Georgia Power Company; Notice of Availability of Environmental Assessment, 75618-75619 [2022-26841]
Download as PDF
lotter on DSK11XQN23PROD with NOTICES1
75618
Federal Register / Vol. 87, No. 236 / Friday, December 9, 2022 / Notices
turbine-generator units; and (e) an
approximately 10-foot-long east
abutment; (2) an existing impoundment
with a surface area of 35 acres at an
elevation of 74.0 feet national geodetic
vertical datum of 1929; (3) a new intake
structure with a 70- to 100-foot-long
angled trashrack with 0.75-inch clear
bar spacing; (4) two new 10-foot-long,
10-foot-high steel headgates; (5) a new
40-foot-long, 60-foot-wide tailrace; (6) a
new 850-foot-long, 13.8-kilovolt
transmission line connecting the
turbine-generator units to the regional
grid; and (7) appurtenant facilities. The
estimated annual generation of the
Slater Hydroelectric Project would be
3,500 megawatt-hours.
Applicant Contact: Mr. William Fay,
White Rapids, LLC, 4145 Church Street,
P.O. Box 193, Palmer, Massachusetts
01079; phone: (413) 362–5410; email:
fayengineeringservices@gmail.com.
FERC Contact: Erin Kimsey; phone:
(202) 502–8621; email: Erin.Kimsey@
ferc.gov.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
ferconline.ferc.gov/eFiling.aspx.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://ferconline.ferc.gov/
QuickComment.aspx. You must include
your name and contact information at
the end of your comments. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, you may submit a
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852. The first page of any filing
should include docket number P–
15282–000.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
VerDate Sep<11>2014
17:50 Dec 08, 2022
Jkt 259001
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support.
Dated: December 5, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–26774 Filed 12–8–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13–042]
Green Island Power Authority; Albany
Engineering Corporation; Notice of
Application for Partial Transfer of
License and Soliciting Comments,
Motions To Intervene, and Protests
On October 21, 2022, Green Island
Power Authority (transferor) and Albany
Engineering Corporation (transferee) colicensees for the Green Island
Hydroelectric Project No. 13, filed
jointly an application for a partial
transfer of license. The project is located
at the U.S. Army Corps of Engineers
(Corps) Green Island-Troy Lock and
Dam on the Hudson River, in Albany
County, New York. The project occupies
federal land under the jurisdiction of
the Corps.1
The applicants seek Commission
approval to partially transfer the license
for the Green Island Hydroelectric
Project from the Green Island Power
Authority and Albany Engineering
Power Corporation as co-licensees to
Albany Engineering Corporation as the
sole licensee.
Applicants Contact: For the
transferor: Ms. Kristin Swinton, Green
Island Power Authority, 69 Hudson
Avenue, Green Island, NY 12183,
Phone: (518) 271–9397, Email: kristin@
greenislandpowerauthority.com.
For the transferee: Mr. James A.
Besha, P.E., and Ms. Wendy Jo Carey,
P.E., Albany Engineering Corporation, 5
Washington Square, Albany, NY 12205,
Phone: (518) 456–7712, Emails: jim@
albanyengineering.com wendy@
albanyengineering.com.
FERC Contact: Anumzziatta
Purchiaroni, Phone: (202) 502–6191,
Email: Anumzziatta.purchiaroni@
ferc.gov.
1 Green Island Power Authority, 140 FERC
¶ 62,133 (2012).
PO 00000
Frm 00033
Fmt 4703
Sfmt 4703
Deadline for filing comments, motions
to intervene, and protests: 30 days from
the date that the Commission issues this
notice. The Commission strongly
encourages electronic filing. Please file
comments, motions to intervene, and
protests using the Commission’s eFiling
system at https://www.ferc.gov/docsfiling/efiling.asp. Commenters can
submit brief comments up to 6,000
characters, without prior registration,
using the eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY).
In lieu of electronic filing, you may
submit a paper copy. Submissions sent
via U.S. Postal Service must be
addressed to, Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to, Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. The first
page of any filing should include docket
number P–13–042. Comments emailed
to Commission staff are not considered
part of the Commission record.
