Northern States Power Company-Minnesota; Xcel Energy; Monticello Nuclear Generating Plant, Unit 1, 13474-13476 [2023-04443]

Download as PDF 13474 Federal Register / Vol. 88, No. 42 / Friday, March 3, 2023 / Notices This information will be used by the NASA ASO and Human Resources (HR) personnel, during the candidate selection process (approx. 2-year duration), to gain insight into the candidates’ work ethic and professionalism as demonstrated in previous related employment activities. Respondents may include the astronaut candidate’s previous employer(s)/directreporting manager, as well as coworkers and other references provided by the candidate. II. Methods of Collection III. Data Title: NASA Astronaut Candidate Selection (ASCAN) Qualifications Inquiry. OMB Number: 2700–0156. Type of Review: Renewal of Existing Information Collection. Affected Public: Individuals. Estimated Annual Number of Activities: 2,000. Estimated Number of Respondents per Activity: 1. Annual Responses: 2,000. Estimated Time per Response: 20 minutes. Estimated Total Annual Burden Hours: 669. Estimated Total Annual Cost: $50,905.00. ddrumheller on DSK120RN23PROD with NOTICES1 IV. Request for Comments Comments are invited on: (1) Whether the proposed collection of information is necessary for the proper performance of the functions of NASA, including whether the information collected has practical utility; (2) the accuracy of NASA’s estimate of the burden (including hours and cost) of the proposed collection of information; (3) ways to enhance the quality, utility, and clarity of the information to be collected; and (4) ways to minimize the burden of the collection of information on respondents, including automated collection techniques or the use of other forms of information technology. Comments submitted in response to this notice will be summarized and included in the request for OMB approval of this information collection. They will also become a matter of public record. [FR Doc. 2023–04399 Filed 3–2–23; 8:45 am] BILLING CODE 7510–13–P VerDate Sep<11>2014 19:33 Mar 02, 2023 Jkt 259001 [Docket No. 50–263; NRC–2023–0031] Northern States Power Company— Minnesota; Xcel Energy; Monticello Nuclear Generating Plant, Unit 1 Nuclear Regulatory Commission. ACTION: Subsequent license renewal application; opportunity to request a hearing and to petition for leave to intervene. AGENCY: The U.S. Nuclear Regulatory Commission (NRC) is considering an application for the subsequent license renewal of Renewed Facility Operating License No. DPR–22, which authorizes Northern States Power Company, a Minnesota corporation (NSPM or the applicant), doing business as Xcel Energy, to operate Monticello Nuclear Generating Plant (MNGP), Unit 1. The subsequent renewed license would authorize the applicant to operate MNGP for an additional 20 years beyond the period specified in the current license. The current operating license for MNGP expires September 8, 2030. DATES: A request for a hearing or petition for leave to intervene must be filed by May 2, 2023. ADDRESSES: Please refer to Docket ID NRC–2021–0031 when contacting the NRC about the availability of information regarding this document. You may obtain publicly available information related to this document using any of the following methods: • Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC–2021–0031. Address questions about Docket IDs in Regulations.gov to Stacy Schumann; telephone: 301–287–0624; email: Stacy.Schumann@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document. • NRC’s Agencywide Documents Access and Management System (ADAMS): You may obtain publicly available documents online in the ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/ adams.html. To begin the search, select ‘‘Begin Web-based ADAMS Search.’’ For problems with ADAMS, please contact the NRC’s Public Document Room (PDR) reference staff at 1–800–397–4209, 301– 415–4737, or by email to PDR.Resource@nrc.gov. The ADAMS accession number for each document referenced (if it is available in ADAMS) is provided the first time that it is mentioned in this document. SUMMARY: Electronic and optionally by paper. William Edwards-Bodmer, NASA PRA Clearance Officer. NUCLEAR REGULATORY COMMISSION PO 00000 Frm 00053 Fmt 4703 Sfmt 4703 • Public Library: A copy of the subsequent license renewal application for MNGP can be accessed at the following public library: Monticello Great River Regional Library, 200 West 6th St., Monticello, MN 55362. • NRC’s PDR: You may examine and purchase copies of public documents, by appointment, at the NRC’s PDR, Room P1 B35, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852. To make an appointment to visit the PDR, please send an email to PDR.Resource@nrc.gov or call 1–800–397–4209 or 301–415– 4737, between 8 a.m. and 4 p.m. eastern time (ET), Monday through Friday, except Federal holidays. FOR FURTHER INFORMATION CONTACT: Jessica Hammock, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001; telephone: 301–415– 0740; email: Jessica.Hammock@nrc.gov. SUPPLEMENTARY