Lake Lynn Generation, LLC; Notice of Application Tendered for Filing With The Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments, 77099-77100 [2022-27310]
Download as PDF
Federal Register / Vol. 87, No. 241 / Friday, December 16, 2022 / Notices
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: December 12, 2022.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2022–27337 Filed 12–15–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2459–279]
lotter on DSK11XQN23PROD with NOTICES1
Lake Lynn Generation, LLC; Notice of
Application Tendered for Filing With
The Commission and Soliciting
Additional Study Requests and
Establishing Procedural Schedule for
Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 2459–279.
c. Date filed: November 30, 2022.
d. Applicant: Lake Lynn Generation,
LLC.
e. Name of Project: Lake Lynn
Hydroelectric Project.
f. Location: On the Cheat River, near
the city of Morgantown, in Monongalia
County, West Virginia, and near the
borough of Point Marion, in Fayette
County, Pennsylvania. The project does
not occupy any federal land.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Jody Smet, Lake
Lynn Generation, LLC, 7315 Wisconsin
Avenue, Suite 1100W, Bethesda, MD
20814; Phone at (240) 482–2700; or
email at Jody.Smet@eaglecreekre.com.
i. FERC Contact: Joshua Dub at (202)
502–8138, or joshua.dub@ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
VerDate Sep<11>2014
20:05 Dec 15, 2022
Jkt 259001
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: January 29, 2023.
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
ferconline.ferc.gov/FERCOnline.aspx.
For assistance, please contact FERC
Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. All filings
must clearly identify the project name
and docket number on the first page:
Lake Lynn Hydroelectric Project (P–
2459–279).
m. The application is not ready for
environmental analysis at this time.
n. The existing Lake Lynn Project
consists of: (1) a 13 mile-long, 1,729acre impoundment (Lake Lynn) with a
maximum storage capacity of 72,300
acre-feet at a normal water surface
elevation of 870 feet National Geodetic
Vertical Datum of 1929 (NGVD 29) and
a normal minimum storage capacity of
51,100 acre-feet at 857 feet NGVD 29; (2)
a 1,000-foot-long, 125-foot-high,
concrete gravity dam with a 624-footlong spillway section controlled by 26,
PO 00000
Frm 00043
Fmt 4703
Sfmt 4703
77099
21-foot-wide by 17-foot-high, Tainter
gates; (3) a concrete intake structure
equipped with a log boom and eight
trash racks with 4-inch clear bar
spacing; (4) eight 12-foot-wide by 18foot-deep gated reinforced concrete
penstocks; (5) a 160-foot-long by 94.5foot-wide powerhouse containing four
Francis generating units with a
combined capacity of 51.2 megawatts;
and (6) two 800-foot-long transmission
lines that run from the powerhouse to
a substation within the project
boundary.
The Lake Lynn Project is currently
operated as a peaking facility with
storage. The hours of peaking vary
depending on environmental and
economic considerations. The current
license requires Lake Lynn Generation,
LLC to maintain Cheat Lake between
868 feet and 870 feet NGVD 29 from
May 1 through October 31, 857 feet and
870 feet NGVD 29 from November 1
through March 31, and 863 feet and 870
feet NGVD 29 from April 1 through
April 30 each year. The current license
also requires Lake Lynn Generation,
LLC to release a downstream minimum
flow of 212 cubic-feet-per-second (cfs),
or inflow, from the dam when not
generating, with an absolute minimum
flow of 100 cfs regardless of inflow,
when not generating. The project
generates about 144,741 megawatt-hours
annually.
Lake Lynn Generation, LLC proposes
to continue operating the project as a
peaking facility with storage, and does
not propose any new development at
the project.
o. In addition to publishing the full
text of this notice in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
notice, as well as other documents in
the proceeding (e.g., license application)
via the internet through the
Commission’s Home Page (https://
www.ferc.gov), using the ‘‘eLibrary’’
link. Enter the docket number,
excluding the last three digits in the
docket number field to access the
document (P–2459). For assistance,
contact FERC at FERCOnlineSupport@
ferc.gov, or call toll-free, (866) 208–
3676, or (202) 502–8659 (TTY).
You may also register online at
https://ferconline.ferc.gov/FERCOnline.
aspx to be notified via email of new
filings and issuances related to this or
other pending projects. For assistance,
contact FERC Online Support.
p. Procedural schedule and final
amendments: The application will be
processed according to the following
preliminary schedule. Revisions to the
schedule will be made as appropriate.
