourages electronic filing. Please file 
comments, recommendations, terms and conditions, and prescriptions 
using the Commission's eFiling system at https://ferconline.ferc.gov/FERCOnline.asp. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
https://ferconline.ferc.gov/QuickComment.asp. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
[email protected]">FERCOnline[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy. 
Submissions sent via the U.S. Postal Service must be addressed to: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via 
any other carrier must be addressed to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, 
Maryland 20852. All filings must clearly identify the project name and 
docket number on the first page: Pyrites Hydroelectric Project P-6115-
016.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted and is now ready for 
environmental analysis.
    The Council on Environmental Quality (CEQ) issued a final rule on 
April 20, 2022, revising the regulations under 40 CFR parts 1502, 1507, 
and 1508 that Federal agencies use to implement the National 
Environmental Policy Act (NEPA) (see National Environmental Policy Act 
Implementing Regulations Revisions, 87 FR 23,453-70). The final rule 
became effective on May 20, 2022. Commission staff intends to conduct 
its NEPA review in accordance with CEQ's new regulations.
    l. The Pyrites Project consists of: (1) a 170-foot-long and 12-
foot-high concrete Ambursen overflow spillway with 1.5-foot-high 
flashboards, a 115-foot-long concrete auxiliary spillway, and a 208-
foot-long non-overflow dam, which includes a 50-foot-wide intake 
structure; (2) a 6-foot-diameter, 700-foot-long steel penstock running 
from the intake structure to an upper powerhouse and a 10-foot-
diameter, 2,160-foot-long penstock running from the intake structure to 
a lower powerhouse; (3) a 21-foot by 31-foot upper powerhouse located 
700 feet downstream of the intake structure containing one 1.2-megawatt 
(MW) turbine/generator unit operating under a rated head of 76 feet and 
a 50-foot by 53-foot lower powerhouse located 1,200 feet downstream of 
the tailrace containing two 3.5-MW turbine/generator units operating 
under a rated head of 111 feet; (4) a 50-foot by 97-foot, 115/4.16/2.3-
kilovolt (kV) switchyard and substation for use by both powerhouses; 
(5) a 470-foot-long 2.3-kV transmission line connecting the upper 
powerhouse to the switchyard; (6) a 1,150-foot-long 4.16-kV 
transmission line connecting the lower powerhouse to the switchyard; 
and (7) appurtenant facilities.
    The Pyrites Project is operated in a run-of-river mode with an 
average annual generation of 27,865 megawatt-hours.
    Pyrites Hydro proposes to continue to operate the project in a run-
of-river mode and maintain a continuous minimum flow to the bypassed 
reach of 45 cubic feet per second or inflow to the impoundment, 
whichever is less.
    m. A copy of the application can be viewed on the Commission's 
website at https://www.ferc.gov using the ``eLibrary'' link. Enter the 
docket number excluding the last three digits in the docket number 
field to access the document. For assistance, contact FERC Online 
Support. At this time, the Commission has suspended access to the 
Commission's Public Reference Room. For assistance, contact FERC at 
[email protected]">FERCOnline[email protected] or call toll-free, (886) 208-3676 or TTY, 
(202) 502-8659.
    All filings must (1) bear in all capital letters the title 
``COMMENTS,'' ``REPLY COMMENTS,'' ``RECOMMENDATIONS,'' ``TERMS AND 
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the 
name of the applicant and

[[Page 39842]]

the project number of the application to which the filing responds; (3) 
furnish the name, address, and telephone number of the person 
submitting the filing; and (4) otherwise comply with the requirements 
of 18 CFR 385.2001 through 385.2005. All comments, recommendations, 
terms and conditions or prescriptions must set forth their evidentiary 
basis and otherwise comply with the requirements of 18 CFR 4.34(b). 
Agencies may obtain copies of the application directly from the 
applicant. Each filing must be accompanied by proof of service on all 
persons listed on the service list prepared by the Commission in this 
proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. The applicant must file no later than 60 days following the date 
of issuance of this notice: (1) a copy of the water quality 
certification; (2) a copy of the request for certification, including 
proof of the date on which the certifying agency received the request; 
or (3) evidence of waiver of water quality certification. Please note 
that the certification request must comply with 40 CFR 121.5(b), 
including documentation that a pre-filing meeting request was submitted 
to the certifying authority at least 30 days prior to submitting the 
certification request. Please also note that the certification request 
must be sent to the certifying authority and to the Commission 
concurrently.
    o. Procedural schedule: The application will be processed according 
to the following schedule. Revisions to the schedule will be made as 
appropriate.

------------------------------------------------------------------------
                 Milestone                           Target date
------------------------------------------------------------------------
Filing of Comments, Recommendations, Terms  August 2023.
 and Conditions, and Prescriptions.
Filing of Reply Comments..................  September 2023
------------------------------------------------------------------------

    p. The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
environmental justice communities, Tribal members and others, access 
publicly available information and navigate Commission processes. For 
public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, the public is 
encouraged to contact OPP at (202) 502-6595 or [email protected].

    Dated: June 13, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-13079 Filed 6-16-23; 8:45 am]
BILLING CODE 6717-01-P