Tivis Branch Hydro, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 31262-31263 [2023-10382]
Download as PDF
lotter on DSK11XQN23PROD with NOTICES1
31262
Federal Register / Vol. 88, No. 94 / Tuesday, May 16, 2023 / Notices
foot-wide fixed wheel gates and a log
chute; (2) the 235-surface-acre Gorge
Lake with a gross storage capacity of
8,200 acre-feet at normal maximum
water surface elevation of 881.5 feet; (3)
a bifurcated intake structure with two
20-foot-wide, 88.9-foot-long openings
and trashracks; (4) a 20.5-foot-diameter,
11,000-foot-long concrete-lined power
tunnel; (5) three 10-foot-diameter
penstocks and one 15-foot-diameter
penstock, each 1,600 feet long and each
fitted with a 10-foot-diameter butterfly
biplane and relief valves; (6) a surge
tank; (7) a powerhouse containing four
generating units with a total authorized
installed capacity of 189.3 MW; (8) a
switchyard; (9) a 230-kV, 36.8-mile-long
transmission line extending from Gorge
Switchyard to North Mountain
Substation; and (10) appurtenant
facilities.
The three project developments are
hydraulically coordinated to operate as
a single project. Project operation under
the existing license is designed to meet
four objectives, which are prioritized as
follows: (1) flood control, (2) salmon
and steelhead protection flows
downstream of Gorge Powerhouse, (3)
recreation, and (4) power generation. To
achieve these goals, City Light adheres
to specific license requirements for Ross
Lake levels and for stream flows and
ramping rates downstream of Gorge
Powerhouse.
Under existing operations, Ross Lake
is drawn down on a yearly basis during
winter to capture flows from spring
runoff and to provide for downstream
flood control. The drawdown typically
begins after Labor Day and continues
until the lake reaches its lowest level in
late March or early April. The current
license requires City Light to draw
down Ross Lake to a level that provides
60,000 acre-feet of storage for flood
control by November 15 and 120,000
acre-feet by December 1 and to maintain
this available storage through March 15.
Ross Lake levels are also managed to
meet recreational needs during the
summer months. The current license
requires City Light to fill Ross Lake as
soon as possible after April 15, achieve
full pool depth by July 31, and maintain
full pool depth through Labor Day.
The Diablo Development is operated
to regulate flow between the Ross and
Gorge Developments. Under normal
operation, Diablo Lake typically
fluctuates between 4 and 5 feet per day.
The Ross Powerhouse and Diablo
Powerhouse are typically operated
continuously to pass flow downstream,
although generation is occasionally
increased or decreased for short periods
to help meet load-following demand or
other project purposes.
VerDate Sep<11>2014
17:33 May 15, 2023
Jkt 259001
The Gorge Development is operated
primarily to provide a continuous,
stable flow regime in the upper Skagit
River for salmon and steelhead
protection. City Light typically limits
Gorge Lake fluctuations to about 3 to 5
feet and does not typically operate the
powerhouse to meet load-following
demand. The Gorge Development
creates a 2.5-mile-long bypassed reach
of the Skagit River between the dam and
powerhouse. There are no minimum
flow requirements in the existing
license for the Gorge bypassed reach.
Therefore, except during spill events at
Gorge Dam, bypassed reach flow is
limited to accretion flow, spill-gate
seepage, tributary input, and
precipitation runoff.
l. In addition to publishing the full
text of this notice in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
notice, as well as other documents in
the proceeding (e.g., license application)
via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document (P–553).
For assistance, contact FERC at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). At this time, the Commission has
suspended access to the Commission’s
Public Reference Room. For assistance,
contact FERC at FERCOnlineSupport@
ferc.gov or call toll free, (886) 208–3676
or TTY (202) 502–8659.
m. You may also register online at
https://ferconline.ferc.gov/FERCOnline.
aspx to be notified via email of new
filings and issuances related to this or
other pending projects. For assistance,
contact FERC Online Support.
n. Procedural Schedule:
The application will be processed
according to the following preliminary
Hydro Licensing Schedule. Revisions to
the schedule may be made as
appropriate.
Milestone
Target Date
City Light files final study report for Study CR–04 Properties with Traditional Cultural Significance Study 1.
Notice of Acceptance/Notice
of Ready for Environmental
Analysis.
