Hydro Technology, Inc.; Notice of Application Accepted for Filing, Ready For Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, And Prescriptions, 19950-19951 [2023-06857]
Download as PDF
19950
Federal Register / Vol. 88, No. 64 / Tuesday, April 4, 2023 / Notices
Alabama Department of Environmental
Management (ADEM), in conjunction
with the above captioned project.
Pursuant to 40 CFR 121.6 and section
157.22(b) of the Commission’s
regulations,1 we hereby notify ADEM of
the following:
Date of Receipt of the Certification
Request: August 22, 2022.
Reasonable Period of Time to Act on
the Certification Request: August 22,
2023.
If ADEM fails or refuses to act on the
water quality certification request on or
before the above date, then the agency
certifying authority is deemed waived
pursuant to section 401(a)(1) of the
Clean Water Act, 33 U.S.C. 1341(a)(1).
Dated: March 28, 2023.
Kimberly D. Bose,
Secretary.
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas & Oil
Pipeline Rate and Refund Report filings:
Filings Instituting Proceedings
ddrumheller on DSK120RN23PROD with NOTICES1
Docket Numbers: RP23–605–000.
Applicants: Trunkline Gas Company,
LLC.
Description: § 4(d) Rate Filing: NonConforming List Update—FP&L to be
effective 4/1/2023.
Filed Date: 3/29/23.
Accession Number: 20230329–5103.
Comment Date: 5 p.m. ET 4/10/23.
Docket Numbers: RP23–606–000.
Applicants: El Paso Natural Gas
Company, L.L.C.
Description: § 4(d) Rate Filing:
Negotiated Rate Agreement Update
(SoCal Apr 2023) to be effective 4/1/
2023.
Filed Date: 3/29/23.
Accession Number: 20230329–5126.
Comment Date: 5 p.m. ET 4/10/23.
[FR Doc. 2023–06858 Filed 4–3–23; 8:45 am]
Docket Numbers: RP23–601–000.
Applicants: El Paso Natural Gas
Company, L.L.C.
Description: § 4(d) Rate Filing: NonConforming Agreement Filing (JBS
Tolleson) to be effective 5/1/2023.
Filed Date: 3/28/23.
Accession Number: 20230328–5187.
Comment Date: 5 p.m. ET 4/10/23.
Docket Numbers: RP23–602–000.
Applicants: El Paso Natural Gas
Company, L.L.C.
Description: § 4(d) Rate Filing:
Negotiated Rate Agreement Update (TEP
May 23) to be effective 5/1/2023.
Filed Date: 3/29/23.
Accession Number: 20230329–5067.
Comment Date: 5 p.m. ET 4/10/23.
Docket Numbers: RP23–603–000.
Applicants: Colorado Interstate Gas
Company, L.L.C.
Description: § 4(d) Rate Filing:
Negotiated Rate Agreement Filing (TMV
Apr 23) to be effective 4/1/2023.
Filed Date: 3/29/23.
Accession Number: 20230329–5081.
Comment Date: 5 p.m. ET 4/10/23.
Docket Numbers: RP23–604–000.
Applicants: Trunkline Gas Company,
LLC.
1 18
Description: § 4(d) Rate Filing: NonConforming NRA with FP&L to be
effective 4/1/2023.
Filed Date: 3/29/23.
Accession Number: 20230329–5102.
Comment Date: 5 p.m. ET 4/10/23.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: March 29, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–06983 Filed 4–3–23; 8:45 am]
BILLING CODE 6717–01–P
CFR 157.22(b) (2022).
