Ketchikan Public Utilities; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments, 67468-67469 [2022-24347]
Download as PDF
lotter on DSK11XQN23PROD with NOTICES1
67468
Federal Register / Vol. 87, No. 215 / Tuesday, November 8, 2022 / Notices
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. The first
page of any filing should include the
docket number P–201–033. Comments
emailed to Commission staff are not
considered part of the Commission
record.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. Description of Request: The
licensee proposes to replace and
refurbish project equipment which
would require an amendment to the
license to update the project description
(Exhibit A), Exhibit F drawings, and the
Article 404 Flow Continuation Plan to
reflect the proposed project
modifications and describe the method
for delivering water to the Crystal Lake
Hatchery during an extended project
outage. The licensee proposes to replace
generating equipment (Unit 3) and to
decommission Units 1 and 2. The
project currently consists of two
powerhouses containing generating
units with rated capacities of 1,600
kilowatts (kW) and 400 kW. The
upgraded project generating equipment
would consist of a new turbine
generator with a rated capacity of 1,822
kW and the generating unit would be
housed in a single powerhouse (Unit 3).
The second powerhouse and its
generating equipment (Unit 1 and 2)
would be decommissioned. The
applicant states the major generating
equipment (turbine, generator, and
governor) is reaching the end of its
service life and needs replacement.
Additionally, the penstock leading to
the primary powerhouse that would be
used to house the upgraded generating
equipment requires repairs to provide
extended service life. The proposed
changes to the generating equipment
would result in an increase in the
maximum hydraulic capacity of less
than 15 percent and an increase in
VerDate Sep<11>2014
16:56 Nov 07, 2022
Jkt 259001
name-plate capacity of less than 2
megawatts.
l. Locations of the Application: This
filing may be viewed on the
Commission’s website at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. You may
also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. Agencies may
obtain copies of the application directly
from the applicant.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214,
respectively. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
o. Filing and Service of Documents:
Any filing must (1) bear in all capital
letters the title ‘‘COMMENTS’’,
‘‘PROTEST’’, or ‘‘MOTION TO
INTERVENE’’ as applicable; (2) set forth
in the heading the name of the applicant
and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
commenting, protesting or intervening;
and (4) otherwise comply with the
requirements of 18 CFR 385.2001
through 385.2005. All comments,
motions to intervene, or protests must
set forth their evidentiary basis. Any
filing made by an intervenor must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
385.2010.
Dated: November 1, 2022.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2022–24277 Filed 11–7–22; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00033
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 1922–052]
Ketchikan Public Utilities; Notice of
Application Tendered for Filing With
the Commission and Soliciting
Additional Study Requests and
Establishing Procedural Schedule for
Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
Minor License.
b. Project No.: 1922–052.
c. Date filed: October 27, 2022.
d. Applicant: Ketchikan Public
Utilities (KPU).
e. Name of Project: Beaver Falls
Hydroelectric Project (project).
f. Location: On Beaver Falls Creek in
Ketchikan Gateway Borough, Alaska.
The project occupies 478.4 acres of
United States lands administered by
U.S. Forest Service.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Jennifer
Holstrom, Senior Project Engineer,
Ketchikan Public Utilities, 1065 Fair
Street, Ketchikan, Alaska 99901; (907)
228–4733; or email at jenniferh@ktnak.us.
i. FERC Contact: Kristen Sinclair at
(202) 502–6587, or kristen.sinclair@
ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
E:\FR\FM\08NON1.SGM
08NON1
Federal Register / Vol. 87, No. 215 / Tuesday, November 8, 2022 / Notices
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: December 26, 2022.
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
ferconline.ferc.gov/FERCOnline.aspx.
For assistance, please contact FERC
Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. All filings
must clearly identify the project name
and docket number on the first page:
Beaver Falls Hydroelectric Project (P–
1922–052).
m. The application is not ready for
environmental analysis at this time.
n. Project Description: The existing
Beaver Falls Project consists of two
developments: Silvis and Beaver Falls.
The Silvis development consists of: (1)
a 60-foot-high, 135-foot-long concreteface, rock-filled Upper Silvis Lake dam;
(2) an 800-foot-long excavated rock
spillway channel leading from Upper
Silvis Lake to Lower Silvis Lake; (3) a
300-acre reservoir (Upper Silvis Lake)
with gross storage capacity of
approximately 38,000 acre-feet; (4) a
980-foot-long underground power
tunnel connecting to a 342-foot-long, 36inch-diameter steel penstock that
conveys water to the Silvis Powerhouse;
(5) a 30-feet by 40-feet by 25-feet-high
Silvis powerhouse containing a single
Francis-type turbine with a rated
capacity of 2.1 megawatts; (6) a 150foot-long trapezoidal shaped channel
tailrace discharging into Lower Silvis
Lake; (7) a 2,900-foot-long, 5-kilovolt
submarine cable beneath Lower Silvis
Lake; (8) a 7,000-foot-long, 34.5-kilovolt
aerial transmission line; and (9)
appurtenant facilities.