INFORMATION: I. Introduction The NRC received a subsequent license renewal application (SLRA) from NSPM, dated January 9, 2023 (ADAMS Accession No. ML23009A354), filed pursuant to section 103 of the Atomic Energy Act of 1954, as amended (the Act), and part 54 of title 10 of the Code of Federal Regulations (10 CFR), to renew the operating license for MNGP at 2,004 megawatts thermal. The MNGP unit is a boiling-water reactor designed by General Electric and is located in Monticello, Minnesota. A notice of receipt of the SLRA was published in the Federal Register on January 31, 2023 (88 FR 6327). The NRC staff has determined that NSPM has submitted sufficient information in accordance with 10 CFR 54.19, 54.21, 54.22, 54.23, 51.45, and 51.53(c), to enable the staff to undertake a review of the application, and that the application is, therefore, acceptable for docketing. The current docket no. 50– 263 for Renewed Facility Operating License No. DPR–22, will be retained. The determination to accept the SLRA for docketing does not constitute a determination that a subsequent renewed license should be issued and does not preclude the NRC staff from requesting additional information as the review proceeds. Before issuance of the requested subsequent renewed licenses, the NRC will have made the findings required by the Act and the Commission’s rules and regulations. In accordance with 10 CFR 54.29, the NRC may issue a subsequent renewed license on the basis of its review if it finds that actions have been E:\FR\FM\03MRN1.SGM 03MRN1 Federal Register / Vol. 88, No. 42 / Friday, March 3, 2023 / Notices identified and have been or will be taken with respect to: (1) managing the effects of aging during the period of extended operation on the functionality of structures and components that have been identified as requiring aging management review; and (2) timelimited aging analyses that have been identified as requiring review, such that there is reasonable assurance that the activities authorized by the renewed license will continue to be conducted in accordance with the current licensing basis and that any changes made to the plant’s current licensing basis will comply with the Act and the Commission’s regulations. Additionally, in accordance with 10 CFR 51.95(c), the NRC staff will prepare an environmental impact statement as a supplement to the Commission’s NUREG–1437, ‘‘Generic Environmental Impact Statement for License Renewal of Nuclear Power Plants,’’ dated June 2013 (ADAMS Accession No. ML13106A241). In considering the SLRA, the Commission must find that the applicable requirements of subpart A of 10 CFR part 51 have been satisfied, and that any matters raised under 10 CFR 2.335 have been addressed. Pursuant to 10 CFR 51.26, and as part of the environmental scoping process, the staff intends to hold public scoping meetings. Detailed information regarding the environmental scoping meetings will be the subject of a separate Federal Register notice. ddrumheller on DSK120RN23PROD with NOTICES1 II. Opportunity To Request a Hearing and Petition for Leave To Intervene Within 60 days after the date of publication of this notice, any person (petitioner) whose interest may be affected by this action may file a request for a hearing and petition for leave to intervene (petition) with respect to the action. Petitions shall be filed in accordance with the Commission’s ‘‘Agency Rules of Practice and Procedure’’ in 10 CFR part 2. Interested persons should consult 10 CFR 2.309. If a petition is filed, the presiding officer will rule on the petition and, if appropriate, a notice of a hearing will be issued. Petitions must be filed no later than 60 days from the date of publication of this notice in accordance with the filing instructions in the ‘‘Electronic Submissions (E-Filing)’’ section of this document. Petitions and motions for leave to file new or amended VerDate Sep<11>2014 19:33 Mar 02, 2023 Jkt 259001 contentions that are filed after the deadline will not be entertained absent a determination by the presiding officer that the filing demonstrates good cause by satisfying the three factors in 10 CFR 2.309(c)(1)(i) through (iii). A State, local governmental body, Federally recognized Indian Tribe, or designated agency thereof, may submit a petition to the Commission to participate as a party under 10 CFR 2.309(h) no later than 60 days from the date of publication of this notice. Alternatively, a State, local governmental body, Federally recognized Indian Tribe, or agency thereof may participate as a non-party under 10 CFR 2.315(c). For information about filing a petition and about participation by a person not a party under 10 CFR 2.315, see the information provided at ADAMS Accession No. ML20340A053 (https:// adamswebsearch2.nrc.gov/webSearch2/ main.jsp?Accession Number=ML20340A053) and on the NRC’s public website at https:// www.nrc.gov/about-nrc/regulatory/ adjudicatory/hearing.html#participate. III. Electronic Submissions (E-Filing) All documents filed in NRC adjudicatory