Wyoming Interstate Company, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Diamond Mountain Compressor Station Abandonment Project, 7430-7432 [2023-02252]
Download as PDF
7430
Federal Register / Vol. 88, No. 23 / Friday, February 3, 2023 / Notices
electric power generator in Shelby
County, Alabama.
On October 28, 2022, the Federal
Energy Regulatory Commission (FERC
or Commission) issued a Notice of
Intent (NOI) which identified August 4,
2023 as the issuance date for the final
Environmental Impact Statement (EIS).
However, Commission staff now intends
to prepare an Environmental
Assessment (EA) for the Project and has
therefore revised the planned schedule
for the completion of the environmental
review.1
The October 28, 2022 NOI announced
the opening of a 30-day scoping period
which closed on November 28, 2022.
Commission staff will consider the
information gathered and comments
received during scoping in the
preparation of the EA; interested
stakeholders do not need to resubmit
comments previously submitted.
Commission staff will make the EA
available for public review and
inspection, and solicit comments on the
document from the public. The
Commission will review and consider
any future comments received on the
EA in its consideration of the Project.
This notice identifies the revised
schedule for completion of the EA for
Transco’s Project.
Schedule for Environmental Review
Issuance of the EA March 24, 2023
90-day Federal Authorization Decision
Deadline 2 June 22, 2023
If a schedule change becomes
necessary, an additional notice will be
provided so that the relevant agencies
are kept informed of the project’s
progress.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to https://www.ferc.gov/
ferc-online/overview to register for
eSubscription.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP22–501), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: January 27, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–02253 Filed 2–2–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 5912–003]
Town of Dover-Foxcroft; Notice of
Effectiveness of Withdrawal of
Application for Amendment of
Exemption
On November 23, 2020, the Town of
Dover-Foxcroft (Maine) filed an
application for amendment of the
exemption for the 300-kilowatt
Moosehead Hydroelectric Project No.
5912. On December 30, 2022, the Town
of Dover-Foxcroft filed a request to
withdraw its application.
No motion in opposition to the
request for withdrawal has been filed,
and the Commission has taken no action
to disallow the withdrawal. Pursuant to
Rule 216(b) of the Commission’s Rules
of Practice and Procedure,1 the
withdrawal of the application became
effective on January 16, 2023,2 and this
proceeding is hereby terminated.
Dated: January 30, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–02301 Filed 2–2–23; 8:45 am]
lotter on DSK11XQN23PROD with NOTICES1
1 40
CFR 1501.10 (2020)
2 The Commission’s deadline applies to the
decisions of other federal agencies, and state
agencies acting under federally delegated authority,
that are responsible for federal authorizations,
permits, and other approvals necessary for
proposed projects under the Natural Gas Act. Per
18 CFR 157.22(a), the Commission’s deadline for
other agency’s decisions applies unless a schedule
is otherwise established by federal law.
VerDate Sep<11>2014
17:51 Feb 02, 2023
Jkt 259001
BILLING CODE 6717–01–P
1 18
CFR 385.216(b) (2021).
Commission’s Rules of Practice and
Procedure provide that if a deadline falls on a
Saturday, Sunday, holiday, or other day when the
Commission is closed for business, the deadline
does not end until the close of business on the next
business day. 18 CFR 385.2007(a)(2) (2021).
2 The
PO 00000
Frm 00037
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP23–14–000]
Wyoming Interstate Company, LLC;
Notice of Scoping Period Requesting
Comments on Environmental Issues
for the Proposed Diamond Mountain
Compressor Station Abandonment
Project
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental document, that will
discuss the environmental impacts of
the Diamond Mountain Compressor
Station Abandonment Project (Project)
involving abandonment of facilities by
Wyoming Interstate Company, LLC
(WIC) in Uintah County, Utah. The
Commission will use this environmental
document in its decision-making
process to determine whether the
Project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies regarding the
Project. As part of the National
Environmental Policy Act (NEPA)
review process, the Commission takes
into account concerns the public may
have about proposals and the
environmental impacts that could result
from its action whenever it considers
the issuance of a Certificate of Public
Convenience and Necessity. This
gathering of public input is referred to
as ‘‘scoping.’’ The main goal of the
scoping process is to focus the analysis
in the environmental document on the
important environmental issues.
