Bison Pipeline LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline, 16000-16001 [2023-05286]
Download as PDF
16000
Federal Register / Vol. 88, No. 50 / Wednesday, March 15, 2023 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP23–85–000]
lotter on DSK11XQN23PROD with NOTICES1
Bison Pipeline LLC; Notice of Request
Under Blanket Authorization and
Establishing Intervention and Protest
Deadline
Take notice that on March 3, 2023,
Bison Pipeline LLC (Bison), 700
Louisiana Street, Suite 1300, Houston,
Texas 77002, filed in the above
referenced docket, a prior notice
pursuant to Sections 157.205, 157.210,
and 157.216(b)(2)(iii) of the Federal
Energy Regulatory Commission’s
regulations under the Natural Gas Act
and the blanket certificate issued by the
Commission in Docket No. CP09–161–
000,1 seeking authorization to modify
the operation of its natural gas pipeline
mainline system to reduce the
Maximum Allowable Operating
Pressure (MAOP) and to abandon the
associated system design capacity
located in Campbell County, Wyoming
and Morton County, North Dakota.
Specifically, Bison seeks
authorization to reduce, from 1,440
pounds per square inch gauge (psig) to
1,296 psig, the MAOP of its entire
natural gas pipeline mainline system
from the Buffalo Meter Station, located
in Campbell County, Wyoming, to the
Kurtz Meter Station, located in Morton
County, North Dakota, in compliance
with U.S. Department of
Transportation’s Pipeline and
Hazardous Materials Safety
Administration’s regulations to ensure
continued system integrity and safe
operations. Additionally, Bison requests
authorization to abandon approximately
30.5 million cubic feet per day of
associated system design capacity, all as
more fully set forth in the request which
is on file with the Commission and open
to public inspection.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page
(www.ferc.gov) using the ‘‘eLibrary’’
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document. At
this time, the Commission has
suspended access to the Commission’s
Public Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
1 Bison
Pipeline LLC., 131 FERC ¶ 61,013 (2010).
VerDate Sep<11>2014
18:48 Mar 14, 2023
Jkt 259001
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact the Federal Energy
Regulatory Commission at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TTY, (202)
502–8659.
Any questions concerning this
application should be directed to David
A. Alonzo, Manager, Project
Authorizations, Bison Pipeline LLC, 700
Louisiana Street, Suite 1300, Houston,
Texas 77002, by phone at (832) 320–
477; or by email to david_alonzo@
tcenergy.com.
Public Participation
There are three ways to become
involved in the Commission’s review of
this project: you can file a protest to the
project, you can file a motion to
intervene in the proceeding, and you
can file comments on the project. There
is no fee or cost for filing protests,
motions to intervene, or comments. The
deadline for filing protests, motions to
intervene, and comments is 5:00 p.m.
Eastern Time on May 8, 2023. How to
file protests, motions to intervene, and
comments is explained below.
Protests
Pursuant to section 157.205 of the
Commission’s regulations under the
NGA,2 any person 3 or the Commission’s
staff may file a protest to the request. If
no protest is filed within the time
allowed or if a protest is filed and then
withdrawn within 30 days after the
allowed time for filing a protest, the
proposed activity shall be deemed to be
authorized effective the day after the
time allowed for protest. If a protest is
filed and not withdrawn within 30 days
after the time allowed for filing a
protest, the instant request for
authorization will be considered by the
Commission.
Protests must comply with the
requirements specified in section
157.205(e) of the Commission’s
regulations,4 and must be submitted by
the protest deadline, which is May 8,
2023. A protest may also serve as a
motion to intervene so long as the
protestor states it also seeks to be an
intervenor.
Interventions
Any person has the option to file a
motion to intervene in this proceeding.
Only intervenors have the right to
request rehearing of Commission orders
issued in this proceeding and to
2 18
CFR 157.205.
include individuals, organizations,
businesses, municipalities, and other entities. 18
CFR 385.102(d).
4 18 CFR 157.205(e).
3 Persons
PO 00000
Frm 00049
Fmt 4703
Sfmt 4703
subsequently challenge the
Commission’s orders in the U.S. Circuit
Courts of Appeal.
To intervene, you must submit a
motion to intervene to the Commission
in accordance with Rule 214 of the
Commission’s Rules of Practice and
Procedure 5 and the regulations under
the NGA 6 by the intervention deadline
for the project, which is May 8, 2023. As
described further in Rule 214, your
motion to intervene must state, to the
extent known, your position regarding
the proceeding, as well as your interest
in the proceeding. For an individual,
this could include your status as a
landowner, ratepayer, resident of an
impacted community, or recreationist.
