Northern States Power Company-Wisconsin; Notice Soliciting Scoping Comments, 8838-8839 [2023-02882]
Download as PDF
8838
Federal Register / Vol. 88, No. 28 / Friday, February 10, 2023 / Notices
maintained by DOE. For administrative
purposes only, and in compliance with
requirements of the Office of the Federal
Register, the undersigned DOE Federal
Register Liaison Officer has been
authorized to sign and submit the
document in electronic format for
publication, as an official document of
the Department of Energy. This
administrative process in no way alters
the legal effect of this document upon
publication in the Federal Register.
Signed in Washington, DC on February 7,
2023.
Treena V. Garrett,
Federal Register Liaison Officer, U.S.
Department of Energy.
[FR Doc. 2023–02854 Filed 2–9–23; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
lotter on DSK11XQN23PROD with NOTICES1
Filings Instituting Proceedings
Docket Numbers: RP23–422–000.
Applicants: Ruby Pipeline, L.L.C.
Description: § 4(d) Rate Filing: RP
2023–02–03 Administrative Changes to
be effective 3/6/2023.
Filed Date: 2/3/23.
Accession Number: 20230203–5147.
Comment Date: 5 p.m. ET 2/15/23.
Docket Numbers: RP23–423–000.
Applicants: Iroquois Gas
Transmission System, L.P.
Description: § 4(d) Rate Filing: 2.3.23
Negotiated Rates—Freepoint
Commodities LLC R–7250–45 to be
effective 2/3/2023.
Filed Date: 2/3/23.
Accession Number: 20230203–5164.
Comment Date: 5 p.m. ET 2/15/23.
Docket Numbers: RP23–424–000.
Applicants: Iroquois Gas
Transmission System, L.P.
Description: § 4(d) Rate Filing: 2.3.23
Negotiated Rates—Macquarie Energy
LLC R–4090–26 to be effective 2/3/2023.
Filed Date: 2/3/23.
Accession Number: 20230203–5167.
Comment Date: 5 p.m. ET 2/15/23.
Docket Numbers: RP23–425–000.
Applicants: Iroquois Gas
Transmission System, L.P.
Description: § 4(d) Rate Filing: 2.3.23
Negotiated Rates—Citadel Energy
Marketing LLC R–7705–14 to be
effective 2/3/2023.
Filed Date: 2/3/23.
Accession Number: 20230203–5169.
VerDate Sep<11>2014
17:41 Feb 09, 2023
Jkt 259001
Comment Date: 5 p.m. ET 2/15/23.
DEPARTMENT OF ENERGY
Docket Numbers: RP23–426–000.
Applicants: Iroquois Gas
Transmission System, L.P.
Description: § 4(d) Rate Filing: 2.3.23
Negotiated Rates—Castleton
Commodities Merchant Trading L.P. R–
4010–35 to be effective 2/3/2023.
Filed Date: 2/3/23.
Accession Number: 20230203–5170.
Comment Date: 5 p.m. ET 2/15/23.
Federal Energy Regulatory
Commission
Docket Numbers: RP23–427–000.
Applicants: Iroquois Gas
Transmission System, L.P.
Description: § 4(d) Rate Filing: 2.3.23
Negotiated Rates—Castleton
Commodities Merchant Trading L.P. R–
4010–36 to be effective 2/3/2023.
Filed Date: 2/3/23.
Accession Number: 20230203–5171.
Comment Date: 5 p.m. ET 2/15/23.
Docket Numbers: RP23–428–000.
Applicants: Iroquois Gas
Transmission System, L.P.
Description: § 4(d) Rate Filing: 2.3.23
Negotiated Rates—Uniper Global
Commodities North America LLC R–
7650–05 to be effective2/3/2023.
Filed Date: 2/3/23.
Accession Number: 20230203–5189.
Comment Date: 5 p.m. ET 2/15/23.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: February 6, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–02887 Filed 2–9–23; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00047
Fmt 4703
Sfmt 4703
[Project No. 2639–028]
Northern States Power Company—
Wisconsin; Notice Soliciting Scoping
Comments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: P–2639–028.
c. Date filed: November 30, 2021.
d. Applicant: Northern States Power
Company—Wisconsin.
e. Name of Project: Cornell
Hydroelectric Project.
f. Location: The existing project is
located on the Lower Chippewa River in
the township of Cornell, Chippewa
County, Wisconsin.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Donald R.
