Mojave Pipeline Company, L.L.C.; Notice of Request for Extension of Time, 67892 [2022-24536]
Download as PDF
67892
Federal Register / Vol. 87, No. 217 / Thursday, November 10, 2022 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP21–495–000]
Mojave Pipeline Company, L.L.C.;
Notice of Request for Extension of
Time
lotter on DSK11XQN23PROD with NOTICES1
Take notice that on November 3,
2022, Mojave Pipeline Company, L.L.C.
(Mojave) requested that the Federal
Energy Regulatory Commission
(Commission) grant an extension of time
until December 31, 2022, to complete
construction of its Oak Creek Delivery
Point Project (Project) located in Kern
County, California. Mojave requested
authorization to construct its Project in
a prior notice application filed on
September 13, 2021. Since no protests
were filed within the comment period,
Mojave’s Project was deemed to be
authorized on November 23, 2022.1
Mojave initially anticipated beginning
construction by the end of 2021 once
CalPortand Company (CalPortland) had
obtained all necessary permits in order
to construct and place the new delivery
point into service by January 31, 2022.2
However, due to delays in CalPortland
receiving its necessary permits,
construction on the project did not
begin until October 4, 2022. Since
construction commenced, the planned
construction sequencing first requires
the installation of CalPortland’s meter
station and related connecting lateral to
Mojave’s existing tap site followed by
Mojave’s construction activities. Mojave
anticipates this construction plan will
likely push the completion of the
Mojave Project until December 31, 2022.
This notice establishes a 15-calendar
day intervention and comment period
deadline. Any person wishing to
comment on Mojave’s request for an
extension of time may do so. No reply
comments or answers will be
considered. If you wish to obtain legal
status by becoming a party to the
proceedings for this request, you
should, on or before the comment date
stated below, file a motion to intervene
in accordance with the requirements of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
1 Consistent with Section 157.206(c) of the
Commission’s regulations, Project activities must be
completed one year from the date of authorization,
i.e., November 23, 2022.
2 As described in Mojave’s application, the
Project involves two components: (1) minor work
associated with preparing an existing Mojave tap
that will be tied into a new CalPortland lateral; and
(2) installation of electronic gas measurement
equipment to be located within a new CalPortandowned meter station.
VerDate Sep<11>2014
17:43 Nov 09, 2022
Jkt 259001
and the Regulations under the Natural
Gas Act (18 CFR 157.10).
As a matter of practice, the
Commission itself generally acts on
requests for extensions of time to
complete construction for Natural Gas
Act facilities when such requests are
contested before order issuance. For
those extension requests that are
contested,3 the Commission will aim to
issue an order acting on the request
within 45 days.4 The Commission will
address all arguments relating to
whether the applicant has demonstrated
there is good cause to grant the
extension.5 The Commission will not
consider arguments that re-litigate the
issuance of the certificate order,
including whether the Commission
properly found the project to be in the
public convenience and necessity and
whether the Commission’s
environmental analysis for the
certificate complied with the National
Environmental Policy Act.6 At the time
a pipeline requests an extension of time,
orders on certificates of public
convenience and necessity are final and
the Commission will not re-litigate their
issuance.7 The OEP Director, or his or
her designee, will act on all of those
extension requests that are uncontested.
In addition to publishing the full text
of this document in the Federal
Register, The Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
The Commission strongly encourages
electronic filings of comments, protests
3 Contested proceedings are those where an
intervenor disputes any material issue of the filing.
18 CFR 385.2201(c)(1) (2019).
4 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
5 Id. at P 40.
6 Similarly, the Commission will not re-litigate
the issuance of an NGA section 3 authorization,
including whether a proposed project is not
inconsistent with the public interest and whether
the Commission’s environmental analysis for the
permit order complied with NEPA.
7 Algonquin Gas Transmission, LLC, 170 FERC
¶ 61,144, at P 40 (2020).
PO 00000
Frm 00038
Fmt 4703
Sfmt 4703
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and three copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426.
Comment Date: 5 p.m. Eastern Time
on November 21, 2022.
Dated: November 4, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–24536 Filed 11–9–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG23–21–000.
Applicants: Sandy Ridge Wind 2,
LLC.
Description: Sandy Ridge Wind 2,
LLC submits Notice of Self-Certification
of Exempt Wholesale Generator Status.
Filed Date: 11/4/22.
Accession Number: 20221104–5112.
Comment Date: 5 p.m. ET 11/25/22.
Docket Numbers: EG23–22–000.
Applicants: Sandy Ridge Transco
Interconnection, LLC.
Description: Sandy Ridge Transco
Interconnection, LLC submits Notice of
Self-Certification of Exempt Wholesale
Generator Status.
Filed Date: 11/4/22.
Accession Number: 20221104–5113.
Comment Date: 5 p.m. ET 11/25/22.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER22–1728–003.
Applicants: Basin Electric Power
Cooperative.
Description: Compliance filing: Basin
Electric Submission of Compliance
Filing, Docket No. ER22–1728–002 to be
effective 4/30/2022.