You do not need to have property
directly impacted by the project in order
to intervene. For more information
about motions to intervene, refer to the
FERC website at https://www.ferc.gov/
resources/guides/how-to/intervene.asp.
All timely, unopposed motions to
intervene are automatically granted by
operation of Rule 214(c)(1). Motions to
intervene that are filed after the
intervention deadline are untimely and
may be denied. Any late-filed motion to
intervene must show good cause for
being late and must explain why the
time limitation should be waived and
provide justification by reference to
factors set forth in Rule 214(d) of the
Commission’s Rules and Regulations. A
person obtaining party status will be
placed on the service list maintained by
the Secretary of the Commission and
will receive copies (paper or electronic)
of all documents filed by the applicant
and by all other parties.
Comments
Any person wishing to comment on
the project may do so. The Commission
considers all comments received about
the project in determining the
appropriate action to be taken. To
ensure that your comments are timely
and properly recorded, please submit
your comments on or before May 8,
2023. The filing of a comment alone will
not serve to make the filer a party to the
proceeding. To become a party, you
must intervene in the proceeding.
How To File Protests, Interventions, and
Comments
There are two ways to submit
protests, motions to intervene, and
comments. In both instances, please
reference the Project docket number
CP23–85–000 in your submission.
(1) You may file your protest, motion
to intervene, and comments by using the
5 18
6 18
CFR 385.214.
CFR 157.10.
E:\FR\FM\15MRN1.SGM
15MRN1
Federal Register / Vol. 88, No. 50 / Wednesday, March 15, 2023 / Notices
Commission’s eFiling feature, which is
located on the Commission’s website
(www.ferc.gov) under the link to
Documents and Filings. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ You will be
asked to select the type of filing you are
making; first select ‘‘General’’ and then
select ‘‘Protest’’, ‘‘Intervention’’, or
‘‘Comment on a Filing.’’ The
Commission’s eFiling staff are available
to assist you at (202) 502–8258 or
FercOnlineSupport@ferc.gov.
(2) You can file a paper copy of your
submission. Your submission must
reference the Project docket number
CP23–85–000.
To mail via USPS, use the following
address: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
To mail via any other courier, use the
following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
Protests and motions to intervene
must be served on the applicant either
by mail or email (with a link to the
document) at: David A. Alonzo,
Manager, Project Authorizations, Bison
Pipeline LLC, 700 Louisiana Street,
Suite 1300, Houston, Texas 77002, by
phone at (832) 320–477; or by email to
david_alonzo@tcenergy.com. Any
subsequent submissions by an
intervenor must be served on the
applicant and all other parties to the
proceeding. Contact information for
parties can be downloaded from the
service list at the eService link on FERC
Online.
lotter on DSK11XQN23PROD with NOTICES1
Tracking the Proceeding
Throughout the proceeding,
additional information about the project
will be available from the Commission’s
Office of External Affairs, at (866) 208–
FERC, or on the FERC website at
www.ferc.gov using the ‘‘eLibrary’’ link
as described above. The eLibrary link
also provides access to the texts of all
formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. For more information and to
register, go to www.ferc.gov/docs-filing/
esubscription.asp.
VerDate Sep<11>2014
18:48 Mar 14, 2023
Jkt 259001
Dated: March 9, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–05286 Filed 3–14–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 4639–033]
Ampersand Christine Falls Hydro, LLC;
Notice of Application Accepted for
Filing and Soliciting Motions To
Intervene and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
Minor License.
b. Project No.: 4639–033.
c. Date filed: September 29, 2021.
d. Applicant: Ampersand Christine
Falls Hydro, LLC (Ampersand).
e. Name of Project: Christine Falls
Hydroelectric Project (Christine Falls
Project or project).
f. Location: On the Sacandaga River
near the Village of Speculator, Hamilton
County, New York. The project does not
occupy any federal land.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. Sayad
Moudachirou, Licensing Manager,
Ampersand Christine Falls Hydro LLC,
717 Atlantic Avenue, Suite 1A, Boston,
MA 02111, Phone: 617–933–7206,
Email: sayad@ampersandenergy.com;
and Mr. Jason Huang, Asset Manager,
Ampersand Christine Falls Hydro LLC,
717 Atlantic Avenue, Suite 1A, Boston,
MA 02111, Phone: 773–919–0923,
Email: jasonh@ampersandenergy.com.
i. FERC Contact: Andy Bernick at
(202) 502–8660, or andrew.bernick@
ferc.gov.
j. Deadline for filing motions to
intervene and protests: 60 days from the
issuance date of this notice.
The Commission strongly encourages
electronic filing. Please file motions to
intervene and protests using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, you may submit a
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
PO 00000
Frm 00050
Fmt 4703
Sfmt 4703
16001
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852. All filings must clearly identify
the project name and docket number on
the first page: Christine Falls
Hydroelectric Project (P–4639–033).
