Bison Pipeline LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline, 16000-16001 [2023-05286]

Download as PDF 16000 Federal Register / Vol. 88, No. 50 / Wednesday, March 15, 2023 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP23–85–000] lotter on DSK11XQN23PROD with NOTICES1 Bison Pipeline LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline Take notice that on March 3, 2023, Bison Pipeline LLC (Bison), 700 Louisiana Street, Suite 1300, Houston, Texas 77002, filed in the above referenced docket, a prior notice pursuant to Sections 157.205, 157.210, and 157.216(b)(2)(iii) of the Federal Energy Regulatory Commission’s regulations under the Natural Gas Act and the blanket certificate issued by the Commission in Docket No. CP09–161– 000,1 seeking authorization to modify the operation of its natural gas pipeline mainline system to reduce the Maximum Allowable Operating Pressure (MAOP) and to abandon the associated system design capacity located in Campbell County, Wyoming and Morton County, North Dakota. Specifically, Bison seeks authorization to reduce, from 1,440 pounds per square inch gauge (psig) to 1,296 psig, the MAOP of its entire natural gas pipeline mainline system from the Buffalo Meter Station, located in Campbell County, Wyoming, to the Kurtz Meter Station, located in Morton County, North Dakota, in compliance with U.S. Department of Transportation’s Pipeline and Hazardous Materials Safety Administration’s regulations to ensure continued system integrity and safe operations. Additionally, Bison requests authorization to abandon approximately 30.5 million cubic feet per day of associated system design capacity, all as more fully set forth in the request which is on file with the Commission and open to public inspection. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel 1 Bison Pipeline LLC., 131 FERC ¶ 61,013 (2010). VerDate Sep<11>2014 18:48 Mar 14, 2023 Jkt 259001 Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TTY, (202) 502–8659. Any questions concerning this application should be directed to David A. Alonzo, Manager, Project Authorizations, Bison Pipeline LLC, 700 Louisiana Street, Suite 1300, Houston, Texas 77002, by phone at (832) 320– 477; or by email to david_alonzo@ tcenergy.com. Public Participation There are three ways to become involved in the Commission’s review of this project: you can file a protest to the project, you can file a motion to intervene in the proceeding, and you can file comments on the project. There is no fee or cost for filing protests, motions to intervene, or comments. The deadline for filing protests, motions to intervene, and comments is 5:00 p.m. Eastern Time on May 8, 2023. How to file protests, motions to intervene, and comments is explained below. Protests Pursuant to section 157.205 of the Commission’s regulations under the NGA,2 any person 3 or the Commission’s staff may file a protest to the request. If no protest is filed within the time allowed or if a protest is filed and then withdrawn within 30 days after the allowed time for filing a protest, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request for authorization will be considered by the Commission. Protests must comply with the requirements specified in section 157.205(e) of the Commission’s regulations,4 and must be submitted by the protest deadline, which is May 8, 2023. A protest may also serve as a motion to intervene so long as the protestor states it also seeks to be an intervenor. Interventions Any person has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to 2 18 CFR 157.205. include individuals, organizations, businesses, municipalities, and other entities. 18 CFR 385.102(d). 4 18 CFR 157.205(e). 3 Persons PO 00000 Frm 00049 Fmt 4703 Sfmt 4703 subsequently challenge the Commission’s orders in the U.S. Circuit Courts of Appeal. To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure 5 and the regulations under the NGA 6 by the intervention deadline for the project, which is May 8, 2023. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https://www.ferc.gov/ resources/guides/how-to/intervene.asp. All timely, unopposed motions to intervene are automatically granted by operation of Rule 214(c)(1). Motions to intervene that are filed after the intervention deadline are untimely and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission’s Rules and Regulations. A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties. Comments Any person wishing to comment on the project may do so. The Commission considers all comments received about the project in determining the appropriate action to be taken. To ensure that your comments are timely and properly recorded, please submit your comments on or before May 8, 2023. The filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding. How To File Protests, Interventions, and Comments There are two ways to submit protests, motions to intervene, and comments. In both instances, please reference the Project docket number CP23–85–000 in your submission. (1) You may file your protest, motion to intervene, and comments by using the 5 18 6 18 CFR 385.214. CFR 157.10. E:\FR\FM\15MRN1.SGM 15MRN1 Federal Register / Vol. 88, No. 50 / Wednesday, March 15, 2023 / Notices Commission’s eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select ‘‘General’’ and then select ‘‘Protest’’, ‘‘Intervention’’, or ‘‘Comment on a Filing.’’ The Commission’s eFiling staff are available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. (2) You can file a paper copy of your submission. Your submission must reference the Project docket number CP23–85–000. To mail via USPS, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. To mail via any other courier, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. Protests and motions to intervene must be served on the applicant either by mail or email (with a link to the document) at: David A. Alonzo, Manager, Project Authorizations, Bison Pipeline LLC, 700 Louisiana Street, Suite 1300, Houston, Texas 77002, by phone at (832) 320–477; or by email to david_alonzo@tcenergy.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. lotter on DSK11XQN23PROD with NOTICES1 Tracking the Proceeding Throughout the proceeding, additional information about the project will be available from the Commission’s Office of External Affairs, at (866) 208– FERC, or on the FERC website at www.ferc.gov using the ‘‘eLibrary’’ link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/docs-filing/ esubscription.asp. VerDate Sep<11>2014 18:48 Mar 14, 2023 Jkt 259001 Dated: March 9, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–05286 Filed 3–14–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 4639–033] Ampersand Christine Falls Hydro, LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Subsequent Minor License. b. Project No.: 4639–033. c. Date filed: September 29, 2021. d. Applicant: Ampersand Christine Falls Hydro, LLC (Ampersand). e. Name of Project: Christine Falls Hydroelectric Project (Christine Falls Project or project). f. Location: On the Sacandaga River near the Village of Speculator, Hamilton County, New York. The project does not occupy any federal land. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Mr. Sayad Moudachirou, Licensing Manager, Ampersand Christine Falls Hydro LLC, 717 Atlantic Avenue, Suite 1A, Boston, MA 02111, Phone: 617–933–7206, Email: sayad@ampersandenergy.com; and Mr. Jason Huang, Asset Manager, Ampersand Christine Falls Hydro LLC, 717 Atlantic Avenue, Suite 1A, Boston, MA 02111, Phone: 773–919–0923, Email: jasonh@ampersandenergy.com. i. FERC Contact: Andy Bernick at (202) 502–8660, or andrew.bernick@ ferc.gov. j. Deadline for filing motions to intervene and protests: 60 days from the issuance date of this notice. The Commission strongly encourages electronic filing. Please file motions to intervene and protests using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, PO 00000 Frm 00050 Fmt 4703 Sfmt 4703 16001 DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. All filings must clearly identify the project name and docket number on the first page: Christine Falls Hydroelectric Project (P–4639–033). The Commission’s Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application has been accepted but is not ready for environmental analysis. l. The Christine Falls Project consists of the following existing facilities: (1) a 15-foot-high, 152.6-foot-long concrete gravity dam (includes both abutments), with 3-foot-high wooden flashboards installed along the crest of the 135-footlong spillway; (2) a reservoir with a surface area of 1.1 acres and a storage capacity of 4-acre feet at a normal water surface elevation of 1,699.7 feet National Geodetic Vertical Datum of 1929 (NGVD29); (3) an intake structure; (4) a 613-foot-long steel penstock with a diameter of 6 feet that bifurcates into 3foot-diameter, 45-foot-long and 4-footdiameter, 32-foot-long penstocks; (5) a brick and concrete powerhouse containing two turbine-generator units (i.e., one 275-kilowatt (kW) unit and one 575-kW unit) with a total capacity of 850 kW; (7) a tailrace with a depth of 21 feet; (8) a 610-foot-long bypassed reach; (9) a 185-foot-long underground transmission line connecting the generating units to a 1,000-kilovoltampere step-up transformer; (10) a 9,315-foot-long, 4.16/13.2-kilovolt underground transmission line from the transformer to a point of interconnection; and (11) appurtenant facilities. The Christine Falls Project is operated in a run-of-river mode, with a minimum flow of 25 cubic feet per second (cfs) into the bypassed reach during the months of March, April, and May, and a minimum flow of 10 cfs during the remainder of the year. The project has an average annual generation of 2,478 megawatt-hours. Ampersand proposes to operate the project in a strict run-of-river mode with an impoundment level fluctuation limit of 3 inches from the dam crest or flashboards when in place. As described E:\FR\FM\15MRN1.SGM 15MRN1

