Takes of Marine Mammals Incidental to Specified Activities; Taking Marine Mammals Incidental to U.S. Navy Construction at Portsmouth Naval Shipyard, Kittery, Maine, 20493-20500 [2023-07164]
Download as PDF
ddrumheller on DSK120RN23PROD with NOTICES1
Federal Register / Vol. 88, No. 66 / Thursday, April 6, 2023 / Notices
anticipate using this information in the
future.
Second, we propose consolidating the
fishery-level detail requests from
Question 19: ‘‘Fish Received. In the
table below provide the weight and cost
of fish received.’’ For groundfish
species, the existing form requests
weight not paid for, weight paid for, and
cost of fish by species group for three
fisheries (LE Trawl, LE Fixed Gear, and
Other) as well as Non-vessel sources. In
the revised form, the table will be
consolidated to only request Vessel
sources and Non-vessel sources. This
will be a net reduction of 72 data entry
cells on the form (12 species groups ×
removal of 2 fisheries × 3 fields). We
will no longer request this information
because fishery-detail information can
be obtained from other sources.
Third, we propose revising how
intercompany transfers and inventory
are reported on the form. Similar to the
quota share owner survey, there are
extensive instructions on handling these
two topics, but reporting errors are
extremely common. To facilitate
accurate reporting of intercompany
transfers, we will remove a column
dedicated to transfer information from
Question 19 and remove instructions
about recording transfers in Question
20. Then, all of the transfer-related
information will be moved to a separate
question/table. This change will make
the survey instructions easier to
understand, allow companies that do
not have intercompany transfers to skip
the question entirely, and will make it
easier to detect and remedy mistakes.
Similarly, there are extensive
instructions on how to record inventory
in Question 20 on the existing form, but
no dedicated field for inventory.
Instead, participants are currently
instructed to add inventory to the other
sales categories. We propose adding a
new line for each species group to
record the inventory volume and value.
Similar to the changes to transfers in
Question 19 and 20, the new structure
of Question 20 clarifies how to complete
the form and facilitates identifying and
resolving errors. Finally, this change
will provide new important information
about inventory volumes across years,
providing better information about the
status of the processing sector to the
Pacific Fishery Management Council.
Lastly, a common performance metric
for fisheries programs is hourly wage
payments to processing workers. In the
current form, we request the total
number of workers and total hours
worked for the week that includes the
12th of each month and total annual
compensation payments. To calculate
hourly wages, we must extrapolate to
VerDate Sep<11>2014
21:13 Apr 05, 2023
Jkt 259001
the total hours worked for the year.
Through conversations with
participants, it has become apparent
that within-month employment can
have high variability and our
extrapolations are not always accurate.
We propose requesting the equivalent
compensation value for each of the oneweek windows to allow for a more
accurate calculation of hourly wages.
This additional field will also allow us
to generate an estimate of within-month
employment variability.
The only proposed change to the
Catcher Vessel survey form is to remove
two questions. In 2018, at the request of
participants in the trawl catch share
program, two additional questions were
added, Question 17: ‘‘Do you track
capitalized expenditures and expenses
on fishing gear by type (e.g., midwater
trawl gear, groundfish bottom trawl
gear)?’’ and Question 18: ‘‘Provide the
2021 total capitalized expenditures and
expenses associated with each type of
fishing gear used in West Coast
Fisheries (Washington, Oregon, and
California).’’ Since the implementation
of the questions in 2018, there has only
been one ‘‘Yes’’ out nearly 700 total
responses to Question 17 and therefore
no further information about gearspecific costs have been collected.
Therefore there will be no information
loss associated with removal of these
two questions and there will be a small
reduction in total burden hours.
II. Method of Collection
Vessel, first receiver, and shorebased
processor forms may be submitted via
mail or electronically. All quota share
owner survey forms must be submitted
online as part of the quota share permit
renewal system.
III. Data
OMB Control Number: 0648–0618.
Form Number(s): None.
Type of Review: Regular submission
(Revision and extension of a current
information collection).
Affected Public: Business or other forprofit and not-for-profit organization.
Estimated Number of Respondents:
352.
Estimated Time per Response: 8 hours
for catcher processors, catcher vessels,
and motherships, 1 hour for quota share
permit owners, and 20 hours for first
receivers and shorebased processors.
Estimated Total Annual Burden
Hours: 2,209.
Estimated Total Annual Cost to
Public: $3,668.45 in recordkeeping/
reporting costs.
Respondent’s Obligation: Mandatory.
Legal Authority: 50 CFR 660.114.
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
20493
IV. Request for Comments
We are soliciting public comments to
permit the Department/Bureau to: (a)
Evaluate whether the proposed
information collection is necessary for
the proper functions of the Department,
including whether the information will
have practical utility; (b) Evaluate the
accuracy of our estimate of the time and
cost burden for this proposed collection,
including the validity of the
methodology and assumptions used; (c)
Evaluate ways to enhance the quality,
utility, and clarity of the information to
be collected; and (d) Minimize the
reporting burden on those who are to
respond, including the use of automated
collection techniques or other forms of
information technology.
Comments that you submit in
response to this notice are a matter of
public record. We will include or
summarize each comment in our request
to OMB to approve this ICR. Before
including your address, phone number,
email address, or other personal
identifying information in your
comment, you should be aware that
your entire comment—including your
personal identifying information—may
be made publicly available at any time.
While you may ask us in your comment
to withhold your personal identifying
information from public review, we
cannot guarantee that we will be able to
do so.
Sheleen Dumas,
Department PRA Clearance Officer, Office of
the Under Secretary for Economic Affairs,
Commerce Department.
[FR Doc. 2023–07236 Filed 4–5–23; 8:45 am]
BILLING CODE 3510–22–P
DEPARTMENT OF COMMERCE
National Oceanic and Atmospheric
Administration
[RTID 0648–XC893]
Takes of Marine Mammals Incidental to
Specified Activities; Taking Marine
Mammals Incidental to U.S. Navy
Construction at Portsmouth Naval
Shipyard, Kittery, Maine
National Marine Fisheries
Service (NMFS), National Oceanic and
Atmospheric Administration (NOAA),
Commerce.
ACTION: Notice; issuance of renewal
incidental harassment authorization
(IHA).
AGENCY:
In accordance with the
regulations implementing the Marine
Mammal Protection Act (MMPA), as
amended, notification is hereby given
SUMMARY:
E:\FR\FM\06APN1.SGM
06APN1
20494
Federal Register / Vol. 88, No. 66 / Thursday, April 6, 2023 / Notices
ddrumheller on DSK120RN23PROD with NOTICES1
that NMFS has issued a renewal
incidental harassment authorization
(IHA) to the U.S. Navy (Navy) to
incidentally harass marine mammals
incidental to construction activities
associated with the multifunctional
expansion of Dry Dock 1 project at
Portsmouth Naval Shipyard in Kittery,
Maine.
DATES: This renewal IHA is valid from
April 1, 2023 through March 31, 2024.
FOR FURTHER INFORMATION CONTACT:
Reny Tyson Moore, Office of Protected
Resources, NMFS, (301) 427–8401.
Electronic copies of the original
application, renewal request, and
supporting documents (including NMFS
Federal Register notices of the original
proposed and final authorizations, and
the previous IHA), as well as a list of the
references cited in this document, may
be obtained online at: https://
www.fisheries.noaa.gov/permit/
incidental-take-authorizations-undermarine-mammal-protection-act. In case
of problems accessing these documents,
please call the contact listed above.
SUPPLEMENTARY INFORMATION:
Background
The Marine Mammal Protection Act
(MMPA) prohibits the ‘‘take’’ of marine
mammals, with certain exceptions.
Sections 101(a)(5)(A) and (D) of the
MMPA (16 U.S.C. 1361 et seq.) direct
the Secretary of Commerce (as delegated
to NMFS) to allow, upon request, the
incidental, but not intentional, taking of
small numbers of marine mammals by
U.S. citizens who engage in a specified
activity (other than commercial fishing)
within a specified geographical region if
certain findings are made and either
regulations are issued or, if the taking is
limited to harassment, an incidental
harassment authorization is issued.
Authorization for incidental takings
shall be granted if NMFS finds that the
taking will have a negligible impact on
the species or stock(s) and will not have
an unmitigable adverse impact on the
availability of the species or stock(s) for
taking for subsistence uses (where
relevant). Further, NMFS must prescribe
the permissible methods of taking and
other ‘‘means of effecting the least
practicable adverse impact’’ on the
affected species or stocks and their
habitat, paying particular attention to
rookeries, mating grounds, and areas of
similar significance, and on the
availability of such species or stocks for
taking for certain subsistence uses
(referred to here as ‘‘mitigation
measures’’). Monitoring and reporting of
such takings are also required. The
meaning of key terms such as ‘‘take,’’
‘‘harassment,’’ and ‘‘negligible impact’’
VerDate Sep<11>2014
21:13 Apr 05, 2023
Jkt 259001
can be found in section 3 of the MMPA
(16 U.S.C. 1362) and the agency’s
regulations at 50 CFR 216.103.
NMFS’ regulations implementing the
MMPA at 50 CFR 216.107(e) indicate
that IHAs may be renewed for
additional periods of time not to exceed
1 year for each reauthorization. In the
notice of proposed IHA for the initial
authorization, NMFS described the
circumstances under which we would
consider issuing a renewal for this
activity, and requested public comment
on a potential renewal under those
circumstances. Specifically, on a caseby-case basis, NMFS may issue a onetime 1-year renewal IHA following
notice to the public providing an
additional 15 days for public comments
when (1) up to another year of identical,
or nearly identical, activities as
described in the Detailed Description of
Specified Activities section of the initial
IHA issuance notice is planned or (2)
the activities as described in the
Description of the Specified Activities
and Anticipated Impacts section of the
initial IHA issuance notice would not be
completed by the time the initial IHA
expires and a renewal would allow for
completion of the activities beyond that
described in the DATES section of the
notice of issuance of the initial IHA,
provided all of the following conditions
are met:
1. A request for renewal is received no
later than 60 days prior to the needed
renewal IHA effective date (recognizing
that the renewal IHA expiration date
cannot extend beyond 1 year from
expiration of the initial IHA);
2. The request for renewal must
include the following:
• An explanation that the activities to
be conducted under the requested
renewal IHA are identical to the
activities analyzed under the initial
IHA, are a subset of the activities, or
include changes so minor (e.g.,
reduction in pile size) that the changes
do not affect the previous analyses,
mitigation and monitoring
requirements, or take estimates (with
the exception of reducing the type or
amount of take);
• A preliminary monitoring report
showing the results of the required
monitoring to date and an explanation
showing that the monitoring results do
not indicate impacts of a scale or nature
not previously analyzed or authorized;
and
3. Upon review of the request for
renewal, the status of the affected
species or stocks, and any other
pertinent information, NMFS
determines that there are no more than
minor changes in the activities, the
mitigation and monitoring measures
PO 00000
Frm 00029
Fmt 4703
Sfmt 4703
will remain the same and appropriate,
and the findings in the initial IHA
remain valid.
