Protests and motions to intervene
must be served on the applicant either
by mail at: David A. Alonzo, Manager,
Project Authorizations, Columbia Gas
Transmission, LLC, 700 Louisiana
Street, Suite 1300, Houston, Texas
77002–2700 or at david_alonzo@
tcenergy.com. Any subsequent
submissions by an intervenor must be
served on the applicant and all other
parties to the proceeding. Contact
information for parties can be
downloaded from the service list at the
eService link on FERC Online. Service
can be via email with a link to the
document.
All timely, unopposed 7 motions to
intervene are automatically granted by
operation of Rule 214(c)(1).8 Motions to
intervene that are filed after the
intervention deadline are untimely, and
may be denied. Any late-filed motion to
intervene must show good cause for
being late and must explain why the
time limitation should be waived and
provide justification by reference to
factors set forth in Rule 214(d) of the
Commission’s Rules and Regulations.9
A person obtaining party status will be
placed on the service list maintained by
the Secretary of the Commission and
will receive copies (paper or electronic)
of all documents filed by the applicant
and by all other parties.
Tracking the Proceeding
Throughout the proceeding,
additional information about the project
will be available from the Commission’s
Office of External Affairs, at (866) 208–
FERC, or on the FERC website at
www.ferc.gov using the ‘‘eLibrary’’ link
as described above. The eLibrary link
also provides access to the texts of all
formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. For more information and to
register, go to www.ferc.gov/docs-filing/
esubscription.asp.
Intervention Deadline: 5:00 p.m.
Eastern Time on May 26, 2023.
7 The applicant has 15 days from the submittal of
a motion to intervene to file a written objection to
the intervention.
8 18 CFR 385.214(c)(1).
9 18 CFR 385.214(b)(3) and (d).
VerDate Sep<11>2014
17:07 May 10, 2023
Jkt 259001
Dated: May 5, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–10061 Filed 5–10–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG23–144–000.
Applicants: Clearwater Wind II, LLC.
Description: Clearwater Wind II, LLC
submits Notice of Self-Certification of
Exempt Wholesale Generator Status.
Filed Date: 5/5/23.
Accession Number: 20230505–5056.
Comment Date: 5 p.m. ET 5/26/23.
Docket Numbers: EG23–145–000.
Applicants: Johnson County Power,
LLC.
Description: Johnson County Power,
LLC submits Notice of Self-Certification
of Exempt Wholesale Generator Status.
Filed Date:5/5/23.
Accession Number: 20230505–5066.
Comment Date: 5 p.m. ET 5/26/23.
Docket Numbers: EG23–146–000.
Applicants: RW Miller Power, LLC.
Description: RW Miller Power, LLC
submits Notice of Self-Certification of
Exempt Wholesale Generator Status.
Filed Date: 5/5/23.
Accession Number: 20230505–5067.
Comment Date: 5 p.m. ET 5/26/23.
Docket Numbers: EG23–147–000.
Applicants: Jack County Power, LLC
Description: Jack County Power, LLC
submits Notice of Self-Certification of
Exempt Wholesale Generator Status.
Filed Date: 5/5/23.
Accession Number: 20230505–5069.
Comment Date: 5 p.m. ET 5/26/23.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–2042–044;
ER10–1862–038; ER10–1873–018;
ER10–1875–018; ER10–1876–019;
ER10–1878–018; ER10–1883–018;
ER10–1884–018; ER10–1885–018;
ER10–1888–018; ER10–1893–038;
ER10–1934–038; ER10–1938–039;
ER10–1941–018; ER10–1942–036;
ER10–1947–019; ER10–2985–042;
ER10–3049–043; ER10–3051–043;
ER11–4369–023; ER12–1987–016;
ER12–2261–017; ER12–2645–011;
ER16–2218–024; ER17–696–024; ER19–
1127–008; ER20–1699–006; ER23–944–
002.
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
Applicants: Calpine Community
Energy, LLC, Johanna Energy Center,
LLC, Calpine King City Cogen, LLC,
Calpine Energy Solutions, LLC, North
American Power Business, LLC, Pastoria
Energy Facility L.L.C., Russell City
Energy Company, LLC, O.L.S. EnergyAgnews, Inc., North American Power
and Gas, LLC, Champion Energy, LLC,
Champion Energy Services, LLC,
Champion Energy Marketing LLC, Otay
Mesa Energy Center, LLC, Calpine
Construction Finance Co., L.P., Calpine
Gilroy Cogen, L.P., Calpine Power
America—CA, LLC, CES Marketing IX,
LLC, CES Marketing X, LLC, Creed
Energy Center, LLC, Delta Energy
Center, LLC, Geysers Power Company,
LLC, Gilroy Energy Center, LLC, Goose
Haven Energy Center, LLC, Los Esteros
Critical Energy Facility, LLC, Los
Medanos Energy Center LLC, Metcalf
Energy Center, LLC, Power Contract
Financing, L.L.C., Calpine Energy
Services, L.P.
