Alice Falls Hydro, LLC; Notice of Intent To Prepare an Environmental Assessment, 26298 [2023-09027]

Download as PDF 26298 Federal Register / Vol. 88, No. 82 / Friday, April 28, 2023 / Notices representative of the applicant specified in the particular application. o. Procedural schedule: The application will be processed according to the following schedule. Revisions to the schedule will be made as appropriate. Issue Scoping Document 1 for comments—May 2023 Comments on Scoping Document 1 Due—June 2023 Issue Scoping Document 2 (if necessary)—July 2023 Request Additional Information (if necessary)—July 2023 Issue Notice of Ready for Environmental Analysis—August 2023 Dated: April 24, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–09028 Filed 4–27–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission last three digits in the docket number field to access the document. At this Commission issues EA .... December 2023.1 time, the Commission has suspended Comments on EA ............ January 2024. access to the Commission’s Public Reference Room, due to the 1 The Council on Environmental Quality’s (CEQ) regulations under 40 CFR proclamation declaring a National 1501.10(b)(1) require that EAs be completed Emergency concerning the Novel within 1 year of the federal action agency’s Coronavirus Disease (COVID–19), issued decision to prepare an EA. This notice establishes the Commission’s intent to prepare an by the President on March 13, 2020. For EA for the Alice Falls Project. Therefore, in ac- assistance, contact FERC at cordance with CEQ’s regulations, the EA must FERCOnlineSupport@ferc.gov or call be issued within 1 year of the issuance date of toll-free, (886) 208–3676 or TYY, (202) this notice. 502–8659. Any questions regarding this notice The Commission strongly encourages may be directed to Nicholas Tackett at electronic filings of comments, protests (202) 502–6783 or nicholas.tackett@ and interventions in lieu of paper using ferc.gov. the ‘‘eFile’’ link at https://www.ferc.gov. In lieu of electronic filing, you may Dated: April 24, 2023. submit a paper copy. Submissions sent Kimberly D. Bose, via the U.S. Postal Service must be Secretary. addressed to: Kimberly D. Bose, [FR Doc. 2023–09027 Filed 4–27–23; 8:45 am] Secretary, Federal Energy Regulatory BILLING CODE 6717–01–P Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier DEPARTMENT OF ENERGY must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Commission Rockville, Maryland 20852. Milestone Target date [Docket No. EL23–52–000] [Project No. 5867–054] ddrumheller on DSK120RN23PROD with NOTICES1 Alice Falls Hydro, LLC; Notice of Intent To Prepare an Environmental Assessment On September 29, 2021, Alice Falls Hydro, LLC filed an application for a new major license for the 2.1-megawatt Alice Falls Hydroelectric Project (Alice Falls Project or project; FERC No. 5867). The Alice Falls Project is located on the Ausable River, in the Town of Chesterfield, Clinton and Essex counties, New York. In accordance with the Commission’s regulations, on February 16, 2023, Commission staff issued a notice that the project was ready for environmental analysis (REA notice). Based on the information in the record, including comments filed on the REA notice, staff does not anticipate that licensing the project would constitute a major federal action significantly affecting the quality of the human environment. Therefore, staff intends to prepare an Environmental Assessment (EA) on the application to license the Alice Falls Project. The EA will be issued and circulated for review by all interested parties. All comments filed on the EA will be analyzed by staff and considered in the Commission’s final licensing decision. The application will be processed according to the following schedule. Revisions to the schedule may be made as appropriate. VerDate Sep<11>2014 18:44 Apr 27, 2023 Jkt 259001 MD Solar 2, LLC; Notice of Institution of Section 206 Proceeding and Refund Effective Date On April 24, 2023, the Commission issued an order in Docket No. EL23–52– 000, pursuant to section 206 of the Federal Power Act (FPA), 16 U.S.C. 824e, instituting an investigation into whether MD Solar 2, LLC’s Rate Schedule is unjust, unreasonable, unduly discriminatory or preferential, or otherwise unlawful. MD Solar 2, LLC, 183 FERC ¶ 61,053 (2023). The refund effective date in Docket No. EL23–52–000, established pursuant to section 206(b) of the FPA, will be the date of publication of this notice in the Federal Register. Any interested person desiring to be heard in Docket No. EL23–52–000 must file a notice of intervention or motion to intervene, as appropriate, with the Federal Energy Regulatory Commission, in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure, 18 CFR 385.214 (2022), within 21 days of the date of issuance of the order. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the PO 00000 Frm 00050 Fmt 4703 Sfmt 4703 Dated: April 24, 2023. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2023–09037 Filed 4–27–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Western Area Power Administration Recommendation for the Western Area Power Administration’s Rocky Mountain Region and Colorado River Storage Project Management Center To Pursue Final Negotiations Regarding Membership in the Southwest Power Pool Regional Transmission Organization, and for the Upper Great Plains Region To Expand Its Participation Western Area Power Administration, DOE. ACTION: Notice of recommendation to pursue final negotiations regarding SPP RTO membership. AGENCY: Western Area Power Administration (WAPA), a Power Marketing Administration of the Department of Energy (DOE), recommends the Rocky Mountain Region (WAPA–RM) with its Loveland Area Projects Transmission System and the Colorado River Storage Project Management Center (WAPA–CRSP) with its Colorado River Storage Project Transmission System pursue final negotiations regarding transmission SUMMARY: E:\FR\FM\28APN1.SGM 28APN1

Agencies

[Federal Register Volume 88, Number 82 (Friday, April 28, 2023)]
[Notices]
[Page 26298]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-09027]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 5867-054]


Alice Falls Hydro, LLC; Notice of Intent To Prepare an 
Environmental Assessment

    On September 29, 2021, Alice Falls Hydro, LLC filed an application 
for a new major license for the 2.1-megawatt Alice Falls Hydroelectric 
Project (Alice Falls Project or project; FERC No. 5867). The Alice 
Falls Project is located on the Ausable River, in the Town of 
Chesterfield, Clinton and Essex counties, New York.
    In accordance with the Commission's regulations, on February 16, 
2023, Commission staff issued a notice that the project was ready for 
environmental analysis (REA notice). Based on the information in the 
record, including comments filed on the REA notice, staff does not 
anticipate that licensing the project would constitute a major federal 
action significantly affecting the quality of the human environment. 
Therefore, staff intends to prepare an Environmental Assessment (EA) on 
the application to license the Alice Falls Project.
    The EA will be issued and circulated for review by all interested 
parties. All comments filed on the EA will be analyzed by staff and 
considered in the Commission's final licensing decision.
    The application will be processed according to the following 
schedule. Revisions to the schedule may be made as appropriate.

------------------------------------------------------------------------
               Milestone                           Target date
------------------------------------------------------------------------
Commission issues EA...................  December 2023.\1\
Comments on EA.........................  January 2024.
------------------------------------------------------------------------
\1\ The Council on Environmental Quality's (CEQ) regulations under 40
  CFR 1501.10(b)(1) require that EAs be completed within 1 year of the
  federal action agency's decision to prepare an EA. This notice
  establishes the Commission's intent to prepare an EA for the Alice
  Falls Project. Therefore, in accordance with CEQ's regulations, the EA
  must be issued within 1 year of the issuance date of this notice.

    Any questions regarding this notice may be directed to Nicholas 
Tackett at (202) 502-6783 or [email protected].

    Dated: April 24, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-09027 Filed 4-27-23; 8:45 am]
BILLING CODE 6717-01-P