Download as PDF 15012 Federal Register / Vol. 88, No. 47 / Friday, March 10, 2023 / Notices o. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. Dated: March 6, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–04996 Filed 3–9–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP22–34–000] lotter on DSK11XQN23PROD with NOTICES1 Southern Natural Gas Company, LLC; Notice of Request for Extension of Time Take notice that on February 28, 2023, Southern Natural Gas Company, L.L.C (SNG) requested that the Federal Energy Regulatory Commission (Commission) grant an extension of time, until April 4, 2023, to complete its North System 2022 Project. SNG received a prior notice authorization for the North System 2022 Project on March 5, 2022 which authorized: (1) the construction of approximately 2.2 miles of 8-inchdiameter pipeline (Cordova Connector Line) in Walker County, Alabama; (2) the modification of existing facilities along the SNG system in Walker, Morgan, Calhoun, Jefferson, and Tuscaloosa counties, Alabama; and (3) the re-wheeling the existing Compressor Unit #1 at SNG’s Providence Compressor Station in Tuscaloosa County, Alabama. The commission’s prior notice regulations require SNG to complete the construction of the North System 2022 Project and make it available for service within one year from issuance, or by March 4, 2023.1 In SNG’s request for an extension of time, SNG stated that as the construction of the Project was nearing completion, SNG determined that for operational safety a Remote Terminal Unit needed to be relocated to provide a 25-foot hazardous area radius with additional equipment at its Cordova Start site. Due to this scope addition and rainy condition SNG requests an extension of time in which to complete the Project from the one-year date of March 4, 2023, to the new projected completion date of April 4, 2023. This notice establishes a 15-calendar day intervention and comment period deadline. Any person wishing to comment on SNG’s request for an 1 18 CFR 157.207(c). VerDate Sep<11>2014 17:45 Mar 09, 2023 Jkt 259001 extension of time may do so. No reply comments or answers will be considered. If you wish to obtain legal status by becoming a party to the proceedings for this request, you should, on or before the comment date stated below, file a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act (18 CFR 157.10).2 As a matter of practice, the Commission itself generally acts on requests for extensions of time to complete construction for Natural Gas Act facilities when such requests are contested before order issuance. For those extension requests that are contested,3 the Commission will aim to issue an order acting on the request within 45 days.4 The Commission will address all arguments relating to whether the applicant has demonstrated there is good cause to grant the extension.5 The Commission will not consider arguments that re-litigate the issuance of the Certificate Order, including whether the Commission properly found the project to be in the public convenience and necessity and whether the Commission’s environmental analysis for the certificate complied with the National Environmental Policy Act.6 At the time a pipeline requests an extension of time, orders on certificates of public convenience and necessity are final and the Commission will not re-litigate their issuance.7 The OEP Director, or his or her designee, will act on those extension requests that are uncontested. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this 2 Only motions to intervene from entities that were party to the underlying proceeding will be accepted. Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 39 (2020). 3 Contested proceedings are those where an intervenor disputes any material issue of the filing. 18 CFR 385.2201(c)(1) (2020). 4 Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 40 (2020). 5 Id. P 40. 6 Similarly, the Commission will not re-litigate the issuance of an NGA section 3 authorization, including whether a proposed project is not inconsistent with the public interest and whether the Commission’s environmental analysis for the permit order complied with NEPA. 7 Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 40 (2020). PO 00000 Frm 00043 Fmt 4703 Sfmt 4703 time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning COVID–19, issued by the President on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFile’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original copy of the protest or intervention by U.S. mail to Kimberly D. Bose, Secretary Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Submissions by any other courier in docketed proceedings should be delivered to, Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. Comment Date: 5:00 p.m. Eastern Time on March 21, 2023. Dated: March 6, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–04998 Filed 3–9–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP23–76–000] ANR Pipeline Company; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline Take notice that on February 22, 2023, ANR Pipeline Company (ANR), 700 Louisiana Street, Suite 1300, Houston, Texas 77002–2700, filed in the abovereferenced docket, a prior notice request pursuant to sections 157.205 and 157.216(b) of the Federal Energy Regulatory Commission’s (Commission) regulations under the Natural Gas Act (NGA), and ANR’s blanket certificate issued in Docket No. CP82–480–000,1 for authorization to abandon one injection/withdrawal well and appurtenant facilities located at the Goodwell Storage Field in Newaygo County, Michigan, all as more fully set forth in the application which is on file with the Commission and open for public inspection. 