Additional information about the
Commission’s NEPA process is
described below in the NEPA Process
and Environmental Document section of
this notice.
By this notice, the Commission
requests public comments on the scope
of issues to address in the
environmental document. To ensure
that your comments are timely and
properly recorded, please submit your
comments so that the Commission
receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on
February 27, 2023. Comments may be
submitted in written form. Further
details on how to submit comments are
provided in the Public Participation
section of this notice.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
E:\FR\FM\03FEN1.SGM
03FEN1
Federal Register / Vol. 88, No. 23 / Friday, February 3, 2023 / Notices
lotter on DSK11XQN23PROD with NOTICES1
Your input will help the Commission
staff determine what issues they need to
evaluate in the environmental
document. Commission staff will
consider all written comments during
the preparation of the environmental
document.
If you submitted comments on this
Project to the Commission before the
opening of this docket on November 10,
2022, you will need to file those
comments in Docket No. CP23–14–000
to ensure they are considered as part of
this proceeding.
This notice is being sent to the
Commission’s current environmental
mailing list for this Project. State and
local government representatives should
notify their constituents of this
proposed Project and encourage them to
comment on their areas of concern.
Public Participation
There are three methods you can use
to submit your comments to the
Commission. Please carefully follow
these instructions so that your
comments are properly recorded. The
Commission encourages electronic filing
of comments and has staff available to
assist you at (866) 208–3676 or
FercOnlineSupport@ferc.gov.
(1) You can file your comments
electronically using the eComment
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. Using
eComment is an easy method for
submitting brief, text-only comments on
a project;
(2) You can file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to FERC Online. With
eFiling, you can provide comments in a
variety of formats by attaching them as
a file with your submission. New
eFiling users must first create an
account by clicking on ‘‘eRegister.’’ You
will be asked to select the type of filing
you are making; a comment on a
particular project is considered a
‘‘Comment on a Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
Commission. Be sure to reference the
Project docket number (CP23–14–000)
on your letter. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852.
VerDate Sep<11>2014
17:51 Feb 02, 2023
Jkt 259001
Additionally, the Commission offers a
free service called eSubscription which
makes it easy to stay informed of all
issuances and submittals regarding the
dockets/projects to which you
subscribe. These instant email
notifications are the fastest way to
receive notification and provide a link
to the document files which can reduce
the amount of time you spend
researching proceedings. Go to https://
www.ferc.gov/ferc-online/overview to
register for eSubscription.
Summary of the Proposed Project
WIC proposes the abandonment inplace of its Diamond Mountain
Compressor Station and associated
facilities encompassing 3.4 acres in
Uintah County, Utah. The existing
mainline block valve and associated
access road (0.8 acre) would continue
operating normally. No anticipated
ground disturbance is associated with
the proposed Project. WIC is proposing
this abandonment due to the progressive
decline of natural gas production in the
Uintah basin over the past decade.
The Project would consist of the
following actions:
• disconnecting pipes from compressor
units;
• draining oil and coolant from
turbines;
• draining water from domestic and
heating systems;
• disconnecting power; and
• removing applicable station valves
and turbine surge valves
The general location of the Project
facilities is shown in appendix 1.1
Land Requirements for Construction
The Project as proposed would be
abandoned in-place, no additional land
would be required, and no ground
disturbance is anticipated. The facilities
proposed for abandonment encompass
3.8 acres. The Project occurs on land
owned by WIC, who would continue
inspecting the site for safety and
environmental concerns after the
abandonment.
