Village of Enosburg Falls, Vermont; Notice of Authorization for Continued Project Operation, 31504-31505 [2023-10513]
Download as PDF
31504
Federal Register / Vol. 88, No. 95 / Wednesday, May 17, 2023 / Notices
TABLE 2—PROPOSED CHANGES DUE TO FINAL RULE IN DOCKET NO. RD23–1–000—Continued
Reliability standard & requirement
EOP–011–3 11
Type 5 and
number of
entity
Number of
annual
responses
per entity
Total number
of responses
Average number of burden
hours per response 6
Total burden hours
(1)
(2)
(1) * (2) = (3)
(4)
(3) * (4) = (5)
.........................................................
12 (RC) ......
1
12
14 hrs; $908.46 ......................
168 hrs; $10,901.52.
Sub-Total of EOP–011–3 (ongoing) ................
....................
........................
278
................................................
2,828; $183,508.92.
Sub-Total of ongoing burden averaged over
three years.
....................
........................
92.67
(rounded)
................................................
942.67 hrs. (rounded);
$61,169.64.
Proposed Total Burden Estimate of EOP–
011–3.
....................
........................
370.67
................................................
11,946.67 hrs; $775,219.42
(rounded).
TABLE 3—PROPOSED CHANGES DUE TO FINAL RULE IN DOCKET NO. RD23–1–000 FOR EOP–012–1
Reliability standard & requirement
Type and
number of
entity
Number of
annual
responses
per entity
Total number
of responses
Average number of burden
hours per response 12
Total burden hours
(1)
(2)
(1) * (2) = (3)
(4)
(3) * (4) = (5)
FERC–725S
One Time Estimate—Years 1 and 2 EOP–012–1
EOP–012–1 13 .........................................................
EOP–012–1 .............................................................
1,107 (GO)
981 (GOP) ..
1
1
1,107
981
150 hrs.; $9,733.50 ................
10 hrs; $648.90 ......................
166,050 hrs; $10,774,984.50.
9,810 hrs; $636,570.90.
Sub-Total for EOP–012–1 (one-time) ..............
....................
........................
2,088
160 hrs; $10,382.40 ...............
175,860 hrs; $11,411,555.40.
Ongoing Estimate—Year 3 ongoing EOP–012–1
EOP–012–1 .............................................................
EOP–012–1 .............................................................
Sub-Total for EOP–012–1 (ongoing) ...............
1,107 (GO)
981 (GOP) ..
....................
1
1
........................
1,107
981
2,088
40 hrs; $2,595.60 ...................
10 hrs; $648.90 ......................
50 hrs; $ 3,244.50 ..................
40,680 hrs; $2,639,725.20.
9,810 hrs; $ 636,570.90.
50,490 hrs; $ 3,276,296.10.
Sub-Total of ongoing burden averaged over
three years.
....................
........................
696
................................................
16,830 hrs; $1,092,098.70.
Proposed Total Burden Estimate of EOP–
012–1.
....................
........................
2,784
................................................
192,690 hrs; $12,503,654.10.
Comments: Comments are invited on:
(1) whether the collection of
ddrumheller on DSK120RN23PROD with NOTICES1
6 The
estimated hourly cost (salary plus benefits)
is a combination based on the Bureau of Labor
Statistics (BLS), as of 2022, for 75% of the average
of an Electrical Engineer (17–2071)—$77.02,
mechanical engineers (17–2141)—$67.79. $77.02 +
$67.79/2 = 72.405 × .75 = 54.303 ($54.30-rounded)
($54.30/hour) and 25% of an Information and
Record Clerk (43–4199) $42.35 × .25% = 10.5875
($10.59 rounded) ($10.59/hour), for a total ($54.30
+ $10.59 = $64.89/hour).
7 Reduce the estimate for balancing authorities
from EOP–011–2 down from previous 60 hours to
6 hours for EOP–011–3.
8 Reduce the estimate for reliability coordinators
from EOP–011–2 down from previous 40 hours to
28 hours for EOP–011–3.
9 Reduce the estimate for transmission operators
from EOP–011–2 down from previous 50 hours to
10 hours for EOP–011–3.
10 Reduce the estimate for balancing authorities
from EOP–011–2 down from previous 50 hours to
10 hours for EOP–011–3.
11 Reduce the estimate for reliability coordinators
from EOP–011–2 down from previous 20 hours to
14 hours for EOP–011–3.
12 The estimated hourly cost (salary plus benefits)
is a combination based on the Bureau of Labor
Statistics (BLS), as of 2022, for 75% of the average
of an Electrical Engineer (17–2071)—$77.02,
mechanical engineers (17–2141)—$67.79. $77.02 +
$67.79/2 = 72.405 × .75 = 54.303 ($54.30-rounded)
VerDate Sep<11>2014
18:34 May 16, 2023
Jkt 259001
information is necessary for the proper
performance of the functions of the
Commission, including whether the
information will have practical utility;
(2) the accuracy of the agency’s estimate
of the burden and cost of the collection
of information, including the validity of
the methodology and assumptions used;
(3) ways to enhance the quality, utility
and clarity of the information collection;
and (4) ways to minimize the burden of
the collection of information on those
who are to respond, including the use
of automated collection techniques or
other forms of information technology.
