Green Mountain Power Corporation; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions, 11906-11907 [2023-03838]
Download as PDF
11906
Federal Register / Vol. 88, No. 37 / Friday, February 24, 2023 / Notices
authority from the Secretary of Energy.
That document with the original
signature and date is maintained by the
Department of Energy. For
administrative purposes only, and in
compliance with requirements of the
Office of the Federal Register, the
undersigned Department of Energy
Federal Register Liaison Officer has
been authorized to sign and submit the
document in electronic format for
publication, as an official document of
the Department of Energy. This
administrative process in no way alters
the legal effect of this document upon
publication in the Federal Register.
Signed in Washington, DC, on February 21,
2023.
Treena V. Garrett,
Federal Register Liaison Officer, U.S.
Department of Energy.
[FR Doc. 2023–03870 Filed 2–23–23; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2445–028]
ddrumheller on DSK120RN23PROD with NOTICES
Green Mountain Power Corporation;
Notice of Application Accepted for
Filing, Soliciting Motions To Intervene
and Protests, Ready for Environmental
Analysis, and Soliciting Comments,
Recommendations, Terms and
Conditions, and Prescriptions
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
Minor License.
b. Project No.: 2445–028.
c. Date Filed: December 23, 2021.
d. Applicant: Green Mountain Power
Corporation.
e. Name of Project: Center Rutland
Hydroelectric Project (project).
f. Location: On Otter Creek in Rutland
County, Vermont. The project does not
occupy any federal land.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. Jason Lisai,
Green Mountain Power Corporation, 163
Acorn Lane, Colchester, VT 05446–
6611; Phone at (802) 770–2195, or email
at jason.lisai@
greenmountainpower.com.
i. FERC Contact: Taconya D. Goar at
(202) 502–8394, or Taconya.Goar@
ferc.gov.
j. Deadline for filing motions to
intervene and protests, comments,
recommendations, terms and
conditions, and prescriptions: 60 days
VerDate Sep<11>2014
18:15 Feb 23, 2023
Jkt 259001
from the issuance date of this notice;
reply comments are due 105 days from
the issuance date of this notice.
The Commission strongly encourages
electronic filing. Please file motions to
intervene and protests, comments,
recommendations, terms and
conditions, and prescriptions using the
Commission’s eFiling system at https://
ferconline.ferc.gov/FERCOnline.aspx.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://ferconline.ferc.gov/
QuickComment.aspx. You must include
your name and contact information at
the end of your comments. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, you may submit a
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852. The first page of any filing
should include docket number P–2445–
028.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person on the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. This application has been accepted
for filing and is now ready for
environmental analysis.
l. Project Description: The existing
Center Rutland Hydroelectric Project
consists of: (1) a 190-foot-long, 14-foothigh concrete and stone masonry gravity
dam that includes: (a) a 174-foot-long
spillway section with a crest elevation
of 504.8 feet National Geodetic Vertical
Datum of 1929 (NGVD 29); and (b) a 16foot-long non-overflow section; (2) an
impoundment with a surface area of 13
acres and a storage capacity of 30 acrefeet at an elevation of 507.4 feet NGVD
29; (3) a 13-foot-long, 7- to 30-foot-wide
forebay; (4) a 39.58-foot-wide, 18-foothigh concrete and marble masonry
intake structure with a 6.7-foot-wide,
6.5-foot-high steel headgate and a 30foot-wide, 12-foot-high trashrack with
9⁄16-inch clear bar spacing; (5) a 6-foot-
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
diameter, 75-foot-long steel penstock;
(6) a 40-foot-long, 33-foot-wide stone
and marble masonry powerhouse
containing one 275-kilowatt horizontalshaft turbine-generator; (7) a 480-volt/
12.47-kilovolt (kV) transformer and 80foot-long, 12.47-kV transmission line
that interconnects with the local
distribution grid; (8) a 0.35-mile-long
fiber optic cable for smart grid
communications with the electric
system; and (9) appurtenant facilities.
The project creates an approximately
100-foot-long bypassed reach of Otter
Creek.
The current license requires: (1) runof-river operation, such that outflow
from the project approximates inflow to
the impoundment; (2) a minimum
bypassed reach flow of 80 cubic feet per
second (cfs) or inflow to the
impoundment, whichever is less, from
June 1 through October 15; and (3) a
minimum flow of 90 percent of inflow
to the impoundment downstream of the
powerhouse when refilling the
impoundment following a drawdown
for maintenance or emergencies. In
addition, the current license requires
the implementation of a recreation plan
that includes provisions for installing an
off-street parking area, signage,
landscaping, a picnic area, and a
marked footpath to the river.