proceedings including documents filed by an interested State, local governmental body, Federally recognized Indian Tribe, or designated agency thereof that requests to participate under 10 CFR 2.315(c), must be filed in accordance with 10 CFR 2.302. The E-Filing process requires participants to submit and serve all adjudicatory documents over the internet, or in some cases, to mail copies on electronic storage media, unless an exemption permitting an alternative filing method, as further discussed, is granted. Detailed guidance on electronic submissions is located in the ‘‘Guidance for Electronic Submissions to the NRC’’ (ADAMS Accession No. ML13031A056) and on the NRC’s public website at https://www.nrc.gov/site-help/esubmittals.html. To comply with the procedural requirements of E-Filing, at least 10 days prior to the filing deadline, the participant should contact the Office of the Secretary by email at Hearing.Docket@nrc.gov, or by telephone at 301–415–1677, to (1) request a digital identification (ID) certificate, which allows the participant (or its counsel or representative) to digitally sign submissions and access PO 00000 Frm 00054 Fmt 4703 Sfmt 4703 13475 the E-Filing system for any proceeding in which it is participating; and (2) advise the Secretary that the participant will be submitting a petition or other adjudicatory document (even in instances in which the participant, or its counsel or representative, already holds an NRC-issued digital ID certificate). Based upon this information, the Secretary will establish an electronic docket for the proceeding if the Secretary has not already established an electronic docket. Information about applying for a digital ID certificate is available on the NRC’s public website at https:// www.nrc.gov/site-help/e-submittals/ getting-started.html. After a digital ID certificate is obtained and a docket created, the participant must submit adjudicatory documents in Portable Document Format. Guidance on submissions is available on the NRC’s public website at https://www.nrc.gov/ site-help/electronic-sub-ref-mat.html. A filing is considered complete at the time the document is submitted through the NRC’s E-Filing system. To be timely, an electronic filing must be submitted to the E—Filing system no later than 11:59 p.m. ET on the due date. Upon receipt of a transmission, the E-Filing system time-stamps the document and sends the submitter an email confirming receipt of the document. The E-Filing system also distributes an email that provides access to the document to the NRC’s Office of the General Counsel and any others who have advised the Office of the Secretary that they wish to participate in the proceeding, so that the filer need not serve the document on those participants separately. Therefore, applicants and other participants (or their counsel or representative) must apply for and receive a digital ID certificate before adjudicatory documents are filed to obtain access to the documents via the E-Filing system. A person filing electronically using the NRC’s adjudicatory E-Filing system may seek assistance by contacting the NRC’s Electronic Filing Help Desk through the ‘‘Contact Us’’ link located on the NRC’s public website at https:// www.nrc.gov/site-help/esubmittals.html, by email to MSHD.Resource@nrc.gov, or by a tollfree call at 1–866–672–7640. The NRC Electronic Filing Help Desk is available between 9 a.m. and 6 p.m., ET, Monday through Friday, except Federal holidays. E:\FR\FM\03MRN1.SGM 03MRN1 ddrumheller on DSK120RN23PROD with NOTICES1 13476 Federal Register / Vol. 88, No. 42 / Friday, March 3, 2023 / Notices Participants who believe that they have good cause for not submitting documents electronically must file an exemption request, in accordance with 10 CFR 2.302(g), with their initial paper filing stating why there is good cause for not filing electronically and requesting authorization to continue to submit documents in paper format. Such filings must be submitted in accordance with 10 CFR 2.302(b)–(d). Participants filing adjudicatory documents in this manner are responsible for serving their documents on all other participants. Participants granted an exemption under 10 CFR 2.302(g)(2) must still meet the electronic formatting requirement in 10 CFR 2.302(g)(1), unless the participant also seeks and is granted an exemption from 10 CFR 2.302(g)(1). Documents submitted in adjudicatory proceedings will appear in the NRC’s electronic hearing docket, which is publicly available at https:// adams.nrc.gov/ehd, unless excluded pursuant to an order of the presiding officer. If you do not have an NRCissued digital ID certificate as previously described, click ‘‘cancel’’ when the link requests certificates and you will be automatically directed to the NRC’s electronic hearing dockets where you will be able to access any publicly available documents in a particular hearing docket. Participants are requested not to include personal privacy information such as social security numbers, home addresses, or personal phone