E:\FR\FM\16DEN1.SGM
16DEN1
77100
Federal Register / Vol. 87, No. 241 / Friday, December 16, 2022 / Notices
Issue Deficiency Letter (if necessary)—
February 2023
Request Additional Information—
February 2023
Issue Acceptance Letter—June 2023
Issue Scoping Document 1 for
comments—June 2023
Issue Scoping Document 2 (if
necessary)—August 2023
Issue Notice of Ready for Environmental
Analysis—August 2023
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: December 12, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–27310 Filed 12–15–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Federal Energy Regulatory
Commission
[Project No. 14992–000]
Notice of Surrender of Preliminary
Permit; Pumped Hydro Storage LLC
Take notice that Pumped Hydro
Storage LLC, permittee for the proposed
Salt Trail Canyon Pumped Storage
Project, has requested that its
preliminary permit be terminated. The
permit was issued on May 21, 2020, and
would have expired on April 30, 2023.1
The project would have been located on
the Little Colorado River in Coconino
County, Arizona.
The preliminary permit for Project
No. 14992 will remain in effect until the
close of business, January 11, 2023. But,
if the Commission is closed on this day,
then the permit remains in effect until
the close of business on the next day in
which the Commission is open.2 New
applications for this site may not be
submitted until after the permit
surrender is effective.
Dated: December 12, 2022.
Kimberly D. Bose,
Secretary.
[Project No. 14995–000]
Pumped Hydro Storage LLC; Notice of
Surrender of Preliminary Permit
Take notice that Pumped Hydro
Storage LLC, permittee for the proposed
San Francisco River Pumped Storage
Project, has requested that its
preliminary permit be terminated. The
permit was issued on February 18, 2021
and would have expired on January 31,
2024.1 The project would have been
located on the San Francisco River in
Greenlee County, Arizona and Catron
County, New Mexico, on land that is
part of the Apache-Sitgreaves National
Forest in Arizona and the Gila National
Forest in New Mexico.
The preliminary permit for Project
No. 14995 will remain in effect until the
close of business, January 11, 2023. But,
if the Commission is closed on this day,
then the permit remains in effect until
the close of business on the next day in
which the Commission is open.2 New
applications for this site may not be
submitted until after the permit
surrender is effective.
lotter on DSK11XQN23PROD with NOTICES1
DEPARTMENT OF ENERGY
Dated: December 12, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–27312 Filed 12–15–22; 8:45 am]
BILLING CODE 6717–01–P
FERC ¶ 61,122 (2021).
CFR 385.2007(a)(2) (2021).
[FR Doc. 2022–27314 Filed 12–15–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 6634–003]
Shasta Meadows, Inc.; Notice of
Application for Surrender of
Exemption, Soliciting Comments,
Motions To Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Application for
surrender of exemption.
b. Project No: P–6634–003.
c. Date Filed: February 8, 2019.
d. Applicant: Shasta Meadows, Inc.
e. Name of Project: Prather Creek
Hydroelectric Project.
f. Location: The project is located on
Prather Creek, in Siskiyou County,
California.
g. Filed Pursuant to: Public Utility
Regulatory Policies Act of 1978, 16
U.S.C. 2705, 2708.
h. Applicant Contact: Mr. Anthony
Ralphs, Shasta Meadows, Inc., 2415
1 174
1 171
2 18
2 18
VerDate Sep<11>2014
20:05 Dec 15, 2022
Jkt 259001
PO 00000
FERC ¶ 61,137 (2020).
CFR 385.2007(a)(2) (2021).
Frm 00044
Fmt 4703
Sfmt 4703
Wishing Star Way, Chula Vista,
California 91915, (619) 437–9200,
tralphs@mac.com.
i. FERC Contact: Ashish Desai, (202)
502–8370, Ashish.Desai@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests:
January 11, 2023.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, and protests using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, MD 20852. The first page of
any filing should include the docket
number P–6634–003. Comments
emailed to Commission staff are not
considered part of the Commission
record.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. Description of Request: The
exemptee proposes to surrender its
exemption for the project. The power
purchasing agreement for the project
expired in 2013 and the exemptee has
been unable to enter into a new
agreement. Currently, the project is nonoperational and no water flows through
penstock. The exemptee proposes to
leave all project works secured in place
including the powerhouse and
generator.