Filed Date: 11/4/22.
Accession Number: 20221104–5022.
Comment Date: 5 p.m. ET 11/25/22.
Docket Numbers: ER23–1–001.
Applicants: ITC Midwest LLC,
Interstate Power and Light Company.
Description: Tariff Amendment:
Interstate Power and Light Company
submits tariff filing per 35.17(b):
Amendment to O&T Agreement Exhibits
and Appendices Update (2022) to be
effective 12/2/2022.
E:\FR\FM\10NON1.SGM
10NON1
Agencies
[Federal Register Volume 87, Number 217 (Thursday, November 10, 2022)]
[Notices]
[Page 67892]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-24536]
[[Page 67892]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP21-495-000]
Mojave Pipeline Company, L.L.C.; Notice of Request for Extension
of Time
Take notice that on November 3, 2022, Mojave Pipeline Company,
L.L.C. (Mojave) requested that the Federal Energy Regulatory Commission
(Commission) grant an extension of time until December 31, 2022, to
complete construction of its Oak Creek Delivery Point Project (Project)
located in Kern County, California. Mojave requested authorization to
construct its Project in a prior notice application filed on September
13, 2021. Since no protests were filed within the comment period,
Mojave's Project was deemed to be authorized on November 23, 2022.\1\
---------------------------------------------------------------------------
\1\ Consistent with Section 157.206(c) of the Commission's
regulations, Project activities must be completed one year from the
date of authorization, i.e., November 23, 2022.
---------------------------------------------------------------------------
Mojave initially anticipated beginning construction by the end of
2021 once CalPortand Company (CalPortland) had obtained all necessary
permits in order to construct and place the new delivery point into
service by January 31, 2022.\2\ However, due to delays in CalPortland
receiving its necessary permits, construction on the project did not
begin until October 4, 2022. Since construction commenced, the planned
construction sequencing first requires the installation of
CalPortland's meter station and related connecting lateral to Mojave's
existing tap site followed by Mojave's construction activities. Mojave
anticipates this construction plan will likely push the completion of
the Mojave Project until December 31, 2022.
---------------------------------------------------------------------------
\2\ As described in Mojave's application, the Project involves
two components: (1) minor work associated with preparing an existing
Mojave tap that will be tied into a new CalPortland lateral; and (2)
installation of electronic gas measurement equipment to be located
within a new CalPortand-owned meter station.
---------------------------------------------------------------------------
This notice establishes a 15-calendar day intervention and comment
period deadline. Any person wishing to comment on Mojave's request for
an extension of time may do so. No reply comments or answers will be
considered. If you wish to obtain legal status by becoming a party to
the proceedings for this request, you should, on or before the comment
date stated below, file a motion to intervene in accordance with the
requirements of the Commission's Rules of Practice and Procedure (18
CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act
(18 CFR 157.10).
As a matter of practice, the Commission itself generally acts on
requests for extensions of time to complete construction for Natural
Gas Act facilities when such requests are contested before order
issuance. For those extension requests that are contested,\3\ the
Commission will aim to issue an order acting on the request within 45
days.\4\ The Commission will address all arguments relating to whether
the applicant has demonstrated there is good cause to grant the
extension.\5\ The Commission will not consider arguments that re-
litigate the issuance of the certificate order, including whether the
Commission properly found the project to be in the public convenience
and necessity and whether the Commission's environmental analysis for
the certificate complied with the National Environmental Policy Act.\6\
At the time a pipeline requests an extension of time, orders on
certificates of public convenience and necessity are final and the
Commission will not re-litigate their issuance.\7\ The OEP Director, or
his or her designee, will act on all of those extension requests that
are uncontested.
---------------------------------------------------------------------------
\3\ Contested proceedings are those where an intervenor disputes
any material issue of the filing. 18 CFR 385.2201(c)(1) (2019).
\4\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40
(2020).
\5\ Id. at P 40.
\6\ Similarly, the Commission will not re-litigate the issuance
of an NGA section 3 authorization, including whether a proposed
project is not inconsistent with the public interest and whether the
Commission's environmental analysis for the permit order complied
with NEPA.
\7\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40
(2020).
---------------------------------------------------------------------------
In addition to publishing the full text of this document in the
Federal Register, The Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (https://www.ferc.gov) using
the ``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to Commission's Public Reference
Room, due to the proclamation declaring a National Emergency concerning
the Novel Coronavirus Disease (COVID-19), issued by the President on
March 13, 2020. For assistance, contact FERC at
[email protected] or call toll-free, (886) 208-3676 or TYY,
(202) 502-8659.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at https://www.ferc.gov. Persons unable to file electronically should
submit an original and three copies of the protest or intervention to
the Federal Energy Regulatory Commission, 888 First Street NE,
Washington, DC 20426.
Comment Date: 5 p.m. Eastern Time on November 21, 2022.
Dated: November 4, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-24536 Filed 11-9-22; 8:45 am]
BILLING CODE 6717-01-P