An additional public comment period
of 15 days (for a total of 45 days), with
direct notice by email, phone, or postal
service to commenters on the initial
IHA, is provided to allow for any
additional comments on the proposed
renewal. A description of the renewal
process may be found on our website at:
www.fisheries.noaa.gov/national/
marine-mammal-protection/incidentalharassment-authorization-renewals.
History of Request
On April 1, 2022, NMFS issued an
IHA to the Navy to take marine
mammals incidental to construction
activities associated with the
multifunctional expansion of Dry Dock
1 project (also referred to as P–381) at
Portsmouth Naval Shipyard in Kittery,
Maine (87 FR 19886, April 6, 2022),
effective from April 1, 2022 through
March 31, 2022. On January 31, 2023,
NMFS received an application for the
renewal of that initial IHA. NMFS
received a revised application for the
renewal IHA on February 24, 2023. As
described in the application for renewal
IHA, the activities for which incidental
take is requested consist of activities
that are covered by the initial
authorization but will not be completed
prior to its expiration. As required, the
applicant also provided a preliminary
monitoring report which confirms that
the applicant has implemented the
required mitigation and monitoring, and
which also shows that no impacts of a
scale or nature not previously analyzed
or authorized have occurred as a result
of the activities conducted. There are no
changes from the proposed
authorization in this final authorization.
Description of the Specified Activities
and Anticipated Impacts
Multifunctional Expansion of Dry
Dock 1 (P–381) is one of three projects
that support the overall expansion and
modification of Dry Dock 1, located in
the western extent of the Portsmouth
Naval Shipyard. The two additional
projects, construction of a super flood
basin (P–310) and extension of portal
crane rail and utilities (P–1074), are
currently under construction. In-water
work associated with these projects was
completed under separate IHAs issued
by NMFS in 2019 (84 FR 24476, May 28,
2019), and in a renewal of the 2019 IHA
(86 FR 14598, March 17, 2021). The
projects have been phased to support
Navy mission schedules. P–381 will be
constructed within the same footprint of
the super flood basin over an
approximate 7-year period, during
E:\FR\FM\06APN1.SGM
06APN1
20495
Federal Register / Vol. 88, No. 66 / Thursday, April 6, 2023 / Notices
which 5 years of in-water work will
occur. The initial IHA authorized takes
for marine mammals during the first
year of in-water construction for P–381
occurring from April 2022 through
March 2023. All work beyond year 1 has
been addressed in proposed incidental
take regulations (88 FR 3146, January
18, 2023).
The purpose of this project,
Multifunctional Expansion of Dry Dock
1 (P–381), is to modify the super flood
basin to create two additional dry
docking positions (Dry Dock 1 North
and Dry Dock 1 West) in front of the
existing Dry Dock 1 East. The super
flood basin provides the starting point
for the P–381 work (see Figure 1–2 of
the Navy’s application for the initial
IHA). This renewal will cover a subset
of the activities covered in the initial
IHA that will not be completed during
the effective IHA period due to project
delays (see Detailed Description of the
Activity for specific activities to be
covered in the renewal IHA). This
includes the preparation of the walls
and floors of the super flood basin to
support the placement of the monoliths
and the construction of the two dry
dock positions.
Construction activities that could
affect marine mammals are limited to
in-water pile driving and removal
activities, rock hammering, rotary
drilling, and down-the-hole (DTH)
hammering. Under the initial IHA, Level
A harassment and Level B harassment
was authorized for harbor porpoises
(Phocoena phocoena), harbor seals
(Phoca vitulina), gray seals (Halichoerus
grypus), harp seals (Pagophilus
groenlandicus) and hooded seals
(Cystophora cristata). Neither the Navy
nor NMFS expects serious injury or
mortality to result from this activity
and, therefore, a renewal IHA is
appropriate.
The following documents are
referenced in this notification and
include important supporting
information:
• Initial 2022 Final IHA (87 FR
19886, April 6, 2022);
• Initial 2022 Proposed IHA (87 FR
11860, March 3, 2022);
• Initial IHA application and
References;
• Letter of Authorization (LOA)
Application Addendum Memo (October
31, 2022); and
• 2023 Proposed renewal IHA (88 FR
15982, March 15, 2023).
All of these referenced documents are
available at https://
www.fisheries.noaa.gov/action/
incidental-take-authorization-us-navyconstruction-portsmouth-navalshipyard-kittery-maine.
Detailed Description of the Activity
A detailed description of the
construction activities for which take is
authorized here may be found in the
Federal Register notices of the proposed
(87 FR 11860, March 3, 2022) and final
(87 FR 19886, April 6, 2022) IHAs for
the initial authorization as well as in the
LOA Application Addendum Memo
(submitted to NMFS on October 31,
2023), which described project
modifications and shifting Fleet
submarine schedules. As previously
mentioned, this request is for a subset
of the activities authorized in the initial
IHA that would not be completed prior
to its expiration due to project delays.
The location, timing, and nature of the
activities, including the types of
equipment planned for use, are identical
to those described in the previous
notices. Table 1 describes the status of
all activities covered under the initial
IHA as well as the amount of activities
covered under the renewal IHA. This
renewal IHA is effective for a period not
exceeding 1 year from the date of
expiration of the initial IHA.
TABLE 1—STATUS OF PILE DRIVING AND DRILLING ACTIVITIES
Number
remaining to
be installed
under
renewal IHA
1 shaft/day; 1
hour/day.
14
6
20
6
1 shaft/day; 9
hours/day.
1 casing/day; 15
minutes/casing.
6.5 days/shaft; 10
hours/day.
1 shaft/day; 1
hour/day.
14
6
20
6
10
10
20
10
2
18
130
117
0
0
18
0
1 shaft/day; 9
hours/day.
1 casing/day; 15
minutes/casing.
7.5 days/shaft; 10
hours/day.
1 shaft/day; 1
hour/day.
0
0
18
0
0
0
18
0
0
0
135
0
0
0
38
0
0
0
38
0
0
0
38
0
0
0
38
0
6
0
6
0
0
0
18
0
0
0
9
0
Total amount
Activity component
Method
Center Wall—Install
Foundation Support Piles.
20 drilled shafts 1 ..
Install 102-inch diameter outer
casing.
Pre-drill 102-inch
diameter socket.
Remove 102-inch
outer casing.
Drill 78-inch diameter shaft.
Install 102-inch diameter outer
casing.
Pre-drill 102-inch
diameter socket.
Remove 102-inch
outer casing.
Drill 78-inch diameter shaft.
Install 102-inch diameter outer
casing.
Pre-drill 102-inch
diameter socket.
Remove 102-inch
outer casing.
Drill 78-inch diameter shaft.
42-inch diameter
shaft.
Rotary Drill ...........
Rotary Drill ...........
Mono-hammer
DTH.
1 shaft/day; 9
hours/day.
1 casing/day; 15
minutes/casing.
3.5 days/shaft; 10
hours/day.
1 shaft/day; 10
hours/day.
9-inch diameter
holes.
9-inch diameter
holes.
Mono-hammer
DTH.
Mono-hammer
DTH.
2 holes/day; 5
hours/hole.
2 holes/day; 5
hours/hole.
Center Wall—Install
Diving Board
Shafts 2.
Center Wall—Temporary Launching
Piles.
Center Wall Tie
Downs 3.
Center Wall—Access Platform Tie
Downs 3.
VerDate Sep<11>2014
18 drilled shafts ....
38 drilled shafts ....
Center Wall—Access Platform
Support 3.
ddrumheller on DSK120RN23PROD with NOTICES1
Number
installed
under initial
IHA
Daily production
rate
Activity
6 drilled shafts ......
Install 36 rock anchors.
Install 18 rock anchors.
21:13 Apr 05, 2023
Jkt 259001
PO 00000
Rotary Drill ...........
Cluster drill DTH ...
Rotary Drill ...........
Rotary Drill ...........
Rotary Drill ...........
Cluster drill DTH ...
Rotary Drill ...........
Rotary Drill ...........
Rotary Drill ...........
Cluster drill DTH ...
Frm 00030
Fmt 4703
Sfmt 4703
E:\FR\FM\06APN1.SGM
06APN1
Total
production
days
Number of
production
days under
renewal IHA
20496
Federal Register / Vol. 88, No. 66 / Thursday, April 6, 2023 / Notices
TABLE 1—STATUS OF PILE DRIVING AND DRILLING ACTIVITIES—Continued
Number
installed
under initial
IHA
Number
remaining to
be installed
under
renewal IHA
4 piles/day; 5 minutes and; 300
blows/pile.
0
16
4
4
Impact with initial
vibratory set.
8 piles/day; 5 minutes and; 300
blows/pile.
60
0
8
0
Granite block demolition.
Hydraulic rock
hammering.
2.5 hours/day .......
0
0
NA
0
238 sheet piles .....
18-inch wide flatsheets.
Vibratory extraction.
4 piles/day; 5 minutes/pile.
0
238
60
60
985 cy ...................
Excavate bedrock
Hydraulic rock
hammering.
9 hours/day ..........
0
985
77
77
Drill 500 relief
holes.
Drill 46 rock borings (50 cy).
Drill 28 shafts .......
4–6 inch holes ......
Mono-hammer
DTH.
Mono-hammer
DTH.
Mono-hammer
DTH.
25 holes/day; 24
minutes/hole.
2 borings/day; 5
hours/boring.
1 shaft/day; 10
hours/day.
0
500
20
20
46
0
5 24
0
0
28
28
28
Hydraulic rock
hammering.
Hydraulic rock
hammering.
Mono-hammer
DTH.
Mono-hammer
DTH.
5 hours/day ..........
92
20
56
10
12 hours/day ........
27 holes/day; 22.2
minutes/hole.
700
300
2800
977
100
48
80
37
2 borings/day; 5
hours/boring.
0
365
183
183
Activity
Total amount
Center Wall—Install
Tie-In to Existing
West Closure
Wall.
Berth 11 End
Wall—Install Secant Pile Guide
Wall.
Berth 1—Remove
Granite Block
Quay Wall 4.
P–310 West Closure Wall—Remove Closure
Wall.
P–310 West Closure Wall—Mechanical Rock
Excavation.
P–310 West Closure Wall—Mechanical Rock
Excavation.
West Closure
wall—Berth 11
Abutment—Install
Piles.
Berth 11—Remove
Shutter Panels.
Berth 11 Face—
Mechanical Rock
Removal at Basin
Floor.
Berth 11 Face—
Mechanical Rock
at Abutment.
Dry Dock 1 North
Entrance—Drill
Tremie Tie
Downs.
