Notice of Intent To Prepare an Environmental Impact Statement To Analyze the Potential Environmental Effects From Maintaining Secretary Jewell's Coal Leasing Moratorium, 26588-26590 [2023-08960]

Download as PDF 26588 Federal Register / Vol. 88, No. 83 / Monday, May 1, 2023 / Notices A. Overview of Information Collection Title of Information Collection: Electronic Line of Credit Control System (eLOCCS) System Access Authorization Form. OMB Approval Number: 2535–0102. Type of Request: Reinstatement with change. Form Number: HUD–27054e. telecommunications-relay-service-trs. Copies of available documents submitted to OMB may be obtained from Ms. Guido. SUPPLEMENTARY INFORMATION: This notice informs the public that HUD is seeking approval from OMB for the information collection described in Section A. Information collection Number of respondents Responses per annum Burden hour per response Annual burden hours Hourly cost per response Annual cost HUD—27054e .............. 2,420.00 1.00 2,420.00 0.17 411.00 $24.29 $9,992.91 Total ...................... ........................ ........................ ........................ ........................ 411.00 $24.29 $9,992.91 B. Solicitation of Public Comment DEPARTMENT OF THE INTERIOR This notice is soliciting comments from members of the public and affected parties concerning the collection of information described in Section A on the following: (1) Whether the proposed collection of information is necessary for the proper performance of the functions of the agency, including whether the information will have practical utility; (2) The accuracy of the agency’s estimate of the burden of the proposed collection of information; (3) Ways to enhance the quality, utility, and clarity of the information to be collected; and (4) Ways to minimize the burden of the collection of information on those who are to respond; including through the use of appropriate automated collection techniques or other forms of information technology, e.g., permitting electronic submission of responses. HUD encourages interested parties to submit comment in response to these questions. Bureau of Land Management C. Authority Section 3507 of the Paperwork Reduction Act of 1995, 44 U.S.C. Chapter 35. George J. Tomchick, Deputy Chief Financial Officer. [FR Doc. 2023–09062 Filed 4–28–23; 8:45 am] BILLING CODE 4210–67–P lotter on DSK11XQN23PROD with NOTICES1 Frequency of response Description of the need for the information and proposed use: Establish access to the eLOCCS payment system. Respondents: State or Local Government; Public Housing Authorities (PHAs), Individuals or Households. VerDate Sep<11>2014 17:10 Apr 28, 2023 Jkt 259001 [BLM_HQ_FRN_MO4500170190] Notice of Intent To Prepare an Environmental Impact Statement To Analyze the Potential Environmental Effects From Maintaining Secretary Jewell’s Coal Leasing Moratorium Bureau of Land Management, Interior. ACTION: Notice of intent. AGENCY: In compliance with the National Environmental Policy Act of 1969, as amended (NEPA), and consistent with direction from the U.S. District Court of Montana, the Bureau of Land Management (BLM) intends to prepare an environmental impact statement (EIS) to analyze the potential environmental effects from maintaining or revoking former Secretary of the Interior Sally Jewell’s coal leasing moratorium. This notice begins the process of defining the scope of the EIS by providing background on the Federal coal program and the direction received from the United States District Court for the District of Montana in Citizens for Clean Energy, v. U.S. Dep’t of the Interior. With this notice, the BLM also solicits public comments for consideration in establishing the scope and content of the EIS. DATES: The BLM invites interested agencies, States, Tribes, local governments, industry, organizations, and members of the public to submit comments or suggestions to assist in identifying significant issues that should be included in the scope of BLM’s review of the potential environmental impacts from maintaining or revoking former Secretary Jewell’s coal leasing moratorium. The BLM will consider all written comments received or postmarked SUMMARY: PO 00000 Frm 00073 Fmt 4703 Sfmt 4703 during the public comment period, which will close on June 15, 2023. ADDRESSES: You may submit written comments by the following methods: • Website: https://eplanning.blm.gov/ eplanning-ui/project/2024545/510. This is the preferred method of commenting. • Email: BLM_HQ_320_ CoalProgramReview@blm.gov. • Mail, personal, or messenger delivery: National Coal Program Review, 1849 C Street NW, Room 5622, Washington, DC 20240. FOR FURTHER INFORMATION CONTACT: Timothy Barnes, Acting Chief, Division of Solid Minerals, telephone: 541–416– 6858, email: tbarnes@blm.gov. Individuals in the United States who are deaf, blind, hard of