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of the
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’. For instructions on
connecting to eLibrary, refer to the last page of this
notice. At this time, the Commission has suspended
access to the Commission’s Public Reference Room
due to the proclamation declaring a National
Emergency concerning the Novel Coronavirus
Disease (COVID–19), issued by the President on
March 13, 2020. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll free, (886)
208–3676 or TTY (202) 502–8659.
PO 00000
Frm 00038
Fmt 4703
Sfmt 4703
7431
NEPA Process and the Environmental
Document
Any environmental document issued
by the Commission will discuss impacts
that could occur as a result of the
abandonment of the proposed Project
facilities under the relevant general
resource areas:
• geology and soils;
• water resources and wetlands;
• vegetation and wildlife;
• threatened and endangered species;
• cultural resources;
• land use; and
• air quality and noise.
Commission staff will evaluate
reasonable alternatives to the proposed
Project and make recommendations on
how to lessen or avoid impacts on the
various resource areas. An abandonment
by removal alternative is also being
considered by FERC staff. This
alternative would cause temporary
ground disturbance to 10.2 acres during
the removal process. The mainline block
valve station and access road (0.8 acre)
would still remain in operation after
removal. The alternative would consist
of the following actions:
• removal of all aboveground
equipment;
• removal of all piping;
• removal of fluids, electrical buildings
and foundations; and
• removal of fencing.
Your comments will help
Commission staff identify and focus on
the issues that might have an effect on
the human environment and potentially
eliminate others from further study and
discussion in the environmental
document.
Following this scoping period,
Commission staff will determine
whether to prepare an Environmental
Assessment (EA) or an Environmental
Impact Statement (EIS). The EA or the
EIS will present Commission staff’s
independent analysis of the issues. If
Commission staff prepares an EA, a
Notice of Schedule for the Preparation
of an Environmental Assessment will be
issued. The EA may be issued for an
allotted public comment period. The
Commission would consider timely
comments on the EA before making its
decision regarding the proposed Project.
If Commission staff prepares an EIS, a
Notice of Intent to Prepare an EIS/
Notice of Schedule will be issued,
which will open up an additional
comment period. Staff will then prepare
a draft EIS which will be issued for
public comment. Commission staff will
consider all timely comments received
during the comment period on the draft
EIS and revise the document, as
E:\FR\FM\03FEN1.SGM
03FEN1
7432
Federal Register / Vol. 88, No. 23 / Friday, February 3, 2023 / Notices
necessary, before issuing a final EIS.
Any EA or draft and final EIS will be
available in electronic format in the
public record through eLibrary and the
Commission’s natural gas
environmental documents web page
(https://www.ferc.gov/industries-data/
natural-gas/environment/
environmental-documents). If
eSubscribed, you will receive instant
email notification when the
environmental document is issued.
With this notice, the Commission is
asking agencies with jurisdiction by law
and/or special expertise with respect to
the environmental issues of this Project
to formally cooperate in the preparation
of the environmental document.2
Agencies that would like to request
cooperating agency status should follow
the instructions for filing comments
provided under the Public Participation
section of this notice.
Consultation Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, the Commission is
using this notice to initiate consultation
with the applicable State Historic
Preservation Office(s), and to solicit
their views and those of other
government agencies, interested Indian
tribes, and the public on the Project’s
potential effects on historic properties.3
The environmental document for this
Project will document findings on the
impacts on historic properties and
summarize the status of consultations
under section 106.
lotter on DSK11XQN23PROD with NOTICES1
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials; Native
American Tribes; other interested
parties; and local libraries and
newspapers. This list also includes all
affected landowners (as defined in the
Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
2 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at title 40, Code of Federal
Regulations, section 1501.8.
3 The Advisory Council on Historic Preservation’s
regulations are at title 36, Code of Federal
Regulations, part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
VerDate Sep<11>2014
17:51 Feb 02, 2023
Jkt 259001
comments on the Project and includes a
mailing address with their comments.
Commission staff will update the
environmental mailing list as the
analysis proceeds to ensure that
Commission notices related to this
environmental review are sent to all
individuals, organizations, and
government entities interested in and/or
potentially affected by the proposed
Project.