VerDate Sep<11>2014
19:41 Apr 03, 2023
Jkt 259001
PO 00000
Frm 00048
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2544–052]
Hydro Technology, Inc.; Notice of
Application Accepted for Filing, Ready
For Environmental Analysis and
Soliciting Comments,
Recommendations, Terms and
Conditions, And Prescriptions
Take notice that the following license
application has been filed with the
Commission and is available for public
inspection.
a. Type of Application: Subsequent
License.
b. Project No.: P–2544–052.
c. Date filed: December 27, 2021.
d. Applicant: Hydro Technology, Inc.
e. Name of Project: Meyers Falls
Hydroelectric Project (Project).
f. Location: The existing project is
located on the Colville River near the
city of Kettle Falls, Stevens County,
Washington. The project does not affect
federal lands.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Benjamin
Hendrickson, President, Hydro
Technology Systems, Inc., 897
Greenwood Loop Rd., PO Box 245,
Kettle Falls, WA 99141; Telephone (509)
933–7629.
i. FERC Contact: Maryam Zavareh,
(202) 502–8474, maryam.zavareh@
ferc.gov.
j. Deadline for filing comments,
recommendations, terms and
conditions, and prescriptions: 60 days
from the issuance date of this notice;
reply comments are due 105 days from
the issuance date of this notice.
The Commission strongly encourages
electronic filing. Please file comments,
recommendations, terms and
conditions, and prescriptions using the
Commission’s eFiling system at https://
ferconline.ferc.gov/FERC.aspx.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://ferconline.ferc.gov/
Quick.aspx. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
The first page of any filing should
include docket number P–2544–052.
The Commission’s Rules of Practice
require all intervenors filing documents
E:\FR\FM\04APN1.SGM
04APN1
ddrumheller on DSK120RN23PROD with NOTICES1
Federal Register / Vol. 88, No. 64 / Tuesday, April 4, 2023 / Notices
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
for filing and is now ready for
environmental analysis.
l. The existing Meyers Falls Project
consists of: (1) a 10-acre reservoir; (2) a
24.5-foot-high, 306-foot-long, concrete
and earth-fill embankment dam; (3) a
100-foot-long concrete spillway section
containing five 20 feet, 3.5 inch wide, 6
feet high bulkheads; (3) a 46-foot-wide,
20-foot-deep, 360-foot-long intake
channel with a 19-foot-wide and 11foot-deep trashrack at the entrance
point; (4) a 4-foot-diameter, 323-footlong steel penstock conveying flow from
intake to powerhouse; (5) a 31.5-footwide, 55.5-foot-long, 15.5-foot-high steel
reinforced concrete powerhouse
containing two generating units with a
total installed capacity of 1.2 megawatts;
(7) a 4,600-foot-long, 13.8-kilovolt
transmission line; and (8) appurtenant
facilities. The Meyers Falls Project is
operated in a run-of-river mode with an
average annual generation of 7,883
megawatt-hours per year.
m. A copy of the application can be
viewed on the Commission’s website at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
All filings must (1) bear in all capital
letters the title ‘‘COMMENTS’’, ‘‘REPLY
COMMENTS’’,
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person submitting the
filing; and (4) otherwise comply with
the requirements of 18 CFR 385.2001
through 385.2005. All comments,
recommendations, terms and conditions
or prescriptions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicant.
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding, in
VerDate Sep<11>2014
19:41 Apr 03, 2023
Jkt 259001
accordance with 18 CFR 4.34(b) and
385.2010.
You may also register online at
https://ferconline.ferc.gov/
FERCOnline.aspx to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. The applicant must file no later
than 60 days following the date of
issuance of this notice either: (1)
evidence of the date on which the
certifying agency received the
certification request; (2) a copy of the
water quality certification; or (3)
evidence of waiver of water quality
certification. Please note that the
certification request must comply with
40 CFR 121.5(b), including
documentation that a pre-filing meeting
request was submitted to the certifying
authority at least 30 days prior to
submitting the certification request.
Please also note that the certification
request must be sent to the certifying
authority and to the Commission
concurrently
o. Procedural schedule: The
application will be processed according
to the following schedule. Revisions to
the schedule will be made as
appropriate.
Deadline for Filing Comments,
Recommendations, and Agency
Terms and Conditions/Prescriptions:
May 2023
Licensee’s Reply to REA Comments: July
2023
p. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of this notice.