numbers in their filings unless an NRC regulation or other law requires submission of such information. With respect to copyrighted works, except for limited excerpts that serve the purpose of the adjudicatory filings and would constitute a Fair Use application, participants should not include copyrighted materials in their submission. Detailed information about the license renewal process can be found under the Nuclear Reactors icon at https:// www.nrc.gov/reactors/operating/ licensing/renewal.html on the NRC’s public website. Copies of the application to renew the operating license for MNGP are available for public inspection at the NRC’s PDR, and on the NRC’s public website at https:// www.nrc.gov/reactors/operating/ licensing/renewal/applications.html. The application may be accessed in ADAMS through the NRC Library on the internet at https://www.nrc.gov/readingrm/adams.html under ADAMS Accession No. ML23009A354. As previously stated, persons who do not have access to ADAMS or who encounter problems in accessing the VerDate Sep<11>2014 19:33 Mar 02, 2023 Jkt 259001 documents located in ADAMS may contact the NRC’s PDR reference staff by telephone at 1–800–397–4209 or 301– 415–4737, or by email to PDR.Resource@nrc.gov. Dated: February 28, 2023. For the Nuclear Regulatory Commission. Lauren K. Gibson, Chief, License Renewal Project Branch, Division of New and Renewed Licenses, Office of Nuclear Reactor Regulation. [FR Doc. 2023–04443 Filed 3–2–23; 8:45 am] BILLING CODE 7590–01–P POSTAL REGULATORY COMMISSION [Docket Nos. MC2023–116 and CP2023–119] New Postal Products Postal Regulatory Commission. Notice. AGENCY: ACTION: The Commission is noticing a recent Postal Service filing for the Commission’s consideration concerning a negotiated service agreement. This notice informs the public of the filing, invites public comment, and takes other administrative steps. DATES: Comments are due: March 7, 2023. SUMMARY: Submit comments electronically via the Commission’s Filing Online system at https:// www.prc.gov. Those who cannot submit comments electronically should contact the person identified in the FOR FURTHER INFORMATION CONTACT section by telephone for advice on filing alternatives. ADDRESSES: FOR FURTHER INFORMATION CONTACT: David A. Trissell, General Counsel, at 202–789–6820. SUPPLEMENTARY INFORMATION: Table of Contents I. Introduction II. Docketed Proceeding(s) I. Introduction The Commission gives notice that the Postal Service filed request(s) for the Commission to consider matters related to negotiated service agreement(s). The request(s) may propose the addition or removal of a negotiated service agreement from the Market Dominant or the Competitive product list, or the modification of an existing product currently appearing on the Market Dominant or the Competitive product list. Section II identifies the docket number(s) associated with each Postal Service request, the title of each Postal Service request, the request’s acceptance PO 00000 Frm 00055 Fmt 4703 Sfmt 9990 date, and the authority cited by the Postal Service for each request. For each request, the Commission appoints an officer of the Commission to represent the interests of the general public in the proceeding, pursuant to 39 U.S.C. 505 (Public Representative). Section II also establishes comment deadline(s) pertaining to each request. The public portions of the Postal Service’s request(s) can be accessed via the Commission’s website (https:// www.prc.gov). Non-public portions of the Postal Service’s request(s), if any, can be accessed through compliance with the requirements of 39 CFR 3011.301.1 The Commission invites comments on whether the Postal Service’s request(s) in the captioned docket(s) are consistent with the policies of title 39. For request(s) that the Postal Service states concern Market Dominant product(s), applicable statutory and regulatory requirements include 39 U.S.C. 3622, 39 U.S.C. 3642, 39 CFR part 3030, and 39 CFR part 3040, subpart B. For request(s) that the Postal Service states concern Competitive product(s), applicable statutory and regulatory requirements include 39 U.S.C. 3632, 39 U.S.C. 3633, 39 U.S.C. 3642, 39 CFR part 3035, and 39 CFR part 3040, subpart B. Comment deadline(s) for each request appear in section II. II. Docketed Proceeding(s) 1. Docket No(s).: MC2023–116 and CP2023–119; Filing Title: USPS Request to Add Priority Mail, First-Class Package Service & Parcel Select Contract 7 to Competitive Product List and Notice of Filing Materials Under Seal; Filing Acceptance Date: February 27, 2023; Filing Authority: 39 U.S.C. 3642, 39 CFR 3040.130 through 3040.135, and 39 CFR 3035.105; Public Representative: Katalin K. Clendenin; Comments Due: March 7, 2023. This Notice will be published in the Federal Register. Erica A. Barker, Secretary. [FR Doc. 2023–04420 Filed 3–2–23; 8:45 am] BILLING CODE 7710–FW–P 1 See Docket No. RM2018–3, Order Adopting Final Rules Relating to Non-Public Information, June 27, 2018, Attachment A at 19–22 (Order No. 4679). E:\FR\FM\03MRN1.SGM 03MRN1