If you need to make changes to your
name/address, or if you would like to
remove your name from the mailing list,
please complete one of the following
steps:
(1) Send an email to
GasProjectAddressChange@ferc.gov
stating your request. You must include
the docket number CP23–14–000 in
your request. If you are requesting a
change to your address, please be sure
to include your name and the correct
address. If you are requesting to delete
your address from the mailing list,
please include your name and address
as it appeared on this notice. This email
address is unable to accept comments.
OR
(2) Return the attached ‘‘Mailing List
Update Form’’ (appendix 2).
Additional Information
Additional information about the
Project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website at www.ferc.gov using the
eLibrary link. Click on the eLibrary link,
click on ‘‘General Search’’ and enter the
docket number in the ‘‘Docket Number’’
field. Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or (866)
208–3676, or for TTY, contact (202)
502–8659.
The eLibrary link also provides access
to the texts of all formal documents
issued by the Commission, such as
orders, notices, and rulemakings.
Public sessions or site visits will be
posted on the Commission’s calendar
located at https://www.ferc.gov/newsevents/events along with other related
information.
Dated: January 27, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023–02252 Filed 2–2–23; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00039
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 4718–000]
Cocheco Falls Associates; Notice of
Authorization for Continued Project
Operation
The license for the Cocheco Falls Dam
Hydroelectric Project No. 4718 was
issued for a period ending December 31,
2022.
Section 15(a)(1) of the FPA, 16 U.S.C.
808(a)(1), requires the Commission, at
the expiration of a license term, to issue
from year-to-year an annual license to
the then licensee(s) under the terms and
conditions of the prior license until a
new license is issued, or the project is
otherwise disposed of as provided in
section 15 or any other applicable
section of the FPA. If the project’s prior
license waived the applicability of
section 15 of the FPA, then, based on
section 9(b) of the Administrative
Procedure Act, 5 U.S.C. 558(c), and as
set forth at 18 CFR 16.21(a), if the
licensee of such project has filed an
application for a subsequent license, the
licensee may continue to operate the
project in accordance with the terms
and conditions of the license after the
minor or minor part license expires,
until the Commission acts on its
application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 4718
is issued to Cocheco Falls Associates for
a period effective January 1, 2023,
through December 31, 2023, or until the
issuance of a new license for the project
or other disposition under the FPA,
whichever comes first. If issuance of a
new license (or other disposition) does
not take place on or before December 31,
2023, notice is hereby given that,
pursuant to 18 CFR 16.18(c), an annual
license under section 15(a)(1) of the
FPA is renewed automatically without
further order or notice by the
Commission, unless the Commission
orders otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that Cocheco Falls Associates is
authorized to continue operation of the
Cocheco Falls Dam Hydroelectric
Project under the terms and conditions
of the prior license until the issuance of
E:\FR\FM\03FEN1.SGM
03FEN1
Agencies
[Federal Register Volume 88, Number 23 (Friday, February 3, 2023)]
[Notices]
[Pages 7430-7432]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-02252]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP23-14-000]
Wyoming Interstate Company, LLC; Notice of Scoping Period
Requesting Comments on Environmental Issues for the Proposed Diamond
Mountain Compressor Station Abandonment Project
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental document, that will discuss
the environmental impacts of the Diamond Mountain Compressor Station
Abandonment Project (Project) involving abandonment of facilities by
Wyoming Interstate Company, LLC (WIC) in Uintah County, Utah. The
Commission will use this environmental document in its decision-making
process to determine whether the Project is in the public convenience
and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies regarding the Project. As part of the National Environmental
Policy Act (NEPA) review process, the Commission takes into account
concerns the public may have about proposals and the environmental
impacts that could result from its action whenever it considers the
issuance of a Certificate of Public Convenience and Necessity. This
gathering of public input is referred to as ``scoping.'' The main goal
of the scoping process is to focus the analysis in the environmental
document on the important environmental issues. Additional information
about the Commission's NEPA process is described below in the NEPA
Process and Environmental Document section of this notice.
