Northern States Power Company; Notice of Application Tendered for Filing With The Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments, 3402-3403 [2023-00950]

Download as PDF 3402 Federal Register / Vol. 88, No. 12 / Thursday, January 19, 2023 / Notices Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. All filings must clearly identify the project name and docket number on the first page: Superior Falls Hydroelectric Project (P– 2587–066). m. This application is not ready for environmental analysis at this time. n. The existing Superior Falls Project consists of: (1) a reservoir with a surface area of 16.3-acres with a storage capacity of 78.2 acre-feet; (2) a 240-footlong, 28.5-foot-high dam; (3) a 1,697foot-long, 7-foot diameter conduit; (4) a 28-foot-diameter by 28-foot-high surge tank; (5) two 207-foot-long by 54-inchdiameter penstocks extending from the surge tank to the powerhouse; (6) a powerhouse containing two turbine- Commission’s Public Reference Room due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19) issued on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or (202) 502– 8659 (TTY). You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. p. Procedural Schedule: The application will be processed according to the following preliminary schedule. Revisions to the schedule will be made as appropriate. Milestone Target date Issue Deficiency Letter (if necessary) ............................................................................................................................................ Request Additional Information (if necessary) ................................................................................................................................ Issue Scoping Document 1 for comments ..................................................................................................................................... Issue Scoping Document 2 (if necessary) ...................................................................................................................................... March 2023. April 2023. September 2023. December 2023. q. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. Dated: January 12, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–00951 Filed 1–18–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2610–012] Northern States Power Company; Notice of Application Tendered for Filing With The Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments khammond on DSKJM1Z7X2PROD with NOTICES generator units each rated at 825 kilowatts with a combined plant capacity of 1.65 megawatts; (7) a 200foot-long above ground transmission line; and (8) appurtenant facilities. The Superior Falls Project is operated in a run-of-river mode with an estimated average annual energy production of 11,436 megawatt-hours, based on a fiveyear period ending in 2021. Northern States Power Company proposes to continue operating the project as a runof-river facility and does not propose any new construction to the project. o. A copy of the application can be viewed on the Commission’s website at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Subsequent License. b. Project No.: 2610–012. c. Date Filed: December 30, 2022. d. Applicant: Northern States Power Company. VerDate Sep<11>2014 17:49 Jan 18, 2023 Jkt 259001 e. Name of Project: Saxon Falls Hydroelectric Project (Saxon Falls Project). f. Location: The Saxon Falls Project is located on the Montreal River in Iron County, Wisconsin and Gogebic County, Michigan. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)–825(r). h. Applicant Contact: Matt Miller, Hydro License Consultant, Northern States Power Company, 1414 West Hamilton Avenue, P.O. Box 8, Eau Claire. Wisconsin 54702–0008, (715) 737–1353 or email at matthew.i.miller@ xcelenergy.com. i. FERC Contact: Lee Emery at (202) 502–8379 or email at lee.emery@ ferc.gov. j. Cooperating Agencies: Federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues that wish to cooperate in the preparation of the environmental document should follow the instructions for filing such requests described in item l below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See, 94 FERC ¶ 61,076 (2001). k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission’s regulations, if any resource agency, Indian Tribe, or person believes that an additional scientific study should be conducted in PO 00000 Frm 00027 Fmt 4703 Sfmt 4703 order to form an adequate factual basis for a complete analysis of the application on its merit, the resource agency, Indian Tribe, or person must file a request for a study with the Commission not later than 60 days from the date of filing of the application, and serve a copy of the request on the applicant. l. Deadline for filing additional study requests and requests for cooperating agency status: February 28, 2023. The Commission strongly encourages electronic filing. Please file additional study requests and requests for cooperating agency status using the Commission’s eFiling system at https:// ferconline.ferc.gov/FERCOnline.aspx. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. All filings must clearly identify the project name and docket number on the first page: Saxon Falls Hydroelectric Project (P– 2610–012). E:\FR\FM\19JAN1.SGM 19JAN1 Federal Register / Vol. 88, No. 12 / Thursday, January 19, 2023 / Notices m. This application is not ready for environmental analysis at this time. n. The Saxon Falls Project consists of: (1) a reservoir with a surface area of 65.5 acres with a storage capacity of 524 acre-feet; (2) a 440-foot-long, 40-foothigh dam; (3) a 1,670-foot-long, 6-foot diameter conduit; (4) a 23.5-footdiameter by 59.5-foot-high surge tank; (5) two 156-foot-long by 56-inchdiameter penstocks extending from the surge tank to the powerhouse; (6) a powerhouse containing two turbinegenerator units each rated at 750 kilowatts with a combined plant capacity of 1.5 megawatts; (7) a 0.25mile-long above ground transmission line; and (8) appurtenant facilities. The Saxon Falls Project is operated in a run-of-river mode with an estimated average annual energy production of 10,015 megawatt-hours, based on a fiveyear period ending in 2021. Northern States Power Company proposes to continue operating the project as a runof-river facility and does not propose any new construction to the project. o. A copy of the application can be viewed on the Commission’s website at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19) issued on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or (202) 502– 8659 (TTY). You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. p. Procedural Schedule: The application will be processed according to the following preliminary schedule. Revisions to the schedule will be made as appropriate. Milestone Target date Issue Deficiency Letter (if necessary) ............................................................................................................................................ Request Additional Information (if necessary) ................................................................................................................................ Issue Scoping Document 1 for comments ..................................................................................................................................... Issue Scoping Document 2 (if necessary) ...................................................................................................................................... March 2023. April 2023. September 2023. December 2023. q. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. Dated: January 12, 2023. Kimberly D. Bose, Secretary. [FR Doc. 2023–00950 Filed 1–18–23; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Environmental Conservation of the following: Date of Receipt of the Certification Request: December 16, 2022. Reasonable Period of Time to Act on the Certification Request: One year (December 16, 2023). If the Vermont Department of Environmental Conservation fails or refuses to act on the water quality certification request on or before the above date, then the agency certifying authority is deemed waived pursuant to section 401(a)(1) of the Clean Water Act, 33 U.S.C. 1341(a)(1). Dated: January 11, 2023. Kimberly D. Bose, Secretary. [Project No. 5944–024] [FR Doc. 2023–00892 Filed 1–18–23; 8:45 am] Moretown Hydroelectric, LLC; Notice of Waiver Period for Water Quality Certification Application khammond on DSKJM1Z7X2PROD with NOTICES 3403 On December 20, 2022, Moretown Hydroelectric, LLC submitted to the Federal Energy Regulatory Commission (Commission) evidence of the date on which the certifying agency received the certification request for a Clean Water Act section 401(a)(1) water quality certification filed with the Vermont Department of Environmental Conservation, in conjunction with the above captioned project. Pursuant to 40 CFR 121.6 and section [4.34(b)(5), 5.23(b), 153.4, or 157.22] of the Commission’s regulations,1 we hereby notify the Vermont Department of 1 18 CFR [4.34(b)(5)/5.23(b)/153.4/157.22]. VerDate Sep<11>2014 17:49 Jan 18, 2023 Jkt 259001 BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER15–1434–006. Applicants: ISO New England Inc., Emera Maine. Description: Compliance filing: ISO New England Inc. submits tariff filing per 35: Versant Power; Docket No. ER15–1434 Revised Joint offer of Settlement to be effective N/A. Filed Date: 1/12/23. PO 00000 Frm 00028 Fmt 4703 Sfmt 4703 Accession Number: 20230112–5000. Comment Date: 5 p.m. ET 2/2/23. Docket Numbers: ER20–2119–002. Applicants: ISO New England Inc., Versant Power. Description: Compliance filing: ISO New England Inc. submits tariff filing per 35: Versant Power; Docket No. ER20–2119 Revised Joint Offer of Settlement to be effective N/A. Filed Date: 1/12/23. Accession Number: 20230112–5001. Comment Date: 5 p.m. ET 2/2/23. Docket Numbers: ER23–226–001. Applicants: Southwest Power Pool, Inc. Description: Tariff Amendment: Deficiency Response—Fourth Amended and Restated WDJAs to be effective 12/ 28/2022. Filed Date: 1/11/23. Accession Number: 20230111–5072. Comment Date: 5 p.m. ET 1/25/23. Docket Numbers: ER23–446–001. Applicants: Duke Energy Indiana, LLC. Description: Tariff Amendment: DEIRequest to Defer Action on Construction Agreement to be effective 12/31/9998. Filed Date: 1/12/23. Accession Number: 20230112–5071. Comment Date: 5 p.m. ET 2/2/23. Docket Numbers: ER23–817–000. Applicants: WPL Bear Creek Solar, LLC. Description: Tariff Amendment: WPL Bear Creek Solar Cancellation of MBR Tariff to be effective 1/11/2023. Filed Date: 1/11/23. Accession Number: 20230111–5126. E:\FR\FM\19JAN1.SGM 19JAN1