Agencies

[Federal Register Volume 88, Number 42 (Friday, March 3, 2023)]
[Notices]
[Pages 13474-13476]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-04443]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 50-263; NRC-2023-0031]


Northern States Power Company--Minnesota; Xcel Energy; Monticello 
Nuclear Generating Plant, Unit 1

AGENCY: Nuclear Regulatory Commission.

ACTION: Subsequent license renewal application; opportunity to request 
a hearing and to petition for leave to intervene.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is considering an 
application for the subsequent license renewal of Renewed Facility 
Operating License No. DPR-22, which authorizes Northern States Power 
Company, a Minnesota corporation (NSPM or the applicant), doing 
business as Xcel Energy, to operate Monticello Nuclear Generating Plant 
(MNGP), Unit 1. The subsequent renewed license would authorize the 
applicant to operate MNGP for an additional 20 years beyond the period 
specified in the current license. The current operating license for 
MNGP expires September 8, 2030.

DATES: A request for a hearing or petition for leave to intervene must 
be filed by May 2, 2023.

ADDRESSES: Please refer to Docket ID NRC-2021-0031 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly available information related to this document 
using any of the following methods:
     Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2021-0031. Address 
questions about Docket IDs in Regulations.gov to Stacy Schumann; 
telephone: 301-287-0624; email: [email protected]. For technical 
questions, contact the individual listed in the For Further Information 
Contact section of this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS 
Search.'' For problems with ADAMS, please contact the NRC's Public 
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or 
by email to [email protected]. The ADAMS accession number for each 
document referenced (if it is available in ADAMS) is provided the first 
time that it is mentioned in this document.
     Public Library: A copy of the subsequent license renewal 
application for MNGP can be accessed at the following public library: 
Monticello Great River Regional Library, 200 West 6th St., Monticello, 
MN 55362.
     NRC's PDR: You may examine and purchase copies of public 
documents, by appointment, at the NRC's PDR, Room P1 B35, One White 
Flint North, 11555 Rockville Pike, Rockville, Maryland 20852. To make 
an appointment to visit the PDR, please send an email to 
[email protected] or call 1-800-397-4209 or 301-415-4737, between 8 
a.m. and 4 p.m. eastern time (ET), Monday through Friday, except 
Federal holidays.

FOR FURTHER INFORMATION CONTACT: Jessica Hammock, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001; telephone: 301-415-0740; email: [email protected].

SUPPLEMENTARY INFORMATION: 

I. Introduction

    The NRC received a subsequent license renewal application (SLRA) 
from NSPM, dated January 9, 2023 (ADAMS Accession No. ML23009A354), 
filed pursuant to section 103 of the Atomic Energy Act of 1954, as 
amended (the Act), and part 54 of title 10 of the Code of Federal 
Regulations (10 CFR), to renew the operating license for MNGP at 2,004 
megawatts thermal. The MNGP unit is a boiling-water reactor designed by 
General Electric and is located in Monticello, Minnesota. A notice of 
receipt of the SLRA was published in the Federal Register on January 
31, 2023 (88 FR 6327).
    The NRC staff has determined that NSPM has submitted sufficient 
information in accordance with 10 CFR 54.19, 54.21, 54.22, 54.23, 
51.45, and 51.53(c), to enable the staff to undertake a review of the 
application, and that the application is, therefore, acceptable for 
docketing. The current docket no. 50-263 for Renewed Facility Operating 
License No. DPR-22, will be retained. The determination to accept the 
SLRA for docketing does not constitute a determination that a 
subsequent renewed license should be issued and does not preclude the 
NRC staff from requesting additional information as the review 
proceeds.
    Before issuance of the requested subsequent renewed licenses, the 
NRC will have made the findings required by the Act and the 
Commission's rules and regulations. In accordance with 10 CFR 54.29, 
the NRC may issue a subsequent renewed license on the basis of its 
review if it finds that actions have been