Dated: May 11, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–10511 Filed 5–16–23; 8:45 am]
BILLING CODE 6717–01–P
($54.30/hour) and 25% percent of an Information
and Record Clerk (43–4199) $42.35 × .25% =
10.5875 ($10.59 rounded) ($10.59/hour), for a total
($54.30 + $10.59 = $64.89/hour).
13 The estimates for the generator owner and
generator operator are being moved from the current
EOP–011–2 to the new EOP–012–1.
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2905–000]
Village of Enosburg Falls, Vermont;
Notice of Authorization for Continued
Project Operation
The license for the Enosburg Falls
Hydroelectric Project No. 2905 was
issued for a period ending April 30,
2023.
Section 15(a)(1) of the FPA, 16 U.S.C.
808(a)(1), requires the Commission, at
the expiration of a license term, to issue
from year-to-year an annual license to
the then licensee(s) under the terms and
conditions of the prior license until a
new license is issued, or the project is
otherwise disposed of as provided in
section 15 or any other applicable
section of the FPA. If the project’s prior
license waived the applicability of
section 15 of the FPA, then, based on
section 9(b) of the Administrative
Procedure Act, 5 U.S.C. 558(c), and as
set forth at 18 CFR 16.21(a), if the
E:\FR\FM\17MYN1.SGM
17MYN1
Federal Register / Vol. 88, No. 95 / Wednesday, May 17, 2023 / Notices
licensee of such project has filed an
application for a subsequent license, the
licensee may continue to operate the
project in accordance with the terms
and conditions of the license after the
minor or minor part license expires,
until the Commission acts on its
application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 2905
is issued to the Village of Enosburg
Falls, Vermont, for a period effective
May 1, 2023, through April 30, 2024, or
until the issuance of a new license for
the project or other disposition under
the FPA, whichever comes first. If
issuance of a new license (or other
disposition) does not take place on or
before April 30, 2024, notice is hereby
given that, pursuant to 18 CFR 16.18(c),
an annual license under section 15(a)(1)
of the FPA is renewed automatically
without further order or notice by the
Commission, unless the Commission
orders otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that the Village of Enosburg Falls,
Vermont is authorized to continue
operation of the Enosburg Falls
Hydroelectric Project under the terms
and conditions of the prior license until
the issuance of a new license for the
project or other disposition under the
FPA, whichever comes first.
Dated: May 11, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–10513 Filed 5–16–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
ddrumheller on DSK120RN23PROD with NOTICES1
Combined Notice of Filings #1
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG23–152–000.
Applicants: Sun Pond, LLC.
Description: Sun Pond, LLC submits
Notice of Self–Certification of Exempt
Wholesale Generator Status.
Filed Date: 5/11/23.
Accession Number: 20230511–5060.
Comment Date: 5 p.m. ET 6/1/23.
Docket Numbers: EG23–153–000.
VerDate Sep<11>2014
18:34 May 16, 2023
Jkt 259001
Applicants: Oak Lessee, LLC.
Description: Oak Lessee, LLC submits
Notice of Self–Certification of Exempt
Wholesale Generator Status.
Filed Date: 5/11/23.
Accession Number: 20230511–5080.
Comment Date: 5 p.m. ET 6/1/23.
Take notice that the Commission
received the following Complaints and
Compliance filings in EL Dockets:
Docket Numbers: EL23–66–000.
Applicants: Calpine Corporation v.
PJM Interconnection, L.L.C.
Description: Complaint of Calpine
Corporation v. PJM Interconnection,
L.L.C.
Filed Date: 5/10/23.
Accession Number: 20230510–5181.
Comment Date: 5 p.m. ET 6/9/23.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER23–762–002.
Applicants: The Dayton Power and
Light Company, PJM Interconnection,
L.L.C.
Description: Compliance Filing and
Motion to Accept Late Filing of the
Dayton Power and Light Company.
Filed Date: 5/10/23.
Accession Number: 20230510–5178.
Comment Date: 5 p.m. ET 5/31/23.
Docket Numbers: ER23–1123–001.
Applicants: Portland General Electric
Company.
Description: Tariff Amendment:
Response to Deficiency Letter—PGE
OATT Attachment P to be effective 4/
16/2023.
Filed Date: 5/11/23.
Accession Number: 20230511–5108.
Comment Date: 5 p.m. ET 6/1/23.
Docket Numbers: ER23–1418–001.
Applicants: AES WR Limited
Partnership.
