Combined Notice of Filings #1, 17564-17565 [2023-05905]
Download as PDF
17564
Federal Register / Vol. 88, No. 56 / Thursday, March 23, 2023 / Notices
Filed Date: 3/17/23.
Accession Number: 20230317–5072.
Comment Date: 5 p.m. ET 4/7/23.
Docket Numbers: ER23–1418–000.
Applicants: AES WR Limited
Partnership.
Description: Baseline eTariff Filing:
Application for Market Based Rate to be
effective 6/1/2023.
Filed Date: 3/17/23.
Accession Number: 20230317–5084.
Comment Date: 5 p.m. ET 4/7/23.
Docket Numbers: ER23–1419–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original NSA, SA No. 6833; Queue No.
AE2–148 to be effective 2/17/2023.
Filed Date: 3/17/23.
Accession Number: 20230317–5089.
Comment Date: 5 p.m. ET 4/7/23.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: March 17, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–06009 Filed 3–22–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
ddrumheller on DSK120RN23PROD with NOTICES1
Combined Notice of Filings #1
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG23–93–000.
Applicants: Double Black Diamond
Solar Power, LLC.
Description: Double Black Diamond
Solar Power, LLC submits Notice of
Self-Certification of Exempt Wholesale
Generator Status.
VerDate Sep<11>2014
19:23 Mar 22, 2023
Jkt 259001
Filed Date: 3/16/23.
Accession Number: 20230316–5087.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: EG23–94–000.
Applicants: Landrace Holdings, LLC.
Description: Landrace Holdings, LLC
submits Notice of Self-Certification of
Exempt Wholesale Generator Status.
Filed Date: 3/16/23.
Accession Number: 20230316–5130.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: EG23–95–000.
Applicants: PGR 2021 Lessee 18, LLC.
Description: PGR 2021 Lessee 18, LLC
submits Notice of Self-Certification of
Exempt Wholesale Generator Status.
Filed Date: 3/16/23.
Accession Number: 20230316–5134.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: EG23–96–000.
Applicants: Virginia Line Solar, LLC.
Description: Virginia Line Solar, LLC
submits Notice of Self-Certification of
Exempt Wholesale Generator Status.
Filed Date: 3/16/23.
Accession Number: 20230316–5142.
Comment Date: 5 p.m. ET 4/6/23.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER15–1668–004.
Applicants: Phoenix Energy Group,
LLC.
Description: Notice of Non-Material
Change in Status of Phoenix Energy
Group, LLC.
Filed Date: 3/15/23.
Accession Number: 20230315–5216.
Comment Date: 5 p.m. ET 4/5/23.
Docket Numbers: ER17–405–000;
ER17–406–000.
Applicants: American Electric Power
Service Corporation, PJM
Interconnection, L.L.C., American
Electric Power Service Corporation, PJM
Interconnection, L.L.C.
Description: Formal Challenge of the
Joint Consumer Group to the 2022
Annual Formula Rate Update of AEP
East Operating Companies.
Filed Date: 3/8/23.
Accession Number: 20230308–5176.
Comment Date: 5 p.m. ET 4/7/23.
Docket Numbers: ER20–1298–004.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: Compliance filing: 2023–
03–16_MISO TO’s Order 864 Deficiency
Response to be effective 1/27/2020.
Filed Date: 3/16/23.
Accession Number: 20230316–5107.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER22–1165–003.
Applicants: PJM Interconnection,
L.L.C.
Description: Compliance filing: Order
No. 676–J Compliance Revisions to
PO 00000
Frm 00049
Fmt 4703
Sfmt 4703
Tariff, Section 4.2 to be effective 2/23/
2023.
Filed Date: 3/16/23.
Accession Number: 20230316–5096.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23–868–001.
Applicants: PEI Power LLC.
Description: Tariff Amendment:
Supplement to Tariff Filing to be
effective 1/19/2023.
Filed Date: 3/16/23.
Accession Number: 20230316–5069.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23–1064–001.
Applicants: Upper Missouri G. & T.
Electric Cooperative, Inc.
Description: Tariff Amendment:
Amended Cert. of Concurrence—SPS
Serv. Agreement to be effective 1/12/
2023.
Filed Date: 3/16/23.
Accession Number: 20230316–5032.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23–1398–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original ISA, Service Agreement No.