Dry Dock 1 North
Entrance—Install
Temporary
Cofferdam.
Berth 1—Remove
Sheet Piles.
Berth 1 Top of
Wall—Demolition
For Waler Installation 6.
Berth 1 Mechanical
Rock Removal at
Basin Floor 7.
Removal of Berth 1
Emergency Repair Sheets 7.
Removal of Berth 1
Emergency Repair Tremie Concrete 7.
16 sheet piles .......
28-inch wide Zshaped sheets.
Impact with initial
vibratory set.
60 sheet piles .......
28-inch wide Zshaped sheets.
610 cy ...................
Totals ..............
112 panels ............
3,500 cy ................
Drill 1,277 relief
holes 1.
Activity component
42-inch diameter
casing.
42-inch diameter
casing.
Demolish shutter
panels.
Excavate Bedrock
4–6 inch holes ......
Daily production
rate
Method
Number of
production
days under
renewal IHA
Drill 365 rock borings (1,220 cy).
42-inch diameter
casing.
Drill 50 rock anchors 1.
9-inch holes ..........
Mono-hammer
DTH.
2 holes/day; 2
hours/hole.
0
25
25
25
Install 48 sheet
piles 1.
28-inch wide Zshaped sheets.
Impact with initial
vibratory set.
8 sheets/day; 5
minutes and 300
blows/pile.
0
48
6
6
Remove 12 sheet
piles.
30 lf ......................
25-inch wide; Zshaped sheets.
Mechanical concrete demolition.
Hydraulic rock
hammering.
Hydraulic rock
hammering.
6 hours/day ..........
0
12
3
3
10 hours/day ........
NA
NA
NA
NA
200 cy ...................
Excavate Bedrock
Hydraulic rock
hammering.
13 cy/day; 12
hours/day.
0
200
39
39
108 sheet piles .....
25-inch wide Zshaped sheets.
Vibratory extraction.
6 piles/day; 5 minutes/pile.
0
108
18
18
500 cy ...................
Mechanical concrete demolition.
Hydraulic rock
hammering.
4 hours/day ..........
0
500
15
15
...............................
...............................
...............................
...............................
1,244
6,862
1,278
744
1 The
ddrumheller on DSK120RN23PROD with NOTICES1
Total
production
days
amount of this activity was adjusted in a memo describing project modifications and shifting Fleet submarine schedules that was submitted to NMFS on October 31, 2022. The memo can be found at https://www.fisheries.noaa.gov/action/incidental-take-authorization-us-navy-construction-portsmouth-naval-shipyard-kitterymaine-0.
2 The schedule for this work shifted as described in the aforementioned memo submitted to NMFS on October 31, 2022. This activity is now addressed in the proposed rulemaking/LOA (88 FR 3146, January 18, 2023).
3 These activities are no longer needed.
4 This activity is complete; it was performed above the water line. The underwater portion of this activity is addressed in the proposed rulemaking/LOA (88 FR 3146,
January 18).
5 An additional day was added to account for equipment repositioning.
6 This activity is complete; it was performed above the water line.
7 This activity was added to the initial IHA in the aforementioned memo submitted to NMFS on October 31, 2022.
VerDate Sep<11>2014
21:13 Apr 05, 2023
Jkt 259001
PO 00000
Frm 00031
Fmt 4703
Sfmt 4703
E:\FR\FM\06APN1.SGM
06APN1
20497
Federal Register / Vol. 88, No. 66 / Thursday, April 6, 2023 / Notices
Description of Marine Mammals in the
Area of Specified Activities
A description of the marine mammals
in the area of the activities for which
take is authorized here, including
information on abundance, status,
distribution, and hearing, may be found
in the Notice of the proposed IHA for
the initial authorization (87 FR 11860,
March 3, 2022). NMFS has reviewed the
monitoring data from the initial IHA,
recent draft Stock Assessment Reports,
information on relevant Unusual
Mortality Events, and other scientific
literature, and determined that neither
this nor any other new information
affects which species or stocks have the
potential to be affected or the pertinent
information in the Description of the
Marine Mammals in the Area of
Specified Activities contained in the
supporting documents for the initial
IHA.
Potential Effects on Marine Mammals
and their Habitat
A description of the potential effects
of the specified activity on marine
mammals and their habitat for the
activities for which the authorization of
take is authorized here may be found in
the Federal Register notice of the
proposed IHA for the initial
authorization (87 FR 11860, March 3,
2022). NMFS has reviewed the
monitoring data from the initial IHA,
recent draft Stock Assessment Reports,
information on relevant Unusual
Mortality Events, and other scientific
literature, and determined that neither
this nor any other new information
affects our initial analysis of impacts on
marine mammals and their habitat.
Estimated Take
A detailed description of the methods
and inputs used to estimate take for the
specified activity are found in the
Federal Register notices of the proposed
(87 FR 11860, March 3, 2022) and final
(87 FR 19886, April 6, 2022) IHAs for
the initial authorization as well as the
Federal Register notice of the proposed
renewal IHA (88 FR 15982, March 15,
2023). Specifically, the marine mammal
density and occurrence data applicable
to this authorization remain unchanged
from the previously issued IHA.
Similarly, the stocks taken and types of
take remain unchanged from the
previously issued IHA. Since the initial
IHA was issued, NMFS updated its
recommendations on source pressure
levels (SPLs) to use when evaluating
DTH systems and reevaluated the data
available on rock hammering activities.
Updates to recommended SPLs for these
activities, however, did not result in any
changes to the estimated take as
described in the proposed renewal IHA
(88 FR 15982, March 15, 2023).
Tables 2, 3, and 4 provide the
authorized take by Level A and Level B
harassment for harbor porpoises, harbor
seals, and grey seals, respectively. Given
that a subset of the initially covered
activities would be occurring, the
number of days of operation, and thus
number of takes, has been reduced for
each species. Note that the final take
numbers differ slightly from those
provided in the Navy’s request for
renewal of the IHA based on rounding
errors found in the request. Further, in
the initial IHA that was issued, takes by
Level B harassment for harbor seals and
grey seals were increased to more
accurately reflect the number of seal
sightings reported in recent monitoring
reports. However, this adjustment has
not been requested or made for the
renewal IHA based on the reduction in
the number of construction days. The
take calculation for hooded and harp
seals remains the same from the initial
IHA (see the Federal Register notices of
the proposed (87 FR 11860, March 3,
2022) and final (87 FR 19886, April 6,
2022) IHAs for the initial authorization
for more information).
ddrumheller on DSK120RN23PROD with NOTICES1
TABLE 2—AUTHORIZED TAKE BY LEVEL A AND LEVEL B HARASSMENT OF HARBOR PORPOISE BY PROJECT ACTIVITY FOR
THE RENEWAL IHA
Number of
production
days under
renewal IHA
Level A
harassment
zone (km2)
Takes by
Level A
harassment
Level B
harassment
zone
(km2)
Take by
Level B
harassment
0.4
0.4
0.4
0.4
0.4
0.4
0.00001
0.00025
0.00000
0.41742
0.00045
0.40341
0
0
0
2
0
0
0.41742
0.41742
0.41742
0.41742
0.41742
0.41742
0
0
0
0
0
0
60
0.4
0.00014
0
0.41742
1
Hydraulic rock hammering.
77
0.4
0.41742
1
0.277858
0
Drill 500 relief holes ..
Mono-hammer DTH ...
20
0.4
0.04811
0
0.41742
0
Drill 28 shafts ............
Mono-hammer DTH ...
28
0.4
0.41742
0
0.41742
0
112 panels .................
Hydraulic rock hammering.
Hydraulic rock hammering.
10
0.4
0.41742
0
0.277858
0
80
0.4
0.41742
1
0.277858
0
Activity
Total amount
Method
Center Wall—Install Foundation Support Piles.
20 drilled shafts .........
Center Wall—Install Tie-In
to Existing West Closure
Wall.
P–310 West Closure
Wall—Remove Closure
Wall.
P–310 West Closure
Wall—Mechanical Rock
Excavation.
P–310 West Closure
Wall—Mechanical Rock
Excavation.
West Closure wall—Berth
11 Abutment—Install
Piles.
Berth 11—Remove Shutter
Panels.
Berth 11 Face—Mechanical Rock Removal at
Basin Floor.
16 sheet piles ............
Rotary Drill .................
Rotary Drill .................
Rotary Drill .................
Cluster drill DTH ........
Initial vibratory set .....
Impact ........................
6
6
10
117
4
4
238 sheet piles ..........
Vibratory extraction ...
985 cy ........................
Berth 11 Face—Mechanical Rock at Abutment.
Dry Dock 1 North Entrance—Drill Tremie Tie
Downs.
Dry Dock 1 North Entrance—Install Temporary Cofferdam.
VerDate Sep<11>2014
3,500 cy .....................
Density
Drill 1,277 relief holes
Drill 365 rock borings
(1,220 cy).
Drill 50 rock anchors
Mono-hammer DTH ...
Mono-hammer DTH ...
37
183
0.4
0.4
0.04811
0.41742
0
3
0.41742
0.41742
1
0
Mono-hammer DTH ...
25
0.4
0.03036
0
0.41742
0
Install 48 sheet piles
Initial vibratory set .....
Impact ........................
6
6
0.4
0.4
0.00104
0.41742
0
0
0.41742
0.41742
0
0
21:13 Apr 05, 2023
Jkt 259001
PO 00000
Frm 00032
Fmt 4703
Sfmt 4703
E:\FR\FM\06APN1.SGM
06APN1
20498
Federal Register / Vol. 88, No. 66 / Thursday, April 6, 2023 / Notices
TABLE 2—AUTHORIZED TAKE BY LEVEL A AND LEVEL B HARASSMENT OF HARBOR PORPOISE BY PROJECT ACTIVITY FOR
THE RENEWAL IHA—Continued
Number of
production
days under
renewal IHA
Activity
Total amount
Method
Berth 1—Remove Sheet
Piles.
Berth 1 Mechanical Rock
Removal at Basin Floor.
Removal of Berth 1 Emergency Repair Sheets.
Removal of Berth 1 Emergency Repair Tremie
Concrete.
Remove 12 sheet
piles.
200 cy ........................
Hydraulic rock hammering.
Hydraulic rock hammering.
Vibratory extraction ...
500 cy ........................
Hydraulic rock hammering.
Total Estimated Take
....................................
....................................
108 sheet piles ..........
Density
Level A
harassment
zone (km2)
Takes by
Level A
harassment
Level B
harassment
zone
(km2)
Take by
Level B
harassment
3
0.4
0.41742
0
0.277858
0
39
0.4
0.41742
1
0.277858
0
18
0.4
0.00073
0
0.41742
0
15
0.4
0.41742
0
0.277858
0
....................
....................
....................
10
....................
