Download as PDF 75616 Federal Register / Vol. 87, No. 236 / Friday, December 9, 2022 / Notices Description: § 4(d) Rate Filing: 2022– 12–02 Negotiated Rate Agreement to be effective 12/3/2022. Filed Date: 12/5/22. Accession Number: 20221205–5000. Comment Date: 5 p.m. ET 12/19/22. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. Filings in Existing Proceedings Docket Numbers: RP19–57–005. Applicants: Algonquin Gas Transmission, LLC. Description: Compliance filing: New York Delivery Surcharge Verplank Fire eff 1–1–23 to be effective 1/1/2023. Filed Date: 12/2/22. Accession Number: 20221202–5118. Comment Date: 5 p.m. ET 12/14/22. Any person desiring to protest in any the above proceedings must file in accordance with Rule 211 of the Commission’s Regulations (18 CFR 385.211) on or before 5:00 p.m. Eastern time on the specified comment date. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: December 5, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–26772 Filed 12–8–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission lotter on DSK11XQN23PROD with NOTICES1 [Docket No. CP23–18–000] Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline Take notice that November 21, 2022, Columbia Gas Transmission, LLC (Columbia) filed a prior notice request for authorization, in accordance with 18 VerDate Sep<11>2014 17:50 Dec 08, 2022 Jkt 259001 CFR 157.205 and 157.208 of the Federal Energy Regulatory Commission’s (Commission) regulations under the Natural Gas Act and Columbia’s blanket certificate issued in Docket No. CP83– 76–000 to perform various modifications of the existing 18-inch and 20-inch Line D420 Pipeline in Ohio to enable the in-line inspection or pigging of Line D420. Specifically, Columbia proposes to: (1) install one new 24’’ × 20’’ bi-directional launcher/ receiver station, valves, fitting, and pipe at Mod Point 1 in Sandusky County, Ohio; (2) install one new 24’’ × 20’’ bidirectional launcher/receiver at Mod Point 5 in Sandusky County, Ohio; (3) install one new 24’’ × 18’’ bi-directional launcher/receiver at Mod Point 6 in Lucas County, Ohio; (4) install, replace, and/or remove appurtenances, including valves, stopples, and pipe, at the remaining three (3) Mod Points within Sandusky and Ottawa Counties, Ohio. Columbia estimates that the cost of the project will be about $13 million, all as more fully set forth in the application which is on file with the Commission and open for public inspection. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Any questions concerning this application should be directed to Allison Wells, Legal Counsel, Columbia Gas Transmission, LLC, 700 Louisiana Street, Suite 1300, Houston, Texas 77002–2700 at (832) 320–5376; or email at allison_wells@tcenergy.com. Pursuant to section 157.9 of the Commission’s Rules of Practice and Procedure,1 within 90 days of this Notice the Commission staff will either: complete its environmental review and place it into the Commission’s public record (eLibrary) for this proceeding; or 1 18 PO 00000 CFR (Code of Federal Regulations) 157.9. Frm 00031 Fmt 4703 Sfmt 4703 issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or environmental assessment (EA) for this proposal. The filing of an EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Public Participation There are three ways to become involved in the Commission’s review of this project: you can file a protest to the project, you can file a motion to intervene in the proceeding, and you can file comments on the project. There is no fee or cost for filing protests, motions to intervene, or comments. The deadline for filing protests, motions to intervene, and comments is 5:00 p.m. Eastern Time on January 30, 2023. How to file protests, motions to intervene, and comments is explained below. Protests Pursuant to section 157.205 of the Commission’s regulations under the NGA,2 any person 3 or the Commission’s staff may file a protest to the request. If no protest is filed within the time allowed or if a protest is filed and then withdrawn within 30 days after the allowed time for filing a protest, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request for authorization will be considered by the Commission. Protests must comply with the requirements specified in section 157.205(e) of the Commission’s regulations,4 and must be submitted by the protest deadline, which is January 30, 2023. A protest may also serve as a motion to intervene so long as the protestor states it also seeks to be an intervenor. 