hearing, or have a speech disability may dial 711 (TTY, TDD, or TeleBraille) to access telecommunications relay services. Individuals outside the United States should use the relay services offered within their country to make international calls to the point-ofcontact in the United States. SUPPLEMENTARY INFORMATION: The BLM will prepare an EIS to analyze the potential environmental effects from maintaining or revoking former Secretary Jewell’s coal leasing moratorium, as ordered by the U.S. District Court for the District of Montana in Citizens for Clean Energy, v. U.S. Dep’t of the Interior, 4:17–cv–00042– BMM (D. Mont. 2022).1 The court’s decision is related to the environmental analysis that the BLM previously prepared to assess lifting a Federal coal leasing moratorium established on January 15, 2016, by then Secretary of the Interior Sally Jewell. Secretary Jewell established the moratorium through Secretary’s Order No. 3338 1 The Intervenor-Appellants, the National Mining Association, State of Wyoming and State of Montana, appealed this decision on October 7, 2022, and October 11, 2022, respectively. Citizens for Clean Energy v. Dep’t of the Interior, Civ. No. 22–35789 (9th Cir.). E:\FR\FM\01MYN1.SGM 01MYN1 Federal Register / Vol. 88, No. 83 / Monday, May 1, 2023 / Notices lotter on DSK11XQN23PROD with NOTICES1 (Jewell Order), which directed the BLM to conduct a programmatic review of the Federal coal program through preparation of an EIS under NEPA. On March 29, 2017, then former Secretary of the Interior Ryan Zinke issued Secretary’s Order No. 3348 (Zinke Order), which revoked the Jewell Order, halted preparation of the EIS, and lifted the moratorium on Federal coal leasing. Background Under the Mineral Leasing Act of 1920 (MLA), as amended, 30 U.S.C. 181 et seq., and the Mineral Leasing Act for Acquired Lands of 1947 (MLAAL), as amended, 30 U.S.C. 351 et seq., the BLM is responsible for leasing Federal coal and regulation of the development of that coal on approximately 570 million acres of the 700 million acres of mineral estate that is owned by the Federal Government. This responsibility encompasses Federal mineral rights on Federal lands and Federal mineral rights located under surface lands with nonFederal ownership. Under the authority of the MLA and MLAAL, the BLM administers leasing and monitors coal production. Other Departmental bureaus, in particular the Office of Surface Mining Reclamation and Enforcement (OSMRE) and the Office of Natural Resources Revenue (ONRR), also take actions related to coal mining on Federal lands. The OSMRE, and those States that have regulatory primacy under the Surface Mining Control and Reclamation Act of 1977, permit coal mining and reclamation activities, and monitor reclamation and reclamation bonding actions. The ONRR collects and audits all payments required under the lease, including bonus bids, royalties, and rental payments, and distributes those funds between the Federal Treasury and the States where coal resources are located. The Jewell Order imposed a moratorium on the issuance of new Federal coal leases for thermal coal, with limited exceptions, until completion of the EIS. On March 29, 2017, the Zinke Order implemented Executive Order (E.O.) 13783, which was entitled, ‘‘Promoting Energy Independence and Economic Security,’’ by rescinding the Jewell Order. Immediately thereafter, Citizens for Clean Energy, Ecocheyenne, Montana Environmental Information Center, Center for Biological Diversity, Defenders of Wildlife, Sierra Club, WildEarth Guardians, and the Northern Cheyenne Tribe filed a lawsuit in the U.S. District Court for the District of Montana asserting that the issuance of the Zinke Order required an environmental analysis in compliance VerDate Sep<11>2014 17:10 Apr 28, 2023 Jkt 259001 with NEPA. Additionally, the States of California, New York, New Mexico, and Washington also filed suit and the Court consolidated the cases. The National Mining Association and the States of Wyoming and Montana intervened. On April 19, 2019, the Court held that the Zinke Order was a final agency action that triggered the need to comply with NEPA, requiring the Department to conduct an appropriate environmental review of that action. To comply with the Court’s Order, the BLM released an environmental assessment (EA) for public comment on May 22, 2019, and published the final EA and a Finding of No Significant Impact (FONSI) on its website on February 26, 2020. Shortly thereafter, the Plaintiffs amended their complaints to challenge the scope and content of the EA. On January 20, 2021, President Biden issued E.O. 13990, entitled, ‘‘Executive Order on Protecting Public Health and the Environment and Restoring Science to Tackle the Climate Crisis,’’ revoking E.O. 13783. On April 16, 2021, Secretary Haaland rescinded the Zinke Order through Secretary’s Order 3398, but did not reinstate the Federal coal leasing moratorium. On August 12, 2022, the Court vacated and remanded the EA and associated FONSI and reinstated ‘‘[t]he coal leasing program moratorium established by the Jewell Order . . . until the completion of sufficient NEPA review analyzing revocation of the moratorium.’’ Order at 19. The Court determined that the EA’s analysis failed ‘‘to consider all direct, indirect, and cumulative impacts of re-starting the Federal coal-leasing program.’’ Order at 13. Further, the Court held that the BLM should have considered ‘‘a potential alternative that provided a baseline of an indefinite moratorium’’ rather than limiting the EA’s analysis to those leases granted during the estimated Programmatic EIS timeline providing that the ‘‘BLM’s analysis should have considered the effect of restarting coal leasing from a forward-looking perspective, including connected actions.’’ Id. The Court directed the ‘‘BLM [to] perform NEPA analysis that considers the full scope of the Zinke Order’s effect on all then-pending lease applications, and other connected, cumulative, or similar actions.’’ Order at 17. In October 2022, IntervenorDefendants appealed the decision to the U.S. Court of Appeals for the Ninth Circuit. Public Scoping Process All public scoping comments must be submitted by email or by mail to the addresses listed under ADDRESSES. PO 00000 Frm 00074 Fmt 4703 Sfmt 4703 26589 Before including you address, phone number, email address, or other personal identifying information in your comment, you should be aware that your entire comment, including your personal identifying information, may be made public at any time. While you may request in your comment to have your personal identifying information withheld from public review, the BLM cannot guarantee that this will occur. The BLM will review and consider all public scoping comments received and will prepare a Scoping Summary Report. The Scoping Summary Report will be used by the BLM to identify issues to be included in the environmental analysis in the EIS, resources and issues that can be dismissed from detailed analysis because they are not present or not affected, and potential alternatives to be analyzed. Request for Identification of Potential Alternatives, Information, and Analyses Relevant to the Scope of the Analysis of the Potential Environmental Effects From Maintaining Secretary Jewell’s Coal Leasing Moratorium on Pending Federal Coal Lease Applications In addition to comments concerning the scope of the environmental analysis, commenters are encouraged to identify relevant information, studies, and analyses that would assist the BLM in taking further action on the moratorium instituted by the Jewell Order and identifying potential alternatives. Lead and Cooperating Agencies The BLM is the lead agency for this EIS. Other Federal agencies, State, Tribal, and local governments with special expertise that are interested in participating in the preparation of this EIS should contact the previously mentioned Acting Chief of the Division of Solid Minerals. Decision Maker Director, Bureau of Land Management. Nature of Decision To Be Made Informed by the environmental analysis, the BLM will consider whether and to what extent to continue the coal leasing moratorium imposed by the Jewell Order on January 15, 2016, lifted by the Zinke Order on March 29, 2017, and reinstated by the U.S. District Court of Montana on August 12, 2022. E:\FR\FM\01MYN1.SGM 01MYN1 26590 Federal Register / Vol. 88, No. 83 / Monday, May 1, 2023 / Notices (Authority: 43 U.S.C. 1701 et seq., 30 U.S.C. 118 et seq., 30 U.S.C. 351 et seq.) Benjamin E. Gruber, Acting Assistant Director, Energy, Minerals and Realty Management, Bureau of Land Management, Department of the Interior. [FR Doc. 2023–08960 Filed 4–28–23; 8:45 am] BILLING CODE 4331–29–P DEPARTMENT OF THE INTERIOR National Park Service [NPS–SER–VIIS–35617; PS.SSELA386.00.1] Land Exchange at Virgin Islands National Park; Correction National Park Service, Interior. Notice of land exchange; correction. AGENCY: ACTION: The National Park Service published a document in the Federal Register of April 25, 2023, concerning request for comments on a Notice of Land Exchange at the Virgin Islands National Park. The document contained a typographical error in the DATES section. SUMMARY: FOR FURTHER INFORMATION CONTACT: Russell Webb, Supervisory Realty Specialist, russell_webb@nps.gov, Land Resources Program Office—National Park Service, 2975 Horseshoe Dr. S, Suite 800, Naples, Florida 34104, telephone (239) 261–0865. SUPPLEMENTARY INFORMATION: Correction In the Federal Register of April 25, 2023, in FR Doc. 2023–08623, on page 25014, in the third column, correct the DATES caption to read: The effective date of this Notice of land exchange is April 25, 2023. Comments