Premium Energy Holdings, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 6721-6722 [2023-02087]
Download as PDF
lotter on DSK11XQN23PROD with NOTICES1
Federal Register / Vol. 88, No. 21 / Wednesday, February 1, 2023 / Notices
to replace the existing 6-foot-high
wooden flashboards on the 176-feet long
north section of spillway, which has a
crest elevation of 534.2 feet, with an
inflatable crest gate system. The
proposal would result in a top crest
elevation of 534.2 feet and the top of the
inflatable crest gate, when fully raised,
would be 539.9 feet (same as existing
impoundment elevation). During
construction, the applicant requests to
temporarily draw down the
impoundment (normal pond elevation
at 539.9 feet NGVD29) to install a
cofferdam on the upstream face of the
dam to facilitate safe work conditions.
The applicant proposes to draw down
the impoundment from June 29 to July
20, 2023 by approximately 1.2 feet to
install the cofferdam. Then the
applicant would install the cofferdam
and begin phase 1 construction from
July 21 to mid-September, and during
this phase proposes to maintain the
water level at the dam crest elevation.
Phase 2 construction would last from
mid-September to November 23, and no
draw down below the dam crest is
anticipated during the transition from
the phase 1 to phase 2. Finally, the
cofferdam removal draw down is
anticipated to last approximately 1
week, from November 23 to December 2,
2023 (water levels would be drawn
down to elevation 533.0 ft or
approximately 1.2 feet below the dam
crest). During construction, the
applicant proposes to continue to
operate the project in a run-of-river
mode and would maintain minimum
flow requirements during and after
construction.
l. Locations of the Application: This
filing may be viewed on the
Commission’s website at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. You may
also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. Agencies may
obtain copies of the application directly
from the applicant.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214,
VerDate Sep<11>2014
21:04 Jan 31, 2023
Jkt 259001
respectively. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
o. Filing and Service of Documents:
Any filing must (1) bear in all capital
letters the title ‘‘COMMENTS’’,
‘‘PROTEST’’, or ‘‘MOTION TO
INTERVENE’’ as applicable; (2) set forth
in the heading the name of the applicant
and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
commenting, protesting or intervening;
and (4) otherwise comply with the
requirements of 18 CFR 385.2001
through 385.2005. All comments,
motions to intervene, or protests must
set forth their evidentiary basis. Any
filing made by an intervenor must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
385.2010.
Dated: January 26, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–02091 Filed 1–31–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 15270–000]
Premium Energy Holdings, LLC; Notice
of Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On March 31, 2022, Premium Energy
Holdings, LLC filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act (FPA),
proposing to study the feasibility of the
Santa Margarita Pumped Storage Hydro
Project to be located approximately 10
miles southeast of Lan Luis Obispo,
California in San Luis Obispo County.
The sole purpose of a preliminary
permit, if issued, is to grant the permit
holder priority to file a license
application during the permit term. A
preliminary permit does not authorize
the permit holder to perform any landdisturbing activities or otherwise enter
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
6721
upon lands or waters owned by others
without the owners’ express permission.
The proposed project would consist of
the following: (1) an existing upper
reservoir (Santa Margarita Lake) at an
elevation of 1,300 feet above average
mean sea level, with a surface area of
1,100 acres and a total storage capacity
of 23,840 acre-feet; (2) an existing lower
reservoir (Lopez Lake) at an elevation of
560 feet above average mean sea level,
with a surface area of 950 acres and a
storage capacity of 49,900 acre-feet; (3)
0.84-mile-long headrace tunnel, 0.19mile-long vertical shaft, 5.86-mile-long
horizontal tunnel, 0.09-mile-long
penstock, and 1.22-mile-long tailrace
tunnel to connect the powerhouse to the
reservoirs; (4) a new powerhouse that
would house 4 new pump-turbines
rated at 150 megawatts each; (5) a new
substation constructed in the western
shore of Lake Lopez near the
powerhouse, interconnected to the
regional electrical utility network with
either; (6) a new 2.5-mile-long 500kilovolt (kV) transmission line from the
powerhouse to a new switchyard
located 1.3 miles south of the Lopez
dam that will connect with PG&E’s 500kV line, or a new 4.5-mile-long 500-kV
line that will connect the powerhouse to
PG&E’s 500-kV line at a new switchyard
located 0.5 miles from Talley Vineyard
using Lopez road as an existing right-ofway; and (7) appurtenant facilities. The
estimated annual power generation at
the Santa Margarita Pumped Storage
Project would be 1,200,000 megawatthours.
Applicant Contact: Victor M. Rojas,
Managing Director, Premium Energy
Holdings, LLC, 355 South Lemon Ave.,
Suite A, Walnut, California 91789;
phone: (909) 595–5314; victor.rojas@
pehllc.net.
