DEPARTMENT OF ENERGY
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Federal Energy Regulatory
Commission
[Project No. 8866–013]
Combined Notice of Filings #1
Black Canyon Bliss, LLC; Notice of
Intent To Prepare an Environmental
Assessment
On February 28, 2022, Black Canyon
Bliss LLC filed an application for a
subsequent license to continue
operating the existing 24-kilowatt
Stevenson No. 2 Hydroelectric Project
No. 8866 (Stevenson No. 2 Project or
project). The project is located on an
unnamed tributary to the Snake River in
Gooding County, Idaho. The project
does not occupy federal land.
In accordance with the Commission’s
regulations, on November 14, 2022,
Commission staff issued a notice that
the project was ready for environmental
analysis (REA notice). Based on the
information in the record, including
comments filed on the REA notice, staff
does not anticipate that licensing the
project would constitute a major federal
action significantly affecting the quality
of the human environment. Therefore,
staff intends to prepare an
Environmental Assessment (EA) on the
application to license the Stevenson No.
2 Project.
The EA will be issued and circulated
for review by all interested parties. All
comments filed on the EA will be
analyzed by staff and considered in the
Commission’s final licensing decision.
The application will be processed
according to the following schedule.
Revisions to the schedule may be made
as appropriate.
Milestone
Commission issues
EA.
Target date
July 2023.1
Any questions regarding this notice
may be directed to Maryam Zavareh at
(202) 502–8474 or maryam.zavareh@
ferc.gov.
Dated: February 14, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–03546 Filed 2–17–23; 8:45 am]
lotter on DSK11XQN23PROD with NOTICES1
BILLING CODE 6717–01–P
1 The Council on Environmental Quality’s (CEQ)
regulations under 40 CFR 1501.10(b)(1) require that
EAs be completed within 1 year of the federal
action agency’s decision to prepare an EA. This
notice establishes the Commission’s intent to
prepare an EA for the Stevenson No. 2 Project.
Therefore, in accordance with CEQ’s regulations,
the Final EA must be issued within 1 year of the
issuance date of this notice.
VerDate Sep<11>2014
17:54 Feb 17, 2023
Jkt 259001
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC23–56–000.
Applicants: Kentucky Power
Company, AEP Kentucky Transmission
Company, Inc., Liberty Utilities Co.
Description: Joint Application for
Authorization Under Section 203 of the
Federal Power Act of Liberty Utilities
Co.
Filed Date: 2/14/23.
Accession Number: 20230214–5108.
Comment Date: 5 p.m. ET 3/31/23.
Take notice that the Commission
received the following Complaints and
Compliance filings in EL Dockets:
Docket Numbers: EL22–89–000.
Applicants: Cage Ranch Solar, LLC
and Cage Ranch Solar II, LLC vs.
Southwest Power Pool, Inc.
Description: Motion to Answer,
Answer, and Amendment to Complaint
and Petition filed on September 20,
2022, by Cage Ranch Solar, LLC, et al.
Filed Date: 2/13/23.
Accession Number: 20230213–5176.
Comment Date: 5 p.m. ET 3/6/23.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER22–2968–001.
Applicants: Southwest Power Pool,
Inc.
Description: Tariff Amendment:
Deficiency Response—Provisions for
Self-Funding Network Upgrades to be
effective 12/1/2022.
Filed Date: 2/14/23.
Accession Number: 20230214–5098.
Comment Date: 5 p.m. ET 3/7/23.
Docket Numbers: ER23–69–001.
Applicants: Southwest Power Pool,
Inc.
Description: Tariff Amendment:
Deficiency Response—Lincoln Electric
System Revisions to Formula Rate
Protocols to be effective 4/1/2023.
Filed Date: 1/30/23.
Accession Number: 20230130–5196.
Comment Date: 5 p.m. ET 2/28/23.
Docket Numbers: ER23–1109–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original ISA, SA No. 6770; Queue No.