6824; Queue No. AE2–120 to be
effective 2/14/2023.
Filed Date: 3/16/23.
Accession Number: 20230316–5002.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23–1399–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Correction to 2022 Annual Regional
Transmission Expansion Plan Update
Filing to be effective 1/1/2022.
Filed Date: 3/16/23.
Accession Number: 20230316–5010.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23–1401–000.
Applicants: Niagara Mohawk Power
Corporation, New York Independent
System Operator, Inc.
Description: § 205(d) Rate Filing:
Niagara Mohawk Power Corporation
submits tariff filing per 35.13(a)(2)(iii:
NYISO-National Grid Joint 205: SGIA
Hawthorn Solar Project SA2756 to be
effective 3/2/2023.
Filed Date: 3/16/23.
Accession Number: 20230316–5016.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23–1402–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
Ameren Illinois Company.
Description: § 205(d) Rate Filing:
Midcontinent Independent System
Operator, Inc. submits tariff filing per
35.13(a)(2)(iii: 2023–03–16_SA 4014
Ameren IL-Flora Solar E&P (J1679) to be
effective 3/17/2023.
Filed Date: 3/16/23.
E:\FR\FM\23MRN1.SGM
23MRN1
17565
ddrumheller on DSK120RN23PROD with NOTICES1
Federal Register / Vol. 88, No. 56 / Thursday, March 23, 2023 / Notices
Accession Number: 20230316–5031.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23–1403–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Amendment to ISA, SA No. 6274;
Queue No. AE2–133 (amend) to be
effective 5/16/2023.
Filed Date: 3/16/23.
Accession Number: 20230316–5048.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23–1406–000.
Applicants: Nevada Power Company.
Description: § 205(d) Rate Filing:
OATT Section 205 Amendments in
Response to Order EL23–27 to be
effective 12/1/2022.
Filed Date: 3/16/23.
Accession Number: 20230316–5094.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23–1407–000.
Applicants: Transource Pennsylvania,
LLC, PJM Interconnection, L.L.C.
Description: § 205(d) Rate Filing:
Transource Pennsylvania, LLC submits
tariff filing per 35.13(a)(2)(iii:
Transource Pennsylvania, LLC Order
No. 679 Application to be effective 5/
16/2023.
Filed Date: 3/16/23.
Accession Number: 20230316–5124.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23–1408–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Revisions to Sch. 12-Appx A: February
2023 RTEP, 30-Day Comment Period
Requested to be effective 6/14/2023.
Filed Date: 3/16/23.
Accession Number: 20230316–5140.
Comment Date: 5 p.m. ET 4/6/23.
Take notice that the Commission
received the following electric
reliability filings
Docket Numbers: RD23–4–000.
Applicants: North American Electric
Reliability Corporation.
Description: North American Electric
Reliability Corporation submits Petition
for Approval of Proposed Reliability
Standard PCR–002–4.
Filed Date: 3/10/23.
Accession Number: 20230310–5272.
Comment Date: 5 p.m. ET 4/10/23.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5 p.m. Eastern
VerDate Sep<11>2014
19:23 Mar 22, 2023
Jkt 259001
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: March 16, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–05905 Filed 3–22–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
On July 30, 2021, Winooski
Hydroelectric Company filed an
application for a subsequent license to
continue operating the existing 856kilowatt Winooski 8 Hydroelectric
Project No. 6470 (Winooski 8 Project or
project). The project is located on the
Winooski River in Washington County,
Vermont. The project does not occupy
federal land.
In accordance with the Commission’s
regulations, on January 4, 2023,
Commission staff issued a notice that
the project was ready for environmental
analysis (REA notice). Based on the
information in the record, including
comments filed on the REA notice, staff
does not anticipate that licensing the
project would constitute a major federal
action significantly affecting the quality
of the human environment. Therefore,
staff intends to prepare a single
Environmental Assessment (EA) on the
application to license the Winooski 8
Project.
The EA will be issued and circulated
for review by all interested parties. All
comments filed on the EA will be
analyzed by staff and considered in the
Commission’s final licensing decision.
The application will be processed
according to the following schedule.
Revisions to the schedule may be made
as appropriate.