2
TABLE 3—CALCULATED TAKE BY LEVEL A AND LEVEL B HARASSMENT OF HARBOR SEAL BY PROJECT ACTIVITY FOR THE
PROPOSED RENEWAL IHA
Takes by
Level A
harassment
Level B
harassment
zone
(km2)
Take by
Level B
harassment
3
3
3
3
3
3
0.00001
0.00009
0.00000
0.41742
0.00008
0.20116
0
0
0
146
0
2
0.41742
0.41742
0.41742
0.41742
0.41742
0.41742
8
8
13
0
5
3
60
3
0.00002
0
0.41742
75
Hydraulic rock hammering.
77
3
0.41742
96
0.277858
0
Drill 500 relief holes ..
Mono-hammer DTH ...
20
3
0.01455
1
0.41742
24
Drill 28 shafts ............
Mono-hammer DTH ...
28
3
0.41742
35
0.41742
0
112 panels .................
Hydraulic rock hammering.
Hydraulic rock hammering.
10
3
0.41742
13
0.277858
0
80
3
0.41742
100
0.277858
0
Total amount
Method
Center Wall—Install Foundation Support Piles.
20 drilled shafts .........
Center Wall—Install Tie-In
to Existing West Closure
Wall.
P–310 West Closure
Wall—Remove Closure
Wall.
P–310 West Closure
Wall—Mechanical Rock
Excavation.
P–310 West Closure
Wall—Mechanical Rock
Excavation.
West Closure Wall—Berth
11 Abutment—Install
Piles.
Berth 11—Remove Shutter
Panels.
Berth 11 Face—Mechanical Rock Removal at
Basin Floor.
16 sheet piles ............
Rotary Drill .................
Rotary Drill .................
Rotary Drill .................
Cluster drill DTH ........
Initial vibratory set .....
Impact ........................
6
6
10
117
4
4
238 sheet piles ..........
Vibratory extraction ...
985 cy ........................
Berth 11 Face—Mechanical Rock at Abutment.
Dry Dock 1 North Entrance—Drill Tremie Tie
Downs.
Dry Dock 1 North Entrance—Install Temporary Cofferdam.
Berth 1—Remove Sheet
Piles.
Berth 1 Mechanical Rock
Removal at Basin Floor.
Removal of Berth 1 Emergency Repair Sheets.
Removal of Berth 1 Emergency Repair Tremie
Concrete.
Total Estimated Take
ddrumheller on DSK120RN23PROD with NOTICES1
Level A
harassment
zone
(km2)
Number of
production
days under
renewal IHA
Activity
3,500 cy .....................
Density
Drill 1,277 relief holes
Drill 365 rock borings
(1,220 cy).
Drill 50 rock anchors
Mono-hammer DTH ...
Mono-hammer DTH ...
37
183
3
3
0.01455
0.41742
2
229
0.41742
0.41742
45
0
Mono-hammer DTH ...
25
3
0.00903
1
0.41742
31
Install 48 sheet piles
Initial vibratory set .....
Impact ........................
6
6
3
3
0.00104
0.36495
8
7
0.41742
1.50227
0
1
Remove 12 sheet
piles.
200 cy ........................
Hydraulic rock hammering.
Hydraulic rock hammering.
Vibratory extraction ...
3
3
0.41742
4
0.277858
0
39
3
0.41742
49
0.277858
0
18
3
0.00014
0
0.41742
23
15
3
0.41742
19
0.277858
0
....................
....................
....................
704
....................
244
108 sheet piles ..........
500 cy ........................
Hydraulic rock hammering.
....................................
....................................
TABLE 4—CALCULATED TAKE BY LEVEL A AND LEVEL B HARASSMENT OF GREY SEAL BY PROJECT ACTIVITY FOR THE
RENEWAL IHA
Number of
production
days under
renewal IHA
Activity
Total amount
Method
Center Wall—Install Foundation Support Piles.
20 drilled shafts .........
Rotary Drill .................
Rotary Drill .................
VerDate Sep<11>2014
21:13 Apr 05, 2023
Jkt 259001
PO 00000
Frm 00033
Fmt 4703
6
6
Sfmt 4703
Density
0.02
0.02
Level A
harassment
zone
(km2)
Takes by
Level A
harassment
Level B
harassment
zone
(km2)
Take by
Level B
harassment
0.00001
0.00009
0
0
0.41742
0.41742
1
1
E:\FR\FM\06APN1.SGM
06APN1
20499
Federal Register / Vol. 88, No. 66 / Thursday, April 6, 2023 / Notices
TABLE 4—CALCULATED TAKE BY LEVEL A AND LEVEL B HARASSMENT OF GREY SEAL BY PROJECT ACTIVITY FOR THE
RENEWAL IHA—Continued
Activity
Total amount
Center Wall—Install Tie-In
to Existing West Closure
Wall.
P–310 West Closure
Wall—Remove Closure
Wall.
P–310 West Closure
Wall—Mechanical Rock
Excavation.
P–310 West Closure
Wall—Mechanical Rock
Excavation.
West Closure Wall—Berth
11 Abutment—Install
Piles.
Berth 11—Remove Shutter
Panels.
Berth 11 Face—Mechanical Rock.
Removal at Basin Floor ....
Berth 11 Face—Mechanical Rock at Abutment.
Dry Dock 1 North Entrance—Drill Tremie Tie
Downs.
Dry Dock 1 North Entrance—Install Temporary Cofferdam.
Berth 1—Remove Sheet
Piles.
Berth 1 Mechanical Rock
Removal at Basin Floor.
Removal of Berth 1 Emergency Repair Sheets.
Removal of Berth 1 Emergency Repair Tremie
Concrete.
Total Estimated Take
Number of
production
days under
renewal IHA
Method
Density
Level A
harassment
zone
(km2)
Takes by
Level A
harassment
Level B
harassment
zone
(km2)
Take by
Level B
harassment
Rotary Drill .................
Cluster drill DTH ........
Initial vibratory set .....
Impact ........................
10
117
4
4
0.02
0.02
0.02
0.02
0.00000
0.41742
0.00008
0.20116
0
10
0
0
0.41742
0.41742
0.41742
0.41742
1
0
0
0
238 sheet piles ..........
Vibratory extraction ...
60
0.02
0.00002
0
0.41742
5
985 cy ........................
Hydraulic rock hammering.
77
0.02
0.41742
6
0.277858
0
Drill 500 relief holes ..
Mono-hammer DTH ...
20
0.02
0.01455
0
0.41742
2
Drill 28 shafts ............
Mono-hammer DTH ...
28
0.02
0.41742
2
0.41742
0
112 panels .................
Hydraulic rock hammering.
Hydraulic rock hammering.
Mono-hammer DTH ...
Mono-hammer DTH ...
10
0.02
0.41742
1
0.277858
0
80
0.02
0.41742
7
0.277858
0
37
183
0.02
0.02
0.01455
0.41742
0
15
0.41742
0.41742
3
0
Mono-hammer DTH ...
25
0.02
0.00903
0
0.41742
2
Install 48 sheet piles
Initial vibratory set .....
Impact ........................
6
6
0.02
0.02
0.00104
0.36495
0
0
0.41742
0.41742
1
0
Remove 12 sheet
piles.
200 cy ........................
Hydraulic rock hammering.
Hydraulic rock hammering.
Vibratory extraction ...
3
0.02
0.41742
0
0.277858
0
39
0.02
0.41742
3
0.277858
0
18
0.02
0.00014
0
0.41742
2
15
0.02
0.41742
1
0.277858
0
....................
....................
....................
45
....................
18
16 sheet piles ............
3,500 cy .....................
Drill 1,277 relief holes
Drill 365 rock borings
(1,220 cy).
Drill 50 rock anchors
108 sheet piles ..........
500 cy ........................
Hydraulic rock hammering.
....................................
....................................
Table 5 summarizes the authorized
take for all species described as a
percentage of stock abundance.
TABLE 5—TAKE ESTIMATES AS A PERCENTAGE OF STOCK ABUNDANCE
Species
Stock
(NEST)
Harbor porpoise ......................
Harbor seal .............................
Gray seal ................................
Hooded seal ............................
Harp seal ................................
Gulf of Maine/Bay of Fundy (95,543) .....................................
Western North Atlantic (61,336) .............................................
Western North Atlantic (27,300) .............................................
Western North Atlantic (593,500) ...........................................
Western North Atlantic (7.6 million) .......................................
ddrumheller on DSK120RN23PROD with NOTICES1
Description of Mitigation, Monitoring
and Reporting Measures
The mitigation, monitoring, and
reporting measures included as
requirements in the authorization are
identical to those included in the FR
Notice announcing the issuance of the
initial IHA (87 FR 19886, April 6, 2022),
and the discussion of the least
practicable adverse impact included in
that document remains accurate. The
VerDate Sep<11>2014
21:13 Apr 05, 2023
Jkt 259001
Level A
harassment
same measures are proposed for this
renewal and are summarized here:
• The Navy must delay pile driving
activities should poor environmental
conditions restrict full visibility of the
applicable shutdown zones;
• The Navy must ensure that all
construction supervisors and crews, the
monitoring team, and relevant Navy
staff are trained prior to commencing
work;
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
10
695
45
0
0
Level B
harassment
2
240
18
5
5
Percent of
stock
<0.1
<0.1
<0.1
<0.1
<0.1
• The Navy must implement a 10 m
shutdown zone around construction
activities to avoid direct physical
interaction with marine mammals;
• The Navy must establish and
implement shutdown and monitoring
zones for all pile driving activities based
on the activity type and marine mammal
hearing group (see Table 13 in the FR
Notice announcing the issuance of the
initial IHA (87 FR 19886, April 6, 2022)
E:\FR\FM\06APN1.SGM
06APN1
ddrumheller on DSK120RN23PROD with NOTICES1
20500
Federal Register / Vol. 88, No. 66 / Thursday, April 6, 2023 / Notices
for the shutdown and monitoring
zones);
• The Navy must implement soft start
techniques while impact driving
whereby hammer energy is gradually
ramped up;
• The Navy must install a bubble
curtain across any openings at the
entrance of super flood basin to
attenuate sound for the sound sources
that encompass the entire ROI, which
include during DTH excavation (DTH
mono-hammer and cluster drill),
hydraulic rock hammering, and impact
pile driving of sheet piles;
• The Navy must employ at least
three protected species observers (PSOs)
to monitor the shutdown and
monitoring zones;
• The Navy must monitor for the
presence of marine mammals 30
minutes prior to the initial pile-driving
activity (i.e., pre-start clearance
monitoring) through 30 minutes postcompletion of pile driving activity. If a
marine mammal is observed entering or
within the shutdown zones, pile driving
will be delayed or halted;
• The Navy will delay or halt pile
driving activities upon observation of
either a species for which incidental
take is not authorized or a species for
which incidental take has been
authorized but the authorized number of
takes has been met, entering or within
the harassment zone;
• The Navy will conduct a sound
source verification study for rotary
drilling, DTH excavation (DTH monohammer and cluster drill), and rock
hammering activities for any remaining
piles required to be monitored following
their acoustic monitoring plan as
described in the FR Notice announcing
the issuance of the initial IHA (87 FR
19886, April 6, 2022);
• The Navy must submit a draft
report detailing all monitoring within 90
calendar days of the completion of
marine mammal monitoring or 60 days
prior to the issuance of any subsequent
IHA for this project, whichever comes
first;
• The Navy must prepare and submit
final report within 30 days following
resolution of comments on the draft
report from NMFS;
• The Navy must submit all PSO
datasheets and/or raw sighting data (in
a separate file from the Final Report
referenced immediately above); and
• The Navy must report injured or
dead marine mammals.
