Union Falls Hydropower, L.P.; Notice Soliciting Scoping Comments, 30306-30307 [2023-10058]
Download as PDF
ddrumheller on DSK120RN23PROD with NOTICES1
30306
Federal Register / Vol. 88, No. 91 / Thursday, May 11, 2023 / Notices
foot-long, 2.3-kilovolt (kV) generator
leads; (8) a 2.3/46-kV step-up
transformer bank; (9) a 300-foot-long,
46-kV transmission line; (10) a tailrace;
and (11) appurtenant facilities.
The Franklin Falls Project operates in
a modified run-of-river mode. If inflow
exceeds the hydraulic capacity of the
units, the project operates continuously
at full load. When the inflow is less than
the hydraulic capacity of the project, the
project is operated in a run-of-river
mode utilizing pondage as needed for
daily flow regulation and to suit power
requirements of the New York
Independent System Operator. The
project has an average annual generation
of 10,349 megawatt-hours.
Erie does not propose changes to
project facilities or operation. Erie
proposes to continue to: (1) provide a
minimum base flow of 245 cubic feet
per second (cfs) or inflow, whichever is
less, from March 1 through June 1 from
the Franklin Falls powerhouse; and
from June 2 to March 1 reservoir inflow
is released from the powerhouse, as
needed for the downstream Saranac
Project No. 4472 to maintain a
minimum base flow of 165 cfs, or
inflow, whichever is less; (2) limit the
maximum total drawdown of the
Franklin Falls impoundment to 2 feet
below the top of the flashboards, or 1
foot below the spillway crest when
flashboards are not in use (Erie annually
installs flashboards at Franklin Falls by
the first week of June, unless flow
conditions warrant otherwise); (3)
provide a minimum flow to the
bypassed reach of 125 cfs or inflow,
whichever is less, from March 31
through May 31 for the protection of
walleye spawning and incubation (the
release schedule may be modified on a
year-to-year basis based on water
temperatures and the presence/absence
of walleye, upon mutual agreement
between Erie and the New York State
Department of Environmental
Conservation); and (4) operate and
maintain the hand-carry boat launch
and canoe portage.
Erie proposes to modify the project
boundary by removing approximately
1.12 acres along the northern shoreline
of the project impoundment that are not
needed for project operation and adding
approximately 0.14 acre to include the
project’s existing hand-carry boat
launch. In addition, Erie proposes to
implement its proposed bald eagle
management plan, invasive species
management plan, and impoundment
drawdown plan.
m. In addition to publishing the full
text of this document in the Federal
Register, the Commission provides all
interested individuals an opportunity to
VerDate Sep<11>2014
17:07 May 10, 2023
Jkt 259001
view and/or print the contents of this
document via the internet through the
Commission’s Home Page
(www.ferc.gov) using the ‘‘eLibrary’’
link. Enter the docket number,
excluding the last three digits, in the
docket number field to access the
document (P–15000). At this time, the
Commission has suspended access to
the Commission’s Public Access Room.
For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TTY, (202)
502–8659.
n. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
o. Scoping Process:
Commission staff will prepare either
an environmental assessment (EA) or an
environmental impact statement (EIS)
that describes and evaluates the
probable effects, if any, of the licensee’s
proposed action and alternatives. The
EA or EIS will consider environmental
impacts and reasonable alternatives to
the proposed action. The Commission’s
scoping process will help determine the
required level of analysis and satisfy the
National Environmental Policy Act
(NEPA) scoping requirements,
irrespective of whether the Commission
prepares an EA or an EIS. At this time,
we do not anticipate holding on-site
scoping meetings. Instead, we are
soliciting written comments and
suggestions on the preliminary list of
issues and alternatives to be addressed
in the NEPA document, as described in
scoping document 1 (SD1), issued May
5, 2023.
Copies of SD1 outlining the subject
areas to be addressed in the NEPA
document were distributed to the
parties on the Commission’s mailing list
and the applicant’s distribution list.
Copies of SD1 may be viewed on the
web at https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call 1–866–
208–3676 or for TTY, (202) 502–8659.
DEPARTMENT OF ENERGY
Dated: May 5, 2023.
Kimberly D. Bose,
Secretary.
