Southern Natural Gas Company, LLC; Notice of Request for Extension of Time, 15012 [2023-04998]
Download as PDF
15012
Federal Register / Vol. 88, No. 47 / Friday, March 10, 2023 / Notices
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: March 6, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–04996 Filed 3–9–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP22–34–000]
lotter on DSK11XQN23PROD with NOTICES1
Southern Natural Gas Company, LLC;
Notice of Request for Extension of
Time
Take notice that on February 28, 2023,
Southern Natural Gas Company, L.L.C
(SNG) requested that the Federal Energy
Regulatory Commission (Commission)
grant an extension of time, until April
4, 2023, to complete its North System
2022 Project. SNG received a prior
notice authorization for the North
System 2022 Project on March 5, 2022
which authorized: (1) the construction
of approximately 2.2 miles of 8-inchdiameter pipeline (Cordova Connector
Line) in Walker County, Alabama; (2)
the modification of existing facilities
along the SNG system in Walker,
Morgan, Calhoun, Jefferson, and
Tuscaloosa counties, Alabama; and (3)
the re-wheeling the existing Compressor
Unit #1 at SNG’s Providence
Compressor Station in Tuscaloosa
County, Alabama. The commission’s
prior notice regulations require SNG to
complete the construction of the North
System 2022 Project and make it
available for service within one year
from issuance, or by March 4, 2023.1
In SNG’s request for an extension of
time, SNG stated that as the
construction of the Project was nearing
completion, SNG determined that for
operational safety a Remote Terminal
Unit needed to be relocated to provide
a 25-foot hazardous area radius with
additional equipment at its Cordova
Start site. Due to this scope addition and
rainy condition SNG requests an
extension of time in which to complete
the Project from the one-year date of
March 4, 2023, to the new projected
completion date of April 4, 2023.
This notice establishes a 15-calendar
day intervention and comment period
deadline. Any person wishing to
comment on SNG’s request for an
1 18
CFR 157.207(c).
VerDate Sep<11>2014
17:45 Mar 09, 2023
Jkt 259001
extension of time may do so. No reply
comments or answers will be
considered. If you wish to obtain legal
status by becoming a party to the
proceedings for this request, you
should, on or before the comment date
stated below, file a motion to intervene
in accordance with the requirements of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the Natural
Gas Act (18 CFR 157.10).2
As a matter of practice, the
Commission itself generally acts on
requests for extensions of time to
complete construction for Natural Gas
Act facilities when such requests are
contested before order issuance. For
those extension requests that are
contested,3 the Commission will aim to
issue an order acting on the request
within 45 days.4 The Commission will
address all arguments relating to
whether the applicant has demonstrated
there is good cause to grant the
extension.5 The Commission will not
consider arguments that re-litigate the
issuance of the Certificate Order,
including whether the Commission
properly found the project to be in the
public convenience and necessity and
whether the Commission’s
environmental analysis for the
certificate complied with the National
Environmental Policy Act.6 At the time
a pipeline requests an extension of time,
orders on certificates of public
convenience and necessity are final and
the Commission will not re-litigate their
issuance.7 The OEP Director, or his or
her designee, will act on those extension
requests that are uncontested.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
2 Only motions to intervene from entities that
were party to the underlying proceeding will be
accepted. Algonquin Gas Transmission, LLC, 170
FERC ¶ 61,144, at P 39 (2020).
3 Contested proceedings are those where an
intervenor disputes any material issue of the filing.
18 CFR 385.2201(c)(1) (2020).
4 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
5 Id. P 40.
6 Similarly, the Commission will not re-litigate
the issuance of an NGA section 3 authorization,
including whether a proposed project is not
inconsistent with the public interest and whether
the Commission’s environmental analysis for the
permit order complied with NEPA.
7 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
PO 00000
Frm 00043
Fmt 4703
Sfmt 4703
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning COVID–19,
issued by the President on March 13,
2020. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFile’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original copy of the
protest or intervention by U.S. mail to
Kimberly D. Bose, Secretary Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
Submissions by any other courier in
docketed proceedings should be
delivered to, Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
Comment Date: 5:00 p.m. Eastern
Time on March 21, 2023.
Dated: March 6, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–04998 Filed 3–9–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP23–76–000]
ANR Pipeline Company; Notice of
Request Under Blanket Authorization
and Establishing Intervention and
Protest Deadline
Take notice that on February 22, 2023,
ANR Pipeline Company (ANR), 700
Louisiana Street, Suite 1300, Houston,
Texas 77002–2700, filed in the abovereferenced docket, a prior notice request
pursuant to sections 157.205 and
157.216(b) of the Federal Energy
Regulatory Commission’s (Commission)
regulations under the Natural Gas Act
(NGA), and ANR’s blanket certificate
issued in Docket No. CP82–480–000,1
for authorization to abandon one
injection/withdrawal well and
appurtenant facilities located at the
Goodwell Storage Field in Newaygo
County, Michigan, all as more fully set
forth in the application which is on file
with the Commission and open for
public inspection.