on the land exchange must be received by 11:59 p.m. ET on June 9, 2023. DATES: Mark A. Foust, Regional Director, Interior Region 2. [FR Doc. 2023–09158 Filed 4–26–23; 4:15 pm] BILLING CODE 4312–52–P DEPARTMENT OF THE INTERIOR lotter on DSK11XQN23PROD with NOTICES1 Bureau of Reclamation [RR04093000, XXXR4081G3, RX.05940913. FY19400] Public Meeting of the Glen Canyon Dam Adaptive Management Work Group AGENCY: Bureau of Reclamation, Interior. VerDate Sep<11>2014 17:10 Apr 28, 2023 Jkt 259001 ACTION: Notice of public meeting. In accordance with the Federal Advisory Committee Act of 1972, the Bureau of Reclamation (Reclamation) is publishing this notice to announce that a Federal Advisory Committee meeting of the Glen Canyon Dam Adaptive Management Work Group (AMWG) will take place. DATES: The meeting will be held virtually on Wednesday, May 17, 2023, beginning at 9 a.m. (MDT) and concluding four (4) hours later in the respective time zones. ADDRESSES: The virtual meeting held on Wednesday, May 17, 2023, may be accessed at: https://rec.webex.com/rec/ j.php?MTID=m069d7dac9f042ce419b 775a5d2b462ff; Meeting Number: 2763 284 1693, Password: May17; Phone Number: (877) 932–7704; Passcode: 8410783. FOR FURTHER INFORMATION CONTACT: Mr. William Stewart, Bureau of Reclamation, telephone (385) 622–2179, email at wstewart@usbr.gov. Individuals in the United States who are deaf, deafblind, hard of hearing, or have a speech disability may dial 711 (TTY, TDD, or TeleBraille) to access telecommunications relay services. Individuals outside the United States should use the relay services offered within their country to make international calls to the point-ofcontact in the United States. SUPPLEMENTARY INFORMATION: The Glen Canyon Dam Adaptive Management Program (GCDAMP) was implemented as a result of the Record of Decision on the Operation of Glen Canyon Dam Final Environmental Impact Statement to comply with consultation requirements of the Grand Canyon Protection Act (Pub. L. 102–575) of 1992. The AMWG makes recommendations to the Secretary of the Interior concerning Glen Canyon Dam operations and other management actions to protect resources downstream of Glen Canyon Dam, consistent with the Grand Canyon Protection Act. The AMWG meets two to three times a year. Agenda: The AMWG will meet to receive updates on: (1) current basin hydrology and water year 2023 operations; (2) experiments considered for implementation in 2023; and (3) long-term funding considerations. The AMWG will also discuss other administrative and resource issues pertaining to the GCDAMP. To view a final copy of the agenda and documents related to the May meeting, please visit Reclamation’s website at https:// SUMMARY: PO 00000 Frm 00075 Fmt 4703 Sfmt 4703 www.usbr.gov/uc/progact/amp/ amwg.html. Meeting Accessibility/Special Accommodations: The meeting is open to the public. Please make requests in advance for sign language interpreter services, assistive listening devices, or other reasonable accommodations. We ask that you contact Mr. William Stewart (see FOR FURTHER INFORMATION CONTACT) section of this notice at least seven (7) business days prior to the meeting to give the Department of the Interior sufficient time to process your request. All reasonable accommodation requests are managed on a case-by-case basis. Public Disclosure of Comments: Time will be allowed for any individual or organization wishing to make extemporaneous and/or formal oral comments. To allow for full consideration of information by the AMWG members, written notice should be provided to Mr. William Stewart (see FOR FURTHER INFORMATION CONTACT) prior to the meeting. Depending on the number of persons wishing to speak, and the time available, the time for individual comments may be limited. Any written comments received will be provided to the AMWG members. Before including your address, phone number, email address, or other personal identifying information in your comment, you should be aware that your entire comment—including your personal identifying information—may be made publicly available at any time. While you can ask us in your comment to withhold your personal identifying information from public review, we cannot guarantee that we will be able to do so. Authority: 5 U.S.C. appendix 10. William Stewart, Adaptive Management Group Chief, Resources Management Division, Upper Colorado Basin—Interior Region 7. [FR Doc. 2023–09157 Filed 4–28–23; 8:45 am] BILLING CODE 4332–90–P INTERNATIONAL TRADE COMMISSION Notice of Receipt of Complaint; Solicitation of Comments Relating to the Public Interest International Trade Commission. ACTION: Notice. AGENCY: Notice is hereby given that the U.S. International Trade Commission has received a complaint entitled Certain Blood Flow Restriction Devices with Rotatable Windlasses and SUMMARY: E:\FR\FM\01MYN1.SGM 01MYN1