AE2–071 & Cancellation of IISA, SA No.
6378 to be effective 1/17/2023.
Filed Date: 2/14/23.
Accession Number: 20230214–5029.
Comment Date: 5 p.m. ET 3/7/23.
PO 00000
Frm 00013
Fmt 4703
Sfmt 9990
10507
Docket Numbers: ER23–1110–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original NSA, SA No. 6784; Queue No.
NQ–71 to be effective 1/25/2023.
Filed Date: 2/14/23.
Accession Number: 20230214–5059.
Comment Date: 5 p.m. ET 3/7/23.
Docket Numbers: ER23–1111–000.
Applicants: Southwestern Public
Service Company, Southwest Power
Pool, Inc.
Description: § 205(d) Rate Filing:
Southwestern Public Service Company
submits tariff filing per 35.13(a)(2)(iii:
SPS Formula Rate Revisions to
Incorporate Changes Accepted in ER22–
2955 to be effective 1/1/2023.
Filed Date: 2/14/23.
Accession Number: 20230214–5073.
Comment Date: 5 p.m. ET 3/7/23.
Docket Numbers: ER23–1112–000.
Applicants: PacifiCorp.
Description: § 205(d) Rate Filing:
OATT Revised LGIP Sections 38,
Attachment N to be effective 4/16/2023.
Filed Date: 2/14/23.
Accession Number: 20230214–5119.
Comment Date: 5 p.m. ET 3/7/23.
Docket Numbers: ER23–1113–000.
Applicants: Tri-State Generation and
Transmission Association, Inc.
Description: § 205(d) Rate Filing:
Revisions to Rate Schedule FERC No.
281 Modified CTP Methodology to be
effective 4/17/2023.
Filed Date: 2/14/23.
Accession Number: 20230214–5144.
Comment Date: 5 p.m. ET 3/7/23.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: February 14, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–03552 Filed 2–17–23; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\21FEN1.SGM
21FEN1
Agencies
[Federal Register Volume 88, Number 34 (Tuesday, February 21, 2023)]
[Notices]
[Page 10507]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-03546]
[[Page 10507]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 8866-013]
Black Canyon Bliss, LLC; Notice of Intent To Prepare an
Environmental Assessment
On February 28, 2022, Black Canyon Bliss LLC filed an application
for a subsequent license to continue operating the existing 24-kilowatt
Stevenson No. 2 Hydroelectric Project No. 8866 (Stevenson No. 2 Project
or project). The project is located on an unnamed tributary to the
Snake River in Gooding County, Idaho. The project does not occupy
federal land.
In accordance with the Commission's regulations, on November 14,
2022, Commission staff issued a notice that the project was ready for
environmental analysis (REA notice). Based on the information in the
record, including comments filed on the REA notice, staff does not
anticipate that licensing the project would constitute a major federal
action significantly affecting the quality of the human environment.
Therefore, staff intends to prepare an Environmental Assessment (EA) on
the application to license the Stevenson No. 2 Project.
The EA will be issued and circulated for review by all interested
parties. All comments filed on the EA will be analyzed by staff and
considered in the Commission's final licensing decision.
The application will be processed according to the following
schedule. Revisions to the schedule may be made as appropriate.
---------------------------------------------------------------------------
\1\ The Council on Environmental Quality's (CEQ) regulations
under 40 CFR 1501.10(b)(1) require that EAs be completed within 1
year of the federal action agency's decision to prepare an EA. This
notice establishes the Commission's intent to prepare an EA for the
Stevenson No. 2 Project. Therefore, in accordance with CEQ's
regulations, the Final EA must be issued within 1 year of the
issuance date of this notice.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Commission issues EA...................... July 2023.\1\
------------------------------------------------------------------------
Any questions regarding this notice may be directed to Maryam
Zavareh at (202) 502-8474 or [email protected].
Dated: February 14, 2023.
Kimberly D. Bose,
Secretary.