Tennessee Gas Pipeline Company, LLC; Notice of Availability of the Draft Environmental Impact Statement for the Proposed Cumberland Project, 8417-8418 [2023-02748]
Download as PDF
Federal Register / Vol. 88, No. 27 / Thursday, February 9, 2023 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP22–493–000]
khammond on DSKJM1Z7X2PROD with NOTICES
Tennessee Gas Pipeline Company,
LLC; Notice of Availability of the Draft
Environmental Impact Statement for
the Proposed Cumberland Project
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) has prepared a draft
Environmental Impact Statement (EIS)
for the Cumberland Project (Project),
proposed by Tennessee Gas Pipeline
Company, LLC (Tennessee) in the
above-referenced docket. Tennessee
requests a Certificate of Public
Convenience and Necessity to construct,
operate, and maintain certain natural
gas transmission pipeline and facilities
in Dickson, Houston, and Stewart
Counties, Tennessee. The Project
purpose is to provide up to 245,040
dekatherms per day of new firm
transportation service to the Tennessee
Valley Authority’s (TVA) Cumberland
Natural Gas Combined Cycle Power
Plant.
The draft EIS assesses the potential
environmental effects of the
construction and operation of the
Project in accordance with the
requirements of the National
Environmental Policy Act (NEPA). The
FERC staff concludes that approval of
the proposed Project, with the
mitigation measures recommended in
the EIS, would result in some adverse
environmental impacts. Most of these
impacts would be temporary and occur
during construction (e.g., impacts on
wetlands, land use, traffic, and noise).
Except for climate change impacts that
are not characterized in the EIS as
significant or insignificant, Commission
staff conclude that project effects would
not be significant. As part of the
analysis, Commission staff developed
specific mitigation measures (included
in the draft EIS as recommendations).
Staff recommend that these mitigation
measures be attached as conditions to
any authorization issued by the
Commission.
The U.S. Army Corps of Engineers
and the U.S. Environmental Protection
Agency participated as cooperating
agencies in the preparation of the EIS.
Cooperating agencies have jurisdiction
by law or special expertise with respect
to resources potentially affected by a
proposal and participate in the NEPA
analysis. Although both agencies
provided input to the conclusions and
recommendations presented in the draft
EIS, each agency may present its own
VerDate Sep<11>2014
16:28 Feb 08, 2023
Jkt 259001
conclusions and recommendations in
any applicable Records of Decision or
other documentation for the Project.
The draft EIS addresses the potential
environmental effects of the
construction and operation of the
following Project facilities, all in the
state of Tennessee:
• Cumberland Pipeline: Construction
of approximately 32 miles of new 30inch-diameter natural gas pipeline,
which would connect at Tennessee’s
existing Line 100–3 and Line 100–4.
The Cumberland Pipeline would be
located in Dickson, Houston, and
Stewart Counties.
• Pressure Regulation Station:
Construction of two new bi-directional
back pressure regulation facilities on
Line 100–3 and Line 100–4, at milepost
0.0 of the proposed new Cumberland
Pipeline in Dickson County.
• Cumberland Meter Station:
Construction of a new meter station at
the terminus of the Cumberland
Pipeline, located within TVA’s property
in Stewart County.
• Launcher and Receiver:
Construction of in-line inspection traps,
for in-line inspection tools at each end
of the Cumberland Pipeline.
• Mainline Valves: Construction of
three new mainline valves. One would
be installed at an intermediate location
along the Cumberland Pipeline, and the
remaining two would be on Tennessee’s
Line 100–3 and Line 100–4 within the
new Pressure Regulation Station.
