Briar Hydro Associates, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments, 77824-77825 [2022-27589]

Download as PDF lotter on DSK11XQN23PROD with NOTICES1 77824 Federal Register / Vol. 87, No. 243 / Tuesday, December 20, 2022 / Notices Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. All filings must clearly identify the project name and docket number on the first page: Penacook Upper Falls Project (P–6689–018). m. The application is not ready for environmental analysis at this time. n. The Penacook Upper Falls Project consists of the following existing facilities: (1) an impoundment with a surface area of 11.4-acres at an elevation of 306.0 feet above National Geodetic Vertical Datum 1929; (2) a 21-foot-high, 187-foot-long timber stoplog dam with a gated concrete spillway ; (3) a 58-footwide, 15-foot-long forebay; (4) a 12.5foot-wide, 39.3-foot-high trashrack with 3.5-inch clear spacing; (5) a 44-footwide by 81-foot-long, concrete powerhouse, integral to the dam, containing one Kaplan turbine generating unit with a capacity of 3.02 megawatts; (6) a 350-foot-long, 47-footwide tailrace; (7) transmission facilities consisting of a 4.16/34.5- kilovolt (kV) transformer and a 50-foot-long, 34.5-kV transmission line; and (8) other appurtenances. The project operates in a run-of-river mode and had an average annual generation of 13,825,011 kilowatt-hours between 2012 and 2021. No changes to the project are proposed. o. Copies of the application may be viewed on the Commission’s website at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document (P–6689). For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or (202) 502– 8659 (TTY). You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. p. Procedural schedule and final amendments: The application will be processed according to the following preliminary schedule. Revisions to the schedule will be made as appropriate. Issue Deficiency Letter (if necessary)— February 2023 Request Additional Information (if necessary)—March 2023 Issue Acceptance Letter—May 2023 Issue Scoping Document 1 for comments—May 2023 Issue Scoping Document 2 (if necessary)—August 2023 Issue Notice of Ready for Environmental Analysis August—2023 VerDate Sep<11>2014 18:41 Dec 19, 2022 Jkt 259001 q. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. Dated: December 14, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–27586 Filed 12–19–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: Filings Instituting Proceedings Docket Numbers: CP23–25–000. Applicants: Southern Natural Gas Company, L.L.C. Description: Southern Natural Gas Company, L.L.C submits Abbreviated Application for Authorization to Abandon Services Under Certificate of Public Convenience and Necessity under CP23–25. Filed Date: 12/13/2022. Accession Number: 20221213–5057. Comment Date: 5 p.m. ET 1/3/23. Docket Numbers: RP23–280–000. Applicants: Guardian Pipeline, L.L.C. Description: § 4(d) Rate Filing: Negotiated PAL Koch Energy Services, LLC GN0822 to be effective 12/14/2022. Filed Date: 12/14/22. Accession Number: 20221214–5030. Comment Date: 5 p.m. ET 12/27/22. Docket Numbers: RP23–281–000. Applicants: Southern Natural Gas Company, L.L.C. Description: § 4(d) Rate Filing: Georgia Pacific Negotiated Rate to be effective 12/15/2022. Filed Date: 12/14/22. Accession Number: 20221214–5042. Comment Date: 5 p.m. ET 12/27/22. Docket Numbers: RP23–282–000. Applicants: Florida Gas Transmission Company, LLC. Description: § 4(d) Rate Filing: New Service Agreements—Brotman to be effective 1/1/2023. Filed Date: 12/14/22. Accession Number: 20221214–5048. Comment Date: 5 p.m. ET 12/27/22. Docket Numbers: RP23–283–000. Applicants: Florida Gas Transmission Company, LLC. Description: § 4(d) Rate Filing: Update Non-Conforming List—Brotman to be effective 1/1/2023. PO 00000 Frm 00038 Fmt 4703 Sfmt 4703 Filed Date: 12/14/22. Accession Number: 20221214–5049. Comment Date: 5 p.m. ET 12/27/22. Docket Numbers: RP23–284–000. Applicants: Alliance Pipeline L.P. Description: § 4(d) Rate Filing: Tariff Notice Address Change Filing to be effective 1/14/2023. Filed Date: 12/14/22. Accession Number: 20221214–5075. Comment Date: 5 p.m. ET 12/27/22. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: December 14, 2022. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2022–27622 Filed 12–19–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 3342–025] Briar Hydro Associates, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: New License. b. Project No.: 3342–025. c. Date Filed: November 30, 2022. d. Applicant: Briar Hydro Associates. e. Name of Project: Penacook Lower Falls Hydroelectric Project. f. Location: On the Contoocook River, in City of Concord, and Town of Boscawen, Merrimack County, New E:\FR\FM\20DEN1.SGM 20DEN1 Federal Register / Vol. 87, No. 243 / Tuesday, December 20, 2022 / Notices Hampshire. No federal lands are located within the project boundary. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Andrew J. Locke, Essex Hydro Associates, LLC, 55 Union Street, Boston, MA 02108; (617) 357–0032; email—alocke@ essexhydro.com. i. FERC Contact: Jeanne Edwards at (202) 502–6181; or jeanne.edwards@ ferc.gov. j. Cooperating agencies: Federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues that wish to cooperate in the preparation of the environmental document should follow the instructions for filing such requests described in item l below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See, 94 FERC ¶ 61,076 (2001). k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission’s regulations, if any resource agency, Indian Tribe, or person believes that an additional scientific study should be conducted in order to form an adequate factual basis for a complete analysis of the application on its merit, the resource agency, Indian Tribe, or person must file a request for a study with the Commission not later than 60 days from the date of filing of the application, and serve a copy of the request on the applicant. l. Deadline for filing additional study requests and requests for cooperating agency status: January 29, 2023. The Commission strongly encourages electronic filing. Please file additional study requests and requests for cooperating agency status using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. All filings must clearly identify the project name and docket number on the first page: Penacook Lower Falls Project (P–3342–025). m. The application is not ready for environmental analysis at this time. n. The Penacook Lower Falls Project consists of the following existing facilities: (1) an impoundment with a surface area of 8.4-acres at an elevation of 278.6 feet National Geodetic Vertical Datum 1929; (2) a concrete dam with a 15-footlong, 70-foot-wide forebay, a 106-footlong, gated spillway, a 316-foot-long auxiliary spillway, and a 140-foot-long, gated diversion structure; (3) a 23.3-footlong, 46.1-foot-high trash rack with a 3.625-inch clear spacing; (4) a 35-footwide by 97.5-foot-long concrete powerhouse, integral with the spillway, containing one Kaplan style turbinegenerator unit with a capacity of 4.6 megawatts; (5) a 700-foot-long, 45-foot wide tailrace; (6) transmission facilities consisting of a 4.16/34.5 kilovolt (kV) transformer and 200-foot-long, 34.5-kV transmission line; and (7) other appurtenances. The project operates in a run-of-river mode. The project had an average annual generation of 20,198,820 kWh kilowatt-hours between 2012 and 2021. No changes in the project operation are proposed. o. Copies of the application may be viewed on the Commission’s website at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document (P–3342). For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or (202) 502– 8659 (TTY). You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. p. Procedural schedule and final amendments: The application will be processed according to the following preliminary schedule. Revisions to the schedule will be made as appropriate. Issue Deficiency Letter (if necessary) ............................................................................................................................ Request Additional Information (if necessary) ............................................................................................................... Issue Acceptance Letter ................................................................................................................................................. Issue Scoping Document 1 for comments ..................................................................................................................... Issue Scoping Document 2 (if necessary) ..................................................................................................................... Issue Notice of Ready for Environmental Analysis ........................................................................................................ q. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. Federal Energy Regulatory Commission [Docket No. ER23–618–000] Dated: December 14, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–27589 Filed 12–19–22; 8:45 am] BILLING CODE 6717–01–P lotter on DSK11XQN23PROD with NOTICES1 DEPARTMENT OF ENERGY Sandy Ridge Wind 2, LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding of Sandy Ridge Wind 2, LLC’s application for market-based rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR VerDate Sep<11>2014 18:41 Dec 19, 2022 Jkt 259001 PO 00000 Frm 00039 Fmt 4703 Sfmt 4703 77825 February 2023. March 2023. May 2023. May 2023. August 2023 August 2023. part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is January 3, 2023. E:\FR\FM\20DEN1.SGM 20DEN1