l. Locations of the Application: This
filing may be viewed on the
Commission’s website at https://
E:\FR\FM\16DEN1.SGM
16DEN1
Agencies
[Federal Register Volume 87, Number 241 (Friday, December 16, 2022)]
[Notices]
[Pages 77099-77100]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-27310]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2459-279]
Lake Lynn Generation, LLC; Notice of Application Tendered for
Filing With The Commission and Soliciting Additional Study Requests and
Establishing Procedural Schedule for Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 2459-279.
c. Date filed: November 30, 2022.
d. Applicant: Lake Lynn Generation, LLC.
e. Name of Project: Lake Lynn Hydroelectric Project.
f. Location: On the Cheat River, near the city of Morgantown, in
Monongalia County, West Virginia, and near the borough of Point Marion,
in Fayette County, Pennsylvania. The project does not occupy any
federal land.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Jody Smet, Lake Lynn Generation, LLC, 7315
Wisconsin Avenue, Suite 1100W, Bethesda, MD 20814; Phone at (240) 482-
2700; or email at [email protected].
i. FERC Contact: Joshua Dub at (202) 502-8138, or
[email protected].
j. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See, 94 FERC ]
61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: January 29, 2023.
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at https://ferconline.ferc.gov/FERCOnline.aspx. For assistance, please contact FERC Online Support at
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy.
Submissions sent via the U.S. Postal Service must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via
any other carrier must be addressed to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville,
Maryland 20852. All filings must clearly identify the project name and
docket number on the first page: Lake Lynn Hydroelectric Project (P-
2459-279).
m. The application is not ready for environmental analysis at this
time.
n. The existing Lake Lynn Project consists of: (1) a 13 mile-long,
1,729-acre impoundment (Lake Lynn) with a maximum storage capacity of
72,300 acre-feet at a normal water surface elevation of 870 feet
National Geodetic Vertical Datum of 1929 (NGVD 29) and a normal minimum
storage capacity of 51,100 acre-feet at 857 feet NGVD 29; (2) a 1,000-
foot-long, 125-foot-high, concrete gravity dam with a 624-foot-long
spillway section controlled by 26, 21-foot-wide by 17-foot-high,
Tainter gates; (3) a concrete intake structure equipped with a log boom
and eight trash racks with 4-inch clear bar spacing; (4) eight 12-foot-
wide by 18-foot-deep gated reinforced concrete penstocks; (5) a 160-
foot-long by 94.5-foot-wide powerhouse containing four Francis
generating units with a combined capacity of 51.2 megawatts; and (6)
two 800-foot-long transmission lines that run from the powerhouse to a
substation within the project boundary.
The Lake Lynn Project is currently operated as a peaking facility
with storage. The hours of peaking vary depending on environmental and
economic considerations. The current license requires Lake Lynn
Generation, LLC to maintain Cheat Lake between 868 feet and 870 feet
NGVD 29 from May 1 through October 31, 857 feet and 870 feet NGVD 29
from November 1 through March 31, and 863 feet and 870 feet NGVD 29
from April 1 through April 30 each year. The current license also
requires Lake Lynn Generation, LLC to release a downstream minimum flow
of 212 cubic-feet-per-second (cfs), or inflow, from the dam when not
generating, with an absolute minimum flow of 100 cfs regardless of
inflow, when not generating. The project generates about 144,741
megawatt-hours annually.
Lake Lynn Generation, LLC proposes to continue operating the
project as a peaking facility with storage, and does not propose any
new development at the project.
o. In addition to publishing the full text of this notice in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this notice, as well
as other documents in the proceeding (e.g., license application) via
the internet through the Commission's Home Page (https://www.ferc.gov),
using the ``eLibrary'' link. Enter the docket number, excluding the
last three digits in the docket number field to access the document (P-
2459). For assistance, contact FERC at [email protected], or
call toll-free, (866) 208-3676, or (202) 502-8659 (TTY).
You may also register online at https://ferconline.ferc.gov/FERCOnline.aspx to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. Procedural schedule and final amendments: The application will
be processed according to the following preliminary schedule. Revisions
to the schedule will be made as appropriate.
[[Page 77100]]
Issue Deficiency Letter (if necessary)--February 2023
Request Additional Information--February 2023
Issue Acceptance Letter--June 2023
Issue Scoping Document 1 for comments--June 2023
Issue Scoping Document 2 (if necessary)--August 2023
Issue Notice of Ready for Environmental Analysis--August 2023
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: December 12, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-27310 Filed 12-15-22; 8:45 am]
BILLING CODE 6717-01-P