Agencies

[Federal Register Volume 88, Number 12 (Thursday, January 19, 2023)]
[Notices]
[Pages 3402-3403]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-00950]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2610-012]


Northern States Power Company; Notice of Application Tendered for 
Filing With The Commission and Soliciting Additional Study Requests and 
Establishing Procedural Schedule for Relicensing and a Deadline for 
Submission of Final Amendments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Subsequent License.
    b. Project No.: 2610-012.
    c. Date Filed: December 30, 2022.
    d. Applicant: Northern States Power Company.
    e. Name of Project: Saxon Falls Hydroelectric Project (Saxon Falls 
Project).
    f. Location: The Saxon Falls Project is located on the Montreal 
River in Iron County, Wisconsin and Gogebic County, Michigan.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Matt Miller, Hydro License Consultant, 
Northern States Power Company, 1414 West Hamilton Avenue, P.O. Box 8, 
Eau Claire. Wisconsin 54702-0008, (715) 737-1353 or email at 
[email protected].
    i. FERC Contact: Lee Emery at (202) 502-8379 or email at 
[email protected].
    j. Cooperating Agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item l below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See, 94 FERC ] 
61,076 (2001).
    k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's 
regulations, if any resource agency, Indian Tribe, or person believes 
that an additional scientific study should be conducted in order to 
form an adequate factual basis for a complete analysis of the 
application on its merit, the resource agency, Indian Tribe, or person 
must file a request for a study with the Commission not later than 60 
days from the date of filing of the application, and serve a copy of 
the request on the applicant.
    l. Deadline for filing additional study requests and requests for 
cooperating agency status: February 28, 2023.
    The Commission strongly encourages electronic filing. Please file 
additional study requests and requests for cooperating agency status 
using the Commission's eFiling system at https://ferconline.ferc.gov/FERCOnline.aspx. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy. 
Submissions sent via the U.S. Postal Service must be addressed to: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via 
any other carrier must be addressed to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, 
Maryland 20852. All filings must clearly identify the project name and 
docket number on the first page: Saxon Falls Hydroelectric Project (P-
2610-012).

[[Page 3403]]

    m. This application is not ready for environmental analysis at this 
time.
    n. The Saxon Falls Project consists of: (1) a reservoir with a 
surface area of 65.5 acres with a storage capacity of 524 acre-feet; 
(2) a 440-foot-long, 40-foot-high dam; (3) a 1,670-foot-long, 6-foot 
diameter conduit; (4) a 23.5-foot-diameter by 59.5-foot-high surge 
tank; (5) two 156-foot-long by 56-inch-diameter penstocks extending 
from the surge tank to the powerhouse; (6) a powerhouse containing two 
turbine-generator units each rated at 750 kilowatts with a combined 
plant capacity of 1.5 megawatts; (7) a 0.25-mile-long above ground 
transmission line; and (8) appurtenant facilities.
    The Saxon Falls Project is operated in a run-of-river mode with an 
estimated average annual energy production of 10,015 megawatt-hours, 
based on a five-year period ending in 2021. Northern States Power 
Company proposes to continue operating the project as a run-of-river 
facility and does not propose any new construction to the project.
    o. A copy of the application can be viewed on the Commission's 
website at https://www.ferc.gov using the ``eLibrary'' link. Enter the 
docket number excluding the last three digits in the docket number 
field to access the document. At this time, the Commission has 
suspended access to the Commission's Public Reference Room due to the 
proclamation declaring a National Emergency concerning the Novel 
Coronavirus Disease (COVID-19) issued on March 13, 2020. For 
assistance, contact FERC at [email protected] or call toll-
free, (866) 208-3676 or (202) 502-8659 (TTY).
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    p. Procedural Schedule: The application will be processed according 
to the following preliminary schedule. Revisions to the schedule will 
be made as appropriate.

------------------------------------------------------------------------
                  Milestone                           Target date
------------------------------------------------------------------------
Issue Deficiency Letter (if necessary).......  March 2023.
Request Additional Information (if necessary)  April 2023.
Issue Scoping Document 1 for comments........  September 2023.
Issue Scoping Document 2 (if necessary)......  December 2023.
------------------------------------------------------------------------

    q. Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

    Dated: January 12, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-00950 Filed 1-18-23; 8:45 am]