1 The Commission’s Rules of Practice and
Procedure provide that if a deadline falls on a
Saturday, Sunday, holiday, or other day when the
Commission is closed for business, the deadline
does not end until the close of business on the next
business day. 18 CFR 385.2007(a)(2). Because the
30-day deadline falls on a Sunday (i.e., June 4,
2023), the deadline is extended until the close of
business on Monday, June 5, 2023.
[FR Doc. 2023–10064 Filed 5–10–23; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00031
Fmt 4703
Sfmt 4703
Federal Energy Regulatory
Commission
[Project No. 4472–031]
Union Falls Hydropower, L.P.; Notice
Soliciting Scoping Comments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 4472–031.
c. Date filed: June 30, 2022.
d. Applicant: Union Falls
Hydropower, L.P. (Union Falls Hydro).
e. Name of Project: Saranac
Hydroelectric Project (Saranac Project or
project).
f. Location: The existing project is
located on the Saranac River, in the
town of Franklin in Franklin County
and the town of Black Brook in Clinton
County, New York.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Ms. Sherri
Loon, Coordinator—Operations USA,
Kruger Energy, 423 Brunswick Ave.,
Gardiner, ME 04345; phone: (207) 203–
3026; email: Sherri.Loon@kruger.com;
and Mr. Lewis Loon, General Manager,
Operations and Maintenance—USA,
Kruger Energy, 432 Brunswick Ave.,
Gardiner, ME 04345; phone: (207) 203–
3027; email: Lewis.Loon@kruger.com.
i. FERC Contact: Joshua Dub at (202)
502–8138, or joshua.dub@ferc.gov.
j. Deadline for filing scoping
comments: June 5, 2023.1
The Commission strongly encourages
electronic filing. Please file scoping
comments using the Commission’s
eFiling system at https://www.ferc.gov/
docs-filing/efiling.asp. Commenters can
submit brief comments up to 6,000
characters, without prior registration,
using the eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy via U.S. Postal
E:\FR\FM\11MYN1.SGM
11MYN1
ddrumheller on DSK120RN23PROD with NOTICES1
Federal Register / Vol. 88, No. 91 / Thursday, May 11, 2023 / Notices
Service to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission,
888 First Street NE, Room 1A,
Washington, DC 20426. Submissions
sent via any other carrier must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. All filings
must clearly identify the project name
and docket number on the first page:
Saranac Hydroelectric Project (P–4472–
031).
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application is not ready for
environmental analysis at this time.
l. The Saranac Project consists of the
following existing facilities: (1) a 151foot-long, 24-foot-high dam having a
147-foot-long spillway section with a
crest elevation of 1,408.49 feet 2 topped
with 1-foot-high flashboards; (2) an
integral, 36-foot-long, gated intake
structure at the dam’s north side; (3) a
reservoir having a surface area of 1,630
acres and a gross storage capacity of
8,900 acre-feet at a pool elevation of
1,409.49 feet; (4) an 11-foot-diameter,
1,433-foot-long steel penstock that
bifurcates into two 7-foot-diameter, 71foot-long penstocks; (5) a surge vent; (6)
a powerhouse containing two turbinegenerator units with a total rated
capacity of 2.6 megawatts; (7) two 4.16kilovolt (kV) generator leads; (8) a 4.16/
46-kV, 3,000-kV-amps step-up
transformer bank; (9) a 90-foot-long, 46kV transmission line; (10) a tailrace; and
(11) appurtenant facilities.
The Saranac Project operates in a
modified run-of-river mode through the
use of a float control for the purpose of
generating electric power, with a
minimum flow of 30 cubic feet per
second (cfs) in the bypassed reach from
April 1 through June 30, and a
minimum flow of 10 cfs during the
remainder of the year. The project has
an average annual generation of 745
megawatt-hours.
Union Falls Hydro does not propose
changes to project facilities. Union Falls
Hydro proposes to: (1) limit the
maximum daily drawdown of the
project impoundment to no more than 3
2 All elevations are in National Geodetic Vertical
Datum of 1929.