Hartinger, Director, Hydro Plants, 1414
W Hamilton Avenue, P.O. Box 8; Eau
Claire, WI 54701; donald.r.hartinger@
xcelenergy.com; (612) 321–3063.
i. FERC Contact: Michael Davis at
(202) 502–8339; or michael.davis@
ferc.gov.
j. Deadline for filing scoping
comments: March 8, 2023.
The Commission strongly encourages
electronic filing. Please file scoping
comments using the Commission’s
eFiling system at https://www.ferc.gov/
docs-filing/efiling.asp. Commenters can
submit brief comments up to 6,000
characters, without prior registration,
using the eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
The first page of any filing should
include docket number P–2639–028.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
E:\FR\FM\10FEN1.SGM
10FEN1
lotter on DSK11XQN23PROD with NOTICES1
Federal Register / Vol. 88, No. 28 / Friday, February 10, 2023 / Notices
also serve a copy of the document on
that resource agency.
k. This application is not ready for
environmental analysis at this time.
l. Project Description: The project
consists of the following existing
facilities: (1) a reservoir having 985
acres surface area, gross storage capacity
of 8,000 acre-feet and a net storage
capacity of 1,500 acre-feet at a
maximum normal water surface
elevation of 1,002.0 National Geodetic
Vertical Datum 1929 (NGVD); (2) an
861-foot-long earth and concrete dam
including: (a) a 42-foot-wide east
concrete non-overflow section with a
top elevation of 1,010.0 feet NGVD, (b)
a 131-foot-long, 151.5-foot-wide, 82foot-high powerhouse-intake structure
containing three horizontal shaft
turbine-generators rated at 10 megawatts
each and one vertical shaft turbinegenerator rated at 750 kilowatts, (c) an
85-foot-long gated spillway containing
two 37-foot-wide by 23.3-foot-high
Tainter gates with top of pier elevation
of 1,008.0 feet NGVD, (d) a 10-foot-long
non-overflow concrete dam section with
a top elevation of 1,004.2 feet NGVD, (e)
a 292-foot-long gated spillway
containing 12 20-foot-long by 16-foothigh steel Tainter gates with a top of
pier elevation of 1,004.2 feet NGVD, (f)
a 210-foot-long by 28-foot-high overflow
concrete section topped with 48-inchhigh flashboards with top of flashboard
elevation of 1,002.2 feet NGVD, and (g)
a 91-foot-long west earthen embankment
with a top elevation of 1,010.0 feet
NGVD; (3) four 160-foot-long, 7.2kilovolt (kV) transmission lines
connecting the powerhouse to an
adjacent project owned substation that
is the point of interconnection to a 115kV distribution line belonging to the
Northern States Power Company—
Wisconsin; and (4) appurtenant
facilities. The project average annual
generation between 2016 and 2020 was
113,839 megawatt hours.
m. In addition to publishing the full
text of this notice in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
notice, as well as other documents in
the proceeding (e.g., scoping document)
via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number, excluding the
last three digits, in the docket number
field to access the document (P–2639).
For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or TYY, (202)
502–8659.
You may also register online at https://
www.ferc.gov/docs-filing/
VerDate Sep<11>2014
17:41 Feb 09, 2023
Jkt 259001
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Scoping Process:
Commission staff will prepare either
an environmental assessment (EA) or an
environmental impact statement (EIS)
that describes and evaluates the
probable effects, if any, of the licensee’s
proposed action and alternatives. The
EA or EIS will consider environmental
impacts and reasonable alternatives to
the proposed action. The Commission’s
scoping process will help determine the
required level of analysis and satisfy the
National Environmental Policy Act
(NEPA) scoping requirements,
irrespective of whether the Commission
prepares an EA or an EIS. At this time,
we do not anticipate holding on-site
scoping meetings. Instead, we are
soliciting written comments and
suggestions on the preliminary list of
issues and alternatives to be addressed
in the NEPA document, as described in
scoping document 1 (SD1), issued
February 6, 2023.
Copies of the SD1 outlining the
subject areas to be addressed in the
NEPA document were distributed to the
parties on the Commission’s mailing list
and the applicant’s distribution list.