Dated: March 28, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–06857 Filed 4–3–23; 8:45 am]
BILLING CODE 6717–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OGC–2023–0191; FRL–10804–01–
OGC]
Proposed Consent Decree, Clean Air
Act Citizen Suit
Environmental Protection
Agency (EPA).
ACTION: Notice of proposed consent
decree; request for public comment.
AGENCY:
In accordance with the Clean
Air Act, as amended (CAA or the Act),
notice is hereby given of a proposed
consent decree in Citizens for Clean Air,
et al. v. Michael S. Regan, et al., No.
SUMMARY:
PO 00000
Frm 00049
Fmt 4703
Sfmt 4703
19951
2:22–cv–01382–RSL (W.D. Wa.). On
September 28, 2022, Plaintiffs Citizens
for Clean Air and Sierra Club filed a
complaint in the United States District
Court for the Western District of
Washington alleging that the
Environmental Protection Agency (EPA
or the Agency) failed to perform a nondiscretionary duty in accordance with
the Act to take final action to approve,
disapprove or conditionally approve, in
whole or in part, a nonattainment state
implementation plan (SIP) submission
made by the State of Alaska. The State
made the SIP submission at issue to
address certain nonattainment area plan
requirements for purposes of the 2006
24-hour PM2.5 national ambient air
quality standards (NAAQS) for the
Fairbanks North Star Borough area. The
proposed consent decree would
establish a deadline for EPA to take final
action on the SIP submission.
DATES: Written comments on the
proposed consent decree must be
received by May 4, 2023.
ADDRESSES: Submit your comments,
identified by Docket ID No. EPA–HQ–
OGC–2023–0191, online at https://
www.regulations.gov (EPA’s preferred
method). Follow the online instructions
for submitting comments.
Instructions: All submissions received
must include the Docket ID number for
this action. Comments received may be
posted without change to https://
www.regulations.gov, including any
personal information provided. For
detailed instructions on sending
comments and additional information
on the rulemaking process, see the
‘‘Additional Information about
Commenting on the Proposed Consent
Decree’’ heading under the
SUPPLEMENTARY INFORMATION section of
this document.
FOR FURTHER INFORMATION CONTACT:
Geoffrey L. Wilcox, Air and Radiation
Law Office, Office of General Counsel,
U.S. Environmental Protection Agency;
telephone (202) 564–5601; email
address wilcox.geoffrey@epa.gov.
SUPPLEMENTARY INFORMATION:
I. Obtaining a Copy of the Proposed
Consent Decree
The official public docket for this
action (identified by Docket ID No.
EPA–HQ–OGC–2023–0191) contains a
copy of the proposed consent decree.
The official public docket is available
for public viewing at the Office of
Environmental Information (OEI) Docket
in the EPA Docket Center, EPA West,
Room 3334, 1301 Constitution Ave. NW,
Washington, DC. The EPA Docket
Center Public Reading Room is open
from 8:30 a.m. to 4:30 p.m., Monday
E:\FR\FM\04APN1.SGM
04APN1
Agencies
[Federal Register Volume 88, Number 64 (Tuesday, April 4, 2023)]
[Notices]
[Pages 19950-19951]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-06857]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2544-052]
Hydro Technology, Inc.; Notice of Application Accepted for
Filing, Ready For Environmental Analysis and Soliciting Comments,
Recommendations, Terms and Conditions, And Prescriptions
Take notice that the following license application has been filed
with the Commission and is available for public inspection.
a. Type of Application: Subsequent License.
b. Project No.: P-2544-052.
c. Date filed: December 27, 2021.
d. Applicant: Hydro Technology, Inc.
e. Name of Project: Meyers Falls Hydroelectric Project (Project).
f. Location: The existing project is located on the Colville River
near the city of Kettle Falls, Stevens County, Washington. The project
does not affect federal lands.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Benjamin Hendrickson, President, Hydro
Technology Systems, Inc., 897 Greenwood Loop Rd., PO Box 245, Kettle
Falls, WA 99141; Telephone (509) 933-7629.
i. FERC Contact: Maryam Zavareh, (202) 502-8474,
[email protected].
j. Deadline for filing comments, recommendations, terms and
conditions, and prescriptions: 60 days from the issuance date of this
notice; reply comments are due 105 days from the issuance date of this
notice.