Description: Notice of Change in
Status of Calpine Energy Services, L.P.,
et al.
Filed Date: 5/1/23.
Accession Number: 20230501–5586.
Comment Date: 5 p.m. ET 5/22/23.
Docket Numbers: ER10–2294–008;
ER11–3808–007; ER11–3980–007;
ER13–413–008; ER13–534–007; ER13–
2103–005; ER13–2414–004; ER15–2330–
004; ER16–131–004; ER20–2696–001;
ER17–737–001; ER17–2471–005; ER17–
2472–005; ER18–301–004; ER18–664–
005; ER22–645–001; ER18–2214–002;
ER18–2216–002; ER18–2435–004;
ER19–1047–003; ER20–2977–001;
ER22–1882–002; ER22–2178–002;
ER22–2799–001; ER22–2800–001;
ER22–2801–001.
Applicants: VESI 25 LLC, VESI 24
LLC, VESI 21 LLC, ORNI 50 LLC, VESI
10 LLC, ORNI 34 LLC, VESIVEC LLC,
ORNI 41 LLC, Plumsted 537 LLC,
Stryker 22, LLC, Ormat Dixie Valley
LLC, Steamboat Hills LLC, Ormesa LLC,
ONGP LLC, ORNI 43 LLC, Viridity
Energy Solutions Inc., VESI Pomona
Energy Storage, Inc., Heber Geothermal
Company LLC, ORNI 37 LLC, Mammoth
Three LLC, ORNI 47 LLC, Mammoth
One LLC, USG Oregon LLC, ORNI 14
LLC, ORNI 39 LLC, ORNI 18 LLC.
Description: Notice of Change in
Status of ORNI 18 LLC, et al.
Filed Date: 5/2/23.
Accession Number: 20230502–5280.
Comment Date: 5 p.m. ET 5/23/23.
Docket Numbers: ER10–2381–013;
ER11–2206–014; ER11–2207–014;
ER11–2209–014; ER11–2210–014;
ER11–2211–014; ER11–2855–028;
ER11–2856–028; ER11–2857–028;
ER11–3727–020; ER12–21–026; ER12–
E:\FR\FM\11MYN1.SGM
11MYN1
ddrumheller on DSK120RN23PROD with NOTICES1
Federal Register / Vol. 88, No. 91 / Thursday, May 11, 2023 / Notices
1711–020; ER13–1150–012; ER13–1151–
012; ER13–1991–027; ER13–1992–027;
ER18–814–005; ER19–672–005; ER19–
843–005; ER19–1061–005; ER19–1063–
005; ER19–1200–008; ER20–486–005.
Applicants: Golden Fields Solar III,
LLC, Clearway Power Marketing LLC,
Solar Borrego I LLC, Solar Alpine LLC,
Solar Blythe LLC, Marsh Landing LLC,
Carlsbad Energy Center LLC, Desert
Sunlight 300, LLC, Desert Sunlight 300,
LLC, Alta Wind XI, LLC, Alta Wind X,
LLC, High Plains Ranch II, LLC, Agua
Caliente Solar, LLC, El Segundo Energy
Center LLC, Sun City Project LLC, Sand
Drag LLC, Avenal Park LLC, Alta Wind
I, LLC, Alta Wind III, LLC, Alta Wind II,
LLC, Alta Wind IV, LLC, Alta Wind V,
LLC, Walnut Creek Energy, LLC.
Description: Supplement to March 3,
2023, Notice of Change in Status of
Agua Caliente Solar, LLC, et al.
Filed Date: 5/2/23.
Accession Number: 20230502–5279.
Comment Date: 5 p.m. ET 5/23/23.
Docket Numbers: ER21–2382–000.
Applicants: Shell Energy North
America (US), L.P.
Description: Refund Report: Refund
Report to be effective N/A.
Filed Date: 5/5/23.
Accession Number: 20230505–5182.
Comment Date: 5 p.m. ET 5/26/23.
Docket Numbers: ER23–643–002.
Applicants: PJM Interconnection,
L.L.C.