The Commission mailed a copy of the
Notice of Availability of the Draft
Environmental Impact Statement for the
Proposed Cumberland Project to federal,
state, and local government
representatives and agencies; elected
officials; environmental and public
interest groups; Native American Tribes;
potentially affected landowners and
other interested individuals and groups;
and newspapers and libraries in the
Project area. The draft EIS is only
available in electronic format. It may be
viewed and downloaded from the FERC
website (https://ferc.gov/), on the
natural gas environmental documents
page (https://www.ferc.gov/industriesdata/natural-gas/environmentaloverview/environmental-documents2023). In addition, the draft EIS may be
accessed using the eLibrary link on the
FERC website. Click on the eLibrary link
(https://elibrary.ferc.gov/eLibrary/
search) select ‘‘General Search’’ and
enter the docket number in the ‘‘Docket
Number’’ field, excluding the last three
digits (i.e., CP22–493). Be sure you have
selected an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
8417
or toll free at (866) 208–3676, or for
TTY, contact (202) 502–8659.
The draft EIS is not a decision
document. It presents Commission
staff’s independent analysis of the
environmental issues for the
Commission to consider when
addressing the merits of all issues in
this proceeding. Any person wishing to
comment on the draft EIS may do so.
Your comments should focus on the
draft EIS’ disclosure and discussion of
potential environmental effects,
measures to avoid or lessen
environmental impacts, and the
completeness of the submitted
alternatives, information and analyses.
To ensure consideration of your
comments on the proposal in the final
EIS, it is important that the Commission
receive your comments on or before 5:00
p.m. Eastern Time on March 27, 2023.
For your convenience, there are four
methods you can use to submit your
comments to the Commission. The
Commission will provide equal
consideration to all comments received,
whether filed in written form or
provided orally. The Commission
encourages electronic filing of
comments and has staff available to
assist you at (866) 208–3676 or
FercOnlineSupport@ferc.gov. Please
carefully follow these instructions so
that your comments are properly
recorded.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s website
(https://ferc.gov/) under the link to
FERC Online. This is an easy method for
submitting brief, text-only comments on
a project;
(2) You can file your comments
electronically by using the eFiling
feature on the Commission’s website
(https://ferc.gov/) under the link to
FERC Online. With eFiling, you can
provide comments in a variety of
formats by attaching them as a file with
your submission. New eFiling users
must first create an account by clicking
on ‘‘eRegister.’’ If you are filing a
comment on a particular project, please
select ‘‘Comment on a Filing’’ as the
filing type; or
(3) You can file a paper copy of your
comments by mailing them to the
Commission. Be sure to reference the
Project docket number (CP22–493–000)
on your letter. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
E:\FR\FM\09FEN1.SGM
09FEN1
8418
Federal Register / Vol. 88, No. 27 / Thursday, February 9, 2023 / Notices
khammond on DSKJM1Z7X2PROD with NOTICES
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, MD 20852.
(4) In lieu of sending written or
electronic comments, the Commission
invites you to attend one of the public
comment sessions its staff will conduct
to receive comments on the draft EIS,
scheduled as follows:
Date
Time
Location
2/21/2023 ..............
5:00–8:00 p.m. Central Standard Time ....................
2/22/2023 ..............
5:00–8:00 p.m. Central Standard Time ....................
Events on Main, 105 S Main Street, Dickson, TN 37055, (615) 202–
3453.
Cumberland City Fire Hall, 121 Main Street, Cumberland City, TN
37050, (931) 627–4610.
The primary goal of these comment
sessions is to have you identify the
specific environmental issues and
concerns regarding the draft EIS.
Individual oral comments will be taken
on a one-on-one basis with a court
reporter. This format is designed to
receive the maximum amount of oral
comments, in a convenient way during
the timeframe allotted.
Each comment session is scheduled
from 5:00 p.m. to 8:00 p.m. Central
Standard Time. You may arrive at any
time after 5:00 p.m. There will not be a
formal presentation by Commission staff
when the session opens. If you wish to
speak, the Commission staff will hand
out numbers in the order of your arrival.
Comments will be taken until 8:00 p.m.
However, if no additional numbers have
been handed out and all individuals
who wish to provide comments have
had an opportunity to do so, staff may
conclude the session at 7:30 p.m. Please
see attachment 1 for additional
information on the session format and
conduct.1
Your oral comments will be recorded
by the court reporter (with FERC staff or
representative present) and become part
of the public record for this proceeding.