The Commission strongly encourages electronic filing. Please file
comments, recommendations, terms and conditions, and prescriptions
using the Commission's eFiling system at https://ferconline.ferc.gov/FERC.aspx. Commenters can submit brief comments up to 6,000 characters,
without prior registration, using the eComment system at https://ferconline.ferc.gov/Quick.aspx. You must include your name and contact
information at the end of your comments. For assistance, please contact
FERC Online Support at [email protected], (866) 208-3676 (toll
free), or (202) 502-8659 (TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC 20426. The first page of any filing
should include docket number P-2544-052.
The Commission's Rules of Practice require all intervenors filing
documents
[[Page 19951]]
with the Commission to serve a copy of that document on each person on
the official service list for the project. Further, if an intervenor
files comments or documents with the Commission relating to the merits
of an issue that may affect the responsibilities of a particular
resource agency, they must also serve a copy of the document on that
resource agency.
k. This application has been accepted for filing and is now ready
for environmental analysis.
l. The existing Meyers Falls Project consists of: (1) a 10-acre
reservoir; (2) a 24.5-foot-high, 306-foot-long, concrete and earth-fill
embankment dam; (3) a 100-foot-long concrete spillway section
containing five 20 feet, 3.5 inch wide, 6 feet high bulkheads; (3) a
46-foot-wide, 20-foot-deep, 360-foot-long intake channel with a 19-
foot-wide and 11-foot-deep trashrack at the entrance point; (4) a 4-
foot-diameter, 323-foot-long steel penstock conveying flow from intake
to powerhouse; (5) a 31.5-foot-wide, 55.5-foot-long, 15.5-foot-high
steel reinforced concrete powerhouse containing two generating units
with a total installed capacity of 1.2 megawatts; (7) a 4,600-foot-
long, 13.8-kilovolt transmission line; and (8) appurtenant facilities.
The Meyers Falls Project is operated in a run-of-river mode with an
average annual generation of 7,883 megawatt-hours per year.
m. A copy of the application can be viewed on the Commission's
website at https://www.ferc.gov using the ``eLibrary'' link. Enter the
docket number excluding the last three digits in the docket number
field to access the document. For assistance, contact FERC Online
Support.
All filings must (1) bear in all capital letters the title
``COMMENTS'', ``REPLY COMMENTS'', ``RECOMMENDATIONS,'' ``TERMS AND
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person submitting the filing; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, recommendations, terms and conditions or prescriptions must
set forth their evidentiary basis and otherwise comply with the
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the
application directly from the applicant. Each filing must be
accompanied by proof of service on all persons listed on the service
list prepared by the Commission in this proceeding, in accordance with
18 CFR 4.34(b) and 385.2010.
You may also register online at https://ferconline.ferc.gov/FERCOnline.aspx to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. The applicant must file no later than 60 days following the date
of issuance of this notice either: (1) evidence of the date on which
the certifying agency received the certification request; (2) a copy of
the water quality certification; or (3) evidence of waiver of water
quality certification. Please note that the certification request must
comply with 40 CFR 121.5(b), including documentation that a pre-filing
meeting request was submitted to the certifying authority at least 30
days prior to submitting the certification request. Please also note
that the certification request must be sent to the certifying authority
and to the Commission concurrently
o. Procedural schedule: The application will be processed according
to the following schedule. Revisions to the schedule will be made as
appropriate.
Deadline for Filing Comments, Recommendations, and Agency Terms and
Conditions/Prescriptions: May 2023
Licensee's Reply to REA Comments: July 2023
p. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of this notice.
Dated: March 28, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-06857 Filed 4-3-23; 8:45 am]
BILLING CODE 6717-01-P