2 18 CFR 157.205. include individuals, organizations, businesses, municipalities, and other entities. 18 CFR 385.102(d). 4 18 CFR 157.205(e). 3 Persons E:\FR\FM\09DEN1.SGM 09DEN1 Federal Register / Vol. 87, No. 236 / Friday, December 9, 2022 / Notices Interventions Any person has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission’s orders in the U.S. Circuit Courts of Appeal. To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure 5 and the regulations under the NGA 6 by the intervention deadline for the project, which is January 30, 2023. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https:// www.ferc.gov/how-guides. All timely, unopposed motions to intervene are automatically granted by operation of Rule 214(c)(1). Motions to intervene that are filed after the intervention deadline are untimely and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission’s Rules and Regulations. A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties. lotter on DSK11XQN23PROD with NOTICES1 Comments Any person wishing to comment on the project may do so. The Commission considers all comments received about the project in determining the appropriate action to be taken. To ensure that your comments are timely and properly recorded, please submit your comments on or before January 30, 2023. The filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding. 5 18 6 18 CFR 385.214. CFR 157.10. VerDate Sep<11>2014 17:50 Dec 08, 2022 Jkt 259001 How to File Protests, Interventions, and Comments There are two ways to submit protests, motions to intervene, and comments. In both instances, please reference the Project docket number CP23–18–000 in your submission. (1) You may file your protest, motion to intervene, and comments by using the Commission’s eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select General’’ and then select ‘‘Protest’’, ‘‘Intervention’’, or ‘‘Comment on a Filing’’; or 7 (2) You can file a paper copy of your submission by mailing it to the address below. Your submission must reference the Project docket number CP23–18– 000. To mail via USPS, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426 To mail via any other courier, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852 The Commission encourages electronic filing of submissions (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FERCOnlineSupport@ferc.gov. Protests and motions to intervene must be served on the applicant either by mail or email (with a link to the document) at: Allison Wells, Legal Counsel, Columbia Gas Transmission, LLC, 700 Louisiana Street, Suite 1300, Houston, Texas 77002–2700; or email at allison_wells@tcenergy.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. Tracking the Proceeding Throughout the proceeding, additional information about the project will be available from the Commission’s Office of External Affairs, at (866) 208– FERC, or on the FERC website at 7 Additionally, you may file your comments electronically by using the eComment feature, which is located on the Commission’s website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project. PO 00000 Frm 00032 Fmt 4703 Sfmt 4703 75617 www.ferc.gov using the ‘‘eLibrary’’ link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to https://www.ferc.gov/ferconline/overview. Dated: December 1, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–26844 Filed 12–8–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 15282–000] White Rapids, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications On July 6, 2022, White Rapids, LLC filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Slater Hydroelectric Project No. 15282 (project), to be located on the Blackstone River in Providence County, Rhode Island. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed project would consist of the following: (1) an existing stone masonry dam (Ashton Dam) that includes: (a) an approximately 10-footlong west abutment; (b) an approximately 250-foot-long spillway that would be retrofitted to include a new crest gate; (c) a 25-foot-long, 20-foot high gate structure with two 10-footlong, 10-foot-high openings; (d) a 40foot-long spillway that would be replaced with a new 40-foot-long, 60foot-wide concrete powerhouse that includes two 420-kilowatt Kaplan E:\FR\FM\09DEN1.SGM 09DEN1