The applicant proposes to: (1)
continue operating the project in a runof-river mode; (2) continue releasing a
minimum bypassed reach flow of 80 cfs
or inflow, whichever is less, from June
1 through October 15; (3) release a
minimum bypassed reach flow of 40 cfs
or inflow, whichever is less, from
October 16 through May 31; (4)
implement a seasonal tree clearing
restriction from April 15 through
October 31, for trees that are 4 inches in
diameter or greater, to protect the
federally-listed northern long-eared bat;
(5) develop and implement a flow
management and monitoring plan; and
(6) develop and implement a historic
properties management plan. In
addition, the applicant states that the
recreation facilities required by the
current license were not developed and
that it is not proposing to develop the
facilities as part of relicensing, but
instead proposes to transfer land to the
Town of Rutland, Vermont, so that the
Town can develop recreation facilities
in the same location.
m. A copy of the application can be
viewed on the Commission’s website at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. At this time, the
E:\FR\FM\24FEN1.SGM
24FEN1
Federal Register / Vol. 88, No. 37 / Friday, February 24, 2023 / Notices
Commission has suspended access to
the Commission’s Public Reference
Room due to the proclamation declaring
a National Emergency concerning the
Novel Coronavirus Disease (COVID–19),
issued by the President on March 13,
2020. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll free, (886) 208–3676 or TTY (202)
502–8659.
n. Anyone may submit comments, a
protest, or a motion to intervene in
accordance with the requirements of
Rules of Practice and Procedure, 18 CFR
385.210, .211, and .214. In determining
the appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
All filings must: (1) bear in all capital
letters the title ‘‘PROTEST,’’ ‘‘MOTION
TO INTERVENE,’’ ‘‘COMMENTS,’’
‘‘REPLY COMMENTS,’’
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, recommendations, terms and
conditions, or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. A copy of all other filings
in reference to this application must be
accompanied by proof of service on all
persons listed on the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
4.34(b) and 385.2010.
You may also register online at
https://ferconline.ferc.gov/
FERCOnline.aspx to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
o. The applicant must file no later
than 60 days following the date of
issuance of this notice: (1) a copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification. Please note that the
certification request must comply with
40 CFR 121.5(b), including
documentation that a pre-filing meeting
request was submitted to the certifying
authority at least 30 days prior to
submitting the certification request.
Please also note that the certification
request must be sent to the certifying
authority and to the Commission
concurrently.
p. Procedural schedule: The
application will be processed according
to the following preliminary schedule.
Revisions to the schedule will be made
as appropriate.
Milestone
Target date
Deadline for filing interventions, protests, comments, recommendations, preliminary terms and conditions, and preliminary
fishway prescriptions.
Deadline for filing reply comments ...................................................................................................................................................
q. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of this notice.
Dated: February 17, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–03838 Filed 2–23–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
ddrumheller on DSK120RN23PROD with NOTICES
Combined Notice of Filings #1
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER20–2004–003.
Applicants: Public Service Electric
and Gas Company, PJM Interconnection,
L.L.C.
Description: Compliance filing: Public
Service Electric and Gas Company
submits tariff filing per 35: PSEG
submits Revisions to PJM Tariff, Att. H–
10 re: Order 864 to be effective 1/27/
2020.
VerDate Sep<11>2014
18:15 Feb 23, 2023
Jkt 259001
Filed Date: 2/17/23.
Accession Number: 20230217–5132.
Comment Date: 5 p.m. ET 3/10/23.
Docket Numbers: ER21–201–002.
Applicants: Atlantic City Electric
Company, PJM Interconnection, L.L.C.
Description: Compliance filing:
Atlantic City Electric Company submits
tariff filing per 35: ACE Supplemental
Compliance Filing in ER21–201 to be
effective N/A.
Filed Date: 2/17/23.
Accession Number: 20230217–5017.
Comment Date: 5 p.m. ET 3/10/23.
Docket Numbers: ER21–203–002.
Applicants: Baltimore Gas and
Electric Company, PJM Interconnection,
L.L.C.
Description: Compliance filing:
Baltimore Gas and Electric Company
submits tariff filing per 35: BGE
Supplemental Compliance Filing in
ER21–203 to be effective N/A.
Filed Date: 2/17/23.
Accession Number: 20230217–5020.
Comment Date: 5 p.m. ET 3/10/23.
Docket Numbers: ER21–204–002.
Applicants: Commonwealth Edison
Company, PJM Interconnection, L.L.C.
Description: Compliance filing:
Commonwealth Edison Company
PO 00000
Frm 00020
Fmt 4703
11907
Sfmt 4703
April 2023.