VerDate Sep<11>2014
17:07 May 10, 2023
Jkt 259001
inches in a 24-hour period, and limit the
total drawdown to 6 inches below the
top of the project’s flashboards, or below
the spillway crest when flashboards are
not present; (2) provide a minimum base
flow of 165 cfs or inflow, whichever is
less, at the dam year-round; (3) increase
the minimum flow in the bypassed
reach to 30 cfs from December 1 through
March 1 and 50 cfs from March 2
through November 30; and (4) install
signage for the canoe portage trail and
tailrace parking area. In addition, Union
Falls Hydro proposes to implement the
following proposed plans: bald eagle
management plan, invasive species
management plan, impoundment
drawdown plan, and operation
compliance monitoring plan.
m. In addition to publishing the full
text of this document in the Federal
Register, the Commission provides all
interested individuals an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page
(www.ferc.gov) using the ‘‘eLibrary’’
link. Enter the docket number,
excluding the last three digits, in the
docket number field to access the
document (P–4472). At this time, the
Commission has suspended access to
the Commission’s Public Access Room.
For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TTY, (202)
502–8659.
n. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
o. Scoping Process: Commission staff
will prepare either an environmental
assessment (EA) or an environmental
impact statement (EIS) that describes
and evaluates the probable effects, if
any, of the licensee’s proposed action
and alternatives. The EA or EIS will
consider environmental impacts and
reasonable alternatives to the proposed
action. The Commission’s scoping
process will help determine the
required level of analysis and satisfy the
National Environmental Policy Act
(NEPA) scoping requirements,
irrespective of whether the Commission
prepares an EA or an EIS. At this time,
we do not anticipate holding on-site
scoping meetings. Instead, we are
soliciting written comments and
suggestions on the preliminary list of
issues and alternatives to be addressed
in the NEPA document, as described in
scoping document 1 (SD1), issued May
5, 2023.
PO 00000
Frm 00032
Fmt 4703
Sfmt 4703
30307
Copies of SD1 outlining the subject
areas to be addressed in the NEPA
document were distributed to the
parties on the Commission’s mailing list
and the applicant’s distribution list.
Copies of SD1 may be viewed on the
web at https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call 1–866–
208–3676 or for TTY, (202) 502–8659.
Dated: May 5, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–10058 Filed 5–10–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2589–088]
Marquette Board of Light and Power;
Notice of Application Accepted for
Filing and Soliciting Comments,
Motions To Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Non-Capacity
Amendment of License to Revise Article
403.
b. Project No.: 2589–088.
c. Date Filed: August 26, 2022.
d. Applicant: Marquette Board of
Light and Power (licensee).
e. Name of Project: Marquette
Hydroelectric Project.
f. Location: The project is located on
the Dead River, near the City of
Marquette, in Marquette County,
Michigan. The project does not occupy
federal lands.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Thomas J.
Skewis, Environmental Compliance,
Marquette Board of Light and Power,
2200 Wright Street, Marquette, MI
49855, (906) 225–8670, tskewis@mblp.
i. FERC Contact: Margaret Noonan,
(202) 502–8971, Margaret.Noonan@
ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests: 30
days from the date of notice issuance.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, and protests using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
E:\FR\FM\11MYN1.SGM
11MYN1
Agencies
[Federal Register Volume 88, Number 91 (Thursday, May 11, 2023)]
[Notices]
[Pages 30306-30307]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-10058]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 4472-031]
Union Falls Hydropower, L.P.; Notice Soliciting Scoping Comments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 4472-031.
c. Date filed: June 30, 2022.
d. Applicant: Union Falls Hydropower, L.P. (Union Falls Hydro).
e. Name of Project: Saranac Hydroelectric Project (Saranac Project
or project).
f. Location: The existing project is located on the Saranac River,
in the town of Franklin in Franklin County and the town of Black Brook
in Clinton County, New York.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Ms. Sherri Loon, Coordinator--Operations USA,
Kruger Energy, 423 Brunswick Ave., Gardiner, ME 04345; phone: (207)
203-3026; email: [email protected]; and Mr. Lewis Loon, General
Manager, Operations and Maintenance--USA, Kruger Energy, 432 Brunswick
Ave., Gardiner, ME 04345; phone: (207) 203-3027; email:
[email protected].
i. FERC Contact: Joshua Dub at (202) 502-8138, or
[email protected].
j. Deadline for filing scoping comments: June 5, 2023.\1\
---------------------------------------------------------------------------
\1\ The Commission's Rules of Practice and Procedure provide
that if a deadline falls on a Saturday, Sunday, holiday, or other
day when the Commission is closed for business, the deadline does
not end until the close of business on the next business day. 18 CFR
385.2007(a)(2). Because the 30-day deadline falls on a Sunday (i.e.,
June 4, 2023), the deadline is extended until the close of business
on Monday, June 5, 2023.