Transcripts will be publicly available on
FERC’s eLibrary system (see page 2 for
instructions on using eLibrary). If a
significant number of people are
interested in providing oral comments
in the one-on-one settings, a time limit
of 5 minutes may be implemented for
each commentor. Although there will
not be a formal presentation,
Commission staff will be available
throughout the comment session to
answer your questions about the
environmental review process.
It is important to note that the
Commission provides equal
consideration to all comments received,
whether filed in written form or
provided at a comment session.
1 The attachment referenced in this notice will
not appear in the Federal Register. A copy of the
attachment was sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE, Washington, DC 20426, or call (202) 502–
8371.
VerDate Sep<11>2014
16:28 Feb 08, 2023
Jkt 259001
Any person seeking to become a party
to the proceeding must file a motion to
intervene pursuant to Rule 214 of the
Commission’s Rules of Practice and
Procedures (18 CFR 385.214). Motions
to intervene are more fully described at
https://www.ferc.gov/how-intervene.
Only intervenors have the right to seek
rehearing or judicial review of the
Commission’s decision. The
Commission grants affected landowners
and others with environmental concerns
intervenor status upon showing good
cause by stating that they have a clear
and direct interest in this proceeding
which no other party can adequately
represent. Simply filing environmental
comments will not give you intervenor
status, but you do not need intervenor
status to have your comments
considered.
Questions?
Additional information about the
Project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website (www.ferc.gov) using the
eLibrary link. The eLibrary link also
provides access to the texts of all formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
In addition, the Commission offers a
free service called eSubscription that
allows you to keep track of all formal
issuances and submittals in the specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to https://www.ferc.gov/
ferc-online/overview to register for
eSubscription.
Dated: February 3, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–02748 Filed 2–8–23; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP23–29–000]
Saguaro Connector Pipeline, L.L.C.;
Notice of Scoping Period Requesting
Comments on Environmental Issues
for the Proposed Border Facilities
Project
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental document, that will
discuss the environmental impacts of
the Border Facilities Project (Project)
involving construction and operation of
facilities by Saguaro Pipeline Connector,
L.L.C. (Saguaro) in Hudspeth County,
Texas. The Commission will use this
environmental document in its
decision-making process to determine
whether the project is in the public
interest.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies regarding the
project. As part of the National
Environmental Policy Act (NEPA)
review process, the Commission takes
into account concerns the public may
have about proposals and the
environmental impacts that could result
from its action whenever it considers
the issuance of an authorization. This
gathering of public input is referred to
as ‘‘scoping.’’ The main goal of the
scoping process is to focus the analysis
in the environmental document on the
important environmental issues.
Additional information about the
Commission’s NEPA process is
described below in the NEPA Process
and Environmental Document section of
this notice.
By this notice, the Commission
requests public comments on the scope
of issues to address in the
environmental document. To ensure
that your comments are timely and
properly recorded, please submit your
comments so that the Commission
receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on March
E:\FR\FM\09FEN1.SGM
09FEN1
Agencies
[Federal Register Volume 88, Number 27 (Thursday, February 9, 2023)]
[Notices]
[Pages 8417-8418]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-02748]
[[Page 8417]]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP22-493-000]
Tennessee Gas Pipeline Company, LLC; Notice of Availability of
the Draft Environmental Impact Statement for the Proposed Cumberland
Project
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) has prepared a draft Environmental Impact Statement (EIS)
for the Cumberland Project (Project), proposed by Tennessee Gas
Pipeline Company, LLC (Tennessee) in the above-referenced docket.
Tennessee requests a Certificate of Public Convenience and Necessity to
construct, operate, and maintain certain natural gas transmission
pipeline and facilities in Dickson, Houston, and Stewart Counties,
Tennessee. The Project purpose is to provide up to 245,040 dekatherms
per day of new firm transportation service to the Tennessee Valley
Authority's (TVA) Cumberland Natural Gas Combined Cycle Power Plant.
