Watson Associates; Notice of Intent To Prepare an Environmental Assessment, 68480 [2022-24817]

Download as PDF 68480 Federal Register / Vol. 87, No. 219 / Tuesday, November 15, 2022 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. IN12–17–000] Total Gas & Power North America, Aaron Hall and Therese Tran; Updated Notice of Designation of Commission Staff as Non-Decisional With respect to an order issued by the Commission on April 28, 2016 in the above-captioned docket,1 with the exceptions noted below, the staff of the Office of Enforcement are designated as non-decisional in deliberations by the Commission in this docket. Accordingly, pursuant to 18 CFR 385.2202 (2022), they will not serve as advisors to the Commission or take part in the Commission’s review of any offer of settlement. Likewise, as nondecisional staff, pursuant to 18 CFR 385.2201 (2022), they are prohibited from communicating with advisory staff concerning any deliberations in this docket. Exceptions to this designation as nondecisional are: Ruedi Aebersold Jeffrey Fang Martin Lawera Eric Primosch Felice Richter Derek Shiau Nicholas Stavlas Ambrea Watts Mehrdad Barikbin Samantha Maurer David Zlotnick Sheryl Caro Serrita Hill Milestone Commission issues EA. Comments on EA ...... Target date May 2023.1 June 2023. Any questions regarding this notice may be directed to Michael Watts at (202) 502–6123 or michael.watts@ ferc.gov. Dated: November 8, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–24817 Filed 11–14–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Debbie-Anne A. Reese, Deputy Secretary. Federal Energy Regulatory Commission [FR Doc. 2022–24835 Filed 11–14–22; 8:45 am] [Docket No. IC22–33–000] BILLING CODE 6717–01–P Commission Information Collection Activities (FERC–547); Comment Request; Extension DEPARTMENT OF ENERGY Federal Energy Regulatory Commission, DOE. ACTION: Notice of information collection and request for comments. AGENCY: Federal Energy Regulatory Commission [Project No. 6240–064] Watson Associates; Notice of Intent To Prepare an Environmental Assessment lotter on DSK11XQN23PROD with NOTICES1 In accordance with the Commission’s regulations, on August 23, 2022, Commission staff issued a notice that the project was ready for environmental analysis (REA Notice). Based on the information in the record, including comments filed on the REA Notice, staff does not anticipate that licensing the project would constitute a major federal action significantly affecting the quality of the human environment. Therefore, staff intends to prepare an Environmental Assessment (EA) on the application to relicense the project. The EA will be issued and circulated for review by all interested parties. All comments filed on the EA will be analyzed by staff and considered in the Commission’s final licensing decision. The application will be processed according to the following schedule. Revisions to the schedule may be made as appropriate. On August 27, 2021, Watson Associates filed a relicense application for the 265-kilowatt Watson Dam Hydroelectric Project No. 6240 (project). The project is located on the Cocheco River in Strafford County, New Hampshire. The project does not occupy federal land. 1 Total Gas & Power North America, Aaron Hall and Therese Tran, 155 FERC ¶ 61,105 (2016). VerDate Sep<11>2014 19:16 Nov 14, 2022 Jkt 259001 In compliance with the requirements of the Paperwork Reduction Act of 1995, the Federal Energy Regulatory Commission (Commission or FERC) is soliciting SUMMARY: 1 The Council on Environmental Quality’s (CEQ) regulations under 40 CFR 1501.10(b)(1) require that EAs be completed within 1 year of the federal action agency’s decision to prepare an EA. This notice establishes the Commission’s intent to prepare an EA for the Watson Dam Hydroelectric Project. Therefore, in accordance with CEQ’s regulations, the EA must be issued within 1 year of the issuance date of this notice. PO 00000 Frm 00044 Fmt 4703 Sfmt 4703 public comment on the currently approved information collection, FERC– 547 (Gas Pipeline Rates: Refund Report Requirements), which will be submitted to the Office of Management and Budget (OMB) for review. DATES: Comments on the collection of information are due December 15, 2022. ADDRESSES: Send written comments on FERC–547 to the Office of Management and Budget (OMB) through www.reginfo.gov/public/do/PRAMain, Attention: Federal Energy Regulatory Commission Desk Officer. Please identify the OMB Control Number 1902–0084 (Gas Pipeline Rates: Refund Report Requirements) in the subject line. Your comments should be sent within 30 days of publication of this notice in the Federal Register. Please submit copies of your comments (identified by Docket No. IC22–33–000 and FERC–547) to the Commission as noted below. Electronic filing through https://www.ferc.gov is preferred. • Electronic Filing: Documents must be filed in acceptable native applications and print-to-PDF, but not in scanned or picture format. • For those unable to file electronically, comments may be filed by USPS mail or by hand (including courier) delivery: D Mail via U.S. Postal Service only, addressed to: Federal Energy Regulatory Commission, Secretary of the Commission, 888 First Street NE, Washington, DC 20426. D Hand (including courier) delivery to: Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, MD 20852. Please reference the specific collection number(s) (FERC–547) and/or title(s) (Gas Pipeline Rates: Refund Report Requirements) in your comments. Instructions: OMB submissions must be formatted and filed in accordance with submission guidelines at: www.reginfo.gov/public/do/PRAMain. Using the search function under the ‘‘Currently Under Review field,’’ select ‘‘Federal Energy Regulatory Commission,’’ click ‘‘submit,’’ and select ‘‘comment’’ to the right of the subject collection. FERC submissions must be formatted and filed in accordance with submission guidelines at: https://www.ferc.gov. For user assistance, contact FERC Online Support by email at ferconlinesupport@ ferc.gov, or by phone at (866) 208–3676 (toll-free). Docket: Users interested in receiving automatic notification of activity in this docket or in viewing/downloading E:\FR\FM\15NON1.SGM 15NON1