Frm 00050
Fmt 4703
Council on Environmental Quality’s
(CEQ)
regulations
under
40
CFR
1501.10(b)(1) require that EAs be completed
within 1 year of the federal action agency’s
decision to prepare an EA. This notice establishes the Commission’s intent to prepare an
EA for the Moretown Project. Therefore, in accordance with CEQ’s regulations, the Final EA
must be issued within 1 year of the issuance
date of this notice.
Any questions regarding this notice
may be directed to Kristen Sinclair at
(202) 502–6587, or kristen.sinclair@
ferc.gov.
Dated: March 17, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
DEPARTMENT OF ENERGY
Winooski Hydroelectric Company;
Notice of Intent To Prepare an
Environmental Assessment
PO 00000
October 2023.
1 The
BILLING CODE 6717–01–P
[Project No. 6470–008]
Commission issues
EA.
Comments on EA ......
Target date
[FR Doc. 2023–06007 Filed 3–22–23; 8:45 am]
Federal Energy Regulatory
Commission
Milestone
Milestone
Target date
September 2023.1
Sfmt 4703
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas & Oil
Pipeline Rate and Refund Report filings:
Filings Instituting Proceedings
Docket Numbers: RP23–576–000.
Applicants: Cove Point LNG, LP.
Description: Section 4(d) Rate Filing:
Cove Point—Rate Schedule LTD–3 to be
effective 4/16/2023.
Filed Date: 3/17/23.
Accession Number: 20230317–5010.
Comment Date: 5 p.m. ET 3/29/23.
Docket Numbers: RP23–577–000.
Applicants: Bison Pipeline LLC.
Description: Compliance filing:
Company Use Gas Annual Report 2023
to be effective N/A.
Filed Date: 3/17/23.
Accession Number: 20230317–5036.
Comment Date: 5 p.m. ET 3/29/23.
Docket Numbers: RP23–578–000.
Applicants: Gas Transmission
Northwest LLC.
Description: Section 4(d) Rate Filing:
Negotiated Rate Agreement—
Tourmaline to be effective 3/17/2023.
Filed Date: 3/17/23.
Accession Number: 20230317–5050.
Comment Date: 5 p.m. ET 3/29/23.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
E:\FR\FM\23MRN1.SGM
23MRN1
Agencies
[Federal Register Volume 88, Number 56 (Thursday, March 23, 2023)]
[Notices]
[Pages 17564-17565]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-05905]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #1
Take notice that the Commission received the following exempt
wholesale generator filings:
Docket Numbers: EG23-93-000.
Applicants: Double Black Diamond Solar Power, LLC.
Description: Double Black Diamond Solar Power, LLC submits Notice
of Self-Certification of Exempt Wholesale Generator Status.
Filed Date: 3/16/23.
Accession Number: 20230316-5087.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: EG23-94-000.
Applicants: Landrace Holdings, LLC.
Description: Landrace Holdings, LLC submits Notice of Self-
Certification of Exempt Wholesale Generator Status.
Filed Date: 3/16/23.
Accession Number: 20230316-5130.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: EG23-95-000.
Applicants: PGR 2021 Lessee 18, LLC.
Description: PGR 2021 Lessee 18, LLC submits Notice of Self-
Certification of Exempt Wholesale Generator Status.
Filed Date: 3/16/23.
Accession Number: 20230316-5134.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: EG23-96-000.
Applicants: Virginia Line Solar, LLC.
Description: Virginia Line Solar, LLC submits Notice of Self-
Certification of Exempt Wholesale Generator Status.
Filed Date: 3/16/23.
Accession Number: 20230316-5142.
Comment Date: 5 p.m. ET 4/6/23.
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER15-1668-004.
Applicants: Phoenix Energy Group, LLC.
Description: Notice of Non-Material Change in Status of Phoenix
Energy Group, LLC.
Filed Date: 3/15/23.
Accession Number: 20230315-5216.
Comment Date: 5 p.m. ET 4/5/23.
Docket Numbers: ER17-405-000; ER17-406-000.
Applicants: American Electric Power Service Corporation, PJM
Interconnection, L.L.C., American Electric Power Service Corporation,
PJM Interconnection, L.L.C.
Description: Formal Challenge of the Joint Consumer Group to the
2022 Annual Formula Rate Update of AEP East Operating Companies.
Filed Date: 3/8/23.
Accession Number: 20230308-5176.
Comment Date: 5 p.m. ET 4/7/23.
Docket Numbers: ER20-1298-004.