By this notice, the Commission requests public comments on the
scope of issues to address in the environmental document. To ensure
that your comments are timely and properly recorded, please submit your
comments so that the Commission receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on February 27, 2023. Comments may be
submitted in written form. Further details on how to submit comments
are provided in the Public Participation section of this notice.
Your comments should focus on the potential environmental effects,
reasonable alternatives, and measures to avoid or lessen environmental
impacts.
[[Page 7431]]
Your input will help the Commission staff determine what issues they
need to evaluate in the environmental document. Commission staff will
consider all written comments during the preparation of the
environmental document.
If you submitted comments on this Project to the Commission before
the opening of this docket on November 10, 2022, you will need to file
those comments in Docket No. CP23-14-000 to ensure they are considered
as part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this Project. State and local government
representatives should notify their constituents of this proposed
Project and encourage them to comment on their areas of concern.
Public Participation
There are three methods you can use to submit your comments to the
Commission. Please carefully follow these instructions so that your
comments are properly recorded. The Commission encourages electronic
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected].
(1) You can file your comments electronically using the eComment
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. Using eComment is an easy method for
submitting brief, text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. With eFiling, you can provide comments
in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making; a comment on a particular project is considered a ``Comment
on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the Commission. Be sure to reference the Project docket number (CP23-
14-000) on your letter. Submissions sent via the U.S. Postal Service
must be addressed to: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC
20426. Submissions sent via any other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission,
12225 Wilkins Avenue, Rockville, Maryland 20852.
Additionally, the Commission offers a free service called
eSubscription which makes it easy to stay informed of all issuances and
submittals regarding the dockets/projects to which you subscribe. These
instant email notifications are the fastest way to receive notification
and provide a link to the document files which can reduce the amount of
time you spend researching proceedings. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
Summary of the Proposed Project
WIC proposes the abandonment in-place of its Diamond Mountain
Compressor Station and associated facilities encompassing 3.4 acres in
Uintah County, Utah. The existing mainline block valve and associated
access road (0.8 acre) would continue operating normally. No
anticipated ground disturbance is associated with the proposed Project.
WIC is proposing this abandonment due to the progressive decline of
natural gas production in the Uintah basin over the past decade.
The Project would consist of the following actions:
disconnecting pipes from compressor units;
draining oil and coolant from turbines;
draining water from domestic and heating systems;
disconnecting power; and
removing applicable station valves and turbine surge valves
The general location of the Project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
www.ferc.gov using the link called ``eLibrary''. For instructions on
connecting to eLibrary, refer to the last page of this notice. At
this time, the Commission has suspended access to the Commission's
Public Reference Room due to the proclamation declaring a National
Emergency concerning the Novel Coronavirus Disease (COVID-19),
issued by the President on March 13, 2020. For assistance, contact
FERC at [email protected] or call toll free, (886) 208-3676
or TTY (202) 502-8659.
---------------------------------------------------------------------------
Land Requirements for Construction
The Project as proposed would be abandoned in-place, no additional
land would be required, and no ground disturbance is anticipated. The
facilities proposed for abandonment encompass 3.8 acres. The Project
occurs on land owned by WIC, who would continue inspecting the site for
safety and environmental concerns after the abandonment.
NEPA Process and the Environmental Document
Any environmental document issued by the Commission will discuss
impacts that could occur as a result of the abandonment of the proposed
Project facilities under the relevant general resource areas:
geology and soils;
water resources and wetlands;
vegetation and wildlife;
threatened and endangered species;
cultural resources;
land use; and
air quality and noise.