Agencies

[Federal Register Volume 87, Number 219 (Tuesday, November 15, 2022)]
[Notices]
[Page 68480]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-24817]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 6240-064]


Watson Associates; Notice of Intent To Prepare an Environmental 
Assessment

    On August 27, 2021, Watson Associates filed a relicense application 
for the 265-kilowatt Watson Dam Hydroelectric Project No. 6240 
(project). The project is located on the Cocheco River in Strafford 
County, New Hampshire. The project does not occupy federal land.
    In accordance with the Commission's regulations, on August 23, 
2022, Commission staff issued a notice that the project was ready for 
environmental analysis (REA Notice). Based on the information in the 
record, including comments filed on the REA Notice, staff does not 
anticipate that licensing the project would constitute a major federal 
action significantly affecting the quality of the human environment. 
Therefore, staff intends to prepare an Environmental Assessment (EA) on 
the application to relicense the project.
    The EA will be issued and circulated for review by all interested 
parties. All comments filed on the EA will be analyzed by staff and 
considered in the Commission's final licensing decision.
    The application will be processed according to the following 
schedule. Revisions to the schedule may be made as appropriate.
---------------------------------------------------------------------------

    \1\ The Council on Environmental Quality's (CEQ) regulations 
under 40 CFR 1501.10(b)(1) require that EAs be completed within 1 
year of the federal action agency's decision to prepare an EA. This 
notice establishes the Commission's intent to prepare an EA for the 
Watson Dam Hydroelectric Project. Therefore, in accordance with 
CEQ's regulations, the EA must be issued within 1 year of the 
issuance date of this notice.

------------------------------------------------------------------------
                 Milestone                           Target date
------------------------------------------------------------------------
Commission issues EA......................  May 2023.\1\
Comments on EA............................  June 2023.
------------------------------------------------------------------------

    Any questions regarding this notice may be directed to Michael 
Watts at (202) 502-6123 or [email protected].

    Dated: November 8, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-24817 Filed 11-14-22; 8:45 am]