Agencies

[Federal Register Volume 88, Number 83 (Monday, May 1, 2023)]
[Notices]
[Pages 26588-26590]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-08960]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF THE INTERIOR

Bureau of Land Management

[BLM_HQ_FRN_MO4500170190]


Notice of Intent To Prepare an Environmental Impact Statement To 
Analyze the Potential Environmental Effects From Maintaining Secretary 
Jewell's Coal Leasing Moratorium

AGENCY: Bureau of Land Management, Interior.

ACTION: Notice of intent.

-----------------------------------------------------------------------

SUMMARY: In compliance with the National Environmental Policy Act of 
1969, as amended (NEPA), and consistent with direction from the U.S. 
District Court of Montana, the Bureau of Land Management (BLM) intends 
to prepare an environmental impact statement (EIS) to analyze the 
potential environmental effects from maintaining or revoking former 
Secretary of the Interior Sally Jewell's coal leasing moratorium. This 
notice begins the process of defining the scope of the EIS by providing 
background on the Federal coal program and the direction received from 
the United States District Court for the District of Montana in 
Citizens for Clean Energy, v. U.S. Dep't of the Interior. With this 
notice, the BLM also solicits public comments for consideration in 
establishing the scope and content of the EIS.

DATES: The BLM invites interested agencies, States, Tribes, local 
governments, industry, organizations, and members of the public to 
submit comments or suggestions to assist in identifying significant 
issues that should be included in the scope of BLM's review of the 
potential environmental impacts from maintaining or revoking former 
Secretary Jewell's coal leasing moratorium.
    The BLM will consider all written comments received or postmarked 
during the public comment period, which will close on June 15, 2023.

ADDRESSES: You may submit written comments by the following methods:
     Website: https://eplanning.blm.gov/eplanning-ui/project/2024545/510. This is the preferred method of commenting.
     Email: [email protected].
     Mail, personal, or messenger delivery: National Coal 
Program Review, 1849 C Street NW, Room 5622, Washington, DC 20240.