PO 00000
Frm 00045
Fmt 4703
March 2024.
April 2024.
Sfmt 4703
Milestone
Filing of recommendations,
preliminary terms and conditions, and fishway prescriptions.
Target Date
June 2024.
1 City Light indicates in section 4.2.9.1 of
the Final License Application Exhibit E that the
study results for this Commission staff-approved study would be filed in the first quarter
of 2024.
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: May 9, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–10357 Filed 5–15–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 15296–000]
Tivis Branch Hydro, LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On January 3, 2023, Tivis Branch
Hydro, LLC, filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act (FPA),
proposing to study the feasibility of the
Flannagan Hydroelectric Project to be
located at the U.S. Army Corps of
Engineers’ (Corps) Huntington District
John W. Flannagan Dam on the Pound
River in Dickenson County, Virginia.
The sole purpose of a preliminary
permit, if issued, is to grant the permit
holder priority to file a license
application during the permit term. A
preliminary permit does not authorize
the permit holder to perform any landdisturbing activities or otherwise enter
upon lands or waters owned by others
without the owners’ express permission.
The proposed project would consist of
the following: (1) new four 0.36megawatt (MW) turbine-generator units
to be placed inside the Corps’ intake
tower with a total installed capacity of
1.44 MW; (2) a new 40-foot-long, 40foot-wide operating space inside the
Corps’ intake tower; (3) a new 300-footlong conduit attached to the access
bridge (which provides access to the
Corps’ intake tower); (4) a new 15-footlong, 15-foot-wide substation pad
including a 4.16/12.47-kilovolt (kV)
step-up transformer; (5) a new 300-footlong, 4.16-kV generator lead to the
E:\FR\FM\16MYN1.SGM
16MYN1
lotter on DSK11XQN23PROD with NOTICES1
Federal Register / Vol. 88, No. 94 / Tuesday, May 16, 2023 / Notices
substation pad; (6) a 30-foot-long, 12.47kV transmission line connecting the
substation pad to the existing 12.47-kV
Appalachian Power Company’s
distribution line; and (7) appurtenant
facilities. The proposed project would
have an annual generation of 8,000
megawatt-hours.
Applicant Contact: Ryan A. Cook,
Tivis Branch Hydro, LLC, 5 Dover
Street, Suite 102, New Bedford, MA
02740; phone: (508) 436–4100.
FERC Contact: Woohee Choi; email:
woohee.choi@ferc.gov; phone: (202)
502–6336.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
ferconline.ferc.gov/eFiling.aspx.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://ferconline.ferc.gov/
QuickComment.aspx. You must include
your name and contact information at
the end of your comments. For
assistance, please contact FERC Online
Support. In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. The first
page of any filing should include docket
number P–15296–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of the Commission’s website at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–15296) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Dated: May 10, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–10382 Filed 5–15–23; 8:45 am]
BILLING CODE 6717–01–P
VerDate Sep<11>2014
17:33 May 15, 2023
Jkt 259001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 15299–000]
LinkPast Solutions, Inc.; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On January 25, 2023, LinkPast
Solutions, Inc., filed an application for
a preliminary permit, pursuant to
section 4(f) of the Federal Power Act
(FPA), proposing to study the feasibility
of hydropower on the Black River in
Jefferson County, New York. The sole
purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The proposed Great Mills Hydro
Project (Plant #2) would consist of the
following: (1) a new 1,850-foot-long dam
(a mix of concrete gravity dam, earthen
dike, and wing walls) at the site of an
existing breached dam; (2) an
impoundment with an approximate
surface area of 140 acres and a storage
capacity of 850 acre-feet at a normal
pool elevation of 589.90 feet National
Geodetic Vertical Datum of 1929; (4) a
new 90-foot-long by 65-foot-wide
reinforced concrete powerhouse
housing two or more axial flow vertical
turbine-generator units with a total
installed capacity of 8 megawatts; (5)
additional new DIVE-turbine-generator
(generator directly connected to the
turbine shaft that can be completely
submerged) units to utilize flows below
the minimum or above the maximum
hydraulic capacities of the main
powerhouse; (6) a new 50-foot-long by
50-foot-wide switchyard; (7) two new
access roads, one on the north and the
other on the south shores of the river;
(8) a new 0.69-mile-long, 115-kilovolt
transmission line; and (9) appurtenant
facilities. The proposed project would
have an average annual generation of
40,000 megawatt-hours.
