MountainWest Overthrust Pipeline, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline, 5328-5329 [2023-01660]

Download as PDF khammond on DSKJM1Z7X2PROD with NOTICES 5328 Federal Register / Vol. 88, No. 18 / Friday, January 27, 2023 / Notices Practice and Procedure, 18 CFR part 45.8. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. On or before the comment date, it is not necessary to serve motions to intervene or protests on persons other than the Applicant. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. Comment Date: 5:00 p.m. Eastern Time on February 10, 2023. Dated: January 23, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–01662 Filed 1–26–23; 8:45 am] BILLING CODE 6717–01–P VerDate Sep<11>2014 16:53 Jan 26, 2023 Jkt 259001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP23–37–000] MountainWest Overthrust Pipeline, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline Take notice that January 13, 2023, MountainWest Overthrust Pipeline, LLC (Overthrust) filed a prior notice request for authorization, in accordance with 18 CFR 157.205, 157.208 and 157.211 of the Federal Energy Regulatory Commission’s (Commission) regulations under the Natural Gas Act and Overthrust’s blanket certificate issued in Docket No. CP82–493–000 to construct, own, operate, and maintain a new delivery point on the Overthrust pipeline system, located in Sweetwater County, Wyoming. Specifically, Overthrust proposes to construct and operate a tap, delivery lateral and meter station, known as the Carbonate Tap meter allocation point (MAP), located near the Solvay chemicals plant facility located approximately 15 miles west of Green River, Wyoming. The project would allow for the delivery 47,000 Dekatherms per day (Dth/d) of natural gas to Solvay from Overthrust’s mainline system. Overthrust estimates that the cost of the project will be about $7.2 million, all as more fully set forth in the application which is on file with the Commission and open for public inspection. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Any questions concerning this application should be directed to Stewart Merrick, Vice President, Legal and Regulatory, MountainWest Pipeline, LLC, 333 South State St., P.O. Box PO 00000 Frm 00030 Fmt 4703 Sfmt 4703 45922, Salt Lake City, UT 84145 at (801) 324–2509; or email at stewart.merrick@ mwpipe.com. Pursuant to Section 157.9 of the Commission’s Rules of Practice and Procedure,1 within 90 days of this Notice the Commission staff will either: complete its environmental review and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or environmental assessment (EA) for this proposal. The filing of an EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Public Participation There are three ways to become involved in the Commission’s review of this project: you can file a protest to the project, you can file a motion to intervene in the proceeding, and you can file comments on the project. There is no fee or cost for filing protests, motions to intervene, or comments. The deadline for filing protests, motions to intervene, and comments is 5:00 p.m. Eastern Time on March 24, 2023. How to file protests, motions to intervene, and comments is explained below. Protests Pursuant to section 157.205 of the Commission’s regulations under the NGA,2 any person 3 or the Commission’s staff may file a protest to the request. If no protest is filed within the time allowed or if a protest is filed and then withdrawn within 30 days after the allowed time for filing a protest, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request for authorization will be considered by the Commission. Protests must comply with the requirements specified in section 1 18 CFR (Code of Federal Regulations) 157.9. CFR 157.205. 3 Persons include individuals, organizations, businesses, municipalities, and other entities. 18 CFR 385.102(d). 2 18 E:\FR\FM\27JAN1.SGM 27JAN1 Federal Register / Vol. 88, No. 18 / Friday, January 27, 2023 / Notices 157.205(e) of the Commission’s regulations,4 and must be submitted by the protest deadline, which is March 24, 2023. A protest may also serve as a motion to intervene so long as the protestor states it also seeks to be an intervenor. khammond on DSKJM1Z7X2PROD with NOTICES Interventions Any person has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission’s orders in the U.S. Circuit Courts of Appeal. To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure 5 and the regulations under the NGA 6 by the intervention deadline for the project, which is March 24, 2023. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https://www.ferc.gov/ how-guides. All timely, unopposed motions to intervene are automatically granted by operation of Rule 214(c)(1). Motions to intervene that are filed after the intervention deadline are untimely and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission’s Rules and Regulations. A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties. Comments Any person wishing to comment on the project may do so. The Commission considers all comments received about the project in determining the appropriate action to be taken. To ensure that your comments are timely and properly recorded, please submit 4 18 CFR 157.205(e). CFR 385.214. 6 18 CFR 157.10. 5 18 VerDate Sep<11>2014 16:53 Jan 26, 2023 Jkt 259001 your comments on or before March 24, 2023. The filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding. How To File Protests, Interventions, and Comments There are two ways to submit protests, motions to intervene, and comments. In both instances, please reference the Project docket number CP23–37–000 in your submission. (1) You may file your protest, motion to intervene, and comments by using the Commission’s eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select ‘‘General’’ and then select ‘‘Protest’’, ‘‘Intervention’’, or ‘‘Comment on a Filing’’; or 7 (2) You can file a paper copy of your submission by mailing it to the address below. Your submission must reference the Project docket number CP23–37– 000. To mail via USPS, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. To send via any other courier, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The Commission encourages electronic filing of submissions (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FERCOnlineSupport@ferc.gov. Protests and motions to intervene must be served to the applicant by mail to: Stewart Merrick, Vice President, Legal and Regulatory MountainWest Pipeline, LLC, 333 South State St., P.O. Box 45922, Salt Lake City, UT 84145 or by email (with a link to the document) at stewart.merrick@mwpipe.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. 7 Additionally, you may file your comments electronically by using the eComment feature, which is located on the Commission’s website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project. PO 00000 Frm 00031 Fmt 4703 Sfmt 4703 5329 Tracking the Proceeding Throughout the proceeding, additional information about the project will be available from the Commission’s Office of External Affairs, at (866) 208– FERC, or on the FERC website at www.ferc.gov using the ‘‘eLibrary’’ link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to https://www.ferc.gov/ferconline/overview. Dated: January 23, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–01660 Filed 1–26–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following Complaints and Compliance filings in EL Dockets: Docket Numbers: EL23–24–000. Applicants: CXA La Paloma, LLC v. California Independent System Operator Corporation. Description: Complaint of CXA La Paloma, LLC v. California Independent System Operator Corporation. Filed Date: 1/23/23. Accession Number: 20230123–5080. Comment Date: 5 p.m. ET 2/22/23. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER22–2719–002. Applicants: PPL Electric Utilities Corporation, PJM Interconnection, L.L.C. Description: Tariff Amendment: PPL Electric Utilities Corporation submits tariff filing per 35.17(b): PPL Electric submits Response to Second Request for Information in ER22–2719 to be effective 1/31/2023. Filed Date: 1/23/23. Accession Number: 20230123–5091. Comment Date: 5 p.m. ET 2/13/23. Docket Numbers: ER23–158–002. E:\FR\FM\27JAN1.SGM 27JAN1