Copies of SD1 may be viewed on the
web at https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call 1–866–
208–3676 or for TTY, (202) 502–8659.
Dated: February 6, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–02882 Filed 2–9–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC23–54–000.
Applicants: Evergy Kansas Central,
Inc., Evergy, Inc., Persimmon Creek
Wind Farm 1, LLC.
Description: Joint Application for
Authorization Under Section 203 of the
Federal Power Act of Evergy Kansas
Central, Inc., et al.
Filed Date: 2/6/23.
Accession Number: 20230206–5088.
Comment Date: 5 p.m. ET 2/27/23.
PO 00000
Frm 00048
Fmt 4703
Sfmt 4703
8839
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG23–80–000.
Applicants: Lockhart ESS, LLC.
Description: Lockhart ESS, LLC
submits Notice of Self-Certification of
Exempt Wholesale Generator Status.
Filed Date: 2/3/23.
Accession Number: 20230203–5205.
Comment Date: 5 p.m. ET 2/24/23.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–1841–028;
ER10–1849–030; ER10–1851–018;
ER10–1852–076; ER10–1857–021;
ER10–1890–025; ER10–1899–020;
ER13–712–032; ER13–752–019; ER13–
1991–026; ER13–1992–026; ER15–2582–
014; ER15–2676–023; ER16–1672–021;
ER17–804–004; ER17–2152–017; ER18–
882–017; ER18–1534–012; ER18–1863–
015; ER18–1978–011; ER19–987–015;
ER19–1003–015; ER19–1393–015;
ER19–1394–015; ER19–2269–008;
ER19–2437–011; ER19–2461–011;
ER20–122–009; ER20–1769–009; ER20–
1980–008; ER20–1986–007; ER20–1987–
010; ER20–2049–007; ER21–1320–005;
ER21–1519–005; ER21–1682–005;
ER21–1879–006; ER21–2118–008;
ER21–2293–008; ER21–2296–007;
ER22–381–006; ER22–2518–002; ER22–
2634–002; ER23–71–001; ER22–2516–
001.
Applicants: Chaves County Solar II,
LLC, Buena Vista Energy Center, LLC,
Buffalo Ridge Wind, LLC, Clearwater
Wind I, LLC, Dunns Bridge Solar Center,
LLC, Ensign Wind Energy, LLC, Fish
Springs Ranch Solar, LLC, Dodge Flat
Solar, LLC, Farmington Solar, LLC,
Elora Solar, LLC, Cool Springs Solar,
LLC, Crystal Lake Wind Energy III, LLC,
Cedar Springs Wind III, LLC, Cerro
Gordo Wind, LLC, Day County Wind I,
LLC, Cedar Springs Wind, LLC, Chicot
Solar, LLC, Crowned Ridge
Interconnection, LLC, Crowned Ridge
Wind, LLC, Emmons-Logan Wind, LLC,
Dougherty County Solar, LLC, Endeavor
Wind II, LLC, Endeavor Wind I, LLC,
Crystal Lake Wind Energy II, LLC,
Crystal Lake Wind Energy I, LLC, Casa
Mesa Wind, LLC, Coolidge Solar I, LLC,
East Hampton Energy Storage Center,
LLC, Elk City Renewables II, LLC,
Cottonwood Wind Project, LLC, Coram
California Development, L.P., Chaves
County Solar, LLC, Cedar Bluff Wind,
LLC, Carousel Wind Farm, LLC, Desert
Sunlight 300, LLC, Desert Sunlight 250,
LLC, Energy Storage Holdings, LLC,
Cimarron Wind Energy, LLC, FPL
Energy Illinois Wind, LLC, FPL Energy
Green Power Wind, LLC, FPL Energy
Cape, LLC, Florida Power & Light
E:\FR\FM\10FEN1.SGM
10FEN1
Agencies
[Federal Register Volume 88, Number 28 (Friday, February 10, 2023)]
[Notices]
[Pages 8838-8839]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-02882]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2639-028]
Northern States Power Company--Wisconsin; Notice Soliciting
Scoping Comments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: P-2639-028.
c. Date filed: November 30, 2021.
d. Applicant: Northern States Power Company--Wisconsin.
e. Name of Project: Cornell Hydroelectric Project.
f. Location: The existing project is located on the Lower Chippewa
River in the township of Cornell, Chippewa County, Wisconsin.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Donald R. Hartinger, Director, Hydro Plants,
1414 W Hamilton Avenue, P.O. Box 8; Eau Claire, WI 54701;
[email protected]; (612) 321-3063.
i. FERC Contact: Michael Davis at (202) 502-8339; or
[email protected].
j. Deadline for filing scoping comments: March 8, 2023.
