Download as PDF Federal Register / Vol. 88, No. 59 / Tuesday, March 28, 2023 / Notices lotter on DSK11XQN23PROD with NOTICES1 How To File Protests, Interventions, and Comments There are two ways to submit protests, motions to intervene, and comments. In both instances, please reference the Project docket number CP23–94–000 in your submission. (1) You may file your protest, motion to intervene, and comments by using the Commission’s eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select General’’ and then select ‘‘Protest’’, ‘‘Intervention’’, or ‘‘Comment on a Filing’’; or 7 (2) You can file a paper copy of your submission by mailing it to the address below. Your submission must reference the Project docket number CP23–94– 000. To mail via USPS, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. To mail via any other courier, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The Commission encourages electronic filing of submissions (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. Protests and motions to intervene must be served on the applicant either by mail or email (with a link to the document) at: Cindy Thompson, Director, Regulatory, Compliance & Information Governance, Southern Star Central Gas Pipeline, Inc., 4700 State Route 56, Owensboro, Kentucky 42301, by phone at (270) 852–4655 or by email to cindy.thompson@southernstar.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. Tracking the Proceeding Throughout the proceeding, additional information about the project will be available from the Commission’s Office of External Affairs, at (866) 208– 7 Additionally, you may file your comments electronically by using the eComment feature, which is located on the Commission’s website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project. VerDate Sep<11>2014 16:59 Mar 27, 2023 Jkt 259001 FERC, or on the FERC website at www.ferc.gov using the ‘‘eLibrary’’ link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/docs-filing/ esubscription.asp. Dated: March 21, 2023. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2023–06367 Filed 3–27–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2354–168] Georgia Power Company; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Application Type: Temporary Variance from Recreation Plan. b. Project No: 2354–168. c. Date Filed: March 3, 2023. d. Applicant: Georgia Power Company. e. Name of Project: North Georgia Hydroelectric Project. f. Location: Nacoochee Park located just below the Nacoochee dam in Rabun County, Georgia. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Applicant Contact: Joseph Charles, 241 Ralph McGill Blvd. NE, BIN 10151, Atlanta, GA 30308; (404)506–2337; jcharles@southernco.com. i. FERC Contact: Mark Carter, (678) 245–3083, mark.carter@ferc.gov. j. Deadline for filing comments, motions to intervene, and protests: April 19, 2023. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ PO 00000 Frm 00020 Fmt 4703 Sfmt 4703 18311 efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket number P–2354–168. Comments emailed to Commission staff are not considered part of the Commission record. k. Description of Request: The licensee requests a variance from Article 418 (Recreation Plan) to close Nacoochee Park beginning August 1, 2023, for a period of up to two years, to support its hydro modernization efforts at the Nacoochee dam and powerhouse. Specifically, the licensee plans to stage equipment and store materials needed for the modernization work at Nacoochee Park and close the park to public access for public safety and project security reasons. l. Locations of the Application: This filing may be viewed on the Commission’s website at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. Agencies may obtain copies of the application directly from the applicant. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214, respectively. In determining the E:\FR\FM\28MRN1.SGM 28MRN1 18312 Federal Register / Vol. 88, No. 59 / Tuesday, March 28, 2023 / Notices appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person commenting, protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. Any filing made by an intervenor must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. Dated: March 21, 2023. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2023–06366 Filed 3–27–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission lotter on DSK11XQN23PROD with NOTICES1 Combined Notice of Filings #1 Take notice that the Commission received the following Complaints and Compliance filings in EL Dockets: Docket Numbers: EL23–48–000. Applicants: Ponderosa Power, LLC v. North Western Corporation. Description: Complaint of Ponderosa Power, LLC v. North Western Corporation. Filed Date: 3/20/23. Accession Number: 20230320–5128. Comment Date: 5 p.m. ET 4/10/23. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER21–378–003. Applicants: Mississippi Power Company. Description: Compliance filing: Gulf States TFA Order No. 864 Supplemental Further Compliance Filing to be effective 1/27/2020. VerDate Sep<11>2014 16:59 Mar 27, 2023 Jkt 259001 Filed Date: 3/21/23. Accession Number: 20230321–5113. Comment Date: 5 p.m. ET 4/11/23. Docket Numbers: ER22–2462–002; EL22–27–001. Applicants: Alabama Power Company, Georgia Power Company, Mississippi Power Company, Alabama Power Company, Georgia Power Company, Mississippi Power Company. Description: Southern Companies submits a Compliance Filing with respect to a revised version of its Formula Rate Protocols as directed in January 19, 2023 Commission Order. Filed Date: 3/20/23. Accession Number: 20230320–5203. Comment Date: 5 p.m. ET 4/10/23. Docket Numbers: ER23–1427–000. Applicants: American Electric Power Service Corporation, Ohio Power Company, PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: American Electric Power Service Corporation submits tariff filing per 35.13(a)(2)(iii: AEP submits one Facilities Agreements re: ILDSA, SA No. 1336 to be effective 5/21/2023. Filed Date: 3/21/23. Accession Number: 20230321–5014. Comment Date: 5 p.m. ET 4/11/23. Docket Numbers: ER23–1428–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Original ISA, Service Agreement No. 6827; Queue No. AE1–108 to be effective 2/21/2023. Filed Date: 3/21/23. Accession Number: 20230321–5016. Comment Date: 5 p.m. ET 4/11/23. Docket Numbers: ER23–1429–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2023–03–21_SA 4015 NSP-Mayhew Creek Solar FSA (J1445) to be effective 5/21/2023. Filed Date: 3/21/23. Accession Number: 20230321–5020. Comment Date: 5 p.m. ET 4/11/23. Docket Numbers: ER23–1430–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: Revisions to Attachment AE to Modify the Regulation Mileage Compensation Design to be effective 12/31/9998. Filed Date: 3/21/23. Accession Number: 20230321–5027. Comment Date: 5 p.m. ET 4/11/23. Docket Numbers: ER23–1431–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Revisions to OATT and OA RE Market Suspension Rules to be effective 6/1/ 2023. PO 00000 Frm 00021 Fmt 4703 Sfmt 9990 Filed Date: 3/21/23. Accession Number: 20230321–5031. Comment Date: 5 p.m. ET 4/11/23. Docket Numbers: ER23–1432–000. Applicants: Southern California Edison Company. Description: Tariff Amendment: Cancel High Desert Power Project IFA (TOT005_SA No. 11) to be effective 5/ 21/2023. Filed Date: 3/21/23. Accession Number: 20230321–5044. Comment Date: 5 p.m. ET 4/11/23. Docket Numbers: ER23–1433–000. Applicants: PacifiCorp. Description: § 205(d) Rate Filing: Constellation FKA Exelon NITSA (OR DA) SA 943 Rev 5 to be effective 3/1/ 2023. Filed Date: 3/21/23. Accession Number: 20230321–5049. Comment Date: 5 p.m. ET 4/11/23. Docket Numbers: ER23–1434–000. Applicants: Sugar Maple Wind, LLC. Description: Baseline eTariff Filing: Shared Facilities Agreement Between Big Savage, LLC and Sugar Maple Wind, LLC to be effective 5/21/2023. Filed Date: 3/21/23. Accession Number: 20230321–5096. Comment Date: 5 p.m. ET 4/11/23. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: March 21, 2023. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2023–06368 Filed 3–27–23; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\28MRN1.SGM 28MRN1