Comments and Responses
A notice of NMFS’ proposal to issue
a renewal IHA to the Navy was
published in the Federal Register on
March 15, 2023 (88 FR 15982). That
VerDate Sep<11>2014
21:13 Apr 05, 2023
Jkt 259001
notice either described, or referenced
descriptions of, the applicant’s activity,
the marine mammal species that may be
affected by the activity, the anticipated
effects on marine mammals and their
habitat, estimated amount and manner
of take, and proposed mitigation,
monitoring and reporting measures.
NMFS received two comments that were
not relevant to the scope of the
proposed action. No other comments
were received.
Determinations
The renewal request consists of a
subset of activities analyzed through the
initial authorization described above. In
analyzing the effects of the activities for
the initial IHA, NMFS determined that
the Navy’s activities would have a
negligible impact on the affected species
or stocks and that authorized take
numbers of each species or stock were
small relative to the relevant stocks (e.g.,
less than one-third the abundance of all
stocks). Although new SPL information
became available for DTH and rock
hammering, none of this new
information affects NMFS’
determinations supporting issuance of
the initial IHA. The mitigation measures
and monitoring and reporting
requirements as described above are
identical to the initial IHA.
NMFS has concluded that there is no
new information suggesting that our
analysis or findings should change from
those reached for the initial IHA. Based
on the information and analysis
contained here and in the referenced
documents, NMFS has determined the
following: (1) the required mitigation
measures will effect the least practicable
impact on marine mammal species or
stocks and their habitat; (2) the
authorized takes will have a negligible
impact on the affected marine mammal
species or stocks; (3) the authorized
takes represent small numbers of marine
mammals relative to the affected stock
abundances; (4) the Navy’s activities
will not have an unmitigable adverse
impact on taking for subsistence
purposes as no relevant subsistence uses
of marine mammals are implicated by
this action; and, (5) appropriate
monitoring and reporting requirements
are included.
National Environmental Policy Act
To comply with the National
Environmental Policy Act of 1969
(NEPA; 42 U.S.C. 4321 et seq.) and
NOAA Administrative Order (NAO)
216–6A, NMFS must review our
proposed action (i.e., the issuance of an
IHA renewal) with respect to potential
impacts on the human environment.
PO 00000
Frm 00035
Fmt 4703
Sfmt 9990
This action is consistent with
categories of activities identified in
Categorical Exclusion B4 (incidental
take authorizations with no anticipated
serious injury or mortality) of the
Companion Manual for NOAA
Administrative Order 216–6A, which do
not individually or cumulatively have
the potential for significant impacts on
the quality of the human environment
and for which we have not identified
any extraordinary circumstances that
would preclude this categorical
exclusion. Accordingly, NMFS
determined that the issuance of the
initial IHA qualified to be categorically
excluded from further NEPA review.
NMFS has determined that the
application of this categorical exclusion
remains appropriate for this renewal
IHA.
Endangered Species Act
Section 7(a)(2) of the Endangered
Species Act of 1973 (ESA; 16 U.S.C.
1531 et seq.) requires that each Federal
agency insure that any action it
authorizes, funds, or carries out is not
likely to jeopardize the continued
existence of any endangered or
threatened species or result in the
destruction or adverse modification of
designated critical habitat. To ensure
ESA compliance for the issuance of
IHAs, NMFS consults internally
whenever we propose to authorize take
for endangered or threatened species.
No incidental take of ESA-listed
species is authorized or expected to
result from this activity. Therefore,
NMFS has determined that formal
consultation under section 7 of the ESA
is not required for this action.
Renewal
NMFS has issued a renewal IHA to
the Navy for the take of marine
mammals incidental to construction
activities associated with the
multifunctional expansion of Dry Dock
1 project at Portsmouth Naval Shipyard
in Kittery, Maine, effective through
March 31, 2024.
Dated: March 31, 2023.
Kimberly Damon-Randall,
Director, Office of Protected Resources,
National Marine Fisheries Service.
[FR Doc. 2023–07164 Filed 4–5–23; 8:45 am]
BILLING CODE 3510–22–P
E:\FR\FM\06APN1.SGM
06APN1
Agencies
[Federal Register Volume 88, Number 66 (Thursday, April 6, 2023)]
[Notices]
[Pages 20493-20500]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-07164]
-----------------------------------------------------------------------
DEPARTMENT OF COMMERCE
National Oceanic and Atmospheric Administration
[RTID 0648-XC893]
Takes of Marine Mammals Incidental to Specified Activities;
Taking Marine Mammals Incidental to U.S. Navy Construction at
Portsmouth Naval Shipyard, Kittery, Maine
AGENCY: National Marine Fisheries Service (NMFS), National Oceanic and
Atmospheric Administration (NOAA), Commerce.
ACTION: Notice; issuance of renewal incidental harassment authorization
(IHA).
-----------------------------------------------------------------------
SUMMARY: In accordance with the regulations implementing the Marine
Mammal Protection Act (MMPA), as amended, notification is hereby given
[[Page 20494]]
that NMFS has issued a renewal incidental harassment authorization
(IHA) to the U.S. Navy (Navy) to incidentally harass marine mammals
incidental to construction activities associated with the
multifunctional expansion of Dry Dock 1 project at Portsmouth Naval
Shipyard in Kittery, Maine.
DATES: This renewal IHA is valid from April 1, 2023 through March 31,
2024.
FOR FURTHER INFORMATION CONTACT: Reny Tyson Moore, Office of Protected
Resources, NMFS, (301) 427-8401. Electronic copies of the original
application, renewal request, and supporting documents (including NMFS
Federal Register notices of the original proposed and final
authorizations, and the previous IHA), as well as a list of the
references cited in this document, may be obtained online at: https://www.fisheries.noaa.gov/permit/incidental-take-authorizations-under-marine-mammal-protection-act. In case of problems accessing these
documents, please call the contact listed above.
SUPPLEMENTARY INFORMATION:
Background
The Marine Mammal Protection Act (MMPA) prohibits the ``take'' of
marine mammals, with certain exceptions. Sections 101(a)(5)(A) and (D)
of the MMPA (16 U.S.C. 1361 et seq.) direct the Secretary of Commerce
(as delegated to NMFS) to allow, upon request, the incidental, but not
intentional, taking of small numbers of marine mammals by U.S. citizens
who engage in a specified activity (other than commercial fishing)
within a specified geographical region if certain findings are made and
either regulations are issued or, if the taking is limited to
harassment, an incidental harassment authorization is issued.
Authorization for incidental takings shall be granted if NMFS finds
that the taking will have a negligible impact on the species or
stock(s) and will not have an unmitigable adverse impact on the
availability of the species or stock(s) for taking for subsistence uses
(where relevant). Further, NMFS must prescribe the permissible methods
of taking and other ``means of effecting the least practicable adverse
impact'' on the affected species or stocks and their habitat, paying
particular attention to rookeries, mating grounds, and areas of similar
significance, and on the availability of such species or stocks for
taking for certain subsistence uses (referred to here as ``mitigation
measures''). Monitoring and reporting of such takings are also
required. The meaning of key terms such as ``take,'' ``harassment,''
and ``negligible impact'' can be found in section 3 of the MMPA (16
U.S.C. 1362) and the agency's regulations at 50 CFR 216.103.
NMFS' regulations implementing the MMPA at 50 CFR 216.107(e)
indicate that IHAs may be renewed for additional periods of time not to
exceed 1 year for each reauthorization. In the notice of proposed IHA
for the initial authorization, NMFS described the circumstances under
which we would consider issuing a renewal for this activity, and
requested public comment on a potential renewal under those
circumstances. Specifically, on a case-by-case basis, NMFS may issue a
one-time 1-year renewal IHA following notice to the public providing an
additional 15 days for public comments when (1) up to another year of
identical, or nearly identical, activities as described in the Detailed
Description of Specified Activities section of the initial IHA issuance
notice is planned or (2) the activities as described in the Description
of the Specified Activities and Anticipated Impacts section of the
initial IHA issuance notice would not be completed by the time the
initial IHA expires and a renewal would allow for completion of the
activities beyond that described in the DATES section of the notice of
issuance of the initial IHA, provided all of the following conditions
are met:
1. A request for renewal is received no later than 60 days prior to
the needed renewal IHA effective date (recognizing that the renewal IHA
expiration date cannot extend beyond 1 year from expiration of the
initial IHA);
2. The request for renewal must include the following:
An explanation that the activities to be conducted under
the requested renewal IHA are identical to the activities analyzed
under the initial IHA, are a subset of the activities, or include
changes so minor (e.g., reduction in pile size) that the changes do not
affect the previous analyses, mitigation and monitoring requirements,
or take estimates (with the exception of reducing the type or amount of
take);
A preliminary monitoring report showing the results of the
required monitoring to date and an explanation showing that the
monitoring results do not indicate impacts of a scale or nature not
previously analyzed or authorized; and
3. Upon review of the request for renewal, the status of the
affected species or stocks, and any other pertinent information, NMFS
determines that there are no more than minor changes in the activities,
the mitigation and monitoring measures will remain the same and
appropriate, and the findings in the initial IHA remain valid.
An additional public comment period of 15 days (for a total of 45
days), with direct notice by email, phone, or postal service to
commenters on the initial IHA, is provided to allow for any additional
comments on the proposed renewal. A description of the renewal process
may be found on our website at: www.fisheries.noaa.gov/national/marine-mammal-protection/incidental-harassment-authorization-renewals.
History of Request
On April 1, 2022, NMFS issued an IHA to the Navy to take marine
mammals incidental to construction activities associated with the
multifunctional expansion of Dry Dock 1 project (also referred to as P-
381) at Portsmouth Naval Shipyard in Kittery, Maine (87 FR 19886, April
6, 2022), effective from April 1, 2022 through March 31, 2022. On
January 31, 2023, NMFS received an application for the renewal of that
initial IHA. NMFS received a revised application for the renewal IHA on
February 24, 2023. As described in the application for renewal IHA, the
activities for which incidental take is requested consist of activities
that are covered by the initial authorization but will not be completed
prior to its expiration. As required, the applicant also provided a
preliminary monitoring report which confirms that the applicant has
implemented the required mitigation and monitoring, and which also
shows that no impacts of a scale or nature not previously analyzed or
authorized have occurred as a result of the activities conducted. There
are no changes from the proposed authorization in this final
authorization.