1 See Michigan Wisconsin Pipe Line Company, 20 FERC ¶ 62,595 (1982). E:\FR\FM\10MRN1.SGM 10MRN1 Federal Register / Vol. 88, No. 47 / Friday, March 10, 2023 / Notices lotter on DSK11XQN23PROD with NOTICES1 In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TTY, (202) 502–8659. Any questions concerning this application should be directed to David A. Alonzo, Manager, Project Authorizations, ANR Pipeline Company, 700 Louisiana Street, Suite 1300, Houston, Texas 77002–2700, at (832) 320–5477 or david_alonzo@ tcenergy.com. Pursuant to Section 157.9 of the Commission’s Rules of Practice and Procedure,2 within 90 days of this Notice the Commission staff will either: complete its environmental review and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or environmental assessment (EA) for this proposal. The filing of an EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Public Participation There are three ways to become involved in the Commission’s review of this project: you can file a protest to the project, you can file a motion to intervene in the proceeding, and you can file comments on the project. There is no fee or cost for filing protests, motions to intervene, or comments. The deadline for filing protests, motions to 2 18 CFR (Code of Federal Regulations) § 157.9. VerDate Sep<11>2014 17:45 Mar 09, 2023 Jkt 259001 intervene, and comments is 5:00 p.m. Eastern Time on May 05, 2023. How to file protests, motions to intervene, and comments is explained below. Protests Pursuant to section 157.205 of the Commission’s regulations under the NGA,3 any person 4 or the Commission’s staff may file a protest to the request. If no protest is filed within the time allowed or if a protest is filed and then withdrawn within 30 days after the allowed time for filing a protest, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request for authorization will be considered by the Commission. Protests must comply with the requirements specified in section 157.205(e) of the Commission’s regulations,5 and must be submitted by the protest deadline, which is May 05, 2023. A protest may also serve as a motion to intervene so long as the protestor states it also seeks to be an intervenor. Interventions Any person has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission’s orders in the U.S. Circuit Courts of Appeal. To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure 6 and the regulations under the NGA 7 by the intervention deadline for the project, which is May 05, 2023. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the 3 18 CFR 157.205. include individuals, organizations, businesses, municipalities, and other entities. 18 CFR 385.102(d). 4 18 cfr 157.205(e). 6 18 CFR 385.214. 7 18 CFR 157.10. 4 Persons PO 00000 Frm 00044 Fmt 4703 Sfmt 4703 15013 FERC website at https://www.ferc.gov/ resources/guides/how-to/intervene.asp. All timely, unopposed motions to intervene are automatically granted by operation of Rule 214(c)(1). Motions to intervene that are filed after the intervention deadline are untimely and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission’s Rules and Regulations. A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties. Comments Any person wishing to comment on the project may do so. The Commission considers all comments received about the project in determining the appropriate action to be taken. To ensure that your comments are timely and properly recorded, please submit your comments on or before May 05, 2023. The filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding. How To File Protests, Interventions, and Comments There are two ways to submit protests, motions to intervene, and comments. In both instances, please reference the Project docket number CP23–76–000 in your submission: (1) You may file your protest, motion to intervene, and comments by using the Commission’s eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select General’’ and then select ‘‘Protest’’, ‘‘Intervention’’, or ‘‘Comment on a Filing’’; or 8 (2) You can file a paper copy of your submission by mailing it to the address below. Your submission must reference the Project docket number CP23–76– 000. To mail via USPS, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory 8 Additionally, you may file your comments electronically by using the eComment feature, which is located on the Commission’s website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project. E:\FR\FM\10MRN1.SGM 10MRN1 15014 Federal Register / Vol. 88, No. 47 / Friday, March 10, 2023 / Notices Commission, 888 First Street NE, Washington, DC 20426 To mail via any other courier, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852 The Commission encourages electronic filing of submissions (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. Protests and motions to intervene must be served on the applicant either by mail or email (with a link to the document) at: David A. Alonzo, Manager, Project Authorizations, ANR Pipeline Company, 700 Louisiana Street, Suite 1300, Houston, TX 77002– 2700 or david_alonzo@tcenergy.