Applicants: Midcontinent Independent System Operator, Inc.
Description: Compliance filing: 2023-03-16_MISO TO's Order 864
Deficiency Response to be effective 1/27/2020.
Filed Date: 3/16/23.
Accession Number: 20230316-5107.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER22-1165-003.
Applicants: PJM Interconnection, L.L.C.
Description: Compliance filing: Order No. 676-J Compliance
Revisions to Tariff, Section 4.2 to be effective 2/23/2023.
Filed Date: 3/16/23.
Accession Number: 20230316-5096.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23-868-001.
Applicants: PEI Power LLC.
Description: Tariff Amendment: Supplement to Tariff Filing to be
effective 1/19/2023.
Filed Date: 3/16/23.
Accession Number: 20230316-5069.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23-1064-001.
Applicants: Upper Missouri G. & T. Electric Cooperative, Inc.
Description: Tariff Amendment: Amended Cert. of Concurrence--SPS
Serv. Agreement to be effective 1/12/2023.
Filed Date: 3/16/23.
Accession Number: 20230316-5032.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23-1398-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: Original ISA, Service
Agreement No. 6824; Queue No. AE2-120 to be effective 2/14/2023.
Filed Date: 3/16/23.
Accession Number: 20230316-5002.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23-1399-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: Correction to 2022 Annual
Regional Transmission Expansion Plan Update Filing to be effective 1/1/
2022.
Filed Date: 3/16/23.
Accession Number: 20230316-5010.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23-1401-000.
Applicants: Niagara Mohawk Power Corporation, New York Independent
System Operator, Inc.
Description: Sec. 205(d) Rate Filing: Niagara Mohawk Power
Corporation submits tariff filing per 35.13(a)(2)(iii: NYISO-National
Grid Joint 205: SGIA Hawthorn Solar Project SA2756 to be effective 3/2/
2023.
Filed Date: 3/16/23.
Accession Number: 20230316-5016.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23-1402-000.
Applicants: Midcontinent Independent System Operator, Inc., Ameren
Illinois Company.
Description: Sec. 205(d) Rate Filing: Midcontinent Independent
System Operator, Inc. submits tariff filing per 35.13(a)(2)(iii: 2023-
03-16_SA 4014 Ameren IL-Flora Solar E&P (J1679) to be effective 3/17/
2023.
Filed Date: 3/16/23.
[[Page 17565]]
Accession Number: 20230316-5031.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23-1403-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: Amendment to ISA, SA No.
6274; Queue No. AE2-133 (amend) to be effective 5/16/2023.
Filed Date: 3/16/23.
Accession Number: 20230316-5048.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23-1406-000.
Applicants: Nevada Power Company.
Description: Sec. 205(d) Rate Filing: OATT Section 205 Amendments
in Response to Order EL23-27 to be effective 12/1/2022.
Filed Date: 3/16/23.
Accession Number: 20230316-5094.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23-1407-000.
Applicants: Transource Pennsylvania, LLC, PJM Interconnection,
L.L.C.
Description: Sec. 205(d) Rate Filing: Transource Pennsylvania, LLC
submits tariff filing per 35.13(a)(2)(iii: Transource Pennsylvania, LLC
Order No. 679 Application to be effective 5/16/2023.
Filed Date: 3/16/23.
Accession Number: 20230316-5124.
Comment Date: 5 p.m. ET 4/6/23.
Docket Numbers: ER23-1408-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: Revisions to Sch. 12-Appx A:
February 2023 RTEP, 30-Day Comment Period Requested to be effective 6/
14/2023.
Filed Date: 3/16/23.
Accession Number: 20230316-5140.
Comment Date: 5 p.m. ET 4/6/23.
Take notice that the Commission received the following electric
reliability filings
Docket Numbers: RD23-4-000.
Applicants: North American Electric Reliability Corporation.
Description: North American Electric Reliability Corporation
submits Petition for Approval of Proposed Reliability Standard PCR-002-
4.
Filed Date: 3/10/23.
Accession Number: 20230310-5272.
Comment Date: 5 p.m. ET 4/10/23.
The filings are accessible in the Commission's eLibrary system
(https://elibrary.ferc.gov/idmws/search/fercgensearch.asp) by querying
the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: March 16, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023-05905 Filed 3-22-23; 8:45 am]