Dated: December 1, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–26842 Filed 12–8–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2354–152]
Georgia Power Company; Notice of
Availability of Environmental
Assessment
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s (Commission)
regulations, 18 CFR part 380, the Office
of Energy Projects has reviewed the
application for a non-capacity
amendment of license for the North
Georgia Project and has prepared an
Environmental Assessment (EA). The
licensee proposes to amend the license
to replace and upgrade four generating
units in the Tugalo powerhouse. The
licensee proposes at the Tugalo
Development to: remove all turbine
E:\FR\FM\09DEN1.SGM
09DEN1
75619
Federal Register / Vol. 87, No. 236 / Friday, December 9, 2022 / Notices
components to refurbish and upgrade,
replace the existing generators, replace
control panels and instrumentation in
the control room, balance plant
electrical and mechanical systems,
upgrade the cooling system, and replace
the spillway gates and trash racks. The
project is located in the Savannah River
basin on the Tallulah, Chattooga, and
Tugalo rivers, in Rabun, Habersham,
and Stephens counties, Georgia, and
Oconee County, South Carolina. The
project does not occupy federal lands.
The EA contains Commission staff’s
analysis of the potential environmental
effects of the proposed amendment and
concludes that, it would not constitute
a major federal action that would
significantly affect the quality of the
human environment.
The Commission provides all
interested persons with an opportunity
to view and/or print the EA via the
internet through the Commission’s
Home Page (https://www.ferc.gov) using
the ‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits
in the docket number field, to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@ferc.gov or tollfree at (866) 208–3676, or for TTY, (202)
502–8659.
You may also register online at
https://ferconline.ferc.gov/
eSubscription.aspx to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
Any comments should be filed within
30 days from the date of this notice. The
Commission strongly encourages
electronic filing. Please file comments
using the Commission’s eFiling system
at https://ferconline.ferc.gov/eFiling.
aspx. Commenters can submit brief
comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
ferconline.ferc.gov/QuickComment.
aspx. You must include your name and
contact information at the end of your
comments. For assistance, please
contact FERC Online Support. In lieu of
electronic filings, you may submit a
paper copy. Submissions sent via the
U.S. Postal Service must be addressed
to: Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington,
DC 20426. Submissions sent via any
other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 12225
Wilkins Avenue, Rockville, Maryland
20852. The first page of any filing
should include docket number P–2354–
152.
For further information, contact
Aneela Mousam at (202) 502–8357 or
aneela.mousam@ferc.gov.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–26841 Filed 12–8–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Effectiveness of Exempt
Wholesale Generator and Foreign
Utility Company Status
Docket Nos.
Eastover Solar LLC ..........................................................................................................................................................................
PGR 2021 Lessee 17, LLC ..............................................................................................................................................................
Yellow Pine Solar, LLC .....................................................................................................................................................................
Mesquite Solar 4, LLC ......................................................................................................................................................................
Mesquite Solar 5, LLC ......................................................................................................................................................................
Fall River Solar, LLC ........................................................................................................................................................................
DLS—Jean Duluth Project Co, LLC .................................................................................................................................................
DLS—Laskin Project Co, LLC ..........................................................................................................................................................
DLS—Sylvan Project Co, LLC ..........................................................................................................................................................
GulfStar Power, LLC .........................................................................................................................................................................
Yellowbud Solar, LLC .......................................................................................................................................................................
Jicarilla Solar 1 LLC .........................................................................................................................................................................
Jicarilla Storage 1 LLC .....................................................................................................................................................................
Colice Hall Solar, LLC ......................................................................................................................................................................
I Squared Capital ..............................................................................................................................................................................
Take notice that during the month of
November 2022, the status of the abovecaptioned entities as Exempt Wholesale
Generators or Foreign Utility Companies
became effective by operation of the
Commission’s regulations. 18 CFR
366.7(a) (2021).
Dated: December 1, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–26843 Filed 12–8–22; 8:45 am]
lotter on DSK11XQN23PROD with NOTICES1
BILLING CODE 6717–01–P
VerDate Sep<11>2014
17:50 Dec 08, 2022
Jkt 259001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER21–2698–000.