FOR FURTHER INFORMATION CONTACT: Timothy Barnes, Acting Chief, Division 
of Solid Minerals, telephone: 541-416-6858, email: [email protected].
    Individuals in the United States who are deaf, blind, hard of 
hearing, or have a speech disability may dial 711 (TTY, TDD, or 
TeleBraille) to access telecommunications relay services. Individuals 
outside the United States should use the relay services offered within 
their country to make international calls to the point-of-contact in 
the United States.

SUPPLEMENTARY INFORMATION: The BLM will prepare an EIS to analyze the 
potential environmental effects from maintaining or revoking former 
Secretary Jewell's coal leasing moratorium, as ordered by the U.S. 
District Court for the District of Montana in Citizens for Clean 
Energy, v. U.S. Dep't of the Interior, 4:17-cv-00042-BMM (D. Mont. 
2022).\1\ The court's decision is related to the environmental analysis 
that the BLM previously prepared to assess lifting a Federal coal 
leasing moratorium established on January 15, 2016, by then Secretary 
of the Interior Sally Jewell. Secretary Jewell established the 
moratorium through Secretary's Order No. 3338

[[Page 26589]]

(Jewell Order), which directed the BLM to conduct a programmatic review 
of the Federal coal program through preparation of an EIS under NEPA. 
On March 29, 2017, then former Secretary of the Interior Ryan Zinke 
issued Secretary's Order No. 3348 (Zinke Order), which revoked the 
Jewell Order, halted preparation of the EIS, and lifted the moratorium 
on Federal coal leasing.
---------------------------------------------------------------------------

    \1\ The Intervenor-Appellants, the National Mining Association, 
State of Wyoming and State of Montana, appealed this decision on 
October 7, 2022, and October 11, 2022, respectively. Citizens for 
Clean Energy v. Dep't of the Interior, Civ. No. 22-35789 (9th Cir.).
---------------------------------------------------------------------------

Background

    Under the Mineral Leasing Act of 1920 (MLA), as amended, 30 U.S.C. 
181 et seq., and the Mineral Leasing Act for Acquired Lands of 1947 
(MLAAL), as amended, 30 U.S.C. 351 et seq., the BLM is responsible for 
leasing Federal coal and regulation of the development of that coal on 
approximately 570 million acres of the 700 million acres of mineral 
estate that is owned by the Federal Government. This responsibility 
encompasses Federal mineral rights on Federal lands and Federal mineral 
rights located under surface lands with non-Federal ownership. Under 
the authority of the MLA and MLAAL, the BLM administers leasing and 
monitors coal production. Other Departmental bureaus, in particular the 
Office of Surface Mining Reclamation and Enforcement (OSMRE) and the 
Office of Natural Resources Revenue (ONRR), also take actions related 
to coal mining on Federal lands. The OSMRE, and those States that have 
regulatory primacy under the Surface Mining Control and Reclamation Act 
of 1977, permit coal mining and reclamation activities, and monitor 
reclamation and reclamation bonding actions. The ONRR collects and 
audits all payments required under the lease, including bonus bids, 
royalties, and rental payments, and distributes those funds between the 
Federal Treasury and the States where coal resources are located.
    The Jewell Order imposed a moratorium on the issuance of new 
Federal coal leases for thermal coal, with limited exceptions, until 
completion of the EIS.
    On March 29, 2017, the Zinke Order implemented Executive Order 
(E.O.) 13783, which was entitled, ``Promoting Energy Independence and 
Economic Security,'' by rescinding the Jewell Order. Immediately 
thereafter, Citizens for Clean Energy, Ecocheyenne, Montana 
Environmental Information Center, Center for Biological Diversity, 
Defenders of Wildlife, Sierra Club, WildEarth Guardians, and the 
Northern Cheyenne Tribe filed a lawsuit in the U.S. District Court for 
the District of Montana asserting that the issuance of the Zinke Order 
required an environmental analysis in compliance with NEPA. 
Additionally, the States of California, New York, New Mexico, and 
Washington also filed suit and the Court consolidated the cases. The 
National Mining Association and the States of Wyoming and Montana 
intervened.
    On April 19, 2019, the Court held that the Zinke Order was a final 
agency action that triggered the need to comply with NEPA, requiring 
the Department to conduct an appropriate environmental review of that 
action. To comply with the Court's Order, the BLM released an 
environmental assessment (EA) for public comment on May 22, 2019, and 
published the final EA and a Finding of No Significant Impact (FONSI) 
on its website on February 26, 2020. Shortly thereafter, the Plaintiffs 
amended their complaints to challenge the scope and content of the EA.
    On January 20, 2021, President Biden issued E.O. 13990, entitled, 
``Executive Order on Protecting Public Health and the Environment and 
Restoring Science to Tackle the Climate Crisis,'' revoking E.O. 13783. 
On April 16, 2021, Secretary Haaland rescinded the Zinke Order through 
Secretary's Order 3398, but did not reinstate the Federal coal leasing 
moratorium.
    On August 12, 2022, the Court vacated and remanded the EA and 
associated FONSI and reinstated ``[t]he coal leasing program moratorium 
established by the Jewell Order . . . until the completion of 
sufficient NEPA review analyzing revocation of the moratorium.'' Order 
at 19. The Court determined that the EA's analysis failed ``to consider 
all direct, indirect, and cumulative impacts of re-starting the Federal 
coal-leasing program.'' Order at 13. Further, the Court held that the 
BLM should have considered ``a potential alternative that provided a 
baseline of an indefinite moratorium'' rather than limiting the EA's 
analysis to those leases granted during the estimated Programmatic EIS 
timeline providing that the ``BLM's analysis should have considered the 
effect of restarting coal leasing from a forward-looking perspective, 
including connected actions.'' Id. The Court directed the ``BLM [to] 
perform NEPA analysis that considers the full scope of the Zinke 
Order's effect on all then-pending lease applications, and other 
connected, cumulative, or similar actions.'' Order at 17. In October 
2022, Intervenor-Defendants appealed the decision to the U.S. Court of 
Appeals for the Ninth Circuit.