Description: Tariff Amendment:
Amendment to ISA, SA No. 5596;
Queue No. AD1–020 to be effective 2/
15/2023.
Filed Date: 5/5/23
Accession Number: 20230505–5136
Comment Date: 5 p.m. ET 5/26/23.
Docket Numbers: ER23–1832–000.
Applicants: Homer City Generation,
L.P.
Description: Tariff Amendment:
Notice of Cancellation of Reactive
Service Tariff to be effective 12/31/9998.
Filed Date: 5/4/23.
Accession Number: 20230504–5129
Comment Date: 5 p.m. ET 5/25/23.
Docket Numbers: ER23–1833–000.
Applicants: Bio Energy (Ohio II), LLC.
Description: Tariff Amendment: Bio
Energy (Ohio II), LLC Notice of MBR
Cancellation to be effective 5/4/2023.
Filed Date: 5/4/23.
Accession Number: 20230504–5130.
Comment Date: 5 p.m. ET 5/25/23.
Docket Numbers: ER23–1834–000.
Applicants: Duke Energy Carolinas,
LLC.
Description: § 205(d) Rate Filing:
DEC–NCEMC NITSA SA No. 210 (2023)
to be effective 5/1/2023.
Filed Date: 5/4/23.
Accession Number: 20230504–5151.
VerDate Sep<11>2014
17:07 May 10, 2023
Jkt 259001
Comment Date: 5 p.m. ET 5/25/23.
DEPARTMENT OF ENERGY
Docket Numbers: ER23–1835–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original ISA, SA No. 6899 and CSA, SA
No. 6900; Queue No. AD2–091 to be
effective 4/5/2023.
Filed Date: 5/5/23.
Accession Number: 20230505–5078.
Comment Date: 5 p.m. ET 5/26/23.
Federal Energy Regulatory
Commission
Docket Numbers: ER23–1836–000.
Applicants: Alabama Power
Company, Georgia Power Company,
Mississippi Power Company.
Description: § 205(d) Rate Filing:
Alabama Power Company submits tariff
filing per 35.13(a)(2)(iii: Evergreen PV1
LGIA Filing to be effective 4/21/2023.
Filed Date: 5/5/23.
Accession Number: 20230505–5115.
Comment Date: 5 p.m. ET 5/26/23.
Docket Numbers: ER23–1837–000
Applicants: PacifiCorp
Description: § 205(d) Rate Filing:
Provisional Large Generator
Interconnection Agreement to be
effective 5/6/2023.
Filed Date: 5/5/23.
Accession Number: 20230505–5124.
Comment Date: 5 p.m. ET 5/26/23.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: May 5, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–10066 Filed 5–10–23; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
30303
[Project No. 3071–008]
Blue Earth County; Notice of
Application for Surrender of
Exemption, Soliciting Comments,
Motions To Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Application for
surrender of exemption.
b. Project No.: P–3071–008.
c. Date Filed: April 14, 2023.
d. Applicant: Blue Earth County.
e. Name of Project: Rapidan Dam
Hydroelectric Project.
f. Location: The project is located on
the Blue Earth River, in Blue Earth
County, approximately 10 miles south
of Mankato, Minnesota. The project
does not occupy any federal lands.
g. Filed Pursuant to: Public Utility
Regulatory Policies Act of 1978, 16
U.S.C. 2705, 2708.
h. Applicant Contact: Ryan Thilges,
P.E., Public Works Director, Blue Earth
County, 35 Map Drive, P.O. Box 3083,
Mankato, MN 56002–3083. Phone (507)
304–4031 or ryan.thilges@
blueearthcountymn.gov.
i. FERC Contact: Diana Shannon,
(202) 502–6136, diana.shannon@
ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests: June
5, 2023.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, and protests using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
E:\FR\FM\11MYN1.SGM
11MYN1
Agencies
[Federal Register Volume 88, Number 91 (Thursday, May 11, 2023)]
[Notices]
[Pages 30302-30303]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-10066]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #1
Take notice that the Commission received the following exempt
wholesale generator filings:
Docket Numbers: EG23-144-000.
Applicants: Clearwater Wind II, LLC.
Description: Clearwater Wind II, LLC submits Notice of Self-
Certification of Exempt Wholesale Generator Status.
Filed Date: 5/5/23.
Accession Number: 20230505-5056.
Comment Date: 5 p.m. ET 5/26/23.
Docket Numbers: EG23-145-000.
Applicants: Johnson County Power, LLC.
Description: Johnson County Power, LLC submits Notice of Self-
Certification of Exempt Wholesale Generator Status.