Agencies

[Federal Register Volume 88, Number 50 (Wednesday, March 15, 2023)]
[Notices]
[Pages 16000-16001]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-05286]



[[Page 16000]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP23-85-000]


Bison Pipeline LLC; Notice of Request Under Blanket Authorization 
and Establishing Intervention and Protest Deadline

    Take notice that on March 3, 2023, Bison Pipeline LLC (Bison), 700 
Louisiana Street, Suite 1300, Houston, Texas 77002, filed in the above 
referenced docket, a prior notice pursuant to Sections 157.205, 
157.210, and 157.216(b)(2)(iii) of the Federal Energy Regulatory 
Commission's regulations under the Natural Gas Act and the blanket 
certificate issued by the Commission in Docket No. CP09-161-000,\1\ 
seeking authorization to modify the operation of its natural gas 
pipeline mainline system to reduce the Maximum Allowable Operating 
Pressure (MAOP) and to abandon the associated system design capacity 
located in Campbell County, Wyoming and Morton County, North Dakota.
---------------------------------------------------------------------------

    \1\ Bison Pipeline LLC., 131 FERC ] 61,013 (2010).
---------------------------------------------------------------------------

    Specifically, Bison seeks authorization to reduce, from 1,440 
pounds per square inch gauge (psig) to 1,296 psig, the MAOP of its 
entire natural gas pipeline mainline system from the Buffalo Meter 
Station, located in Campbell County, Wyoming, to the Kurtz Meter 
Station, located in Morton County, North Dakota, in compliance with 
U.S. Department of Transportation's Pipeline and Hazardous Materials 
Safety Administration's regulations to ensure continued system 
integrity and safe operations. Additionally, Bison requests 
authorization to abandon approximately 30.5 million cubic feet per day 
of associated system design capacity, all as more fully set forth in 
the request which is on file with the Commission and open to public 
inspection.
    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (www.ferc.gov) using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. At this time, 
the Commission has suspended access to the Commission's Public 
Reference Room, due to the proclamation declaring a National Emergency 
concerning the Novel Coronavirus Disease (COVID-19), issued by the 
President on March 13, 2020. For assistance, contact the Federal Energy 
Regulatory Commission at [email protected] or call toll-free, 
(886) 208-3676 or TTY, (202) 502-8659.
    Any questions concerning this application should be directed to 
David A. Alonzo, Manager, Project Authorizations, Bison Pipeline LLC, 
700 Louisiana Street, Suite 1300, Houston, Texas 77002, by phone at 
(832) 320-477; or by email to [email protected].

Public Participation

    There are three ways to become involved in the Commission's review 
of this project: you can file a protest to the project, you can file a 
motion to intervene in the proceeding, and you can file comments on the 
project. There is no fee or cost for filing protests, motions to 
intervene, or comments. The deadline for filing protests, motions to 
intervene, and comments is 5:00 p.m. Eastern Time on May 8, 2023. How 
to file protests, motions to intervene, and comments is explained 
below.

Protests

    Pursuant to section 157.205 of the Commission's regulations under 
the NGA,\2\ any person \3\ or the Commission's staff may file a protest 
to the request. If no protest is filed within the time allowed or if a 
protest is filed and then withdrawn within 30 days after the allowed 
time for filing a protest, the proposed activity shall be deemed to be 
authorized effective the day after the time allowed for protest. If a 
protest is filed and not withdrawn within 30 days after the time 
allowed for filing a protest, the instant request for authorization 
will be considered by the Commission.
---------------------------------------------------------------------------

    \2\ 18 CFR 157.205.
    \3\ Persons include individuals, organizations, businesses, 
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------