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. Tracking the Proceeding Throughout the proceeding, additional information about the project will be available from the Commission’s Office of External Affairs, at (866) 208– FERC, or on the FERC website at www.ferc.gov using the ‘‘eLibrary’’ link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/docs-filing/ esubscription.asp. Dated: March 6, 2023. Kimberly D. Bose, Secretary. lotter on DSK11XQN23PROD with NOTICES1 [FR Doc. 2023–04994 Filed 3–9–23; 8:45 am] BILLING CODE 6717–01–P VerDate Sep<11>2014 17:45 Mar 09, 2023 Jkt 259001 ENVIRONMENTAL PROTECTION AGENCY [EPA–HQ–OPP–2023–0147; FRL–10772–01– OCSPP] Metamitron; Receipt of Application for Emergency Exemption, Solicitation of Public Comment Environmental Protection Agency (EPA). ACTION: Notice. AGENCY: EPA has received specific exemption requests from the Colorado and Nebraska Departments of Agriculture to use the pesticide metamitron (CAS No. 41394–05–2) to treat up to 35,000 acres of sugarbeets to control the weed, Palmer amaranth. The applicants propose the use of a new chemical which has not been registered by EPA. EPA is soliciting public comment before making the decision whether or not to grant the exemptions. DATES: Comments must be received on or before March 27, 2023. ADDRESSES: Submit your comments, identified by docket identification (ID) number EPA–HQ–OPP–2023–0147, through the Federal eRulemaking Portal at https://www.regulations.gov. Follow the online instructions for submitting comments. Do not submit electronically any information you consider to be Confidential Business Information (CBI) or other information whose disclosure is restricted by statute. Additional instructions on commenting and visiting the docket, along with more information about dockets generally, is available at https://www.epa.gov/dockets. FOR FURTHER INFORMATION CONTACT: Daniel Rosenblatt, Acting Director, Registration Division (7505T), Office of Pesticide Programs, Environmental Protection Agency, 1200 Pennsylvania Ave. NW, Washington, DC 20460–0001; main telephone number: (202) 506– 2875; email address: RDFRNotices@ epa.gov. SUMMARY: SUPPLEMENTARY INFORMATION: I. General Information A. Does this action apply to me? You may be potentially affected by this action if you are an agricultural producer, food manufacturer, or pesticide manufacturer. The following list of North American Industrial Classification System (NAICS) codes is not intended to be exhaustive, but rather provides a guide to help readers determine whether this document applies to them. Potentially affected entities may include: • Crop production (NAICS code 111). PO 00000 Frm 00045 Fmt 4703 Sfmt 4703 • Animal production (NAICS code 112). • Food manufacturing (NAICS code 311). • Pesticide manufacturing (NAICS code 32532). B. What should I consider as I prepare my comments for EPA? 1. Submitting CBI. Do not submit this information to EPA through https:// www.regulations.gov or email. Clearly mark the part or all of the information that you claim to be CBI. For CBI information in a disk or CD–ROM that you mail to EPA, mark the outside of the disk or CD–ROM as CBI and then identify electronically within the disk or CD–ROM the specific information that is claimed as CBI. In addition to one complete version of the comment that includes information claimed as CBI, a copy of the comment that does not contain the information claimed as CBI must be submitted for inclusion in the public docket. Information so marked will not be disclosed except in accordance with procedures set forth in 40 CFR part 2. 2. Tips for preparing your comments. When preparing and submitting your comments, see the commenting tips at https://www.epa.gov/dockets/ commenting-epa-dockets. 3. Environmental justice. EPA seeks to achieve environmental justice, the fair treatment and meaningful involvement of any group, including minority and/or low-income populations, in the development, implementation, and enforcement of environmental laws, regulations, and policies. To help address potential environmental justice issues, the Agency seeks information on any groups or segments of the population who, as a result of their location, cultural practices, or other factors, may have atypical or disproportionately high and adverse human health impacts or environmental effects from exposure to the pesticide discussed in this document, compared to the general population. II. What action is the Agency taking? Under section 18 of the Federal Insecticide, Fungicide, and Rodenticide Act (FIFRA) (7 U.S.C. 136p), at the discretion of the EPA Administrator, a Federal or State agency may be exempted from any provision of FIFRA if the EPA Administrator determines that emergency conditions exist which require the exemption. The Colorado and Nebraska Departments of Agriculture have requested the EPA Administrator to issue specific exemptions for the use of metamitron on sugarbeets to control Palmer amaranth. E:\FR\FM\10MRN1.SGM 10MRN1