Description of the Specified Activities and Anticipated Impacts
Multifunctional Expansion of Dry Dock 1 (P-381) is one of three
projects that support the overall expansion and modification of Dry
Dock 1, located in the western extent of the Portsmouth Naval Shipyard.
The two additional projects, construction of a super flood basin (P-
310) and extension of portal crane rail and utilities (P-1074), are
currently under construction. In-water work associated with these
projects was completed under separate IHAs issued by NMFS in 2019 (84
FR 24476, May 28, 2019), and in a renewal of the 2019 IHA (86 FR 14598,
March 17, 2021). The projects have been phased to support Navy mission
schedules. P-381 will be constructed within the same footprint of the
super flood basin over an approximate 7-year period, during
[[Page 20495]]
which 5 years of in-water work will occur. The initial IHA authorized
takes for marine mammals during the first year of in-water construction
for P-381 occurring from April 2022 through March 2023. All work beyond
year 1 has been addressed in proposed incidental take regulations (88
FR 3146, January 18, 2023).
The purpose of this project, Multifunctional Expansion of Dry Dock
1 (P-381), is to modify the super flood basin to create two additional
dry docking positions (Dry Dock 1 North and Dry Dock 1 West) in front
of the existing Dry Dock 1 East. The super flood basin provides the
starting point for the P-381 work (see Figure 1-2 of the Navy's
application for the initial IHA). This renewal will cover a subset of
the activities covered in the initial IHA that will not be completed
during the effective IHA period due to project delays (see Detailed
Description of the Activity for specific activities to be covered in
the renewal IHA). This includes the preparation of the walls and floors
of the super flood basin to support the placement of the monoliths and
the construction of the two dry dock positions.
Construction activities that could affect marine mammals are
limited to in-water pile driving and removal activities, rock
hammering, rotary drilling, and down-the-hole (DTH) hammering. Under
the initial IHA, Level A harassment and Level B harassment was
authorized for harbor porpoises (Phocoena phocoena), harbor seals
(Phoca vitulina), gray seals (Halichoerus grypus), harp seals
(Pagophilus groenlandicus) and hooded seals (Cystophora cristata).
Neither the Navy nor NMFS expects serious injury or mortality to result
from this activity and, therefore, a renewal IHA is appropriate.
The following documents are referenced in this notification and
include important supporting information:
Initial 2022 Final IHA (87 FR 19886, April 6, 2022);
Initial 2022 Proposed IHA (87 FR 11860, March 3, 2022);
Initial IHA application and References;
Letter of Authorization (LOA) Application Addendum Memo
(October 31, 2022); and
2023 Proposed renewal IHA (88 FR 15982, March 15, 2023).
All of these referenced documents are available at https://www.fisheries.noaa.gov/action/incidental-take-authorization-us-navy-construction-portsmouth-naval-shipyard-kittery-maine.
Detailed Description of the Activity
A detailed description of the construction activities for which
take is authorized here may be found in the Federal Register notices of
the proposed (87 FR 11860, March 3, 2022) and final (87 FR 19886, April
6, 2022) IHAs for the initial authorization as well as in the LOA
Application Addendum Memo (submitted to NMFS on October 31, 2023),
which described project modifications and shifting Fleet submarine
schedules. As previously mentioned, this request is for a subset of the
activities authorized in the initial IHA that would not be completed
prior to its expiration due to project delays. The location, timing,
and nature of the activities, including the types of equipment planned
for use, are identical to those described in the previous notices.
Table 1 describes the status of all activities covered under the
initial IHA as well as the amount of activities covered under the
renewal IHA. This renewal IHA is effective for a period not exceeding 1
year from the date of expiration of the initial IHA.
Table 1--Status of Pile Driving and Drilling Activities
--------------------------------------------------------------------------------------------------------------------------------------------------------
Number
Number remaining Number of
Activity Daily installed to be Total production
Activity Total amount component Method production rate under installed production days under
initial IHA under days renewal IHA
renewal IHA
--------------------------------------------------------------------------------------------------------------------------------------------------------
Center Wall--Install 20 drilled Install 102-inch Rotary Drill.... 1 shaft/day; 1 14 6 20 6
Foundation Support Piles. shafts \1\. diameter outer hour/day.
casing.
Pre-drill 102- Rotary Drill.... 1 shaft/day; 9 14 6 20 6
inch diameter hours/day.
socket.
Remove 102-inch Rotary Drill.... 1 casing/day; 10 10 20 10
outer casing. 15 minutes/
casing.
Drill 78-inch Cluster drill 6.5 days/shaft; 2 18 130 117
diameter shaft. DTH. 10 hours/day.
Center Wall--Install Diving 18 drilled Install 102-inch Rotary Drill.... 1 shaft/day; 1 0 0 18 0
Board Shafts \2\. shafts. diameter outer hour/day.
casing.
Pre-drill 102- Rotary Drill.... 1 shaft/day; 9 0 0 18 0
inch diameter hours/day.
socket.
Remove 102-inch Rotary Drill.... 1 casing/day; 0 0 18 0
outer casing. 15 minutes/
casing.
Drill 78-inch Cluster drill 7.5 days/shaft; 0 0 135 0
diameter shaft. DTH. 10 hours/day.
Center Wall--Access Platform 38 drilled Install 102-inch Rotary Drill.... 1 shaft/day; 1 0 0 38 0
Support \3\. shafts. diameter outer hour/day.
casing.
Pre-drill 102- Rotary Drill.... 1 shaft/day; 9 0 0 38 0
inch diameter hours/day.
socket.
Remove 102-inch Rotary Drill.... 1 casing/day; 0 0 38 0
outer casing. 15 minutes/
casing.
Drill 78-inch Cluster drill 3.5 days/shaft; 0 0 38 0
diameter shaft. DTH. 10 hours/day.
Center Wall--Temporary 6 drilled shafts 42-inch diameter Mono-hammer DTH. 1 shaft/day; 10 6 0 6 0
Launching Piles. shaft. hours/day.
Center Wall Tie Downs \3\.... Install 36 rock 9-inch diameter Mono-hammer DTH. 2 holes/day; 5 0 0 18 0
anchors. holes. hours/hole.
Center Wall--Access Platform Install 18 rock 9-inch diameter Mono-hammer DTH. 2 holes/day; 5 0 0 9 0
Tie Downs \3\. anchors. holes. hours/hole.
[[Page 20496]]
Center Wall--Install Tie-In 16 sheet piles.. 28-inch wide Z- Impact with 4 piles/day; 5 0 16 4 4
to Existing West Closure shaped sheets. initial minutes and;
Wall. vibratory set. 300 blows/pile.
Berth 11 End Wall--Install 60 sheet piles.. 28-inch wide Z- Impact with 8 piles/day; 5 60 0 8 0
Secant Pile Guide Wall. shaped sheets. initial minutes and;
vibratory set. 300 blows/pile.
Berth 1--Remove Granite Block 610 cy.......... Granite block Hydraulic rock 2.5 hours/day.. 0 0 NA 0
Quay Wall \4\. demolition. hammering.
P-310 West Closure Wall-- 238 sheet piles. 18-inch wide Vibratory 4 piles/day; 5 0 238 60 60
Remove Closure Wall. flat-sheets. extraction. minutes/pile.
P-310 West Closure Wall-- 985 cy.......... Excavate bedrock Hydraulic rock 9 hours/day.... 0 985 77 77
Mechanical Rock Excavation. hammering.
P-310 West Closure Wall-- Drill 500 relief 4-6 inch holes.. Mono-hammer DTH. 25 holes/day; 0 500 20 20
Mechanical Rock Excavation. holes. ................ Mono-hammer DTH. 24 minutes/ ........... ........... ........... ...........
Drill 46 rock 42-inch diameter hole. 46 0 \5\ 24 0
borings (50 cy). casing. 2 borings/day;
5 hours/boring.
West Closure wall--Berth 11 Drill 28 shafts. 42-inch diameter Mono-hammer DTH. 1 shaft/day; 10 0 28 28 28
Abutment--Install Piles. casing. hours/day.
Berth 11--Remove Shutter 112 panels...... Demolish shutter Hydraulic rock 5 hours/day.... 92 20 56 10
Panels. panels. hammering.
Berth 11 Face--Mechanical 3,500 cy........ Excavate Bedrock Hydraulic rock 12 hours/day... 700 2800 100 80
Rock Removal at Basin Floor. Drill 1,277 4-6 inch holes.. hammering. 27 holes/day; 300 977 48 37
relief holes Mono-hammer DTH. 22.2 minutes/
\1\. hole.
Berth 11 Face--Mechanical Drill 365 rock 42-inch diameter Mono-hammer DTH. 2 borings/day; 0 365 183 183
Rock at Abutment. borings (1,220 casing. 5 hours/boring.
cy).
Dry Dock 1 North Entrance-- Drill 50 rock 9-inch holes.... Mono-hammer DTH. 2 holes/day; 2 0 25 25 25
Drill Tremie Tie Downs. anchors \1\. hours/hole.
Dry Dock 1 North Entrance-- Install 48 sheet 28-inch wide Z- Impact with 8 sheets/day; 5 0 48 6 6
Install Temporary Cofferdam. piles \1\. shaped sheets. initial minutes and
vibratory set. 300 blows/pile.
Berth 1--Remove Sheet Piles.. Remove 12 sheet 25-inch wide; Z- Hydraulic rock 6 hours/day.... 0 12 3 3
piles. shaped sheets. hammering.
Berth 1 Top of Wall-- 30 lf........... Mechanical Hydraulic rock 10 hours/day... NA NA NA NA
Demolition For Waler concrete hammering.
Installation \6\. demolition.
Berth 1 Mechanical Rock 200 cy.......... Excavate Bedrock Hydraulic rock 13 cy/day; 12 0 200 39 39
Removal at Basin Floor \7\. hammering. hours/day.
Removal of Berth 1 Emergency 108 sheet piles. 25-inch wide Z- Vibratory 6 piles/day; 5 0 108 18 18
Repair Sheets \7\. shaped sheets. extraction. minutes/pile.
Removal of Berth 1 Emergency 500 cy.......... Mechanical Hydraulic rock 4 hours/day.... 0 500 15 15
Repair Tremie Concrete \7\. concrete hammering.
demolition.
---------------------------------------------------
Totals................... ................ ................ ................ ............... 1,244 6,862 1,278 744
--------------------------------------------------------------------------------------------------------------------------------------------------------
\1\ The amount of this activity was adjusted in a memo describing project modifications and shifting Fleet submarine schedules that was submitted to
NMFS on October 31, 2022. The memo can be found at https://www.fisheries.noaa.gov/action/incidental-take-authorization-us-navy-construction-portsmouth-naval-shipyard-kittery-maine-0.