Applicants: Portland General Electric
Company.
Description: Puget Sound Energy, Inc.
submits Average System Cost Rate
Filing for Sales of Electric Power to the
Bonneville Power Administration, FY
2024–2025.
Filed Date: 12/1/22.
Accession Number: 20221201–5315.
Comment Date: 5 p.m. ET 12/22/22.
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
EG22–215–000
EG22–216–000
EG22–217–000
EG22–218–000
EG22–219–000
EG22–220–000
EG22–221–000
EG22–222–000
EG22–223–000
EG22–224–000
EG22–225–000
EG22–226–000
EG22–227–000
EG22–228–000
FC22–3–000
Docket Numbers: ER22–2344–001.
Applicants: Southwest Power Pool,
Inc.
Description: Tariff Amendment:
Deficiency Response—Storage Facilities
as Transmission Only Assets to be
effective 12/31/9998.
Filed Date: 12/2/22.
Accession Number: 20221202–5142.
Comment Date: 5 p.m. ET 12/23/22.
Docket Numbers: ER23–557–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Revisions to OATT & OA on Emission
Adders and Calculation of Cost-Based
Offers to be effective 2/1/2023.
Filed Date: 12/2/22.
Accession Number: 20221202–5123.
Comment Date: 5 p.m. ET 12/23/22.
Docket Numbers: ER23–558–000.
E:\FR\FM\09DEN1.SGM
09DEN1
Agencies
[Federal Register Volume 87, Number 236 (Friday, December 9, 2022)]
[Notices]
[Pages 75618-75619]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-26841]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2354-152]
Georgia Power Company; Notice of Availability of Environmental
Assessment
In accordance with the National Environmental Policy Act of 1969
and the Federal Energy Regulatory Commission's (Commission)
regulations, 18 CFR part 380, the Office of Energy Projects has
reviewed the application for a non-capacity amendment of license for
the North Georgia Project and has prepared an Environmental Assessment
(EA). The licensee proposes to amend the license to replace and upgrade
four generating units in the Tugalo powerhouse. The licensee proposes
at the Tugalo Development to: remove all turbine
[[Page 75619]]
components to refurbish and upgrade, replace the existing generators,
replace control panels and instrumentation in the control room, balance
plant electrical and mechanical systems, upgrade the cooling system,
and replace the spillway gates and trash racks. The project is located
in the Savannah River basin on the Tallulah, Chattooga, and Tugalo
rivers, in Rabun, Habersham, and Stephens counties, Georgia, and Oconee
County, South Carolina. The project does not occupy federal lands.
The EA contains Commission staff's analysis of the potential
environmental effects of the proposed amendment and concludes that, it
would not constitute a major federal action that would significantly
affect the quality of the human environment.
The Commission provides all interested persons with an opportunity
to view and/or print the EA via the internet through the Commission's
Home Page (https://www.ferc.gov) using the ``eLibrary'' link. Enter the
docket number, excluding the last three digits in the docket number
field, to access the document. For assistance, contact FERC Online
Support at [email protected] or toll-free at (866) 208-3676,
or for TTY, (202) 502-8659.
You may also register online at https://ferconline.ferc.gov/eSubscription.aspx to be notified via email of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
Any comments should be filed within 30 days from the date of this
notice. The Commission strongly encourages electronic filing. Please
file comments using the Commission's eFiling system at https://ferconline.ferc.gov/eFiling.aspx. Commenters can submit brief comments
up to 6,000 characters, without prior registration, using the eComment
system at https://ferconline.ferc.gov/QuickComment.aspx. You must
include your name and contact information at the end of your comments.
For assistance, please contact FERC Online Support. In lieu of
electronic filings, you may submit a paper copy. Submissions sent via
the U.S. Postal Service must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street NE,
Room 1A, Washington, DC 20426. Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852.
The first page of any filing should include docket number P-2354-152.
For further information, contact Aneela Mousam at (202) 502-8357 or
[email protected].
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-26841 Filed 12-8-22; 8:45 am]