Agencies

[Federal Register Volume 88, Number 47 (Friday, March 10, 2023)]
[Notices]
[Pages 15012-15014]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-04994]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP23-76-000]


ANR Pipeline Company; Notice of Request Under Blanket 
Authorization and Establishing Intervention and Protest Deadline

    Take notice that on February 22, 2023, ANR Pipeline Company (ANR), 
700 Louisiana Street, Suite 1300, Houston, Texas 77002-2700, filed in 
the above-referenced docket, a prior notice request pursuant to 
sections 157.205 and 157.216(b) of the Federal Energy Regulatory 
Commission's (Commission) regulations under the Natural Gas Act (NGA), 
and ANR's blanket certificate issued in Docket No. CP82-480-000,\1\ for 
authorization to abandon one injection/withdrawal well and appurtenant 
facilities located at the Goodwell Storage Field in Newaygo County, 
Michigan, all as more fully set forth in the application which is on 
file with the Commission and open for public inspection.
---------------------------------------------------------------------------

    \1\ See Michigan Wisconsin Pipe Line Company, 20 FERC  
62,595 (1982).

---------------------------------------------------------------------------

[[Page 15013]]

    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (https://www.ferc.gov) using 
the ``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. At this time, 
the Commission has suspended access to the Commission's Public 
Reference Room, due to the proclamation declaring a National Emergency 
concerning the Novel Coronavirus Disease (COVID-19), issued by the 
President on March 13, 2020. For assistance, contact FERC at 
[email protected] or call toll-free, (886) 208-3676 or TTY, 
(202) 502-8659.
    Any questions concerning this application should be directed to 
David A. Alonzo, Manager, Project Authorizations, ANR Pipeline Company, 
700 Louisiana Street, Suite 1300, Houston, Texas 77002-2700, at (832) 
320-5477 or [email protected].
    Pursuant to Section 157.9 of the Commission's Rules of Practice and 
Procedure,\2\ within 90 days of this Notice the Commission staff will 
either: complete its environmental review and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or environmental 
assessment (EA) for this proposal. The filing of an EA in the 
Commission's public record for this proceeding or the issuance of a 
Notice of Schedule for Environmental Review will serve to notify 
federal and state agencies of the timing for the completion of all 
necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's FEIS or EA.
---------------------------------------------------------------------------

    \2\ 18 CFR (Code of Federal Regulations) Sec.  157.9.
---------------------------------------------------------------------------

Public Participation

    There are three ways to become involved in the Commission's review 
of this project: you can file a protest to the project, you can file a 
motion to intervene in the proceeding, and you can file comments on the 
project. There is no fee or cost for filing protests, motions to 
intervene, or comments. The deadline for filing protests, motions to 
intervene, and comments is 5:00 p.m. Eastern Time on May 05, 2023. How 
to file protests, motions to intervene, and comments is explained 
below.

Protests

    Pursuant to section 157.205 of the Commission's regulations under 
the NGA,\3\ any person \4\ or the Commission's staff may file a protest 
to the request. If no protest is filed within the time allowed or if a 
protest is filed and then withdrawn within 30 days after the allowed 
time for filing a protest, the proposed activity shall be deemed to be 
authorized effective the day after the time allowed for protest. If a 
protest is filed and not withdrawn within 30 days after the time 
allowed for filing a protest, the instant request for authorization 
will be considered by the Commission.
---------------------------------------------------------------------------

    \3\ 18 CFR 157.205.
    \4\ Persons include individuals, organizations, businesses, 
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------

    Protests must comply with the requirements specified in section 
157.205(e) of the Commission's regulations,\5\ and must be submitted by 
the protest deadline, which is May 05, 2023. A protest may also serve 
as a motion to intervene so long as the protestor states it also seeks 
to be an intervenor.
---------------------------------------------------------------------------

    \4\ 18 cfr 157.205(e).
---------------------------------------------------------------------------