\2\ The schedule for this work shifted as described in the aforementioned memo submitted to NMFS on October 31, 2022. This activity is now addressed in
the proposed rulemaking/LOA (88 FR 3146, January 18, 2023).
\3\ These activities are no longer needed.
\4\ This activity is complete; it was performed above the water line. The underwater portion of this activity is addressed in the proposed rulemaking/
LOA (88 FR 3146, January 18).
\5\ An additional day was added to account for equipment repositioning.
\6\ This activity is complete; it was performed above the water line.
\7\ This activity was added to the initial IHA in the aforementioned memo submitted to NMFS on October 31, 2022.
[[Page 20497]]
Description of Marine Mammals in the Area of Specified Activities
A description of the marine mammals in the area of the activities
for which take is authorized here, including information on abundance,
status, distribution, and hearing, may be found in the Notice of the
proposed IHA for the initial authorization (87 FR 11860, March 3,
2022). NMFS has reviewed the monitoring data from the initial IHA,
recent draft Stock Assessment Reports, information on relevant Unusual
Mortality Events, and other scientific literature, and determined that
neither this nor any other new information affects which species or
stocks have the potential to be affected or the pertinent information
in the Description of the Marine Mammals in the Area of Specified
Activities contained in the supporting documents for the initial IHA.
Potential Effects on Marine Mammals and their Habitat
A description of the potential effects of the specified activity on
marine mammals and their habitat for the activities for which the
authorization of take is authorized here may be found in the Federal
Register notice of the proposed IHA for the initial authorization (87
FR 11860, March 3, 2022). NMFS has reviewed the monitoring data from
the initial IHA, recent draft Stock Assessment Reports, information on
relevant Unusual Mortality Events, and other scientific literature, and
determined that neither this nor any other new information affects our
initial analysis of impacts on marine mammals and their habitat.
Estimated Take
A detailed description of the methods and inputs used to estimate
take for the specified activity are found in the Federal Register
notices of the proposed (87 FR 11860, March 3, 2022) and final (87 FR
19886, April 6, 2022) IHAs for the initial authorization as well as the
Federal Register notice of the proposed renewal IHA (88 FR 15982, March
15, 2023). Specifically, the marine mammal density and occurrence data
applicable to this authorization remain unchanged from the previously
issued IHA. Similarly, the stocks taken and types of take remain
unchanged from the previously issued IHA. Since the initial IHA was
issued, NMFS updated its recommendations on source pressure levels
(SPLs) to use when evaluating DTH systems and reevaluated the data
available on rock hammering activities. Updates to recommended SPLs for
these activities, however, did not result in any changes to the
estimated take as described in the proposed renewal IHA (88 FR 15982,
March 15, 2023).
Tables 2, 3, and 4 provide the authorized take by Level A and Level
B harassment for harbor porpoises, harbor seals, and grey seals,
respectively. Given that a subset of the initially covered activities
would be occurring, the number of days of operation, and thus number of
takes, has been reduced for each species. Note that the final take
numbers differ slightly from those provided in the Navy's request for
renewal of the IHA based on rounding errors found in the request.
Further, in the initial IHA that was issued, takes by Level B
harassment for harbor seals and grey seals were increased to more
accurately reflect the number of seal sightings reported in recent
monitoring reports. However, this adjustment has not been requested or
made for the renewal IHA based on the reduction in the number of
construction days. The take calculation for hooded and harp seals
remains the same from the initial IHA (see the Federal Register notices
of the proposed (87 FR 11860, March 3, 2022) and final (87 FR 19886,
April 6, 2022) IHAs for the initial authorization for more
information).
Table 2--Authorized Take by Level A and Level B Harassment of Harbor Porpoise by Project Activity for the Renewal IHA
--------------------------------------------------------------------------------------------------------------------------------------------------------
Number of Level A Level B
production harassment Takes by harassment Take by
Activity Total amount Method days under Density zone Level A zone Level B
renewal IHA (km\2\) harassment (km\2\) harassment
--------------------------------------------------------------------------------------------------------------------------------------------------------
Center Wall--Install Foundation 20 drilled shafts.. Rotary Drill....... 6 0.4 0.00001 0 0.41742 0
Support Piles. Rotary Drill....... 6 0.4 0.00025 0 0.41742 0
Rotary Drill....... 10 0.4 0.00000 0 0.41742 0
Cluster drill DTH.. 117 0.4 0.41742 2 0.41742 0
Center Wall--Install Tie-In to 16 sheet piles..... Initial vibratory 4 0.4 0.00045 0 0.41742 0
Existing West Closure Wall. set. 4 0.4 0.40341 0 0.41742 0
Impact.............
P-310 West Closure Wall--Remove 238 sheet piles.... Vibratory 60 0.4 0.00014 0 0.41742 1
Closure Wall. extraction.
P-310 West Closure Wall-- 985 cy............. Hydraulic rock 77 0.4 0.41742 1 0.277858 0
Mechanical Rock Excavation. hammering.
P-310 West Closure Wall-- Drill 500 relief Mono-hammer DTH.... 20 0.4 0.04811 0 0.41742 0
Mechanical Rock Excavation. holes.
West Closure wall--Berth 11 Drill 28 shafts.... Mono-hammer DTH.... 28 0.4 0.41742 0 0.41742 0
Abutment--Install Piles.
Berth 11--Remove Shutter Panels. 112 panels......... Hydraulic rock 10 0.4 0.41742 0 0.277858 0
hammering.
Berth 11 Face--Mechanical Rock 3,500 cy........... Hydraulic rock 80 0.4 0.41742 1 0.277858 0
Removal at Basin Floor. hammering.
Drill 1,277 relief Mono-hammer DTH.... 37 0.4 0.04811 0 0.41742 1
holes.
Berth 11 Face--Mechanical Rock Drill 365 rock Mono-hammer DTH.... 183 0.4 0.41742 3 0.41742 0
at Abutment. borings (1,220 cy).
Dry Dock 1 North Entrance--Drill Drill 50 rock Mono-hammer DTH.... 25 0.4 0.03036 0 0.41742 0
Tremie Tie Downs. anchors.
Dry Dock 1 North Entrance-- Install 48 sheet Initial vibratory 6 0.4 0.00104 0 0.41742 0
Install Temporary Cofferdam. piles. set. 6 0.4 0.41742 0 0.41742 0
Impact.............
[[Page 20498]]
Berth 1--Remove Sheet Piles..... Remove 12 sheet Hydraulic rock 3 0.4 0.41742 0 0.277858 0
piles. hammering.
Berth 1 Mechanical Rock Removal 200 cy............. Hydraulic rock 39 0.4 0.41742 1 0.277858 0
at Basin Floor. hammering.
Removal of Berth 1 Emergency 108 sheet piles.... Vibratory 18 0.4 0.00073 0 0.41742 0
Repair Sheets. extraction.
Removal of Berth 1 Emergency 500 cy............. Hydraulic rock 15 0.4 0.41742 0 0.277858 0
Repair Tremie Concrete. hammering.
-----------------------------------------------------------------------------
Total Estimated Take........ ................... ................... ........... ........... ........... 10 ........... 2
--------------------------------------------------------------------------------------------------------------------------------------------------------
Table 3--Calculated Take by Level A and Level B Harassment of Harbor Seal by Project Activity for the Proposed Renewal IHA
--------------------------------------------------------------------------------------------------------------------------------------------------------
Number of Level A Level B
production harassment Takes by harassment Take by
Activity Total amount Method days under Density zone Level A zone Level B
renewal IHA (km\2\) harassment (km\2\) harassment
--------------------------------------------------------------------------------------------------------------------------------------------------------
Center Wall--Install Foundation 20 drilled shafts.. Rotary Drill....... 6 3 0.00001 0 0.41742 8
Support Piles. Rotary Drill....... 6 3 0.00009 0 0.41742 8
Rotary Drill....... 10 3 0.00000 0 0.41742 13
Cluster drill DTH.. 117 3 0.41742 146 0.41742 0
Center Wall--Install Tie-In to 16 sheet piles..... Initial vibratory 4 3 0.00008 0 0.41742 5
Existing West Closure Wall. set. 4 3 0.20116 2 0.41742 3
Impact.............
P-310 West Closure Wall--Remove 238 sheet piles.... Vibratory 60 3 0.00002 0 0.41742 75
Closure Wall. extraction.
P-310 West Closure Wall-- 985 cy............. Hydraulic rock 77 3 0.41742 96 0.277858 0
Mechanical Rock Excavation. hammering.
P-310 West Closure Wall-- Drill 500 relief Mono-hammer DTH.... 20 3 0.01455 1 0.41742 24
Mechanical Rock Excavation. holes.
West Closure Wall--Berth 11 Drill 28 shafts.... Mono-hammer DTH.... 28 3 0.41742 35 0.41742 0
Abutment--Install Piles.
Berth 11--Remove Shutter Panels. 112 panels......... Hydraulic rock 10 3 0.41742 13 0.277858 0
hammering.
Berth 11 Face--Mechanical Rock 3,500 cy........... Hydraulic rock 80 3 0.41742 100 0.277858 0
Removal at Basin Floor. hammering.
Drill 1,277 relief Mono-hammer DTH.... 37 3 0.01455 2 0.41742 45
holes.
Berth 11 Face--Mechanical Rock Drill 365 rock Mono-hammer DTH.... 183 3 0.41742 229 0.41742 0
at Abutment. borings (1,220 cy).
Dry Dock 1 North Entrance--Drill Drill 50 rock Mono-hammer DTH.... 25 3 0.00903 1 0.41742 31
Tremie Tie Downs. anchors.
Dry Dock 1 North Entrance-- Install 48 sheet Initial vibratory 6 3 0.00104 8 0.41742 0
Install Temporary Cofferdam. piles. set. 6 3 0.36495 7 1.50227 1
Impact.............
Berth 1--Remove Sheet Piles..... Remove 12 sheet Hydraulic rock 3 3 0.41742 4 0.277858 0
piles. hammering.
Berth 1 Mechanical Rock Removal 200 cy............. Hydraulic rock 39 3 0.41742 49 0.277858 0
at Basin Floor. hammering.
Removal of Berth 1 Emergency 108 sheet piles.... Vibratory 18 3 0.00014 0 0.41742 23
Repair Sheets. extraction.
Removal of Berth 1 Emergency 500 cy............. Hydraulic rock 15 3 0.41742 19 0.277858 0
Repair Tremie Concrete. hammering.