Commission staff will evaluate reasonable alternatives to the
proposed Project and make recommendations on how to lessen or avoid
impacts on the various resource areas. An abandonment by removal
alternative is also being considered by FERC staff. This alternative
would cause temporary ground disturbance to 10.2 acres during the
removal process. The mainline block valve station and access road (0.8
acre) would still remain in operation after removal. The alternative
would consist of the following actions:
removal of all aboveground equipment;
removal of all piping;
removal of fluids, electrical buildings and foundations; and
removal of fencing.
Your comments will help Commission staff identify and focus on the
issues that might have an effect on the human environment and
potentially eliminate others from further study and discussion in the
environmental document.
Following this scoping period, Commission staff will determine
whether to prepare an Environmental Assessment (EA) or an Environmental
Impact Statement (EIS). The EA or the EIS will present Commission
staff's independent analysis of the issues. If Commission staff
prepares an EA, a Notice of Schedule for the Preparation of an
Environmental Assessment will be issued. The EA may be issued for an
allotted public comment period. The Commission would consider timely
comments on the EA before making its decision regarding the proposed
Project. If Commission staff prepares an EIS, a Notice of Intent to
Prepare an EIS/Notice of Schedule will be issued, which will open up an
additional comment period. Staff will then prepare a draft EIS which
will be issued for public comment. Commission staff will consider all
timely comments received during the comment period on the draft EIS and
revise the document, as
[[Page 7432]]
necessary, before issuing a final EIS. Any EA or draft and final EIS
will be available in electronic format in the public record through
eLibrary and the Commission's natural gas environmental documents web
page (https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents). If eSubscribed, you will receive instant
email notification when the environmental document is issued.
With this notice, the Commission is asking agencies with
jurisdiction by law and/or special expertise with respect to the
environmental issues of this Project to formally cooperate in the
preparation of the environmental document.\2\
---------------------------------------------------------------------------
\2\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at title 40, Code of Federal
Regulations, section 1501.8.
---------------------------------------------------------------------------
Agencies that would like to request cooperating agency status
should follow the instructions for filing comments provided under the
Public Participation section of this notice.
Consultation Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, the Commission is using this notice to initiate
consultation with the applicable State Historic Preservation Office(s),
and to solicit their views and those of other government agencies,
interested Indian tribes, and the public on the Project's potential
effects on historic properties.\3\ The environmental document for this
Project will document findings on the impacts on historic properties
and summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\3\ The Advisory Council on Historic Preservation's regulations
are at title 36, Code of Federal Regulations, part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials; Native
American Tribes; other interested parties; and local libraries and
newspapers. This list also includes all affected landowners (as defined
in the Commission's regulations) who are potential right-of-way
grantors, whose property may be used temporarily for project purposes,
or who own homes within certain distances of aboveground facilities,
and anyone who submits comments on the Project and includes a mailing
address with their comments. Commission staff will update the
environmental mailing list as the analysis proceeds to ensure that
Commission notices related to this environmental review are sent to all
individuals, organizations, and government entities interested in and/
or potentially affected by the proposed Project.
If you need to make changes to your name/address, or if you would
like to remove your name from the mailing list, please complete one of
the following steps:
(1) Send an email to [email protected] stating your
request. You must include the docket number CP23-14-000 in your
request. If you are requesting a change to your address, please be sure
to include your name and the correct address. If you are requesting to
delete your address from the mailing list, please include your name and
address as it appeared on this notice. This email address is unable to
accept comments. OR
(2) Return the attached ``Mailing List Update Form'' (appendix 2).
Additional Information
Additional information about the Project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website at www.ferc.gov using the eLibrary link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number
in the ``Docket Number'' field. Be sure you have selected an
appropriate date range. For assistance, please contact FERC Online
Support at [email protected] or (866) 208-3676, or for TTY,
contact (202) 502-8659.
The eLibrary link also provides access to the texts of all formal
documents issued by the Commission, such as orders, notices, and
rulemakings.
Public sessions or site visits will be posted on the Commission's
calendar located at https://www.ferc.gov/news-events/events along with
other related information.
Dated: January 27, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-02252 Filed 2-2-23; 8:45 am]