Interventions

    Any person has the option to file a motion to intervene in this 
proceeding. Only intervenors have the right to request rehearing of 
Commission orders issued in this proceeding and to subsequently 
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
    To intervene, you must submit a motion to intervene to the 
Commission in accordance with Rule 214 of the Commission's Rules of 
Practice and Procedure \6\ and the regulations under the NGA \7\ by the 
intervention deadline for the project, which is May 05, 2023. As 
described further in Rule 214, your motion to intervene must state, to 
the extent known, your position regarding the proceeding, as well as 
your interest in the proceeding. For an individual, this could include 
your status as a landowner, ratepayer, resident of an impacted 
community, or recreationist. You do not need to have property directly 
impacted by the project in order to intervene. For more information 
about motions to intervene, refer to the FERC website at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------

    \6\ 18 CFR 385.214.
    \7\ 18 CFR 157.10.
---------------------------------------------------------------------------

    All timely, unopposed motions to intervene are automatically 
granted by operation of Rule 214(c)(1). Motions to intervene that are 
filed after the intervention deadline are untimely and may be denied. 
Any late-filed motion to intervene must show good cause for being late 
and must explain why the time limitation should be waived and provide 
justification by reference to factors set forth in Rule 214(d) of the 
Commission's Rules and Regulations. A person obtaining party status 
will be placed on the service list maintained by the Secretary of the 
Commission and will receive copies (paper or electronic) of all 
documents filed by the applicant and by all other parties.

Comments

    Any person wishing to comment on the project may do so. The 
Commission considers all comments received about the project in 
determining the appropriate action to be taken. To ensure that your 
comments are timely and properly recorded, please submit your comments 
on or before May 05, 2023. The filing of a comment alone will not serve 
to make the filer a party to the proceeding. To become a party, you 
must intervene in the proceeding.

How To File Protests, Interventions, and Comments

    There are two ways to submit protests, motions to intervene, and 
comments. In both instances, please reference the Project docket number 
CP23-76-000 in your submission:
    (1) You may file your protest, motion to intervene, and comments by 
using the Commission's eFiling feature, which is located on the 
Commission's website (www.ferc.gov) under the link to Documents and 
Filings. New eFiling users must first create an account by clicking on 
``eRegister.'' You will be asked to select the type of filing you are 
making; first select General'' and then select ``Protest'', 
``Intervention'', or ``Comment on a Filing''; or \8\
---------------------------------------------------------------------------

    \8\ Additionally, you may file your comments electronically by 
using the eComment feature, which is located on the Commission's 
website at www.ferc.gov under the link to Documents and Filings. 
Using eComment is an easy method for interested persons to submit 
brief, text-only comments on a project.
---------------------------------------------------------------------------

    (2) You can file a paper copy of your submission by mailing it to 
the address below. Your submission must reference the Project docket 
number CP23-76-000.

To mail via USPS, use the following address: Kimberly D. Bose, 
Secretary, Federal Energy Regulatory

[[Page 15014]]

Commission, 888 First Street NE, Washington, DC 20426
To mail via any other courier, use the following address: Kimberly D. 
Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins 
Avenue, Rockville, Maryland 20852

    The Commission encourages electronic filing of submissions (option 
1 above) and has eFiling staff available to assist you at (202) 502-
8258 or [email protected]
    Protests and motions to intervene must be served on the applicant 
either by mail or email (with a link to the document) at: David A. 
Alonzo, Manager, Project Authorizations, ANR Pipeline Company, 700 
Louisiana Street, Suite 1300, Houston, TX 77002-2700 or 
[email protected]. Any subsequent submissions by an intervenor 
must be served on the applicant and all other parties to the 
proceeding. Contact information for parties can be downloaded from the 
service list at the eService link on FERC Online.

Tracking the Proceeding

    Throughout the proceeding, additional information about the project 
will be available from the Commission's Office of External Affairs, at 
(866) 208-FERC, or on the FERC website at www.ferc.gov using the 
``eLibrary'' link as described above. The eLibrary link also provides 
access to the texts of all formal documents issued by the Commission, 
such as orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. For more information and to register, go to 
www.ferc.gov/docs-filing/esubscription.asp.

    Dated: March 6, 2023.
Kimberly D. Bose,
Secretary.