Applicant Contact: Brian McArthur,
LinkPast Solutions, Inc., P.O. Box 5474,
Clark, New Jersey 07066; phone: (848)
628–4414.
FERC Contact: Monir Chowdhury;
phone: (202) 502–6736.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
PO 00000
Frm 00046
Fmt 4703
Sfmt 4703
31263
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
ferconline.ferc.gov/FERCOnline.aspx.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://ferconline.ferc.gov/
QuickComment.aspx. You must include
your name and contact information at
the end of your comments. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, you may submit a
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of the Commission’s website at
https://elibrary.ferc.gov/eLibrary/search.
Enter the docket number (P–15299) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
Dated: May 9, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–10355 Filed 5–15–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. RM98–1–000]
Records Governing Off-the-Record
Communications; Public Notice
This constitutes notice, in accordance
with 18 CFR 385.2201(b), of the receipt
of prohibited and exempt off-the-record
communications.
Order No. 607 (64 FR 51222,
September 22, 1999) requires
Commission decisional employees, who
make or receive a prohibited or exempt
off-the-record communication relevant
to the merits of a contested proceeding,
E:\FR\FM\16MYN1.SGM
16MYN1
Agencies
[Federal Register Volume 88, Number 94 (Tuesday, May 16, 2023)]
[Notices]
[Pages 31262-31263]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-10382]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 15296-000]
Tivis Branch Hydro, LLC; Notice of Preliminary Permit Application
Accepted for Filing and Soliciting Comments, Motions To Intervene, and
Competing Applications
On January 3, 2023, Tivis Branch Hydro, LLC, filed an application
for a preliminary permit, pursuant to section 4(f) of the Federal Power
Act (FPA), proposing to study the feasibility of the Flannagan
Hydroelectric Project to be located at the U.S. Army Corps of
Engineers' (Corps) Huntington District John W. Flannagan Dam on the
Pound River in Dickenson County, Virginia. The sole purpose of a
preliminary permit, if issued, is to grant the permit holder priority
to file a license application during the permit term. A preliminary
permit does not authorize the permit holder to perform any land-
disturbing activities or otherwise enter upon lands or waters owned by
others without the owners' express permission.
The proposed project would consist of the following: (1) new four
0.36-megawatt (MW) turbine-generator units to be placed inside the
Corps' intake tower with a total installed capacity of 1.44 MW; (2) a
new 40-foot-long, 40-foot-wide operating space inside the Corps' intake
tower; (3) a new 300-foot-long conduit attached to the access bridge
(which provides access to the Corps' intake tower); (4) a new 15-foot-
long, 15-foot-wide substation pad including a 4.16/12.47-kilovolt (kV)
step-up transformer; (5) a new 300-foot-long, 4.16-kV generator lead to
the
[[Page 31263]]
substation pad; (6) a 30-foot-long, 12.47-kV transmission line
connecting the substation pad to the existing 12.47-kV Appalachian
Power Company's distribution line; and (7) appurtenant facilities. The
proposed project would have an annual generation of 8,000 megawatt-
hours.
Applicant Contact: Ryan A. Cook, Tivis Branch Hydro, LLC, 5 Dover
Street, Suite 102, New Bedford, MA 02740; phone: (508) 436-4100.
FERC Contact: Woohee Choi; email: [email protected]; phone:
(202) 502-6336.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36.
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, notices of intent, and competing
applications using the Commission's eFiling system at https://ferconline.ferc.gov/eFiling.aspx. Commenters can submit brief comments
up to 6,000 characters, without prior registration, using the eComment
system at https://ferconline.ferc.gov/QuickComment.aspx. You must
include your name and contact information at the end of your comments.
For assistance, please contact FERC Online Support. In lieu of
electronic filing, you may submit a paper copy. Submissions sent via
the U.S. Postal Service must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street NE,
Room 1A, Washington, DC 20426. Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852.
The first page of any filing should include docket number P-15296-000.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of the
Commission's website at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-15296) in the docket number field to access
the document. For assistance, contact FERC Online Support.
Dated: May 10, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-10382 Filed 5-15-23; 8:45 am]
BILLING CODE 6717-01-P