Filed Date:5/5/23.
Accession Number: 20230505-5066.
Comment Date: 5 p.m. ET 5/26/23.
Docket Numbers: EG23-146-000.
Applicants: RW Miller Power, LLC.
Description: RW Miller Power, LLC submits Notice of Self-
Certification of Exempt Wholesale Generator Status.
Filed Date: 5/5/23.
Accession Number: 20230505-5067.
Comment Date: 5 p.m. ET 5/26/23.
Docket Numbers: EG23-147-000.
Applicants: Jack County Power, LLC
Description: Jack County Power, LLC submits Notice of Self-
Certification of Exempt Wholesale Generator Status.
Filed Date: 5/5/23.
Accession Number: 20230505-5069.
Comment Date: 5 p.m. ET 5/26/23.
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER10-2042-044; ER10-1862-038; ER10-1873-018; ER10-
1875-018; ER10-1876-019; ER10-1878-018; ER10-1883-018; ER10-1884-018;
ER10-1885-018; ER10-1888-018; ER10-1893-038; ER10-1934-038; ER10-1938-
039; ER10-1941-018; ER10-1942-036; ER10-1947-019; ER10-2985-042; ER10-
3049-043; ER10-3051-043; ER11-4369-023; ER12-1987-016; ER12-2261-017;
ER12-2645-011; ER16-2218-024; ER17-696-024; ER19-1127-008; ER20-1699-
006; ER23-944-002.
Applicants: Calpine Community Energy, LLC, Johanna Energy Center,
LLC, Calpine King City Cogen, LLC, Calpine Energy Solutions, LLC, North
American Power Business, LLC, Pastoria Energy Facility L.L.C., Russell
City Energy Company, LLC, O.L.S. Energy-Agnews, Inc., North American
Power and Gas, LLC, Champion Energy, LLC, Champion Energy Services,
LLC, Champion Energy Marketing LLC, Otay Mesa Energy Center, LLC,
Calpine Construction Finance Co., L.P., Calpine Gilroy Cogen, L.P.,
Calpine Power America--CA, LLC, CES Marketing IX, LLC, CES Marketing X,
LLC, Creed Energy Center, LLC, Delta Energy Center, LLC, Geysers Power
Company, LLC, Gilroy Energy Center, LLC, Goose Haven Energy Center,
LLC, Los Esteros Critical Energy Facility, LLC, Los Medanos Energy
Center LLC, Metcalf Energy Center, LLC, Power Contract Financing,
L.L.C., Calpine Energy Services, L.P.
Description: Notice of Change in Status of Calpine Energy Services,
L.P., et al.
Filed Date: 5/1/23.
Accession Number: 20230501-5586.
Comment Date: 5 p.m. ET 5/22/23.
Docket Numbers: ER10-2294-008; ER11-3808-007; ER11-3980-007; ER13-
413-008; ER13-534-007; ER13-2103-005; ER13-2414-004; ER15-2330-004;
ER16-131-004; ER20-2696-001; ER17-737-001; ER17-2471-005; ER17-2472-
005; ER18-301-004; ER18-664-005; ER22-645-001; ER18-2214-002; ER18-
2216-002; ER18-2435-004; ER19-1047-003; ER20-2977-001; ER22-1882-002;
ER22-2178-002; ER22-2799-001; ER22-2800-001; ER22-2801-001.
Applicants: VESI 25 LLC, VESI 24 LLC, VESI 21 LLC, ORNI 50 LLC,
VESI 10 LLC, ORNI 34 LLC, VESIVEC LLC, ORNI 41 LLC, Plumsted 537 LLC,
Stryker 22, LLC, Ormat Dixie Valley LLC, Steamboat Hills LLC, Ormesa
LLC, ONGP LLC, ORNI 43 LLC, Viridity Energy Solutions Inc., VESI Pomona
Energy Storage, Inc., Heber Geothermal Company LLC, ORNI 37 LLC,
Mammoth Three LLC, ORNI 47 LLC, Mammoth One LLC, USG Oregon LLC, ORNI
14 LLC, ORNI 39 LLC, ORNI 18 LLC.
Description: Notice of Change in Status of ORNI 18 LLC, et al.
Filed Date: 5/2/23.
Accession Number: 20230502-5280.
Comment Date: 5 p.m. ET 5/23/23.