June 2023.
submits tariff filing per 35: ComEd
Supplemental Compliance Filing in
ER21–204 to be effective N/A.
Filed Date: 2/17/23.
Accession Number: 20230217–5021.
Comment Date: 5 p.m. ET 3/10/23.
Docket Numbers: ER21–205–002.
Applicants: Delmarva Power & Light
Company, PJM Interconnection, L.L.C.
Description: Compliance filing:
Delmarva Power & Light Company
submits tariff filing per 35: Delmarva
Power & Light Supplemental
Compliance Filing in ER21–205 to be
effective N/A.
Filed Date: 2/17/23.
Accession Number: 20230217–5063.
Comment Date: 5 p.m. ET 3/10/23.
Docket Numbers: ER21–206–002.
Applicants: Potomac Electric Power
Company, PJM Interconnection, L.L.C.
Description: Compliance filing:
Potomac Electric Power Company
submits tariff filing per 35: PEPCO
Supplemental Compliance Filing in
ER21–206 to be effective N/A.
Filed Date: 2/17/23.
Accession Number: 20230217–5065.
Comment Date: 5 p.m. ET 3/10/23.
Docket Numbers: ER21–209–002.
E:\FR\FM\24FEN1.SGM
24FEN1
Agencies
[Federal Register Volume 88, Number 37 (Friday, February 24, 2023)]
[Notices]
[Pages 11906-11907]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-03838]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2445-028]
Green Mountain Power Corporation; Notice of Application Accepted
for Filing, Soliciting Motions To Intervene and Protests, Ready for
Environmental Analysis, and Soliciting Comments, Recommendations, Terms
and Conditions, and Prescriptions
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Subsequent Minor License.
b. Project No.: 2445-028.
c. Date Filed: December 23, 2021.
d. Applicant: Green Mountain Power Corporation.
e. Name of Project: Center Rutland Hydroelectric Project (project).
f. Location: On Otter Creek in Rutland County, Vermont. The project
does not occupy any federal land.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Mr. Jason Lisai, Green Mountain Power
Corporation, 163 Acorn Lane, Colchester, VT 05446-6611; Phone at (802)
770-2195, or email at [email protected].
i. FERC Contact: Taconya D. Goar at (202) 502-8394, or
[email protected].
j. Deadline for filing motions to intervene and protests, comments,
recommendations, terms and conditions, and prescriptions: 60 days from
the issuance date of this notice; reply comments are due 105 days from
the issuance date of this notice.
The Commission strongly encourages electronic filing. Please file
motions to intervene and protests, comments, recommendations, terms and
conditions, and prescriptions using the Commission's eFiling system at
https://ferconline.ferc.gov/FERCOnline.aspx. Commenters can submit
brief comments up to 6,000 characters, without prior registration,
using the eComment system at https://ferconline.ferc.gov/QuickComment.aspx. You must include your name and contact information
at the end of your comments. For assistance, please contact FERC Online
Support at [email protected], (866) 208-3676 (toll free), or
(202) 502-8659 (TTY). In lieu of electronic filing, you may submit a
paper copy. Submissions sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room 1A, Washington, DC 20426.
Submissions sent via any other carrier must be addressed to: Kimberly
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins
Avenue, Rockville, Maryland 20852. The first page of any filing should
include docket number P-2445-028.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person on the official service list for the
project. Further, if an intervenor files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency.
k. This application has been accepted for filing and is now ready
for environmental analysis.
l. Project Description: The existing Center Rutland Hydroelectric
Project consists of: (1) a 190-foot-long, 14-foot-high concrete and
stone masonry gravity dam that includes: (a) a 174-foot-long spillway
section with a crest elevation of 504.8 feet National Geodetic Vertical
Datum of 1929 (NGVD 29); and (b) a 16-foot-long non-overflow section;
(2) an impoundment with a surface area of 13 acres and a storage
capacity of 30 acre-feet at an elevation of 507.4 feet NGVD 29; (3) a
13-foot-long, 7- to 30-foot-wide forebay; (4) a 39.58-foot-wide, 18-
foot-high concrete and marble masonry intake structure with a 6.7-foot-
wide, 6.5-foot-high steel headgate and a 30-foot-wide, 12-foot-high
trashrack with \9/16\-inch clear bar spacing; (5) a 6-foot-diameter,
75-foot-long steel penstock; (6) a 40-foot-long, 33-foot-wide stone and
marble masonry powerhouse containing one 275-kilowatt horizontal-shaft
turbine-generator; (7) a 480-volt/12.47-kilovolt (kV) transformer and
80-foot-long, 12.47-kV transmission line that interconnects with the
local distribution grid; (8) a 0.35-mile-long fiber optic cable for
smart grid communications with the electric system; and (9) appurtenant
facilities. The project creates an approximately 100-foot-long bypassed
reach of Otter Creek.