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
but is not ready for environmental
analysis.
l. The Christine Falls Project consists
of the following existing facilities: (1) a
15-foot-high, 152.6-foot-long concrete
gravity dam (includes both abutments),
with 3-foot-high wooden flashboards
installed along the crest of the 135-footlong spillway; (2) a reservoir with a
surface area of 1.1 acres and a storage
capacity of 4-acre feet at a normal water
surface elevation of 1,699.7 feet
National Geodetic Vertical Datum of
1929 (NGVD29); (3) an intake structure;
(4) a 613-foot-long steel penstock with a
diameter of 6 feet that bifurcates into 3foot-diameter, 45-foot-long and 4-footdiameter, 32-foot-long penstocks; (5) a
brick and concrete powerhouse
containing two turbine-generator units
(i.e., one 275-kilowatt (kW) unit and one
575-kW unit) with a total capacity of
850 kW; (7) a tailrace with a depth of
21 feet; (8) a 610-foot-long bypassed
reach; (9) a 185-foot-long underground
transmission line connecting the
generating units to a 1,000-kilovoltampere step-up transformer; (10) a
9,315-foot-long, 4.16/13.2-kilovolt
underground transmission line from the
transformer to a point of
interconnection; and (11) appurtenant
facilities.
The Christine Falls Project is operated
in a run-of-river mode, with a minimum
flow of 25 cubic feet per second (cfs)
into the bypassed reach during the
months of March, April, and May, and
a minimum flow of 10 cfs during the
remainder of the year. The project has
an average annual generation of 2,478
megawatt-hours.
Ampersand proposes to operate the
project in a strict run-of-river mode with
an impoundment level fluctuation limit
of 3 inches from the dam crest or
flashboards when in place. As described
E:\FR\FM\15MRN1.SGM
15MRN1
Agencies
[Federal Register Volume 88, Number 50 (Wednesday, March 15, 2023)]
[Notices]
[Pages 16000-16001]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-05286]
[[Page 16000]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP23-85-000]
Bison Pipeline LLC; Notice of Request Under Blanket Authorization
and Establishing Intervention and Protest Deadline
Take notice that on March 3, 2023, Bison Pipeline LLC (Bison), 700
Louisiana Street, Suite 1300, Houston, Texas 77002, filed in the above
referenced docket, a prior notice pursuant to Sections 157.205,
157.210, and 157.216(b)(2)(iii) of the Federal Energy Regulatory
Commission's regulations under the Natural Gas Act and the blanket
certificate issued by the Commission in Docket No. CP09-161-000,\1\
seeking authorization to modify the operation of its natural gas
pipeline mainline system to reduce the Maximum Allowable Operating
Pressure (MAOP) and to abandon the associated system design capacity
located in Campbell County, Wyoming and Morton County, North Dakota.
---------------------------------------------------------------------------
\1\ Bison Pipeline LLC., 131 FERC ] 61,013 (2010).
---------------------------------------------------------------------------
Specifically, Bison seeks authorization to reduce, from 1,440
pounds per square inch gauge (psig) to 1,296 psig, the MAOP of its
entire natural gas pipeline mainline system from the Buffalo Meter
Station, located in Campbell County, Wyoming, to the Kurtz Meter
Station, located in Morton County, North Dakota, in compliance with
U.S. Department of Transportation's Pipeline and Hazardous Materials
Safety Administration's regulations to ensure continued system
integrity and safe operations. Additionally, Bison requests
authorization to abandon approximately 30.5 million cubic feet per day
of associated system design capacity, all as more fully set forth in
the request which is on file with the Commission and open to public
inspection.
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (www.ferc.gov) using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to the Commission's Public
Reference Room, due to the proclamation declaring a National Emergency
concerning the Novel Coronavirus Disease (COVID-19), issued by the
President on March 13, 2020. For assistance, contact the Federal Energy
Regulatory Commission at [email protected] or call toll-free,
(886) 208-3676 or TTY, (202) 502-8659.
Any questions concerning this application should be directed to
David A. Alonzo, Manager, Project Authorizations, Bison Pipeline LLC,
700 Louisiana Street, Suite 1300, Houston, Texas 77002, by phone at
(832) 320-477; or by email to [email protected].
Public Participation
There are three ways to become involved in the Commission's review
of this project: you can file a protest to the project, you can file a
motion to intervene in the proceeding, and you can file comments on the
project. There is no fee or cost for filing protests, motions to
intervene, or comments. The deadline for filing protests, motions to
intervene, and comments is 5:00 p.m. Eastern Time on May 8, 2023. How
to file protests, motions to intervene, and comments is explained
below.