FERC Contact: Benjamin Mann; email:
benjamin.mann@ferc.gov; phone: (202)
502–8127.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
ferconline.ferc.gov/eFiling.aspx.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://ferconline.ferc.gov/
QuickComment.aspx. You must include
your name and contact information at
E:\FR\FM\01FEN1.SGM
01FEN1
6722
Federal Register / Vol. 88, No. 21 / Wednesday, February 1, 2023 / Notices
the end of your comments. For
assistance, please contact FERC Online
Support. In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. The first
page of any filing should include docket
number P–15270.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s website at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–15270) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
Dated: January 26, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–02087 Filed 1–31–23; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 11286–028]
lotter on DSK11XQN23PROD with NOTICES1
City of Abbeville; Notice of Intent To
File License Application, Filing of PreApplication Document, and Approving
Use of the Traditional Licensing
Process
a. Type of Filing: Notice of Intent to
File License Application and Request to
Use the Traditional Licensing Process
(TLP).
b. Project No.: 11286–028.
c. Dated Filed: November 29, 2022.
d. Submitted By: City of Abbeville.
e. Name of Project: Abbeville
Hydroelectric Project.
f. Location: On the Rocky River in
Abbeville and Anderson Counties,
South Carolina. No federal lands are
occupied by the project works or located
within the project boundary.
g. Filed Pursuant to: 18 CFR 5.3 of the
Commission’s regulations.
h. Applicant Contact: Tim Hall,
Director of Public Utilities, City of
Abbeville, 306 Cambridge Street,
Abbeville, SC 29620; Phone: (864) 366–
5058, Email: thall@abbevillecitysc.com.
i. FERC Contact: Kristine Sillett at
(202) 502–6575 or kristine.sillett@
ferc.gov.
VerDate Sep<11>2014
21:04 Jan 31, 2023
Jkt 259001
j. The City of Abbeville filed its
request to use the TLP on November 29,
2022. The City of Abbeville provided
public notice of its request on November
30, 2022. In a letter dated January 26,
2023, the Director of the Division of
Hydropower Licensing approved the
City of Abbeville’s request to use the
TLP.
k. With this notice, we are initiating
informal consultation with the U.S. Fish
and Wildlife Service and/or NOAA
Fisheries under section 7 of the
Endangered Species Act and the joint
agency regulations thereunder at 50
CFR, Part 402; and NOAA Fisheries
under section 305(b) of the MagnusonStevens Fishery Conservation and
Management Act and implementing
regulations at 50 CFR 600.920. We are
also initiating consultation with the
South Carolina State Historic
Preservation Officer, as required by
section 106, National Historic
Preservation Act, and the implementing
regulations of the Advisory Council on
Historic Preservation at 36 CFR 800.2.
l. With this notice, we are designating
the City of Abbeville as the
Commission’s non-federal
representative for carrying out informal
consultation, pursuant to section 7 of
the Endangered Species Act and section
305(b) of the Magnuson-Stevens Fishery
Conservation and Management Act; and
consultation pursuant to section 106 of
the National Historic Preservation Act.
m. The City of Abbeville filed a PreApplication Document (PAD; including
a proposed process plan and schedule)
with the Commission, pursuant to 18
CFR 5.6 of the Commission’s
regulations.
n. A copy of the PAD may be viewed
on the Commission’s website (https://
www.ferc.gov), using the ‘‘eLibrary’’
link. Enter the docket number,
excluding the last three digits in the
docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCONlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY).
o. The licensee states its unequivocal
intent to submit an application for a
new license for Project No. 11286.
Pursuant to 18 CFR 16.8, 16.9, and 16.10
each application for a new license and
any competing license applications
must be filed with the Commission at
least 24 months prior to the expiration
of the existing license. All applications
for license for this project must be filed
by November 30, 2025.
p. Register online at https://
ferconline.ferc.gov/eSubscription.aspx
to be notified via email of new filing
and issuances related to this or other
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
pending projects. For assistance, contact
FERC Online Support.
Dated: January 26, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023–02089 Filed 1–31–23; 8:45 am]
BILLING CODE 6717–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OPP–2017–0750; FRL–10527–01–
OCSPP]
Pesticide Registration Review;
Proposed Decisions for Several
Pesticides; Notice of Availability
Environmental Protection
Agency (EPA).
AGENCY:
ACTION:
Notice.
This notice announces the
availability of EPA’s proposed interim
and final registration review decisions
and opens a 60-day public comment
period on the proposed decisions for the
following pesticides: coat protein gene
of plum pox virus, dioctyl sodium
sulfosuccinate, isopropyl myristate,
polymeric betaine, undecylenic acid.