The current license requires: (1) run-of-river operation, such that
outflow from the project approximates inflow to the impoundment; (2) a
minimum bypassed reach flow of 80 cubic feet per second (cfs) or inflow
to the impoundment, whichever is less, from June 1 through October 15;
and (3) a minimum flow of 90 percent of inflow to the impoundment
downstream of the powerhouse when refilling the impoundment following a
drawdown for maintenance or emergencies. In addition, the current
license requires the implementation of a recreation plan that includes
provisions for installing an off-street parking area, signage,
landscaping, a picnic area, and a marked footpath to the river.
The applicant proposes to: (1) continue operating the project in a
run-of-river mode; (2) continue releasing a minimum bypassed reach flow
of 80 cfs or inflow, whichever is less, from June 1 through October 15;
(3) release a minimum bypassed reach flow of 40 cfs or inflow,
whichever is less, from October 16 through May 31; (4) implement a
seasonal tree clearing restriction from April 15 through October 31,
for trees that are 4 inches in diameter or greater, to protect the
federally-listed northern long-eared bat; (5) develop and implement a
flow management and monitoring plan; and (6) develop and implement a
historic properties management plan. In addition, the applicant states
that the recreation facilities required by the current license were not
developed and that it is not proposing to develop the facilities as
part of relicensing, but instead proposes to transfer land to the Town
of Rutland, Vermont, so that the Town can develop recreation facilities
in the same location.
m. A copy of the application can be viewed on the Commission's
website at https://www.ferc.gov using the ``eLibrary'' link. Enter the
docket number excluding the last three digits in the docket number
field to access the document. For assistance, contact FERC Online
Support. At this time, the
[[Page 11907]]
Commission has suspended access to the Commission's Public Reference
Room due to the proclamation declaring a National Emergency concerning
the Novel Coronavirus Disease (COVID-19), issued by the President on
March 13, 2020. For assistance, contact FERC at
[email protected] or call toll free, (886) 208-3676 or TTY
(202) 502-8659.
n. Anyone may submit comments, a protest, or a motion to intervene
in accordance with the requirements of Rules of Practice and Procedure,
18 CFR 385.210, .211, and .214. In determining the appropriate action
to take, the Commission will consider all protests or other comments
filed, but only those who file a motion to intervene in accordance with
the Commission's Rules may become a party to the proceeding. Any
comments, protests, or motions to intervene must be received on or
before the specified comment date for the particular application.
All filings must: (1) bear in all capital letters the title
``PROTEST,'' ``MOTION TO INTERVENE,'' ``COMMENTS,'' ``REPLY COMMENTS,''
``RECOMMENDATIONS,'' ``TERMS AND CONDITIONS,'' or ``PRESCRIPTIONS;''
(2) set forth in the heading the name of the applicant and the project
number of the application to which the filing responds; (3) furnish the
name, address, and telephone number of the person protesting or
intervening; and (4) otherwise comply with the requirements of 18 CFR
385.2001 through 385.2005. All comments, recommendations, terms and
conditions, or prescriptions must set forth their evidentiary basis and
otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may
obtain copies of the application directly from the applicant. A copy of
any protest or motion to intervene must be served upon each
representative of the applicant specified in the particular
application. A copy of all other filings in reference to this
application must be accompanied by proof of service on all persons
listed on the service list prepared by the Commission in this
proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
You may also register online at https://ferconline.ferc.gov/FERCOnline.aspx to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
o. The applicant must file no later than 60 days following the date
of issuance of this notice: (1) a copy of the water quality
certification; (2) a copy of the request for certification, including
proof of the date on which the certifying agency received the request;
or (3) evidence of waiver of water quality certification. Please note
that the certification request must comply with 40 CFR 121.5(b),
including documentation that a pre-filing meeting request was submitted
to the certifying authority at least 30 days prior to submitting the
certification request. Please also note that the certification request
must be sent to the certifying authority and to the Commission
concurrently.
p. Procedural schedule: The application will be processed according
to the following preliminary schedule. Revisions to the schedule will
be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Deadline for filing interventions, protests, April 2023.
comments, recommendations, preliminary terms
and conditions, and preliminary fishway
prescriptions.
Deadline for filing reply comments........... June 2023.
------------------------------------------------------------------------
q. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of this notice.
Dated: February 17, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-03838 Filed 2-23-23; 8:45 am]
BILLING CODE 6717-01-P