Agencies

[Federal Register Volume 87, Number 243 (Tuesday, December 20, 2022)]
[Notices]
[Pages 77824-77825]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-27589]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 3342-025]


Briar Hydro Associates, LLC; Notice of Application Tendered for 
Filing With the Commission and Soliciting Additional Study Requests and 
Establishing Procedural Schedule for Relicensing and a Deadline for 
Submission of Final Amendments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: New License.
    b. Project No.: 3342-025.
    c. Date Filed: November 30, 2022.
    d. Applicant: Briar Hydro Associates.
    e. Name of Project: Penacook Lower Falls Hydroelectric Project.
    f. Location: On the Contoocook River, in City of Concord, and Town 
of Boscawen, Merrimack County, New

[[Page 77825]]

Hampshire. No federal lands are located within the project boundary.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Andrew J. Locke, Essex Hydro Associates, LLC, 
55 Union Street, Boston, MA 02108; (617) 357-0032; email_
[email protected]
    i. FERC Contact: Jeanne Edwards at (202) 502-6181; or 
[email protected].
    j. Cooperating agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item l below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See, 94 FERC ] 
61,076 (2001).
    k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's 
regulations, if any resource agency, Indian Tribe, or person believes 
that an additional scientific study should be conducted in order to 
form an adequate factual basis for a complete analysis of the 
application on its merit, the resource agency, Indian Tribe, or person 
must file a request for a study with the Commission not later than 60 
days from the date of filing of the application, and serve a copy of 
the request on the applicant.
    l. Deadline for filing additional study requests and requests for 
cooperating agency status: January 29, 2023.
    The Commission strongly encourages electronic filing. Please file 
additional study requests and requests for cooperating agency status 
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support 
at [email protected], (866) 208-3676 (toll free), or (202) 
502-8659 (TTY). In lieu of electronic filing, you may submit a paper 
copy. Submissions sent via the U.S. Postal Service must be addressed 
to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 
888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent 
via any other carrier must be addressed to: Kimberly D. Bose, 
Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, 
Rockville, Maryland 20852. All filings must clearly identify the 
project name and docket number on the first page: Penacook Lower Falls 
Project (P-3342-025).
    m. The application is not ready for environmental analysis at this 
time.
    n. The Penacook Lower Falls Project consists of the following 
existing facilities:
    (1) an impoundment with a surface area of 8.4-acres at an elevation 
of 278.6 feet National Geodetic Vertical Datum 1929; (2) a concrete dam 
with a 15-foot-long, 70-foot-wide forebay, a 106-foot-long, gated 
spillway, a 316-foot-long auxiliary spillway, and a 140-foot-long, 
gated diversion structure; (3) a 23.3-foot-long, 46.1-foot-high trash 
rack with a 3.625-inch clear spacing; (4) a 35-foot-wide by 97.5-foot-
long concrete powerhouse, integral with the spillway, containing one 
Kaplan style turbine-generator unit with a capacity of 4.6 megawatts; 
(5) a 700-foot-long, 45-foot wide tailrace; (6) transmission facilities 
consisting of a 4.16/34.5 kilovolt (kV) transformer and 200-foot-long, 
34.5-kV transmission line; and (7) other appurtenances.
    The project operates in a run-of-river mode. The project had an 
average annual generation of 20,198,820 kWh kilowatt-hours between 2012 
and 2021. No changes in the project operation are proposed.
    o. Copies of the application may be viewed on the Commission's 
website at https://www.ferc.gov using the ``eLibrary'' link. Enter the 
docket number excluding the last three digits in the docket number 
field to access the document (P-3342). For assistance, contact FERC 
Online Support at [email protected] or call toll-free, (866) 
208-3676 or (202) 502-8659 (TTY).
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects.
    p. Procedural schedule and final amendments: The application will 
be processed according to the following preliminary schedule. Revisions 
to the schedule will be made as appropriate.

----------------------------------------------------------------------------------------------------------------
 
----------------------------------------------------------------------------------------------------------------
Issue Deficiency Letter (if necessary).....................  February 2023.
Request Additional Information (if necessary)..............  March 2023.
Issue Acceptance Letter....................................  May 2023.
Issue Scoping Document 1 for comments......................  May 2023.
Issue Scoping Document 2 (if necessary)....................  August 2023
Issue Notice of Ready for Environmental Analysis...........  August 2023.
----------------------------------------------------------------------------------------------------------------

    q. Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

    Dated: December 14, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-27589 Filed 12-19-22; 8:45 am]
BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.