---------------------------------------------------------------------------
The Commission strongly encourages electronic filing. Please file
scoping comments using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief
comments up to 6,000 characters, without prior registration, using the
eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You
must include your name and contact information at the end of your
comments. For assistance, please contact FERC Online Support at
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy via
U.S. Postal
[[Page 30307]]
Service to: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852. All filings must clearly identify
the project name and docket number on the first page: Saranac
Hydroelectric Project (P-4472-031).
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. This application is not ready for environmental analysis at this
time.
l. The Saranac Project consists of the following existing
facilities: (1) a 151-foot-long, 24-foot-high dam having a 147-foot-
long spillway section with a crest elevation of 1,408.49 feet \2\
topped with 1-foot-high flashboards; (2) an integral, 36-foot-long,
gated intake structure at the dam's north side; (3) a reservoir having
a surface area of 1,630 acres and a gross storage capacity of 8,900
acre-feet at a pool elevation of 1,409.49 feet; (4) an 11-foot-
diameter, 1,433-foot-long steel penstock that bifurcates into two 7-
foot-diameter, 71-foot-long penstocks; (5) a surge vent; (6) a
powerhouse containing two turbine-generator units with a total rated
capacity of 2.6 megawatts; (7) two 4.16-kilovolt (kV) generator leads;
(8) a 4.16/46-kV, 3,000-kV-amps step-up transformer bank; (9) a 90-
foot-long, 46-kV transmission line; (10) a tailrace; and (11)
appurtenant facilities.
---------------------------------------------------------------------------
\2\ All elevations are in National Geodetic Vertical Datum of
1929.
---------------------------------------------------------------------------
The Saranac Project operates in a modified run-of-river mode
through the use of a float control for the purpose of generating
electric power, with a minimum flow of 30 cubic feet per second (cfs)
in the bypassed reach from April 1 through June 30, and a minimum flow
of 10 cfs during the remainder of the year. The project has an average
annual generation of 745 megawatt-hours.
Union Falls Hydro does not propose changes to project facilities.
Union Falls Hydro proposes to: (1) limit the maximum daily drawdown of
the project impoundment to no more than 3 inches in a 24-hour period,
and limit the total drawdown to 6 inches below the top of the project's
flashboards, or below the spillway crest when flashboards are not
present; (2) provide a minimum base flow of 165 cfs or inflow,
whichever is less, at the dam year-round; (3) increase the minimum flow
in the bypassed reach to 30 cfs from December 1 through March 1 and 50
cfs from March 2 through November 30; and (4) install signage for the
canoe portage trail and tailrace parking area. In addition, Union Falls
Hydro proposes to implement the following proposed plans: bald eagle
management plan, invasive species management plan, impoundment drawdown
plan, and operation compliance monitoring plan.
m. In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested individuals an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (www.ferc.gov) using the
``eLibrary'' link. Enter the docket number, excluding the last three
digits, in the docket number field to access the document (P-4472). At
this time, the Commission has suspended access to the Commission's
Public Access Room. For assistance, contact FERC at
[email protected] or call toll-free, (886) 208-3676 or TTY,
(202) 502-8659.
n. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
o. Scoping Process: Commission staff will prepare either an
environmental assessment (EA) or an environmental impact statement
(EIS) that describes and evaluates the probable effects, if any, of the
licensee's proposed action and alternatives. The EA or EIS will
consider environmental impacts and reasonable alternatives to the
proposed action. The Commission's scoping process will help determine
the required level of analysis and satisfy the National Environmental
Policy Act (NEPA) scoping requirements, irrespective of whether the
Commission prepares an EA or an EIS. At this time, we do not anticipate
holding on-site scoping meetings. Instead, we are soliciting written
comments and suggestions on the preliminary list of issues and
alternatives to be addressed in the NEPA document, as described in
scoping document 1 (SD1), issued May 5, 2023.
Copies of SD1 outlining the subject areas to be addressed in the
NEPA document were distributed to the parties on the Commission's
mailing list and the applicant's distribution list. Copies of SD1 may
be viewed on the web at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, call 1-866-
208-3676 or for TTY, (202) 502-8659.
Dated: May 5, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-10058 Filed 5-10-23; 8:45 am]
BILLING CODE 6717-01-P