St. Anthony Hydro, LLC; Notice of Intent To File License Application, Filing of Pre-Application Document, and Approving Use of the Traditional Licensing Process, 14155-14156 [2023-04559]

Download as PDF Federal Register / Vol. 88, No. 44 / Tuesday, March 7, 2023 / Notices the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https://www.ferc.gov/ how-guides. All timely, unopposed motions to intervene are automatically granted by operation of Rule 214(c)(1). Motions to intervene that are filed after the intervention deadline are untimely and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission’s Rules and Regulations. A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties. Comments Any person wishing to comment on the project may do so. The Commission considers all comments received about the project in determining the appropriate action to be taken. To ensure that your comments are timely and properly recorded, please submit your comments on or before April 29, 2023. The filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding. ddrumheller on DSK120RN23PROD with NOTICES1 How To File Protests, Interventions, and Comments There are two ways to submit protests, motions to intervene, and comments. In both instances, please reference the Project docket number CP23–75–000 in your submission. (1) You may file your protest, motion to intervene, and comments by using the Commission’s eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select General’’ and then select ‘‘Protest’’, ‘‘Intervention’’, or ‘‘Comment on a Filing’’; or 7 7 Additionally, you may file your comments electronically by using the eComment feature, which is located on the Commission’s website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for VerDate Sep<11>2014 19:49 Mar 06, 2023 Jkt 259001 (2) You can file a paper copy of your submission by mailing it to the address below. Your submission must reference the Project docket number CP23–75– 000. To mail via USPS, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426 To send via any other courier, use the following address:, Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852 The Commission encourages electronic filing of submissions (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FERCOnlineSupport@ferc.gov. Protests and motions to intervene must be served to the applicant by mail to: David Alonzo, Manager, Project Authorizations, 7000 Louisiana Street, Suite 1300, Houston, Texas 77002–2700 or by email (with a link to the document) at david.alonzo@ tcenergy.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. Tracking the Proceeding Throughout the proceeding, additional information about the project will be available from the Commission’s Office of External Affairs, at (866) 208– FERC, or on the FERC website at www.ferc.gov using the ‘‘eLibrary’’ link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to https://www.ferc.gov/ferconline/overview. Dated: February 28, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–04557 Filed 3–6–23; 8:45 am] BILLING CODE 6717–01–P interested persons to submit brief, text-only comments on a project. PO 00000 Frm 00042 Fmt 4703 Sfmt 4703 14155 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 14552–003] St. Anthony Hydro, LLC; Notice of Intent To File License Application, Filing of Pre-Application Document, and Approving Use of the Traditional Licensing Process a. Type of Filing: Notice of Intent to File License Application and Request to Use the Traditional Licensing Process. b. Project No.: 14552–003. c. Date Filed: January 3, 2023. d. Submitted by: St. Anthony Hydro, LLC. e. Name of Project: St. Anthony Hydroelectric Project. f. Location: On the Henry’s Fork of the Snake River, in Fremont County, Idaho. No federal lands are occupied by the project works or located within the project boundary. g. Filed Pursuant to: 18 CFR 5.3 of the Commission’s regulations. h. Potential Applicant Contact: Peter Josten, GeoSense, LLC, 2742 Saint Charles Ave., Idaho Falls, ID 83404; (208) 339–3542; email—peter.gsense@ gmail.com. i. FERC Contact: John Matkowski at (202) 502–8576; or email at john.matkowski@ferc.gov. j. St. Anthony Hydro, LLC (St. Anthony Hydro) filed its request to use the Traditional Licensing Process on January 3, 2023. St. Anthony Hydro provided public notice of its request on January 6, 2023. In a letter dated February 27, 2023, the Director of the Division of Hydropower Licensing approved St. Anthony Hydro’s request to use the Traditional Licensing Process. k. With this notice, we are initiating informal consultation with the U.S. Fish and Wildlife Service and NOAA Fisheries under section 7 of the Endangered Species Act and the joint agency regulations thereunder at 50 CFR part 402; and NOAA Fisheries under section 305(b) of the Magnuson-Stevens Fishery Conservation and Management Act and implementing regulations at 50 CFR 600.920. We are also initiating consultation with the Idaho State Historic Preservation Officer, as required by section 106, National Historic Preservation Act, and the implementing regulations of the Advisory Council on Historic Preservation at 36 CFR 800.2. l. St. Anthony Hydro filed a PreApplication Document (PAD; including a proposed process plan and schedule) with the Commission, pursuant to 18 E:\FR\FM\07MRN1.SGM 07MRN1 14156 Federal Register / Vol. 88, No. 44 / Tuesday, March 7, 2023 / Notices CFR 5.6 of the Commission’s regulations. m. A copy of the PAD may be viewed on the Commission’s website (https:// www.ferc.gov), using the ‘‘eLibrary’’ link. Enter the docket number, excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). n. The licensee states its unequivocal intent to submit an application for a subsequent license for Project No. P– 14552. Pursuant to 18 CFR 16.20 each application for a subsequent license and any competing license applications must be filed with the Commission at least 24 months prior to the expiration of the existing license. All applications for license for this project must be filed by December 31, 2025. o. Register online at https:// ferconline.ferc.gov/FERCOnline.aspx to be notified via email of new filing and issuances related to this or other pending projects. For assistance, contact FERC Online Support. Dated: February 28, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–04559 Filed 3–6–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings Take notice that the Commission has received the following Natural Gas & Oil Pipeline Rate and Refund Report filings: ddrumheller on DSK120RN23PROD with NOTICES1 Filings Instituting Proceedings Docket Numbers: PR23–35–000. Applicants: Enable Oklahoma Intrastate Transmission, LLC. Description: § 284.123(g) Rate Filing: Enable Revised Fuel Percentages April 1, 2023–March 31, 2024 to be effective 4/1/2023. Filed Date: 2/28/23. Accession Number: 20230228–5226. Comment Date: 5 p.m. ET 3/21/23. 284.123(g) Protest: 5 p.m. ET 5/1/23. Docket Numbers: PR23–36–000. Applicants: Enable Oklahoma Intrastate Transmission, LLC. Description: § 284.123(g) Rate Filing: Enable Revised Fuel Percentages April 1, 2023-March 31, 2024 to be effective 4/1/2023. Filed Date: 3/1/23. Accession Number: 20230301–5002. VerDate Sep<11>2014 19:49 Mar 06, 2023 Jkt 259001 Comment Date: 5 p.m. ET 3/22/23. 284.123(g) Protest: 5 p.m. ET 5/1/23. Docket Numbers: PR23–37–000. Applicants: Valley Crossing Pipeline, LLC. Description: § 284.123 Rate Filing: VCP Address Change Filing to be effective 3/1/2023. Filed Date: 3/1/23. Accession Number: 20230301–5049. Comment Date: 5 p.m. ET 3/22/23. Docket Numbers: RP23–494–000. Applicants: El Paso Natural Gas Company, L.L.C. Description: § 4(d) Rate Filing: NonConforming Agreements Update (SRP 2023) to be effective 4/1/2023. Filed Date: 2/28/23. Accession Number: 20230228–5214. Comment Date: 5 p.m. ET 3/13/23. Docket Numbers: RP23–495–000. Applicants: LA Storage, LLC. Description: § 4(d) Rate Filing: LA Storage 2023 Annual Adjustment of Fuel Retainage Percenta to be effective 4/1/2023. Filed Date: 2/28/23. Accession Number: 20230228–5219. Comment Date: 5 p.m. ET 3/13/23. Docket Numbers: RP23–496–000. Applicants: High Island Offshore System, L.L.C. Description: 2022 Annual Fuel Tracker filing of High Island Offshore System, LLC under RP23–496. Filed Date: 2/28/23. Accession Number: 20230228–5233. Comment Date: 5 p.m. ET 3/13/23. Docket Numbers: RP23–497–000. Applicants: Midcontinent Express Pipeline LLC. Description: § 4(d) Rate Filing: MEP Cashout Filing Feb 2023 to be effective 4/1/2023. Filed Date: 2/28/23. Accession Number: 20230228–5234. Comment Date: 5 p.m. ET 3/13/23. Docket Numbers: RP23–498–000. Applicants: Columbia Gulf Transmission, LLC. Description: § 4(d) Rate Filing: TRA 2023 to be effective 4/1/2023. Filed Date: 2/28/23. Accession Number: 20230228–5264. Comment Date: 5 p.m. ET 3/13/23. Docket Numbers: RP23–499–000. Applicants: Golden Pass Pipeline LLC. Description: § 4(d) Rate Filing: GPPL Retainage Report for 2023 to be effective 4/1/2023. Filed Date: 2/28/23. Accession Number: 20230228–5276. Comment Date: 5 p.m. ET 3/13/23. Docket Numbers: RP23–500–000. Applicants: Tennessee Gas Pipeline Company, L.L.C. PO 00000 Frm 00043 Fmt 4703 Sfmt 4703 Description: § 4(d) Rate Filing: Volume No. 2—Citadel Energy Marketing, LLC SP378772 to be effective 3/1/2023. Filed Date: 2/28/23. Accession Number: 20230228–5279. Comment Date: 5 p.m. ET 3/13/23. Docket Numbers: RP23–501–000. Applicants: Columbia Gas Transmission, LLC. Description: § 4(d) Rate Filing: EPCA 2023 to be effective 4/1/2023. Filed Date: 2/28/23. Accession Number: 20230228–5302. Comment Date: 5 p.m. ET 3/13/23. Docket Numbers: RP23–502–000. Applicants: Columbia Gas Transmission, LLC. Description: § 4(d) Rate Filing: TCRA 2023 to be effective 4/1/2023. Filed Date: 2/28/23. Accession Number: 20230228–5303. Comment Date: 5 p.m. ET 3/13/23. Docket Numbers: RP23–503–000. Applicants: Columbia Gas Transmission, LLC. Description: § 4(d) Rate Filing: RAM 2023 to be effective 4/1/2023. Filed Date: 2/28/23. Accession Number: 20230228–5308. Comment Date: 5 p.m. ET 3/13/23. Docket Numbers: RP23–504–000. Applicants: TransCameron Pipeline, LLC. Description: Annual Report of Operational Purchases and Sales of TransCameron Pipeline, LLC. Filed Date: 2/28/23. Accession Number: 20230228–5349. Comment Date: 5 p.m. ET 3/13/23. Docket Numbers: RP23–505–000. Applicants: WBI Energy Transmission, Inc. Description: § 4(d) Rate Filing: 2023 Negotiated and Non-Conforming SA ONEOK FT–1833 to be effective 4/1/ 2023. Filed Date: 3/1/23. Accession Number: 20230301–5006. Comment Date: 5 p.m. ET 3/13/23. Docket Numbers: RP23–506–000. Applicants: WBI Energy Transmission, Inc. Description: § 4(d) Rate Filing: 2023 Annual Fuel & Electric Power Reimbursement Adjustment to be effective 4/1/2023. Filed Date: 3/1/23. Accession Number: 20230301–5008. Comment Date: 5 p.m. ET 3/13/23. Docket Numbers: RP23–507–000. Applicants: WBI Energy Transmission, Inc. Description: § 4(d) Rate Filing: 2023 Fuel and Electric Power Reimbursement Adjustment Provision to be effective 4/ 1/2023. E:\FR\FM\07MRN1.SGM 07MRN1

