Sites Project Authority; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene, 15709-15710 [2023-05161]

Download as PDF Federal Register / Vol. 88, No. 49 / Tuesday, March 14, 2023 / Notices not include a listing of all documents relevant to the items on the agenda. All public documents, however, may be viewed on line at the Commission’s 15709 website at https://elibrary.ferc.gov/ eLibrary/search using the eLibrary link. 1099TH—MEETING [Open Meeting; March 16, 2023, 10:00 a.m.] Item No. Docket No. Company Administrative A–1 ........ A–2 ........ A–3 ........ AD23–1–000 .......... AD23–2–000 .......... AD06–3–000 .......... Agency Administrative Matters. Customer Matters, Reliability, Security and Market Operations. Market Update. Electric E–1 E–2 E–3 E–4 E–5 E–6 E–7 ........ ........ ........ ........ ........ ........ ........ E–8 ........ E–9 ........ E–10 ...... E–11 ...... E–12 ...... RD23–3–000 .......... ER21–2459–001 .... EL23–31–000 ........ EL22–39–000 ........ EL22–37–000 ........ ES23–23–000 ........ EL15–3–005 .......... E15–704–027 ........ EL22–56–001 ........ EL23–8–000 .......... ER20–2584–001 .... ER22–2377–000 .... EL23–14–000 ........ North American Electric Relaibility Corporation. Tenaska Power Services Co. Commonwealth Edison Company. Public Service Company of Colorado. Idaho Power Company. PJM Interconnection, L.L.C. City and County of San Francisco v. Pacific Gas and Electric Company. Pacific Gas and Electric Company. Iowa Coalition for Affordable Transmission v. ITC Midwest, LLC. Cubit Power One, Inc. v. Consolidated Edison Company of New York, Inc. Transource Maryland, LLC, American Electric Power Service Corporation, and PJM Interconnection, L.L.C. Black Hills Colorado Electric, LLC. Alternative Transmission Inc. Gas G–1 ........ RP22–1105–000 .... G–2 ........ RP21–1143–001 .... Anadarko US Offshore LLC, Murphy Exploration & Production Company—USA, Eni Petroleum US LLC, and INPEX Americas, Inc. Transcontinental Gas Pipe Line Company, LLC. Hydro H–1 ........ P–2322–073 .......... Brookfield White Pine Hydro LLC. Certificates ddrumheller on DSK120RN23PROD with NOTICES1 C–1 C–2 C–3 C–4 C–5 C–6 ........ ........ ........ ........ ........ ........ CP23–11–000 ........ CP21–498–000 ...... CP21–113–000 ...... CP22–41–000 ........ OMITTED. CP21–94–001 ........ Florida Gas Transmission Company, LLC. Columbia Gas Transmission, LLC. Alliance Pipeline L.P. Cameron LNG, LLC. Transcontinental Gas Pipe Line Company, LLC. A free webcast of this event is available through the Commission’s website. Anyone with internet access who desires to view this event can do so by navigating to www.ferc.gov’s Calendar of Events and locating this event in the Calendar. The Federal Energy Regulatory Commission provides technical support for the free webcasts. Please call (202) 502–8680 or email customer@ferc.gov if you have any questions. Immediately following the conclusion of the Commission Meeting, a press briefing will be held in the Commission Meeting Room. Members of the public may view this briefing in the designated overflow room. This statement is intended to notify the public that the press briefings that follow Commission meetings may now be viewed remotely VerDate Sep<11>2014 21:09 Mar 13, 2023 Jkt 259001 at Commission headquarters but will not be telecast. Issued: March 9, 2023. Debbie-Anne A. Reese, Deputy Secretary. DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CD23–6–000] [FR Doc. 2023–05288 Filed 3–10–23; 11:15 am] Sites Project Authority; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene BILLING CODE 6717–01–P PO 00000 On February 22, 2023, the Sites Project Authority, filed a notice of intent to construct a qualifying conduit hydropower facility, pursuant to section 30 of the Federal Power Act (FPA). The proposed Terminal Regulating Reservoir Energy Recovery Project would have an installed capacity of 26,000 kilowatts (kW), and would be located along a pipeline within the water supply system Frm 00071 Fmt 4703 Sfmt 4703 E:\FR\FM\14MRN1.SGM 14MRN1 15710 Federal Register / Vol. 88, No. 49 / Tuesday, March 14, 2023 / Notices near Maxwell, Colusa County, California. Applicant Contact: Jerry Brown, Executive Director, Sites Project Authority, PO Box 517, Maxwell, CA 95955, 925–260–7417, jbrown@ sitesproject.org. FERC Contact: Christopher Chaney, 202–502–6778, christopher.chaney@ ferc.gov. Qualifying Conduit Hydropower Facility Description: The project would consist of: (1) two turbine generator buildings, each housing a 13,000-kW unit, (2) intake and discharge pipes, and (3) appurtenant facilities. The proposed project would have an estimated annual generation of approximately 12,200 megawatt-hours. A qualifying conduit hydropower facility is one that is determined or deemed to meet all the criteria shown in the table below. TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY Statutory provision Description Satisfies (Y/N) FPA 30(a)(3)(A) ........................................ The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch, or similar manmade water conveyance that is operated for the distribution of water for agricultural, municipal, or industrial consumption and not primarily for the generation of electricity. The facility is constructed, operated, or maintained for the generation of electric power and uses for such generation only the hydroelectric potential of a non-federally owned conduit. The facility has an installed capacity that does not exceed 40 megawatts ................ On or before August 9, 2013, the facility is not licensed, or exempted from the licensing requirements of Part I of the FPA. Y FPA 30(a)(3)(C)(i) ..................................... ddrumheller on DSK120RN23PROD with NOTICES1 FPA 30(a)(3)(C)(ii) .................................... FPA 30(a)(3)(C)(iii) ................................... Preliminary Determination: The proposed Terminal Regulating Reservoir Energy Recovery Project will not alter the primary purpose of the conduit, which is for irrigation, municipal water supply, and other uses. Therefore, based upon the above criteria, Commission staff preliminarily determines that the operation of the project described above satisfies the requirements for a qualifying conduit hydropower facility, which is not required to be licensed or exempted from licensing. Comments and Motions to Intervene: Deadline for filing comments contesting whether the facility meets the qualifying criteria is 30 days from the issuance date of this notice. Deadline for filing motions to intervene is 30 days from the issuance date of this notice. Anyone may submit comments or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210 and 385.214. Any motions to intervene must be received on or before the specified deadline date for the particular proceeding. Filing and Service of Responsive Documents: All filings must (1) bear in all capital letters the ‘‘COMMENTS CONTESTING QUALIFICATION FOR A CONDUIT HYDROPOWER FACILITY’’ or ‘‘MOTION TO INTERVENE,’’ as applicable; (2) state in the heading the name of the applicant and the project number of the application to which the filing responds; (3) state the name, address, and telephone number of the person filing; and (4) otherwise comply with the requirements of sections 385.2001 through 385.2005 of the VerDate Sep<11>2014 21:09 Mar 13, 2023 Jkt 259001 Commission’s regulations.1 All comments contesting Commission staff’s preliminary determination that the facility meets the qualifying criteria must set forth their evidentiary basis. The Commission strongly encourages electronic filing. Please file motions to intervene and comments using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may send a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD 20852. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. Locations of Notice of Intent: The Commission provides all interested persons an opportunity to view and/or print the contents of this document via 1 18 PO 00000 CFR 385.2001–2005 (2021). Frm 00072 Fmt 4703 Sfmt 4703 Y Y Y the internet through the Commission’s website at https://www.ferc.gov/docsfiling/elibrary.asp. Enter the docket number (i.e., CD23–6) in the docket number field to access the document. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. Copies of the notice of intent can be obtained directly from the applicant. For assistance, call toll-free 1–866–208– 3676 or email FERCOnlineSupport@ ferc.gov. For TTY, call (202) 502–8659. Dated: March 8, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–05161 Filed 3–13–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Western Area Power Administration Desert Southwest Region Ancillary Services—Rate Order No. WAPA–208 Western Area Power Administration, DOE. ACTION: Notice of rate order concerning formula rates for Energy Imbalance Market services. AGENCY: New formula rates for Energy Imbalance Market (EIM) Administrative Service, Energy Imbalance (EI) Service, and Generator Imbalance (GI) Service for the Western Area Lower Colorado (WALC) Balancing Authority (BA) have been confirmed, approved, and placed into effect on an interim basis. The new formula rates are necessary for the SUMMARY: E:\FR\FM\14MRN1.SGM 14MRN1