Public Scoping Process

    All public scoping comments must be submitted by email or by mail 
to the addresses listed under ADDRESSES. Before including you address, 
phone number, email address, or other personal identifying information 
in your comment, you should be aware that your entire comment, 
including your personal identifying information, may be made public at 
any time. While you may request in your comment to have your personal 
identifying information withheld from public review, the BLM cannot 
guarantee that this will occur. The BLM will review and consider all 
public scoping comments received and will prepare a Scoping Summary 
Report. The Scoping Summary Report will be used by the BLM to identify 
issues to be included in the environmental analysis in the EIS, 
resources and issues that can be dismissed from detailed analysis 
because they are not present or not affected, and potential 
alternatives to be analyzed.

Request for Identification of Potential Alternatives, Information, and 
Analyses Relevant to the Scope of the Analysis of the Potential 
Environmental Effects From Maintaining Secretary Jewell's Coal Leasing 
Moratorium on Pending Federal Coal Lease Applications

    In addition to comments concerning the scope of the environmental 
analysis, commenters are encouraged to identify relevant information, 
studies, and analyses that would assist the BLM in taking further 
action on the moratorium instituted by the Jewell Order and identifying 
potential alternatives.

Lead and Cooperating Agencies

    The BLM is the lead agency for this EIS. Other Federal agencies, 
State, Tribal, and local governments with special expertise that are 
interested in participating in the preparation of this EIS should 
contact the previously mentioned Acting Chief of the Division of Solid 
Minerals.

Decision Maker

    Director, Bureau of Land Management.

Nature of Decision To Be Made

    Informed by the environmental analysis, the BLM will consider 
whether and to what extent to continue the coal leasing moratorium 
imposed by the Jewell Order on January 15, 2016, lifted by the Zinke 
Order on March 29, 2017, and reinstated by the U.S. District Court of 
Montana on August 12, 2022.


[[Page 26590]]


(Authority: 43 U.S.C. 1701 et seq., 30 U.S.C. 118 et seq., 30 U.S.C. 
351 et seq.)

Benjamin E. Gruber,
Acting Assistant Director, Energy, Minerals and Realty Management, 
Bureau of Land Management, Department of the Interior.
[FR Doc. 2023-08960 Filed 4-28-23; 8:45 am]