    Protests must comply with the requirements specified in section 
157.205(e) of the Commission's regulations,\4\ and must be submitted by 
the protest deadline, which is May 8, 2023. A protest may also serve as 
a motion to intervene so long as the protestor states it also seeks to 
be an intervenor.
---------------------------------------------------------------------------

    \4\ 18 CFR 157.205(e).
---------------------------------------------------------------------------

Interventions

    Any person has the option to file a motion to intervene in this 
proceeding. Only intervenors have the right to request rehearing of 
Commission orders issued in this proceeding and to subsequently 
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
    To intervene, you must submit a motion to intervene to the 
Commission in accordance with Rule 214 of the Commission's Rules of 
Practice and Procedure \5\ and the regulations under the NGA \6\ by the 
intervention deadline for the project, which is May 8, 2023. As 
described further in Rule 214, your motion to intervene must state, to 
the extent known, your position regarding the proceeding, as well as 
your interest in the proceeding. For an individual, this could include 
your status as a landowner, ratepayer, resident of an impacted 
community, or recreationist. You do not need to have property directly 
impacted by the project in order to intervene. For more information 
about motions to intervene, refer to the FERC website at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------

    \5\ 18 CFR 385.214.
    \6\ 18 CFR 157.10.
---------------------------------------------------------------------------

    All timely, unopposed motions to intervene are automatically 
granted by operation of Rule 214(c)(1). Motions to intervene that are 
filed after the intervention deadline are untimely and may be denied. 
Any late-filed motion to intervene must show good cause for being late 
and must explain why the time limitation should be waived and provide 
justification by reference to factors set forth in Rule 214(d) of the 
Commission's Rules and Regulations. A person obtaining party status 
will be placed on the service list maintained by the Secretary of the 
Commission and will receive copies (paper or electronic) of all 
documents filed by the applicant and by all other parties.

Comments

    Any person wishing to comment on the project may do so. The 
Commission considers all comments received about the project in 
determining the appropriate action to be taken. To ensure that your 
comments are timely and properly recorded, please submit your comments 
on or before May 8, 2023. The filing of a comment alone will not serve 
to make the filer a party to the proceeding. To become a party, you 
must intervene in the proceeding.

How To File Protests, Interventions, and Comments

    There are two ways to submit protests, motions to intervene, and 
comments. In both instances, please reference the Project docket number 
CP23-85-000 in your submission.
    (1) You may file your protest, motion to intervene, and comments by 
using the

[[Page 16001]]

Commission's eFiling feature, which is located on the Commission's 
website (www.ferc.gov) under the link to Documents and Filings. New 
eFiling users must first create an account by clicking on 
``eRegister.'' You will be asked to select the type of filing you are 
making; first select ``General'' and then select ``Protest'', 
``Intervention'', or ``Comment on a Filing.'' The Commission's eFiling 
staff are available to assist you at (202) 502-8258 or 
[email protected]
    (2) You can file a paper copy of your submission. Your submission 
must reference the Project docket number CP23-85-000.
    To mail via USPS, use the following address: Kimberly D. Bose, 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426.
    To mail via any other courier, use the following address: Kimberly 
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins 
Avenue, Rockville, Maryland 20852.
    Protests and motions to intervene must be served on the applicant 
either by mail or email (with a link to the document) at: David A. 
Alonzo, Manager, Project Authorizations, Bison Pipeline LLC, 700 
Louisiana Street, Suite 1300, Houston, Texas 77002, by phone at (832) 
320-477; or by email to [email protected]. Any subsequent 
submissions by an intervenor must be served on the applicant and all 
other parties to the proceeding. Contact information for parties can be 
downloaded from the service list at the eService link on FERC Online.

Tracking the Proceeding

    Throughout the proceeding, additional information about the project 
will be available from the Commission's Office of External Affairs, at 
(866) 208-FERC, or on the FERC website at www.ferc.gov using the 
``eLibrary'' link as described above. The eLibrary link also provides 
access to the texts of all formal documents issued by the Commission, 
such as orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. For more information and to register, go to 
www.ferc.gov/docs-filing/esubscription.asp.

    Dated: March 9, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-05286 Filed 3-14-23; 8:45 am]
BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.