Agencies

[Federal Register Volume 88, Number 18 (Friday, January 27, 2023)]
[Notices]
[Pages 5328-5329]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-01660]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP23-37-000]


MountainWest Overthrust Pipeline, LLC; Notice of Request Under 
Blanket Authorization and Establishing Intervention and Protest 
Deadline

    Take notice that January 13, 2023, MountainWest Overthrust 
Pipeline, LLC (Overthrust) filed a prior notice request for 
authorization, in accordance with 18 CFR 157.205, 157.208 and 157.211 
of the Federal Energy Regulatory Commission's (Commission) regulations 
under the Natural Gas Act and Overthrust's blanket certificate issued 
in Docket No. CP82-493-000 to construct, own, operate, and maintain a 
new delivery point on the Overthrust pipeline system, located in 
Sweetwater County, Wyoming. Specifically, Overthrust proposes to 
construct and operate a tap, delivery lateral and meter station, known 
as the Carbonate Tap meter allocation point (MAP), located near the 
Solvay chemicals plant facility located approximately 15 miles west of 
Green River, Wyoming. The project would allow for the delivery 47,000 
Dekatherms per day (Dth/d) of natural gas to Solvay from Overthrust's 
mainline system. Overthrust estimates that the cost of the project will 
be about $7.2 million, all as more fully set forth in the application 
which is on file with the Commission and open for public inspection.
    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (https://ferc.gov) using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. At this time, 
the Commission has suspended access to the Commission's Public 
Reference Room, due to the proclamation declaring a National Emergency 
concerning the Novel Coronavirus Disease (COVID-19), issued by the 
President on March 13, 2020. For assistance, contact the Federal Energy 
Regulatory Commission at [email protected] or call toll-free, 
(886) 208-3676 or TYY, (202) 502-8659.
    Any questions concerning this application should be directed to 
Stewart Merrick, Vice President, Legal and Regulatory, MountainWest 
Pipeline, LLC, 333 South State St., P.O. Box 45922, Salt Lake City, UT 
84145 at (801) 324-2509; or email at [email protected].
    Pursuant to Section 157.9 of the Commission's Rules of Practice and 
Procedure,\1\ within 90 days of this Notice the Commission staff will 
either: complete its environmental review and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or environmental 
assessment (EA) for this proposal. The filing of an EA in the 
Commission's public record for this proceeding or the issuance of a 
Notice of Schedule for Environmental Review will serve to notify 
federal and state agencies of the timing for the completion of all 
necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's FEIS or EA.
---------------------------------------------------------------------------

    \1\ 18 CFR (Code of Federal Regulations) 157.9.
---------------------------------------------------------------------------

Public Participation

    There are three ways to become involved in the Commission's review 
of this project: you can file a protest to the project, you can file a 
motion to intervene in the proceeding, and you can file comments on the 
project. There is no fee or cost for filing protests, motions to 
intervene, or comments. The deadline for filing protests, motions to 
intervene, and comments is 5:00 p.m. Eastern Time on March 24, 2023. 
How to file protests, motions to intervene, and comments is explained 
below.