The draft EIS assesses the potential environmental effects of the
construction and operation of the Project in accordance with the
requirements of the National Environmental Policy Act (NEPA). The FERC
staff concludes that approval of the proposed Project, with the
mitigation measures recommended in the EIS, would result in some
adverse environmental impacts. Most of these impacts would be temporary
and occur during construction (e.g., impacts on wetlands, land use,
traffic, and noise). Except for climate change impacts that are not
characterized in the EIS as significant or insignificant, Commission
staff conclude that project effects would not be significant. As part
of the analysis, Commission staff developed specific mitigation
measures (included in the draft EIS as recommendations). Staff
recommend that these mitigation measures be attached as conditions to
any authorization issued by the Commission.
The U.S. Army Corps of Engineers and the U.S. Environmental
Protection Agency participated as cooperating agencies in the
preparation of the EIS. Cooperating agencies have jurisdiction by law
or special expertise with respect to resources potentially affected by
a proposal and participate in the NEPA analysis. Although both agencies
provided input to the conclusions and recommendations presented in the
draft EIS, each agency may present its own conclusions and
recommendations in any applicable Records of Decision or other
documentation for the Project.
The draft EIS addresses the potential environmental effects of the
construction and operation of the following Project facilities, all in
the state of Tennessee:
Cumberland Pipeline: Construction of approximately 32
miles of new 30-inch-diameter natural gas pipeline, which would connect
at Tennessee's existing Line 100-3 and Line 100-4. The Cumberland
Pipeline would be located in Dickson, Houston, and Stewart Counties.
Pressure Regulation Station: Construction of two new bi-
directional back pressure regulation facilities on Line 100-3 and Line
100-4, at milepost 0.0 of the proposed new Cumberland Pipeline in
Dickson County.
Cumberland Meter Station: Construction of a new meter
station at the terminus of the Cumberland Pipeline, located within
TVA's property in Stewart County.
Launcher and Receiver: Construction of in-line inspection
traps, for in-line inspection tools at each end of the Cumberland
Pipeline.
Mainline Valves: Construction of three new mainline
valves. One would be installed at an intermediate location along the
Cumberland Pipeline, and the remaining two would be on Tennessee's Line
100-3 and Line 100-4 within the new Pressure Regulation Station.
The Commission mailed a copy of the Notice of Availability of the
Draft Environmental Impact Statement for the Proposed Cumberland
Project to federal, state, and local government representatives and
agencies; elected officials; environmental and public interest groups;
Native American Tribes; potentially affected landowners and other
interested individuals and groups; and newspapers and libraries in the
Project area. The draft EIS is only available in electronic format. It
may be viewed and downloaded from the FERC website (https://ferc.gov/),
on the natural gas environmental documents page (https://www.ferc.gov/industries-data/natural-gas/environmental-overview/environmental-documents-2023). In addition, the draft EIS may be accessed using the
eLibrary link on the FERC website. Click on the eLibrary link (https://elibrary.ferc.gov/eLibrary/search) select ``General Search'' and enter
the docket number in the ``Docket Number'' field, excluding the last
three digits (i.e., CP22-493). Be sure you have selected an appropriate
date range. For assistance, please contact FERC Online Support at
[email protected] or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659.
The draft EIS is not a decision document. It presents Commission
staff's independent analysis of the environmental issues for the
Commission to consider when addressing the merits of all issues in this
proceeding. Any person wishing to comment on the draft EIS may do so.
Your comments should focus on the draft EIS' disclosure and discussion
of potential environmental effects, measures to avoid or lessen
environmental impacts, and the completeness of the submitted
alternatives, information and analyses. To ensure consideration of your
comments on the proposal in the final EIS, it is important that the
Commission receive your comments on or before 5:00 p.m. Eastern Time on
March 27, 2023.