1 See Michigan Wisconsin Pipe Line Company, 20
FERC ¶ 62,595 (1982).
E:\FR\FM\10MRN1.SGM
10MRN1
Agencies
[Federal Register Volume 88, Number 47 (Friday, March 10, 2023)]
[Notices]
[Page 15012]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-04998]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP22-34-000]
Southern Natural Gas Company, LLC; Notice of Request for
Extension of Time
Take notice that on February 28, 2023, Southern Natural Gas
Company, L.L.C (SNG) requested that the Federal Energy Regulatory
Commission (Commission) grant an extension of time, until April 4,
2023, to complete its North System 2022 Project. SNG received a prior
notice authorization for the North System 2022 Project on March 5, 2022
which authorized: (1) the construction of approximately 2.2 miles of 8-
inch-diameter pipeline (Cordova Connector Line) in Walker County,
Alabama; (2) the modification of existing facilities along the SNG
system in Walker, Morgan, Calhoun, Jefferson, and Tuscaloosa counties,
Alabama; and (3) the re-wheeling the existing Compressor Unit #1 at
SNG's Providence Compressor Station in Tuscaloosa County, Alabama. The
commission's prior notice regulations require SNG to complete the
construction of the North System 2022 Project and make it available for
service within one year from issuance, or by March 4, 2023.\1\
---------------------------------------------------------------------------
\1\ 18 CFR 157.207(c).
---------------------------------------------------------------------------
In SNG's request for an extension of time, SNG stated that as the
construction of the Project was nearing completion, SNG determined that
for operational safety a Remote Terminal Unit needed to be relocated to
provide a 25-foot hazardous area radius with additional equipment at
its Cordova Start site. Due to this scope addition and rainy condition
SNG requests an extension of time in which to complete the Project from
the one-year date of March 4, 2023, to the new projected completion
date of April 4, 2023.
This notice establishes a 15-calendar day intervention and comment
period deadline. Any person wishing to comment on SNG's request for an
extension of time may do so. No reply comments or answers will be
considered. If you wish to obtain legal status by becoming a party to
the proceedings for this request, you should, on or before the comment
date stated below, file a motion to intervene in accordance with the
requirements of the Commission's Rules of Practice and Procedure (18
CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act
(18 CFR 157.10).\2\
---------------------------------------------------------------------------
\2\ Only motions to intervene from entities that were party to
the underlying proceeding will be accepted. Algonquin Gas
Transmission, LLC, 170 FERC ] 61,144, at P 39 (2020).
---------------------------------------------------------------------------
As a matter of practice, the Commission itself generally acts on
requests for extensions of time to complete construction for Natural
Gas Act facilities when such requests are contested before order
issuance. For those extension requests that are contested,\3\ the
Commission will aim to issue an order acting on the request within 45
days.\4\ The Commission will address all arguments relating to whether
the applicant has demonstrated there is good cause to grant the
extension.\5\ The Commission will not consider arguments that re-
litigate the issuance of the Certificate Order, including whether the
Commission properly found the project to be in the public convenience
and necessity and whether the Commission's environmental analysis for
the certificate complied with the National Environmental Policy Act.\6\
At the time a pipeline requests an extension of time, orders on
certificates of public convenience and necessity are final and the
Commission will not re-litigate their issuance.\7\ The OEP Director, or
his or her designee, will act on those extension requests that are
uncontested.
---------------------------------------------------------------------------
\3\ Contested proceedings are those where an intervenor disputes
any material issue of the filing. 18 CFR 385.2201(c)(1) (2020).
\4\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40
(2020).
\5\ Id. P 40.
\6\ Similarly, the Commission will not re-litigate the issuance
of an NGA section 3 authorization, including whether a proposed
project is not inconsistent with the public interest and whether the
Commission's environmental analysis for the permit order complied
with NEPA.
\7\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40
(2020).
---------------------------------------------------------------------------
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (https://ferc.gov) using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to the Commission's Public
Reference Room, due to the proclamation declaring a National Emergency
concerning COVID-19, issued by the President on March 13, 2020. For
assistance, contact FERC at [email protected] or call toll-
free, (886) 208-3676 or TYY, (202) 502-8659.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFile'' link at
https://www.ferc.gov. Persons unable to file electronically should
submit an original copy of the protest or intervention by U.S. mail to
Kimberly D. Bose, Secretary Federal Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426. Submissions by any other courier
in docketed proceedings should be delivered to, Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
Comment Date: 5:00 p.m. Eastern Time on March 21, 2023.
Dated: March 6, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-04998 Filed 3-9-23; 8:45 am]
BILLING CODE 6717-01-P