-----------------------------------------------------------------------------
Total Estimated Take........ ................... ................... ........... ........... ........... 704 ........... 244
--------------------------------------------------------------------------------------------------------------------------------------------------------
Table 4--Calculated Take by Level A and Level B Harassment of Grey Seal by Project Activity for the Renewal IHA
--------------------------------------------------------------------------------------------------------------------------------------------------------
Number of Level A Level B
production harassment Takes by harassment Take by
Activity Total amount Method days under Density zone Level A zone Level B
renewal IHA (km\2\) harassment (km\2\) harassment
--------------------------------------------------------------------------------------------------------------------------------------------------------
Center Wall--Install Foundation 20 drilled shafts.. Rotary Drill....... 6 0.02 0.00001 0 0.41742 1
Support Piles. Rotary Drill....... 6 0.02 0.00009 0 0.41742 1
[[Page 20499]]
Rotary Drill....... 10 0.02 0.00000 0 0.41742 1
Cluster drill DTH.. 117 0.02 0.41742 10 0.41742 0
Center Wall--Install Tie-In to 16 sheet piles..... Initial vibratory 4 0.02 0.00008 0 0.41742 0
Existing West Closure Wall. set. 4 0.02 0.20116 0 0.41742 0
Impact.............
P-310 West Closure Wall--Remove 238 sheet piles.... Vibratory 60 0.02 0.00002 0 0.41742 5
Closure Wall. extraction.
P-310 West Closure Wall-- 985 cy............. Hydraulic rock 77 0.02 0.41742 6 0.277858 0
Mechanical Rock Excavation. hammering.
P-310 West Closure Wall-- Drill 500 relief Mono-hammer DTH.... 20 0.02 0.01455 0 0.41742 2
Mechanical Rock Excavation. holes.
West Closure Wall--Berth 11 Drill 28 shafts.... Mono-hammer DTH.... 28 0.02 0.41742 2 0.41742 0
Abutment--Install Piles.
Berth 11--Remove Shutter Panels. 112 panels......... Hydraulic rock 10 0.02 0.41742 1 0.277858 0
hammering.
Berth 11 Face--Mechanical Rock.. 3,500 cy........... Hydraulic rock 80 0.02 0.41742 7 0.277858 0
hammering.
Removal at Basin Floor.......... Drill 1,277 relief Mono-hammer DTH.... 37 0.02 0.01455 0 0.41742 3
holes.
Berth 11 Face--Mechanical Rock Drill 365 rock Mono-hammer DTH.... 183 0.02 0.41742 15 0.41742 0
at Abutment. borings (1,220 cy).
Dry Dock 1 North Entrance--Drill Drill 50 rock Mono-hammer DTH.... 25 0.02 0.00903 0 0.41742 2
Tremie Tie Downs. anchors.
Dry Dock 1 North Entrance-- Install 48 sheet Initial vibratory 6 0.02 0.00104 0 0.41742 1
Install Temporary Cofferdam. piles. set. 6 0.02 0.36495 0 0.41742 0
Impact.............
Berth 1--Remove Sheet Piles..... Remove 12 sheet Hydraulic rock 3 0.02 0.41742 0 0.277858 0
piles. hammering.
Berth 1 Mechanical Rock Removal 200 cy............. Hydraulic rock 39 0.02 0.41742 3 0.277858 0
at Basin Floor. hammering.
Removal of Berth 1 Emergency 108 sheet piles.... Vibratory 18 0.02 0.00014 0 0.41742 2
Repair Sheets. extraction.
Removal of Berth 1 Emergency 500 cy............. Hydraulic rock 15 0.02 0.41742 1 0.277858 0
Repair Tremie Concrete. hammering.
-----------------------------------------------------------------------------
Total Estimated Take........ ................... ................... ........... ........... ........... 45 ........... 18
--------------------------------------------------------------------------------------------------------------------------------------------------------
Table 5 summarizes the authorized take for all species described as
a percentage of stock abundance.
Table 5--Take Estimates as a Percentage of Stock Abundance
----------------------------------------------------------------------------------------------------------------
Level A Level B Percent of
Species Stock (NEST) harassment harassment stock
----------------------------------------------------------------------------------------------------------------
Harbor porpoise.................... Gulf of Maine/Bay of Fundy 10 2 <0.1
(95,543).
Harbor seal........................ Western North Atlantic 695 240 <0.1
(61,336).
Gray seal.......................... Western North Atlantic 45 18 <0.1
(27,300).
Hooded seal........................ Western North Atlantic 0 5 <0.1
(593,500).
Harp seal.......................... Western North Atlantic (7.6 0 5 <0.1
million).
----------------------------------------------------------------------------------------------------------------
Description of Mitigation, Monitoring and Reporting Measures
The mitigation, monitoring, and reporting measures included as
requirements in the authorization are identical to those included in
the FR Notice announcing the issuance of the initial IHA (87 FR 19886,
April 6, 2022), and the discussion of the least practicable adverse
impact included in that document remains accurate. The same measures
are proposed for this renewal and are summarized here:
The Navy must delay pile driving activities should poor
environmental conditions restrict full visibility of the applicable
shutdown zones;
The Navy must ensure that all construction supervisors and
crews, the monitoring team, and relevant Navy staff are trained prior
to commencing work;
The Navy must implement a 10 m shutdown zone around
construction activities to avoid direct physical interaction with
marine mammals;
The Navy must establish and implement shutdown and
monitoring zones for all pile driving activities based on the activity
type and marine mammal hearing group (see Table 13 in the FR Notice
announcing the issuance of the initial IHA (87 FR 19886, April 6, 2022)
[[Page 20500]]
for the shutdown and monitoring zones);
The Navy must implement soft start techniques while impact
driving whereby hammer energy is gradually ramped up;
The Navy must install a bubble curtain across any openings
at the entrance of super flood basin to attenuate sound for the sound
sources that encompass the entire ROI, which include during DTH
excavation (DTH mono-hammer and cluster drill), hydraulic rock
hammering, and impact pile driving of sheet piles;
The Navy must employ at least three protected species
observers (PSOs) to monitor the shutdown and monitoring zones;
The Navy must monitor for the presence of marine mammals
30 minutes prior to the initial pile-driving activity (i.e., pre-start
clearance monitoring) through 30 minutes post-completion of pile
driving activity. If a marine mammal is observed entering or within the
shutdown zones, pile driving will be delayed or halted;
The Navy will delay or halt pile driving activities upon
observation of either a species for which incidental take is not
authorized or a species for which incidental take has been authorized
but the authorized number of takes has been met, entering or within the
harassment zone;
The Navy will conduct a sound source verification study
for rotary drilling, DTH excavation (DTH mono-hammer and cluster
drill), and rock hammering activities for any remaining piles required
to be monitored following their acoustic monitoring plan as described
in the FR Notice announcing the issuance of the initial IHA (87 FR
19886, April 6, 2022);
The Navy must submit a draft report detailing all
monitoring within 90 calendar days of the completion of marine mammal
monitoring or 60 days prior to the issuance of any subsequent IHA for
this project, whichever comes first;
The Navy must prepare and submit final report within 30
days following resolution of comments on the draft report from NMFS;
The Navy must submit all PSO datasheets and/or raw
sighting data (in a separate file from the Final Report referenced
immediately above); and
The Navy must report injured or dead marine mammals.
Comments and Responses
A notice of NMFS' proposal to issue a renewal IHA to the Navy was
published in the Federal Register on March 15, 2023 (88 FR 15982). That
notice either described, or referenced descriptions of, the applicant's
activity, the marine mammal species that may be affected by the
activity, the anticipated effects on marine mammals and their habitat,
estimated amount and manner of take, and proposed mitigation,
monitoring and reporting measures. NMFS received two comments that were
not relevant to the scope of the proposed action. No other comments
were received.
Determinations
The renewal request consists of a subset of activities analyzed
through the initial authorization described above. In analyzing the
effects of the activities for the initial IHA, NMFS determined that the
Navy's activities would have a negligible impact on the affected
species or stocks and that authorized take numbers of each species or
stock were small relative to the relevant stocks (e.g., less than one-
third the abundance of all stocks). Although new SPL information became
available for DTH and rock hammering, none of this new information
affects NMFS' determinations supporting issuance of the initial IHA.
The mitigation measures and monitoring and reporting requirements as
described above are identical to the initial IHA.
NMFS has concluded that there is no new information suggesting that
our analysis or findings should change from those reached for the
initial IHA. Based on the information and analysis contained here and
in the referenced documents, NMFS has determined the following: (1) the
required mitigation measures will effect the least practicable impact
on marine mammal species or stocks and their habitat; (2) the
authorized takes will have a negligible impact on the affected marine
mammal species or stocks; (3) the authorized takes represent small
numbers of marine mammals relative to the affected stock abundances;
(4) the Navy's activities will not have an unmitigable adverse impact
on taking for subsistence purposes as no relevant subsistence uses of
marine mammals are implicated by this action; and, (5) appropriate
monitoring and reporting requirements are included.
National Environmental Policy Act
To comply with the National Environmental Policy Act of 1969 (NEPA;
42 U.S.C. 4321 et seq.) and NOAA Administrative Order (NAO) 216-6A,
NMFS must review our proposed action (i.e., the issuance of an IHA
renewal) with respect to potential impacts on the human environment.
This action is consistent with categories of activities identified
in Categorical Exclusion B4 (incidental take authorizations with no
anticipated serious injury or mortality) of the Companion Manual for
NOAA Administrative Order 216-6A, which do not individually or
cumulatively have the potential for significant impacts on the quality
of the human environment and for which we have not identified any
extraordinary circumstances that would preclude this categorical
exclusion. Accordingly, NMFS determined that the issuance of the
initial IHA qualified to be categorically excluded from further NEPA
review. NMFS has determined that the application of this categorical
exclusion remains appropriate for this renewal IHA.
Endangered Species Act
Section 7(a)(2) of the Endangered Species Act of 1973 (ESA; 16
U.S.C. 1531 et seq.) requires that each Federal agency insure that any
action it authorizes, funds, or carries out is not likely to jeopardize
the continued existence of any endangered or threatened species or
result in the destruction or adverse modification of designated
critical habitat. To ensure ESA compliance for the issuance of IHAs,
NMFS consults internally whenever we propose to authorize take for
endangered or threatened species.
No incidental take of ESA-listed species is authorized or expected
to result from this activity. Therefore, NMFS has determined that
formal consultation under section 7 of the ESA is not required for this
action.
Renewal
NMFS has issued a renewal IHA to the Navy for the take of marine
mammals incidental to construction activities associated with the
multifunctional expansion of Dry Dock 1 project at Portsmouth Naval
Shipyard in Kittery, Maine, effective through March 31, 2024.
Dated: March 31, 2023.
Kimberly Damon-Randall,
Director, Office of Protected Resources, National Marine Fisheries
Service.
[FR Doc. 2023-07164 Filed 4-5-23; 8:45 am]
BILLING CODE 3510-22-P