Protests
Pursuant to section 157.205 of the Commission's regulations under
the NGA,\2\ any person \3\ or the Commission's staff may file a protest
to the request. If no protest is filed within the time allowed or if a
protest is filed and then withdrawn within 30 days after the allowed
time for filing a protest, the proposed activity shall be deemed to be
authorized effective the day after the time allowed for protest. If a
protest is filed and not withdrawn within 30 days after the time
allowed for filing a protest, the instant request for authorization
will be considered by the Commission.
---------------------------------------------------------------------------
\2\ 18 CFR 157.205.
\3\ Persons include individuals, organizations, businesses,
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------
Protests must comply with the requirements specified in section
157.205(e) of the Commission's regulations,\4\ and must be submitted by
the protest deadline, which is May 8, 2023. A protest may also serve as
a motion to intervene so long as the protestor states it also seeks to
be an intervenor.
---------------------------------------------------------------------------
\4\ 18 CFR 157.205(e).
---------------------------------------------------------------------------
Interventions
Any person has the option to file a motion to intervene in this
proceeding. Only intervenors have the right to request rehearing of
Commission orders issued in this proceeding and to subsequently
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
To intervene, you must submit a motion to intervene to the
Commission in accordance with Rule 214 of the Commission's Rules of
Practice and Procedure \5\ and the regulations under the NGA \6\ by the
intervention deadline for the project, which is May 8, 2023. As
described further in Rule 214, your motion to intervene must state, to
the extent known, your position regarding the proceeding, as well as
your interest in the proceeding. For an individual, this could include
your status as a landowner, ratepayer, resident of an impacted
community, or recreationist. You do not need to have property directly
impacted by the project in order to intervene. For more information
about motions to intervene, refer to the FERC website at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------
\5\ 18 CFR 385.214.
\6\ 18 CFR 157.10.
---------------------------------------------------------------------------
All timely, unopposed motions to intervene are automatically
granted by operation of Rule 214(c)(1). Motions to intervene that are
filed after the intervention deadline are untimely and may be denied.
Any late-filed motion to intervene must show good cause for being late
and must explain why the time limitation should be waived and provide
justification by reference to factors set forth in Rule 214(d) of the
Commission's Rules and Regulations. A person obtaining party status
will be placed on the service list maintained by the Secretary of the
Commission and will receive copies (paper or electronic) of all
documents filed by the applicant and by all other parties.
Comments
Any person wishing to comment on the project may do so. The
Commission considers all comments received about the project in
determining the appropriate action to be taken. To ensure that your
comments are timely and properly recorded, please submit your comments
on or before May 8, 2023. The filing of a comment alone will not serve
to make the filer a party to the proceeding. To become a party, you
must intervene in the proceeding.
How To File Protests, Interventions, and Comments
There are two ways to submit protests, motions to intervene, and
comments. In both instances, please reference the Project docket number
CP23-85-000 in your submission.
(1) You may file your protest, motion to intervene, and comments by
using the
[[Page 16001]]
Commission's eFiling feature, which is located on the Commission's
website (www.ferc.gov) under the link to Documents and Filings. New
eFiling users must first create an account by clicking on
``eRegister.'' You will be asked to select the type of filing you are
making; first select ``General'' and then select ``Protest'',
``Intervention'', or ``Comment on a Filing.'' The Commission's eFiling
staff are available to assist you at (202) 502-8258 or
[email protected]
(2) You can file a paper copy of your submission. Your submission
must reference the Project docket number CP23-85-000.
To mail via USPS, use the following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street NE,
Washington, DC 20426.
To mail via any other courier, use the following address: Kimberly
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852.
Protests and motions to intervene must be served on the applicant
either by mail or email (with a link to the document) at: David A.
Alonzo, Manager, Project Authorizations, Bison Pipeline LLC, 700
Louisiana Street, Suite 1300, Houston, Texas 77002, by phone at (832)
320-477; or by email to [email protected]. Any subsequent
submissions by an intervenor must be served on the applicant and all
other parties to the proceeding. Contact information for parties can be
downloaded from the service list at the eService link on FERC Online.
Tracking the Proceeding
Throughout the proceeding, additional information about the project
will be available from the Commission's Office of External Affairs, at
(866) 208-FERC, or on the FERC website at www.ferc.gov using the
``eLibrary'' link as described above. The eLibrary link also provides
access to the texts of all formal documents issued by the Commission,
such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. For more information and to register, go to
www.ferc.gov/docs-filing/esubscription.asp.
Dated: March 9, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-05286 Filed 3-14-23; 8:45 am]
BILLING CODE 6717-01-P