Protests

    Pursuant to section 157.205 of the Commission's regulations under 
the NGA,\2\ any person \3\ or the Commission's staff may file a protest 
to the request. If no protest is filed within the time allowed or if a 
protest is filed and then withdrawn within 30 days after the allowed 
time for filing a protest, the proposed activity shall be deemed to be 
authorized effective the day after the time allowed for protest. If a 
protest is filed and not withdrawn within 30 days after the time 
allowed for filing a protest, the instant request for authorization 
will be considered by the Commission.
---------------------------------------------------------------------------

    \2\ 18 CFR 157.205.
    \3\ Persons include individuals, organizations, businesses, 
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------

    Protests must comply with the requirements specified in section

[[Page 5329]]

157.205(e) of the Commission's regulations,\4\ and must be submitted by 
the protest deadline, which is March 24, 2023. A protest may also serve 
as a motion to intervene so long as the protestor states it also seeks 
to be an intervenor.
---------------------------------------------------------------------------

    \4\ 18 CFR 157.205(e).
---------------------------------------------------------------------------

Interventions

    Any person has the option to file a motion to intervene in this 
proceeding. Only intervenors have the right to request rehearing of 
Commission orders issued in this proceeding and to subsequently 
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
    To intervene, you must submit a motion to intervene to the 
Commission in accordance with Rule 214 of the Commission's Rules of 
Practice and Procedure \5\ and the regulations under the NGA \6\ by the 
intervention deadline for the project, which is March 24, 2023. As 
described further in Rule 214, your motion to intervene must state, to 
the extent known, your position regarding the proceeding, as well as 
your interest in the proceeding. For an individual, this could include 
your status as a landowner, ratepayer, resident of an impacted 
community, or recreationist. You do not need to have property directly 
impacted by the project in order to intervene. For more information 
about motions to intervene, refer to the FERC website at https://www.ferc.gov/how-guides.
---------------------------------------------------------------------------

    \5\ 18 CFR 385.214.
    \6\ 18 CFR 157.10.
---------------------------------------------------------------------------

    All timely, unopposed motions to intervene are automatically 
granted by operation of Rule 214(c)(1). Motions to intervene that are 
filed after the intervention deadline are untimely and may be denied. 
Any late-filed motion to intervene must show good cause for being late 
and must explain why the time limitation should be waived and provide 
justification by reference to factors set forth in Rule 214(d) of the 
Commission's Rules and Regulations. A person obtaining party status 
will be placed on the service list maintained by the Secretary of the 
Commission and will receive copies (paper or electronic) of all 
documents filed by the applicant and by all other parties.

Comments

    Any person wishing to comment on the project may do so. The 
Commission considers all comments received about the project in 
determining the appropriate action to be taken. To ensure that your 
comments are timely and properly recorded, please submit your comments 
on or before March 24, 2023. The filing of a comment alone will not 
serve to make the filer a party to the proceeding. To become a party, 
you must intervene in the proceeding.

How To File Protests, Interventions, and Comments

    There are two ways to submit protests, motions to intervene, and 
comments. In both instances, please reference the Project docket number 
CP23-37-000 in your submission.
    (1) You may file your protest, motion to intervene, and comments by 
using the Commission's eFiling feature, which is located on the 
Commission's website (www.ferc.gov) under the link to Documents and 
Filings. New eFiling users must first create an account by clicking on 
``eRegister.'' You will be asked to select the type of filing you are 
making; first select ``General'' and then select ``Protest'', 
``Intervention'', or ``Comment on a Filing''; or \7\
---------------------------------------------------------------------------

    \7\ Additionally, you may file your comments electronically by 
using the eComment feature, which is located on the Commission's 
website at www.ferc.gov under the link to Documents and Filings. 
Using eComment is an easy method for interested persons to submit 
brief, text-only comments on a project.
---------------------------------------------------------------------------

    (2) You can file a paper copy of your submission by mailing it to 
the address below. Your submission must reference the Project docket 
number CP23-37-000.
    To mail via USPS, use the following address: Kimberly D. Bose, 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426.
    To send via any other courier, use the following address: Kimberly 
D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins 
Avenue, Rockville, Maryland 20852.
    The Commission encourages electronic filing of submissions (option 
1 above) and has eFiling staff available to assist you at (202) 502-
8258 or [email protected].
    Protests and motions to intervene must be served to the applicant 
by mail to: Stewart Merrick, Vice President, Legal and Regulatory 
MountainWest Pipeline, LLC, 333 South State St., P.O. Box 45922, Salt 
Lake City, UT 84145 or by email (with a link to the document) at 
[email protected]. Any subsequent submissions by an intervenor 
must be served on the applicant and all other parties to the 
proceeding. Contact information for parties can be downloaded from the 
service list at the eService link on FERC Online.

Tracking the Proceeding

    Throughout the proceeding, additional information about the project 
will be available from the Commission's Office of External Affairs, at 
(866) 208-FERC, or on the FERC website at www.ferc.gov using the 
``eLibrary'' link as described above. The eLibrary link also provides 
access to the texts of all formal documents issued by the Commission, 
such as orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. For more information and to register, go to https://www.ferc.gov/ferc-online/overview.

    Dated: January 23, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-01660 Filed 1-26-23; 8:45 am]
BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.