Agencies

[Federal Register Volume 88, Number 44 (Tuesday, March 7, 2023)]
[Notices]
[Pages 14155-14156]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-04559]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14552-003]


St. Anthony Hydro, LLC; Notice of Intent To File License 
Application, Filing of Pre-Application Document, and Approving Use of 
the Traditional Licensing Process

    a. Type of Filing: Notice of Intent to File License Application and 
Request to Use the Traditional Licensing Process.
    b. Project No.: 14552-003.
    c. Date Filed: January 3, 2023.
    d. Submitted by: St. Anthony Hydro, LLC.
    e. Name of Project: St. Anthony Hydroelectric Project.
    f. Location: On the Henry's Fork of the Snake River, in Fremont 
County, Idaho. No federal lands are occupied by the project works or 
located within the project boundary.
    g. Filed Pursuant to: 18 CFR 5.3 of the Commission's regulations.
    h. Potential Applicant Contact: Peter Josten, GeoSense, LLC, 2742 
Saint Charles Ave., Idaho Falls, ID 83404; (208) 339-3542; email_
[email protected]
    i. FERC Contact: John Matkowski at (202) 502-8576; or email at 
[email protected].
    j. St. Anthony Hydro, LLC (St. Anthony Hydro) filed its request to 
use the Traditional Licensing Process on January 3, 2023. St. Anthony 
Hydro provided public notice of its request on January 6, 2023. In a 
letter dated February 27, 2023, the Director of the Division of 
Hydropower Licensing approved St. Anthony Hydro's request to use the 
Traditional Licensing Process.
    k. With this notice, we are initiating informal consultation with 
the U.S. Fish and Wildlife Service and NOAA Fisheries under section 7 
of the Endangered Species Act and the joint agency regulations 
thereunder at 50 CFR part 402; and NOAA Fisheries under section 305(b) 
of the Magnuson-Stevens Fishery Conservation and Management Act and 
implementing regulations at 50 CFR 600.920. We are also initiating 
consultation with the Idaho State Historic Preservation Officer, as 
required by section 106, National Historic Preservation Act, and the 
implementing regulations of the Advisory Council on Historic 
Preservation at 36 CFR 800.2.
    l. St. Anthony Hydro filed a Pre-Application Document (PAD; 
including a proposed process plan and schedule) with the Commission, 
pursuant to 18

[[Page 14156]]

CFR 5.6 of the Commission's regulations.
    m. A copy of the PAD may be viewed on the Commission's website 
(https://www.ferc.gov), using the ``eLibrary'' link. Enter the docket 
number, excluding the last three digits in the docket number field to 
access the document. For assistance, contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY).
    n. The licensee states its unequivocal intent to submit an 
application for a subsequent license for Project No. P-14552. Pursuant 
to 18 CFR 16.20 each application for a subsequent license and any 
competing license applications must be filed with the Commission at 
least 24 months prior to the expiration of the existing license. All 
applications for license for this project must be filed by December 31, 
2025.
    o. Register online at https://ferconline.ferc.gov/FERCOnline.aspx 
to be notified via email of new filing and issuances related to this or 
other pending projects. For assistance, contact FERC Online Support.

    Dated: February 28, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-04559 Filed 3-6-23; 8:45 am]
BILLING CODE 6717-01-P