SUMMARY:
Comments must be received on
or before April 3, 2023.
DATES:
Submit your comments,
identified by docket identification (ID)
number EPA–HQ–OPP–2017–0750,
through the Federal eRulemaking Portal
at https://www.regulations.gov. Follow
the online instructions for submitting
comments. Do not submit electronically
any information you consider to be
Confidential Business Information (CBI)
or other information whose disclosure is
restricted by statute. Additional
instructions on commenting and visiting
the docket, along with more information
about dockets generally, is available at
https://www.epa.gov/dockets.
ADDRESSES:
FOR FURTHER INFORMATION CONTACT:
For pesticide specific information,
contact: The Chemical Review Manager
for the pesticide of interest identified in
Table 1 in Unit IV.
For general information on the
registration review program, contact:
Melanie Biscoe, Pesticide Re-Evaluation
Division (7508P), Office of Pesticide
Programs, Environmental Protection
Agency, 1200 Pennsylvania Ave. NW,
Washington, DC 20460–0001; telephone
number: (202) 566–0701; email address:
biscoe.melanie@epa.gov.
SUPPLEMENTARY INFORMATION:
E:\FR\FM\01FEN1.SGM
01FEN1
Agencies
[Federal Register Volume 88, Number 21 (Wednesday, February 1, 2023)]
[Notices]
[Pages 6721-6722]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-02087]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 15270-000]
Premium Energy Holdings, LLC; Notice of Preliminary Permit
Application Accepted for Filing and Soliciting Comments, Motions To
Intervene, and Competing Applications
On March 31, 2022, Premium Energy Holdings, LLC filed an
application for a preliminary permit, pursuant to section 4(f) of the
Federal Power Act (FPA), proposing to study the feasibility of the
Santa Margarita Pumped Storage Hydro Project to be located
approximately 10 miles southeast of Lan Luis Obispo, California in San
Luis Obispo County. The sole purpose of a preliminary permit, if
issued, is to grant the permit holder priority to file a license
application during the permit term. A preliminary permit does not
authorize the permit holder to perform any land-disturbing activities
or otherwise enter upon lands or waters owned by others without the
owners' express permission.
The proposed project would consist of the following: (1) an
existing upper reservoir (Santa Margarita Lake) at an elevation of
1,300 feet above average mean sea level, with a surface area of 1,100
acres and a total storage capacity of 23,840 acre-feet; (2) an existing
lower reservoir (Lopez Lake) at an elevation of 560 feet above average
mean sea level, with a surface area of 950 acres and a storage capacity
of 49,900 acre-feet; (3) 0.84-mile-long headrace tunnel, 0.19-mile-long
vertical shaft, 5.86-mile-long horizontal tunnel, 0.09-mile-long
penstock, and 1.22-mile-long tailrace tunnel to connect the powerhouse
to the reservoirs; (4) a new powerhouse that would house 4 new pump-
turbines rated at 150 megawatts each; (5) a new substation constructed
in the western shore of Lake Lopez near the powerhouse, interconnected
to the regional electrical utility network with either; (6) a new 2.5-
mile-long 500-kilovolt (kV) transmission line from the powerhouse to a
new switchyard located 1.3 miles south of the Lopez dam that will
connect with PG&E's 500-kV line, or a new 4.5-mile-long 500-kV line
that will connect the powerhouse to PG&E's 500-kV line at a new
switchyard located 0.5 miles from Talley Vineyard using Lopez road as
an existing right-of-way; and (7) appurtenant facilities. The estimated
annual power generation at the Santa Margarita Pumped Storage Project
would be 1,200,000 megawatt-hours.
Applicant Contact: Victor M. Rojas, Managing Director, Premium
Energy Holdings, LLC, 355 South Lemon Ave., Suite A, Walnut, California
91789; phone: (909) 595-5314; [email protected].
FERC Contact: Benjamin Mann; email: [email protected]; phone:
(202) 502-8127.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36.
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, notices of intent, and competing
applications using the Commission's eFiling system at https://ferconline.ferc.gov/eFiling.aspx. Commenters can submit brief comments
up to 6,000 characters, without prior registration, using the eComment
system at https://ferconline.ferc.gov/QuickComment.aspx. You must
include your name and contact information at
[[Page 6722]]
the end of your comments. For assistance, please contact FERC Online
Support. In lieu of electronic filing, you may submit a paper copy.
Submissions sent via the U.S. Postal Service must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via
any other carrier must be addressed to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville,
Maryland 20852. The first page of any filing should include docket
number P-15270.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of
Commission's website at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-15270) in the docket number field to access
the document. For assistance, contact FERC Online Support.
Dated: January 26, 2023.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2023-02087 Filed 1-31-23; 8:45 am]
BILLING CODE 6717-01-P