[[Page 13475]]

identified and have been or will be taken with respect to: (1) managing 
the effects of aging during the period of extended operation on the 
functionality of structures and components that have been identified as 
requiring aging management review; and (2) time-limited aging analyses 
that have been identified as requiring review, such that there is 
reasonable assurance that the activities authorized by the renewed 
license will continue to be conducted in accordance with the current 
licensing basis and that any changes made to the plant's current 
licensing basis will comply with the Act and the Commission's 
regulations.
    Additionally, in accordance with 10 CFR 51.95(c), the NRC staff 
will prepare an environmental impact statement as a supplement to the 
Commission's NUREG-1437, ``Generic Environmental Impact Statement for 
License Renewal of Nuclear Power Plants,'' dated June 2013 (ADAMS 
Accession No. ML13106A241). In considering the SLRA, the Commission 
must find that the applicable requirements of subpart A of 10 CFR part 
51 have been satisfied, and that any matters raised under 10 CFR 2.335 
have been addressed. Pursuant to 10 CFR 51.26, and as part of the 
environmental scoping process, the staff intends to hold public scoping 
meetings. Detailed information regarding the environmental scoping 
meetings will be the subject of a separate Federal Register notice.

II. Opportunity To Request a Hearing and Petition for Leave To 
Intervene

    Within 60 days after the date of publication of this notice, any 
person (petitioner) whose interest may be affected by this action may 
file a request for a hearing and petition for leave to intervene 
(petition) with respect to the action. Petitions shall be filed in 
accordance with the Commission's ``Agency Rules of Practice and 
Procedure'' in 10 CFR part 2. Interested persons should consult 10 CFR 
2.309. If a petition is filed, the presiding officer will rule on the 
petition and, if appropriate, a notice of a hearing will be issued.
    Petitions must be filed no later than 60 days from the date of 
publication of this notice in accordance with the filing instructions 
in the ``Electronic Submissions (E-Filing)'' section of this document. 
Petitions and motions for leave to file new or amended contentions that 
are filed after the deadline will not be entertained absent a 
determination by the presiding officer that the filing demonstrates 
good cause by satisfying the three factors in 10 CFR 2.309(c)(1)(i) 
through (iii).
    A State, local governmental body, Federally recognized Indian 
Tribe, or designated agency thereof, may submit a petition to the 
Commission to participate as a party under 10 CFR 2.309(h) no later 
than 60 days from the date of publication of this notice. 
Alternatively, a State, local governmental body, Federally recognized 
Indian Tribe, or agency thereof may participate as a non-party under 10 
CFR 2.315(c).
    For information about filing a petition and about participation by 
a person not a party under 10 CFR 2.315, see the information provided 
at ADAMS Accession No. ML20340A053 (https://adamswebsearch2.nrc.gov/webSearch2/main.jsp?AccessionNumber=ML20340A053) and on the NRC's 
public website at https://www.nrc.gov/about-nrc/regulatory/adjudicatory/hearing.html#participate.