Docket Numbers: ER10-2381-013; ER11-2206-014; ER11-2207-014; ER11-
2209-014; ER11-2210-014; ER11-2211-014; ER11-2855-028; ER11-2856-028;
ER11-2857-028; ER11-3727-020; ER12-21-026; ER12-
[[Page 30303]]
1711-020; ER13-1150-012; ER13-1151-012; ER13-1991-027; ER13-1992-027;
ER18-814-005; ER19-672-005; ER19-843-005; ER19-1061-005; ER19-1063-005;
ER19-1200-008; ER20-486-005.
Applicants: Golden Fields Solar III, LLC, Clearway Power Marketing
LLC, Solar Borrego I LLC, Solar Alpine LLC, Solar Blythe LLC, Marsh
Landing LLC, Carlsbad Energy Center LLC, Desert Sunlight 300, LLC,
Desert Sunlight 300, LLC, Alta Wind XI, LLC, Alta Wind X, LLC, High
Plains Ranch II, LLC, Agua Caliente Solar, LLC, El Segundo Energy
Center LLC, Sun City Project LLC, Sand Drag LLC, Avenal Park LLC, Alta
Wind I, LLC, Alta Wind III, LLC, Alta Wind II, LLC, Alta Wind IV, LLC,
Alta Wind V, LLC, Walnut Creek Energy, LLC.
Description: Supplement to March 3, 2023, Notice of Change in
Status of Agua Caliente Solar, LLC, et al.
Filed Date: 5/2/23.
Accession Number: 20230502-5279.
Comment Date: 5 p.m. ET 5/23/23.
Docket Numbers: ER21-2382-000.
Applicants: Shell Energy North America (US), L.P.
Description: Refund Report: Refund Report to be effective N/A.
Filed Date: 5/5/23.
Accession Number: 20230505-5182.
Comment Date: 5 p.m. ET 5/26/23.
Docket Numbers: ER23-643-002.
Applicants: PJM Interconnection, L.L.C.
Description: Tariff Amendment: Amendment to ISA, SA No. 5596; Queue
No. AD1-020 to be effective 2/15/2023.
Filed Date: 5/5/23
Accession Number: 20230505-5136
Comment Date: 5 p.m. ET 5/26/23.
Docket Numbers: ER23-1832-000.
Applicants: Homer City Generation, L.P.
Description: Tariff Amendment: Notice of Cancellation of Reactive
Service Tariff to be effective 12/31/9998.
Filed Date: 5/4/23.
Accession Number: 20230504-5129
Comment Date: 5 p.m. ET 5/25/23.
Docket Numbers: ER23-1833-000.
Applicants: Bio Energy (Ohio II), LLC.
Description: Tariff Amendment: Bio Energy (Ohio II), LLC Notice of
MBR Cancellation to be effective 5/4/2023.
Filed Date: 5/4/23.
Accession Number: 20230504-5130.
Comment Date: 5 p.m. ET 5/25/23.
Docket Numbers: ER23-1834-000.
Applicants: Duke Energy Carolinas, LLC.
Description: Sec. 205(d) Rate Filing: DEC-NCEMC NITSA SA No. 210
(2023) to be effective 5/1/2023.
Filed Date: 5/4/23.
Accession Number: 20230504-5151.
Comment Date: 5 p.m. ET 5/25/23.
Docket Numbers: ER23-1835-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: Original ISA, SA No. 6899
and CSA, SA No. 6900; Queue No. AD2-091 to be effective 4/5/2023.
Filed Date: 5/5/23.
Accession Number: 20230505-5078.
Comment Date: 5 p.m. ET 5/26/23.
Docket Numbers: ER23-1836-000.
Applicants: Alabama Power Company, Georgia Power Company,
Mississippi Power Company.
Description: Sec. 205(d) Rate Filing: Alabama Power Company
submits tariff filing per 35.13(a)(2)(iii: Evergreen PV1 LGIA Filing to
be effective 4/21/2023.
Filed Date: 5/5/23.
Accession Number: 20230505-5115.
Comment Date: 5 p.m. ET 5/26/23.
Docket Numbers: ER23-1837-000
Applicants: PacifiCorp
Description: Sec. 205(d) Rate Filing: Provisional Large Generator
Interconnection Agreement to be effective 5/6/2023.
Filed Date: 5/5/23.
Accession Number: 20230505-5124.
Comment Date: 5 p.m. ET 5/26/23.
The filings are accessible in the Commission's eLibrary system
(https://elibrary.ferc.gov/idmws/search/fercgensearch.asp) by querying
the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: May 5, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-10066 Filed 5-10-23; 8:45 am]
BILLING CODE 6717-01-P