For your convenience, there are four methods you can use to submit
your comments to the Commission. The Commission will provide equal
consideration to all comments received, whether filed in written form
or provided orally. The Commission encourages electronic filing of
comments and has staff available to assist you at (866) 208-3676 or
[email protected]. Please carefully follow these instructions
so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment
feature on the Commission's website (https://ferc.gov/) under the link
to FERC Online. This is an easy method for submitting brief, text-only
comments on a project;
(2) You can file your comments electronically by using the eFiling
feature on the Commission's website (https://ferc.gov/) under the link
to FERC Online. With eFiling, you can provide comments in a variety of
formats by attaching them as a file with your submission. New eFiling
users must first create an account by clicking on ``eRegister.'' If you
are filing a comment on a particular project, please select ``Comment
on a Filing'' as the filing type; or
(3) You can file a paper copy of your comments by mailing them to
the Commission. Be sure to reference the Project docket number (CP22-
493-000) on your letter. Submissions sent via the U.S. Postal Service
must be addressed to: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC
20426. Submissions sent via any other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
[[Page 8418]]
Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD
20852.
(4) In lieu of sending written or electronic comments, the
Commission invites you to attend one of the public comment sessions its
staff will conduct to receive comments on the draft EIS, scheduled as
follows:
------------------------------------------------------------------------
Date Time Location
------------------------------------------------------------------------
2/21/2023................. 5:00-8:00 p.m. Events on Main, 105 S
Central Standard Main Street, Dickson,
Time. TN 37055, (615) 202-
3453.
2/22/2023................. 5:00-8:00 p.m. Cumberland City Fire
Central Standard Hall, 121 Main Street,
Time. Cumberland City, TN
37050, (931) 627-4610.
------------------------------------------------------------------------
The primary goal of these comment sessions is to have you identify
the specific environmental issues and concerns regarding the draft EIS.
Individual oral comments will be taken on a one-on-one basis with a
court reporter. This format is designed to receive the maximum amount
of oral comments, in a convenient way during the timeframe allotted.
Each comment session is scheduled from 5:00 p.m. to 8:00 p.m.
Central Standard Time. You may arrive at any time after 5:00 p.m. There
will not be a formal presentation by Commission staff when the session
opens. If you wish to speak, the Commission staff will hand out numbers
in the order of your arrival. Comments will be taken until 8:00 p.m.
However, if no additional numbers have been handed out and all
individuals who wish to provide comments have had an opportunity to do
so, staff may conclude the session at 7:30 p.m. Please see attachment 1
for additional information on the session format and conduct.\1\
---------------------------------------------------------------------------
\1\ The attachment referenced in this notice will not appear in
the Federal Register. A copy of the attachment was sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE, Washington, DC 20426, or call
(202) 502-8371.
---------------------------------------------------------------------------
Your oral comments will be recorded by the court reporter (with
FERC staff or representative present) and become part of the public
record for this proceeding. Transcripts will be publicly available on
FERC's eLibrary system (see page 2 for instructions on using eLibrary).
If a significant number of people are interested in providing oral
comments in the one-on-one settings, a time limit of 5 minutes may be
implemented for each commentor. Although there will not be a formal
presentation, Commission staff will be available throughout the comment
session to answer your questions about the environmental review
process.
It is important to note that the Commission provides equal
consideration to all comments received, whether filed in written form
or provided at a comment session.
Any person seeking to become a party to the proceeding must file a
motion to intervene pursuant to Rule 214 of the Commission's Rules of
Practice and Procedures (18 CFR 385.214). Motions to intervene are more
fully described at https://www.ferc.gov/how-intervene. Only intervenors
have the right to seek rehearing or judicial review of the Commission's
decision. The Commission grants affected landowners and others with
environmental concerns intervenor status upon showing good cause by
stating that they have a clear and direct interest in this proceeding
which no other party can adequately represent. Simply filing
environmental comments will not give you intervenor status, but you do
not need intervenor status to have your comments considered.
Questions?
Additional information about the Project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website (www.ferc.gov) using the eLibrary link. The eLibrary link
also provides access to the texts of all formal documents issued by the
Commission, such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription that allows you to keep track of all formal issuances and
submittals in the specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to https://www.ferc.gov/ferc-online/overview to
register for eSubscription.
Dated: February 3, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-02748 Filed 2-8-23; 8:45 am]
BILLING CODE 6717-01-P