III. Electronic Submissions (E-Filing)

    All documents filed in NRC adjudicatory proceedings including 
documents filed by an interested State, local governmental body, 
Federally recognized Indian Tribe, or designated agency thereof that 
requests to participate under 10 CFR 2.315(c), must be filed in 
accordance with 10 CFR 2.302. The E-Filing process requires 
participants to submit and serve all adjudicatory documents over the 
internet, or in some cases, to mail copies on electronic storage media, 
unless an exemption permitting an alternative filing method, as further 
discussed, is granted. Detailed guidance on electronic submissions is 
located in the ``Guidance for Electronic Submissions to the NRC'' 
(ADAMS Accession No. ML13031A056) and on the NRC's public website at 
https://www.nrc.gov/site-help/e-submittals.html.
    To comply with the procedural requirements of E-Filing, at least 10 
days prior to the filing deadline, the participant should contact the 
Office of the Secretary by email at [email protected], or by 
telephone at 301-415-1677, to (1) request a digital identification (ID) 
certificate, which allows the participant (or its counsel or 
representative) to digitally sign submissions and access the E-Filing 
system for any proceeding in which it is participating; and (2) advise 
the Secretary that the participant will be submitting a petition or 
other adjudicatory document (even in instances in which the 
participant, or its counsel or representative, already holds an NRC-
issued digital ID certificate). Based upon this information, the 
Secretary will establish an electronic docket for the proceeding if the 
Secretary has not already established an electronic docket.
    Information about applying for a digital ID certificate is 
available on the NRC's public website at https://www.nrc.gov/site-help/e-submittals/getting-started.html. After a digital ID certificate is 
obtained and a docket created, the participant must submit adjudicatory 
documents in Portable Document Format. Guidance on submissions is 
available on the NRC's public website at https://www.nrc.gov/site-help/electronic-sub-ref-mat.html. A filing is considered complete at the 
time the document is submitted through the NRC's E-Filing system. To be 
timely, an electronic filing must be submitted to the E--Filing system 
no later than 11:59 p.m. ET on the due date. Upon receipt of a 
transmission, the E-Filing system time-stamps the document and sends 
the submitter an email confirming receipt of the document. The E-Filing 
system also distributes an email that provides access to the document 
to the NRC's Office of the General Counsel and any others who have 
advised the Office of the Secretary that they wish to participate in 
the proceeding, so that the filer need not serve the document on those 
participants separately. Therefore, applicants and other participants 
(or their counsel or representative) must apply for and receive a 
digital ID certificate before adjudicatory documents are filed to 
obtain access to the documents via the E-Filing system.
    A person filing electronically using the NRC's adjudicatory E-
Filing system may seek assistance by contacting the NRC's Electronic 
Filing Help Desk through the ``Contact Us'' link located on the NRC's 
public website at https://www.nrc.gov/site-help/e-submittals.html, by 
email to [email protected], or by a toll-free call at 1-866-672-
7640. The NRC Electronic Filing Help Desk is available between 9 a.m. 
and 6 p.m., ET, Monday through Friday, except Federal holidays.

[[Page 13476]]

    Participants who believe that they have good cause for not 
submitting documents electronically must file an exemption request, in 
accordance with 10 CFR 2.302(g), with their initial paper filing 
stating why there is good cause for not filing electronically and 
requesting authorization to continue to submit documents in paper 
format. Such filings must be submitted in accordance with 10 CFR 
2.302(b)-(d). Participants filing adjudicatory documents in this manner 
are responsible for serving their documents on all other participants. 
Participants granted an exemption under 10 CFR 2.302(g)(2) must still 
meet the electronic formatting requirement in 10 CFR 2.302(g)(1), 
unless the participant also seeks and is granted an exemption from 10 
CFR 2.302(g)(1).
    Documents submitted in adjudicatory proceedings will appear in the 
NRC's electronic hearing docket, which is publicly available at https://adams.nrc.gov/ehd, unless excluded pursuant to an order of the 
presiding officer. If you do not have an NRC-issued digital ID 
certificate as previously described, click ``cancel'' when the link 
requests certificates and you will be automatically directed to the 
NRC's electronic hearing dockets where you will be able to access any 
publicly available documents in a particular hearing docket. 
Participants are requested not to include personal privacy information 
such as social security numbers, home addresses, or personal phone 
numbers in their filings unless an NRC regulation or other law requires 
submission of such information. With respect to copyrighted works, 
except for limited excerpts that serve the purpose of the adjudicatory 
filings and would constitute a Fair Use application, participants 
should not include copyrighted materials in their submission.
    Detailed information about the license renewal process can be found 
under the Nuclear Reactors icon at https://www.nrc.gov/reactors/operating/licensing/renewal.html on the NRC's public website. Copies of 
the application to renew the operating license for MNGP are available 
for public inspection at the NRC's PDR, and on the NRC's public website 
at https://www.nrc.gov/reactors/operating/licensing/renewal/applications.html. The application may be accessed in ADAMS through the 
NRC Library on the internet at https://www.nrc.gov/reading-rm/adams.html under ADAMS Accession No. ML23009A354. As previously stated, 
persons who do not have access to ADAMS or who encounter problems in 
accessing the documents located in ADAMS may contact the NRC's PDR 
reference staff by telephone at 1-800-397-4209 or 301-415-4737, or by 
email to [email protected].

    Dated: February 28, 2023.

    For the Nuclear Regulatory Commission.
Lauren K. Gibson,
Chief, License Renewal Project Branch, Division of New and Renewed 
Licenses, Office of Nuclear Reactor Regulation.
[FR Doc. 2023-04443 Filed 3-2-23; 8:45 am]
BILLING CODE 7590-01-P