Description: Tariff Amendment:
Amendment to Market-Based Rate
Application to be effective 6/1/2023.
Filed Date: 5/11/23.
Accession Number: 20230511–5123.
Comment Date: 5 p.m. ET 6/1/23.
Docket Numbers: ER23–1861–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original IISA and ICSA, Service
Agreement Nos. 6897 and 6898; Queue
No. AF2–120 to be effective 4/11/2023.
Filed Date: 5/11/23.
Accession Number: 20230511–5019.
Comment Date: 5 p.m. ET 6/1/23.
Docket Numbers: ER23–1862–000.
Applicants: Roundhouse Renewable
Energy II, LLC.
Description: Baseline eTariff Filing:
Roundhouse Renewable Energy II, LLC
Application for MBR Authorization to
be effective 7/11/2023.
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
31505
Filed Date: 5/11/23.
Accession Number: 20230511–5043.
Comment Date: 5 p.m. ET 6/1/23.
Docket Numbers: ER23–1863–000.
Applicants: New York Independent
System Operator, Inc.
Description: § 205(d) Rate Filing:
NYISO 205: Transmission Constraint
Pricing Logic Enhancement to be
effective 12/31/9998.
Filed Date: 5/11/23.
Accession Number: 20230511–5051.
Comment Date: 5 p.m. ET 6/1/23.
Docket Numbers: ER23–1864–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original NSA, Service Agreement No.
6883; Queue No. AF1–290 to be
effective 7/11/2023.
Filed Date: 5/11/23.
Accession Number: 20230511–5052.
Comment Date: 5 p.m. ET 6/1/23.
Docket Numbers: ER23–1865–000.
Applicants: PacifiCorp.
Description: Compliance filing:
Compliance Filing of PacifiCorp to
Docket No. EL22–38 to be effective 4/
27/2023.
Filed Date: 5/11/23.
Accession Number: 20230511–5068.
Comment Date: 5 p.m. ET 6/1/23.
Docket Numbers: ER23–1866–000.
Applicants: Southern California
Edison Company.
Description: § 205(d) Rate Filing:
UFA, Centennial Flats with Upstream
HC–1 LLC (TOT899–Q1529/SA300) to
be effective 5/12/2023.
Filed Date: 5/11/23.
Accession Number: 20230511–5078.
Comment Date: 5 p.m. ET 6/1/23.
Docket Numbers: ER23–1867–000.
Applicants: Southern Company
Services, Inc.
Description: Southern Companies
requests waiver from certain Version
003.3 business practice standards of the
North American Energy Standards
Board and incorporated by reference
into Commission Regulations in Order
No. 676–J.
Filed Date: 5/1/23.
Accession Number: 20230501–5596.
Comment Date: 5 p.m. ET 5/22/23.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/fercgen
search.asp) by querying the docket
number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
E:\FR\FM\17MYN1.SGM
17MYN1
Agencies
[Federal Register Volume 88, Number 95 (Wednesday, May 17, 2023)]
[Notices]
[Pages 31504-31505]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-10513]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2905-000]
Village of Enosburg Falls, Vermont; Notice of Authorization for
Continued Project Operation
The license for the Enosburg Falls Hydroelectric Project No. 2905
was issued for a period ending April 30, 2023.
Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the
Commission, at the expiration of a license term, to issue from year-to-
year an annual license to the then licensee(s) under the terms and
conditions of the prior license until a new license is issued, or the
project is otherwise disposed of as provided in section 15 or any other
applicable section of the FPA. If the project's prior license waived
the applicability of section 15 of the FPA, then, based on section 9(b)
of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth
at 18 CFR 16.21(a), if the
[[Page 31505]]
licensee of such project has filed an application for a subsequent
license, the licensee may continue to operate the project in accordance
with the terms and conditions of the license after the minor or minor
part license expires, until the Commission acts on its application. If
the licensee of such a project has not filed an application for a
subsequent license, then it may be required, pursuant to 18 CFR
16.21(b), to continue project operations until the Commission issues
someone else a license for the project or otherwise orders disposition
of the project.
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 2905 is issued to
the Village of Enosburg Falls, Vermont, for a period effective May 1,
2023, through April 30, 2024, or until the issuance of a new license
for the project or other disposition under the FPA, whichever comes
first. If issuance of a new license (or other disposition) does not
take place on or before April 30, 2024, notice is hereby given that,
pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1)
of the FPA is renewed automatically without further order or notice by
the Commission, unless the Commission orders otherwise.
If the project is not subject to section 15 of the FPA, notice is
hereby given that the Village of Enosburg Falls, Vermont is authorized
to continue operation of the Enosburg Falls Hydroelectric Project under
the terms and conditions of the prior license until the issuance of a
new license for the project or other disposition under the FPA,
whichever comes first.
Dated: May 11, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023-10513 Filed 5-16-23; 8:45 am]