Agencies

[Federal Register Volume 87, Number 236 (Friday, December 9, 2022)]
[Notices]
[Pages 75616-75617]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-26844]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP23-18-000]


Columbia Gas Transmission, LLC; Notice of Request Under Blanket 
Authorization and Establishing Intervention and Protest Deadline

    Take notice that November 21, 2022, Columbia Gas Transmission, LLC 
(Columbia) filed a prior notice request for authorization, in 
accordance with 18 CFR 157.205 and 157.208 of the Federal Energy 
Regulatory Commission's (Commission) regulations under the Natural Gas 
Act and Columbia's blanket certificate issued in Docket No. CP83-76-000 
to perform various modifications of the existing 18-inch and 20-inch 
Line D420 Pipeline in Ohio to enable the in-line inspection or pigging 
of Line D420. Specifically, Columbia proposes to: (1) install one new 
24'' x 20'' bi-directional launcher/receiver station, valves, fitting, 
and pipe at Mod Point 1 in Sandusky County, Ohio; (2) install one new 
24'' x 20'' bi-directional launcher/receiver at Mod Point 5 in Sandusky 
County, Ohio; (3) install one new 24'' x 18'' bi-directional launcher/
receiver at Mod Point 6 in Lucas County, Ohio; (4) install, replace, 
and/or remove appurtenances, including valves, stopples, and pipe, at 
the remaining three (3) Mod Points within Sandusky and Ottawa Counties, 
Ohio. Columbia estimates that the cost of the project will be about $13 
million, all as more fully set forth in the application which is on 
file with the Commission and open for public inspection.
    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (https://ferc.gov) using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. At this time, 
the Commission has suspended access to the Commission's Public 
Reference Room, due to the proclamation declaring a National Emergency 
concerning the Novel Coronavirus Disease (COVID-19), issued by the 
President on March 13, 2020. For assistance, contact the Federal Energy 
Regulatory Commission at [email protected] or call toll-free, 
(886) 208-3676 or TYY, (202) 502-8659.
    Any questions concerning this application should be directed to 
Allison Wells, Legal Counsel, Columbia Gas Transmission, LLC, 700 
Louisiana Street, Suite 1300, Houston, Texas 77002-2700 at (832) 320-
5376; or email at [email protected].
    Pursuant to section 157.9 of the Commission's Rules of Practice and 
Procedure,\1\ within 90 days of this Notice the Commission staff will 
either: complete its environmental review and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or environmental 
assessment (EA) for this proposal. The filing of an EA in the 
Commission's public record for this proceeding or the issuance of a 
Notice of Schedule for Environmental Review will serve to notify 
federal and state agencies of the timing for the completion of all 
necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's FEIS or EA.
---------------------------------------------------------------------------

    \1\ 18 CFR (Code of Federal Regulations) 157.9.
---------------------------------------------------------------------------

Public Participation

    There are three ways to become involved in the Commission's review 
of this project: you can file a protest to the project, you can file a 
motion to intervene in the proceeding, and you can file comments on the 
project. There is no fee or cost for filing protests, motions to 
intervene, or comments. The deadline for filing protests, motions to 
intervene, and comments is 5:00 p.m. Eastern Time on January 30, 2023. 
How to file protests, motions to intervene, and comments is explained 
below.

Protests

    Pursuant to section 157.205 of the Commission's regulations under 
the NGA,\2\ any person \3\ or the Commission's staff may file a protest 
to the request. If no protest is filed within the time allowed or if a 
protest is filed and then withdrawn within 30 days after the allowed 
time for filing a protest, the proposed activity shall be deemed to be 
authorized effective the day after the time allowed for protest. If a 
protest is filed and not withdrawn within 30 days after the time 
allowed for filing a protest, the instant request for authorization 
will be considered by the Commission.
---------------------------------------------------------------------------

    \2\ 18 CFR 157.205.
    \3\ Persons include individuals, organizations, businesses, 
municipalities, and other entities. 18 CFR 385.102(d).
---------------------------------------------------------------------------

    Protests must comply with the requirements specified in section 
157.205(e) of the Commission's regulations,\4\ and must be submitted by 
the protest deadline, which is January 30, 2023. A protest may also 
serve as a motion to intervene so long as the protestor states it also 
seeks to be an intervenor.
---------------------------------------------------------------------------

    \4\ 18 CFR 157.205(e).