The Commission strongly encourages electronic filing. Please file
scoping comments using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief
comments up to 6,000 characters, without prior registration, using the
eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You
must include your name and contact information at the end of your
comments. For assistance, please contact FERC Online Support at
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to:
Secretary, Federal Energy Regulatory Commission, 888 First Street NE,
Washington, DC 20426. The first page of any filing should include
docket number P-2639-028.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must
[[Page 8839]]
also serve a copy of the document on that resource agency.
k. This application is not ready for environmental analysis at this
time.
l. Project Description: The project consists of the following
existing facilities: (1) a reservoir having 985 acres surface area,
gross storage capacity of 8,000 acre-feet and a net storage capacity of
1,500 acre-feet at a maximum normal water surface elevation of 1,002.0
National Geodetic Vertical Datum 1929 (NGVD); (2) an 861-foot-long
earth and concrete dam including: (a) a 42-foot-wide east concrete non-
overflow section with a top elevation of 1,010.0 feet NGVD, (b) a 131-
foot-long, 151.5-foot-wide, 82-foot-high powerhouse-intake structure
containing three horizontal shaft turbine-generators rated at 10
megawatts each and one vertical shaft turbine-generator rated at 750
kilowatts, (c) an 85-foot-long gated spillway containing two 37-foot-
wide by 23.3-foot-high Tainter gates with top of pier elevation of
1,008.0 feet NGVD, (d) a 10-foot-long non-overflow concrete dam section
with a top elevation of 1,004.2 feet NGVD, (e) a 292-foot-long gated
spillway containing 12 20-foot-long by 16-foot-high steel Tainter gates
with a top of pier elevation of 1,004.2 feet NGVD, (f) a 210-foot-long
by 28-foot-high overflow concrete section topped with 48-inch-high
flashboards with top of flashboard elevation of 1,002.2 feet NGVD, and
(g) a 91-foot-long west earthen embankment with a top elevation of
1,010.0 feet NGVD; (3) four 160-foot-long, 7.2-kilovolt (kV)
transmission lines connecting the powerhouse to an adjacent project
owned substation that is the point of interconnection to a 115-kV
distribution line belonging to the Northern States Power Company--
Wisconsin; and (4) appurtenant facilities. The project average annual
generation between 2016 and 2020 was 113,839 megawatt hours.
m. In addition to publishing the full text of this notice in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this notice, as well
as other documents in the proceeding (e.g., scoping document) via the
internet through the Commission's Home Page (https://www.ferc.gov) using
the ``eLibrary'' link. Enter the docket number, excluding the last
three digits, in the docket number field to access the document (P-
2639). For assistance, contact FERC at [email protected] or
call toll-free, (866) 208-3676 or TYY, (202) 502-8659.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Scoping Process:
Commission staff will prepare either an environmental assessment
(EA) or an environmental impact statement (EIS) that describes and
evaluates the probable effects, if any, of the licensee's proposed
action and alternatives. The EA or EIS will consider environmental
impacts and reasonable alternatives to the proposed action. The
Commission's scoping process will help determine the required level of
analysis and satisfy the National Environmental Policy Act (NEPA)
scoping requirements, irrespective of whether the Commission prepares
an EA or an EIS. At this time, we do not anticipate holding on-site
scoping meetings. Instead, we are soliciting written comments and
suggestions on the preliminary list of issues and alternatives to be
addressed in the NEPA document, as described in scoping document 1
(SD1), issued February 6, 2023.
Copies of the SD1 outlining the subject areas to be addressed in
the NEPA document were distributed to the parties on the Commission's
mailing list and the applicant's distribution list. Copies of SD1 may
be viewed on the web at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, call 1-866-
208-3676 or for TTY, (202) 502-8659.
Dated: February 6, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-02882 Filed 2-9-23; 8:45 am]