Agencies

[Federal Register Volume 88, Number 59 (Tuesday, March 28, 2023)]
[Notices]
[Pages 18311-18312]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-06366]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2354-168]


Georgia Power Company; Notice of Application Accepted for Filing 
and Soliciting Comments, Motions To Intervene, and Protests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Application Type: Temporary Variance from Recreation Plan.
    b. Project No: 2354-168.
    c. Date Filed: March 3, 2023.
    d. Applicant: Georgia Power Company.
    e. Name of Project: North Georgia Hydroelectric Project.
    f. Location: Nacoochee Park located just below the Nacoochee dam in 
Rabun County, Georgia.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
    h. Applicant Contact: Joseph Charles, 241 Ralph McGill Blvd. NE, 
BIN 10151, Atlanta, GA 30308; (404)506-2337; [email protected].
    i. FERC Contact: Mark Carter, (678) 245-3083, [email protected].
    j. Deadline for filing comments, motions to intervene, and 
protests: April 19, 2023.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, and protests using the Commission's 
eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. 
Commenters can submit brief comments up to 6,000 characters, without 
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact 
information at the end of your comments. For assistance, please contact 
FERC Online Support at [email protected], (866) 208-3676 (toll 
free), or (202) 502-8659 (TTY). In lieu of electronic filing, you may 
submit a paper copy. Submissions sent via the U.S. Postal Service must 
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE, Room 1A, Washington, DC 20426. 
Submissions sent via any other carrier must be addressed to: Kimberly 
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins 
Avenue, Rockville, Maryland 20852. The first page of any filing should 
include docket number P-2354-168. Comments emailed to Commission staff 
are not considered part of the Commission record.
    k. Description of Request: The licensee requests a variance from 
Article 418 (Recreation Plan) to close Nacoochee Park beginning August 
1, 2023, for a period of up to two years, to support its hydro 
modernization efforts at the Nacoochee dam and powerhouse. 
Specifically, the licensee plans to stage equipment and store materials 
needed for the modernization work at Nacoochee Park and close the park 
to public access for public safety and project security reasons.
    l. Locations of the Application: This filing may be viewed on the 
Commission's website at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. You may also register 
online at https://www.ferc.gov/docs-filing/esubscription.asp to be 
notified via email of new filings and issuances related to this or 
other pending projects. For assistance, call 1-866-208-3676 or email 
[email protected], for TTY, call (202) 502-8659. Agencies may 
obtain copies of the application directly from the applicant.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214, respectively. In determining the

[[Page 18312]]

appropriate action to take, the Commission will consider all protests 
or other comments filed, but only those who file a motion to intervene 
in accordance with the Commission's Rules may become a party to the 
proceeding. Any comments, protests, or motions to intervene must be 
received on or before the specified comment date for the particular 
application.
    o. Filing and Service of Documents: Any filing must (1) bear in all 
capital letters the title ``COMMENTS'', ``PROTEST'', or ``MOTION TO 
INTERVENE'' as applicable; (2) set forth in the heading the name of the 
applicant and the project number of the application to which the filing 
responds; (3) furnish the name, address, and telephone number of the 
person commenting, protesting or intervening; and (4) otherwise comply 
with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, motions to intervene, or protests must set forth their 
evidentiary basis. Any filing made by an intervenor must be accompanied 
by proof of service on all persons listed in the service list prepared 
by the Commission in this proceeding, in accordance with 18 CFR 
385.2010.

    Dated: March 21, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.