---------------------------------------------------------------------------

[[Page 75617]]

Interventions

    Any person has the option to file a motion to intervene in this 
proceeding. Only intervenors have the right to request rehearing of 
Commission orders issued in this proceeding and to subsequently 
challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
    To intervene, you must submit a motion to intervene to the 
Commission in accordance with Rule 214 of the Commission's Rules of 
Practice and Procedure \5\ and the regulations under the NGA \6\ by the 
intervention deadline for the project, which is January 30, 2023. As 
described further in Rule 214, your motion to intervene must state, to 
the extent known, your position regarding the proceeding, as well as 
your interest in the proceeding. For an individual, this could include 
your status as a landowner, ratepayer, resident of an impacted 
community, or recreationist. You do not need to have property directly 
impacted by the project in order to intervene. For more information 
about motions to intervene, refer to the FERC website at https://www.ferc.gov/how-guides.
---------------------------------------------------------------------------

    \5\ 18 CFR 385.214.
    \6\ 18 CFR 157.10.
---------------------------------------------------------------------------

    All timely, unopposed motions to intervene are automatically 
granted by operation of Rule 214(c)(1). Motions to intervene that are 
filed after the intervention deadline are untimely and may be denied. 
Any late-filed motion to intervene must show good cause for being late 
and must explain why the time limitation should be waived and provide 
justification by reference to factors set forth in Rule 214(d) of the 
Commission's Rules and Regulations. A person obtaining party status 
will be placed on the service list maintained by the Secretary of the 
Commission and will receive copies (paper or electronic) of all 
documents filed by the applicant and by all other parties.

Comments

    Any person wishing to comment on the project may do so. The 
Commission considers all comments received about the project in 
determining the appropriate action to be taken. To ensure that your 
comments are timely and properly recorded, please submit your comments 
on or before January 30, 2023. The filing of a comment alone will not 
serve to make the filer a party to the proceeding. To become a party, 
you must intervene in the proceeding.

How to File Protests, Interventions, and Comments

    There are two ways to submit protests, motions to intervene, and 
comments. In both instances, please reference the Project docket number 
CP23-18-000 in your submission.
    (1) You may file your protest, motion to intervene, and comments by 
using the Commission's eFiling feature, which is located on the 
Commission's website (www.ferc.gov) under the link to Documents and 
Filings. New eFiling users must first create an account by clicking on 
``eRegister.'' You will be asked to select the type of filing you are 
making; first select General'' and then select ``Protest'', 
``Intervention'', or ``Comment on a Filing''; or \7\
---------------------------------------------------------------------------

    \7\ Additionally, you may file your comments electronically by 
using the eComment feature, which is located on the Commission's 
website at www.ferc.gov under the link to Documents and Filings. 
Using eComment is an easy method for interested persons to submit 
brief, text-only comments on a project.
---------------------------------------------------------------------------

    (2) You can file a paper copy of your submission by mailing it to 
the address below. Your submission must reference the Project docket 
number CP23-18-000.

To mail via USPS, use the following address: Kimberly D. Bose, 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426
To mail via any other courier, use the following address: Kimberly D. 
Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins 
Avenue, Rockville, Maryland 20852

    The Commission encourages electronic filing of submissions (option 
1 above) and has eFiling staff available to assist you at (202) 502-
8258 or [email protected].
    Protests and motions to intervene must be served on the applicant 
either by mail or email (with a link to the document) at: Allison 
Wells, Legal Counsel, Columbia Gas Transmission, LLC, 700 Louisiana 
Street, Suite 1300, Houston, Texas 77002-2700; or email at 
[email protected]. Any subsequent submissions by an intervenor 
must be served on the applicant and all other parties to the 
proceeding. Contact information for parties can be downloaded from the 
service list at the eService link on FERC Online.

Tracking the Proceeding

    Throughout the proceeding, additional information about the project 
will be available from the Commission's Office of External Affairs, at 
(866) 208-FERC, or on the FERC website at www.ferc.gov using the 
``eLibrary'' link as described above. The eLibrary link also provides 
access to the texts of all formal documents issued by the Commission, 
such as orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. For more information and to register, go to https://www.ferc.gov/ferc-online/overview.

    Dated: December 1, 2022.
Kimberly D. Bose,
Secretary.