Agencies

[Federal Register Volume 88, Number 49 (Tuesday, March 14, 2023)]
[Notices]
[Pages 15709-15710]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-05161]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD23-6-000]


Sites Project Authority; Notice of Preliminary Determination of a 
Qualifying Conduit Hydropower Facility and Soliciting Comments and 
Motions To Intervene

    On February 22, 2023, the Sites Project Authority, filed a notice 
of intent to construct a qualifying conduit hydropower facility, 
pursuant to section 30 of the Federal Power Act (FPA). The proposed 
Terminal Regulating Reservoir Energy Recovery Project would have an 
installed capacity of 26,000 kilowatts (kW), and would be located along 
a pipeline within the water supply system

[[Page 15710]]

near Maxwell, Colusa County, California.
    Applicant Contact: Jerry Brown, Executive Director, Sites Project 
Authority, PO Box 517, Maxwell, CA 95955, 925-260-7417, 
[email protected].
    FERC Contact: Christopher Chaney, 202-502-6778, 
[email protected].
    Qualifying Conduit Hydropower Facility Description: The project 
would consist of: (1) two turbine generator buildings, each housing a 
13,000-kW unit, (2) intake and discharge pipes, and (3) appurtenant 
facilities. The proposed project would have an estimated annual 
generation of approximately 12,200 megawatt-hours.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all the criteria shown in the table below.

      Table 1--Criteria for Qualifying Conduit Hydropower Facility
------------------------------------------------------------------------
      Statutory provision              Description       Satisfies (Y/N)
------------------------------------------------------------------------
FPA 30(a)(3)(A)................  The conduit the                      Y
                                  facility uses is a
                                  tunnel, canal,
                                  pipeline, aqueduct,
                                  flume, ditch, or
                                  similar manmade water
                                  conveyance that is
                                  operated for the
                                  distribution of water
                                  for agricultural,
                                  municipal, or
                                  industrial
                                  consumption and not
                                  primarily for the
                                  generation of
                                  electricity.
FPA 30(a)(3)(C)(i).............  The facility is                      Y
                                  constructed,
                                  operated, or
                                  maintained for the
                                  generation of
                                  electric power and
                                  uses for such
                                  generation only the
                                  hydroelectric
                                  potential of a non-
                                  federally owned
                                  conduit.
FPA 30(a)(3)(C)(ii)............  The facility has an                  Y
                                  installed capacity
                                  that does not exceed
                                  40 megawatts.
FPA 30(a)(3)(C)(iii)...........  On or before August 9,               Y
                                  2013, the facility is
                                  not licensed, or
                                  exempted from the
                                  licensing
                                  requirements of Part
                                  I of the FPA.
------------------------------------------------------------------------

    Preliminary Determination: The proposed Terminal Regulating 
Reservoir Energy Recovery Project will not alter the primary purpose of 
the conduit, which is for irrigation, municipal water supply, and other 
uses. Therefore, based upon the above criteria, Commission staff 
preliminarily determines that the operation of the project described 
above satisfies the requirements for a qualifying conduit hydropower 
facility, which is not required to be licensed or exempted from 
licensing.
    Comments and Motions to Intervene: Deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 30 
days from the issuance date of this notice. Deadline for filing motions 
to intervene is 30 days from the issuance date of this notice.
    Anyone may submit comments or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210 and 385.214. Any motions to intervene must be received on or 
before the specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR 
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as 
applicable; (2) state in the heading the name of the applicant and the 
project number of the application to which the filing responds; (3) 
state the name, address, and telephone number of the person filing; and 
(4) otherwise comply with the requirements of sections 385.2001 through 
385.2005 of the Commission's regulations.\1\ All comments contesting 
Commission staff's preliminary determination that the facility meets 
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2021).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at [email protected], (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, you may send a 
paper copy. Submissions sent via the U.S. Postal Service must be 
addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE, Room 1A, Washington, DC 20426. 
Submissions sent via any other carrier must be addressed to: Kimberly 
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins 
Avenue, Rockville, MD 20852. A copy of all other filings in reference 
to this application must be accompanied by proof of service on all 
persons listed in the service list prepared by the Commission in this 
proceeding, in accordance with 18 CFR 385.2010.
    Locations of Notice of Intent: The Commission provides all 
interested persons an opportunity to view and/or print the contents of 
this document via the internet through the Commission's website at 
https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number 
(i.e., CD23-6) in the docket number field to access the document. You 
may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. Copies of the notice of 
intent can be obtained directly from the applicant. For assistance, 
call toll-free 1-866-208-3676 or email [email protected]. For 
TTY, call (202) 502-8659.

    Dated: March 8, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-05161 Filed 3-13-23; 8:45 am]