Kaukauna Utilities; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests, 6248 [2023-01950]

Download as PDF 6248 Federal Register / Vol. 88, No. 20 / Tuesday, January 31, 2023 / Notices The EA will be issued and circulated for review by all interested parties. All comments filed on the EA will be analyzed by staff and considered in the Commission’s final licensing decision. The application will be processed according to the following schedule. Revisions to the schedule may be made as appropriate. Milestone Target date Commission issues EA ............... Comments on EA ........................ August 2023.1 September 2023. Any questions regarding this notice may be directed to Patrick Ely at patrick.ely@ferc.gov or (202) 502–8570. Dated: January 24, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–01872 Filed 1–30–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 10674–020] Kaukauna Utilities; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests khammond on DSKJM1Z7X2PROD with NOTICES Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Request to amend transmission line route and project boundary. b. Project No.: 10674–020. c. Date Filed: October 31, 2022. d. Applicant: Kaukauna Utilities. e. Name of Project: Kimberly Hydroelectric Project. f. Location: The project is located on the Fox River in Outagamie County, Wisconsin. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Mr. Zachary Moureau, Environmental & Compliance Manager, Kaukauna Utilities, 777 Island Street, Kaukauna, WI 54130, (920) 462– 0238. i. FERC Contact: Mr. Steven Sachs, (202) 502–8666, Steven.Sachs@ferc.gov. 1 The Council on Environmental Quality’s (CEQ) regulations under 40 CFR 1501.10(b)(1) require that EAs be completed within 1 year of the federal action agency’s decision to prepare an EA. This notice establishes the Commission’s intent to prepare an EA for the Boyne River Project. Therefore, in accordance with CEQ’s regulations, the EA must be issued within 1 year of the issuance date of this notice. VerDate Sep<11>2014 16:46 Jan 30, 2023 Jkt 259001 j. Deadline for filing comments, motions to intervene, and protests is 30 days from the issuance of this notice by the Commission. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/doc-sfiling/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD 20852. The first page of any filing should include docket number P–10674–020. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Request: The applicant proposes to revise the project boundary to encompass a relocated transmission line which previously ran 320 feet along the north side of Papermill Run and crossed the street to the west of the project, but now travels 366 feet and crosses Papermill Run south of the project before traveling to the west along the south side of the street. The rerouted transmission line connects to the grid at the same location as the previous line and is buried for its entire length. The applicant also proposes to exclude land along the river shoreline from the project boundary that is not needed for project purposes. The project boundary revisions would result in the net addition of 0.04 acres of land to the project. l. In addition to publishing the full text of this document in the Federal PO 00000 Frm 00026 Fmt 4703 Sfmt 4703 Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Motions to Intervene, or Protests: Anyone may submit comments, a motion to intervene, or a protest in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, motions to intervene, or protests must be received on or before the specified comment date for the particular application. o. Filing and Service of Responsive Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘MOTION TO INTERVENE’’, or ‘‘PROTEST’’ as applicable; (2) set forth in the heading the name of the applicant and the project number(s) of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person intervening or protesting; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. Dated: January 13, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–01950 Filed 1–30–23; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\31JAN1.SGM 31JAN1

Agencies

[Federal Register Volume 88, Number 20 (Tuesday, January 31, 2023)]
[Notices]
[Page 6248]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-01950]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 10674-020]


Kaukauna Utilities; Notice of Application Accepted for Filing and 
Soliciting Comments, Motions To Intervene, and Protests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Request to amend transmission line route 
and project boundary.
    b. Project No.: 10674-020.
    c. Date Filed: October 31, 2022.
    d. Applicant: Kaukauna Utilities.
    e. Name of Project: Kimberly Hydroelectric Project.
    f. Location: The project is located on the Fox River in Outagamie 
County, Wisconsin.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Mr. Zachary Moureau, Environmental & 
Compliance Manager, Kaukauna Utilities, 777 Island Street, Kaukauna, WI 
54130, (920) 462-0238.
    i. FERC Contact: Mr. Steven Sachs, (202) 502-8666, 
[email protected].
    j. Deadline for filing comments, motions to intervene, and protests 
is 30 days from the issuance of this notice by the Commission. The 
Commission strongly encourages electronic filing. Please file comments, 
motions to intervene, and protests using the Commission's eFiling 
system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can 
submit brief comments up to 6,000 characters, without prior 
registration, using the eComment system at https://www.ferc.gov/doc-sfiling/ecomment.asp. You must include your name and contact 
information at the end of your comments. For assistance, please contact 
FERC Online Support at [email protected], (866) 208-3676 (toll 
free), or (202) 502-8659 (TTY). In lieu of electronic filing, you may 
submit a paper copy. Submissions sent via the U.S. Postal Service must 
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE, Room 1A, Washington, DC 20426. 
Submissions sent via any other carrier must be addressed to: Kimberly 
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins 
Avenue, Rockville, MD 20852. The first page of any filing should 
include docket number P-10674-020.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person on the official service list for the 
project. Further, if an intervenor files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    k. Description of Request: The applicant proposes to revise the 
project boundary to encompass a relocated transmission line which 
previously ran 320 feet along the north side of Papermill Run and 
crossed the street to the west of the project, but now travels 366 feet 
and crosses Papermill Run south of the project before traveling to the 
west along the south side of the street. The rerouted transmission line 
connects to the grid at the same location as the previous line and is 
buried for its entire length. The applicant also proposes to exclude 
land along the river shoreline from the project boundary that is not 
needed for project purposes. The project boundary revisions would 
result in the net addition of 0.04 acres of land to the project.
    l. In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (https://ferc.gov) using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. For 
assistance, contact FERC at [email protected] or call toll-
free, (886) 208-3676 or TYY, (202) 502-8659.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Motions to Intervene, or Protests: Anyone may submit 
comments, a motion to intervene, or a protest in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, motions to 
intervene, or protests must be received on or before the specified 
comment date for the particular application.
    o. Filing and Service of Responsive Documents: Any filing must (1) 
bear in all capital letters the title ``COMMENTS'', ``MOTION TO 
INTERVENE'', or ``PROTEST'' as applicable; (2) set forth in the heading 
the name of the applicant and the project number(s) of the application 
to which the filing responds; (3) furnish the name, address, and 
telephone number of the person intervening or protesting; and (4) 
otherwise comply with the requirements of 18 CFR 385.2001 through 
385.2005. All comments, motions to intervene, or protests must set 
forth their evidentiary basis. A copy of all other filings in reference 
to this application must be accompanied by proof of service on all 
persons listed in the service list prepared by the Commission in this 
proceeding, in accordance with 18 CFR 385.2010.

    Dated: January 13, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-01950 Filed 1-30-23; 8:45 am]
BILLING CODE 6717-01-P