The Beaver Falls development
consists of: (1) a 32-foot-high, 140-footlong concrete-face, rock-filled Lower
Silvis dam; (2) a spillway with an
ungated control weir and unlined rock
discharge channel; (3) a 67.5-acre
reservoir (Lower Silvis Lake) with gross
storage capacity of approximately 8,052
acre-feet; (4) a 3-foot-high, 40-foot-long
concrete diversion dam on Beaver Falls
Creek; (5) a 3,800-foot-long underground
power tunnel connecting to a 3,610-footlong above ground steel penstock that
conveys water from Lower Silvis Lake to
the Beaver Falls powerhouse and
supplies water to Units 3 and 4 in the
powerhouse; (6) a 225-foot-long adit that
taps the 3,800-foot-long underground
power tunnel and discharges water into
Beaver Falls Creek approximately 500feet upstream of the Beaver Falls
diversion dam; (7) a 4,170-foot-long
above ground steel penstock that
conveys water from the Beaver Falls
Creek diversion dam to the Beaver Falls
powerhouse and supplies Unit 1 in the
powerhouse; (8) a 30-feet by 147-feet by
25-feet-high Beaver Falls powerhouse
containing three horizontal Pelton
generating units with a total installed
capacity of 5 MW (Units 1, 3 and 4; Unit
2 is decommissioned); (9) a Beaver Falls
substation; and (10) appurtenant
facilities. The project generates an
annual average of 54,711,280 megawatthours.
o. In addition to publishing the full
text of this notice in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
notice, as well as other documents in
the proceeding (e.g., license application)
via the internet through the
Commission’s Home Page (https://
www.ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document (P–1922).
For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or (202) 502–
8659 (TTY).
You may also register online at
https://ferconline.ferc.gov/FERCOnline.
aspx to be notified via email of new
filings and issuances related to this or
other pending projects. For assistance,
contact FERC Online Support.
p. Procedural schedule and final
amendments: The application will be
processed according to the following
preliminary schedule. Revisions to the
schedule will be made as appropriate.
Additional Study Requests due ..............................................................................................................................................................................
Issue Deficiency Letter (if necessary) ....................................................................................................................................................................
Request Additional Information (if needed) ............................................................................................................................................................
Issue Notice of Acceptance ....................................................................................................................................................................................
Issue Scoping Document 1 for comments .............................................................................................................................................................
Issue Scoping Document 2 ....................................................................................................................................................................................
Issue Notice of Ready for Environmental Analysis ................................................................................................................................................
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: November 2, 2022.
Kimberly D. Bose,
Secretary.
lotter on DSK11XQN23PROD with NOTICES1
[FR Doc. 2022–24347 Filed 11–7–22; 8:45 am]
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 4784–106]
Topsham Hydro Partners Limited
Partnership (L.P.); Notice of
Availability of Final Environmental
Assessment
BILLING CODE 6717–01–P
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s (Commission)
regulations, 18 CFR part 380, the Office
of Energy Projects has reviewed the
application for license for the Pejepscot
VerDate Sep<11>2014
18:33 Nov 07, 2022
Jkt 259001
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
67469
December 2022.
December 2022.
December 2022.
March 2023.
April 2023.
June 2023.
June 2023.
Hydroelectric Project, located on the
Androscoggin River in Sagadahoc,
Cumberland, and Androscoggin
Counties in the village of Pejepscot and
the town of Topsham, Maine and has
prepared a Final Environmental
Assessment (FEA) for the project. No
federal land is occupied by project
works or located within the project
boundary.
The FEA contains staff’s analysis of
the potential environmental impacts of
the project and concludes that licensing
the project, with appropriate
environmental protective measures,
would not constitute a major federal
action that would significantly affect the
quality of the human environment.
E:\FR\FM\08NON1.SGM
08NON1
Agencies
[Federal Register Volume 87, Number 215 (Tuesday, November 8, 2022)]
[Notices]
[Pages 67468-67469]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-24347]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 1922-052]
Ketchikan Public Utilities; Notice of Application Tendered for
Filing With the Commission and Soliciting Additional Study Requests and
Establishing Procedural Schedule for Relicensing and a Deadline for
Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Subsequent Minor License.
b. Project No.: 1922-052.
c. Date filed: October 27, 2022.
d. Applicant: Ketchikan Public Utilities (KPU).
e. Name of Project: Beaver Falls Hydroelectric Project (project).
f. Location: On Beaver Falls Creek in Ketchikan Gateway Borough,
Alaska. The project occupies 478.4 acres of United States lands
administered by U.S. Forest Service.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Jennifer Holstrom, Senior Project Engineer,
Ketchikan Public Utilities, 1065 Fair Street, Ketchikan, Alaska 99901;
(907) 228-4733; or email at [email protected].
i. FERC Contact: Kristen Sinclair at (202) 502-6587, or
[email protected].
j. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See 94 FERC ]
61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and
[[Page 67469]]
serve a copy of the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: December 26, 2022.
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at https://ferconline.ferc.gov/FERCOnline.aspx. For assistance, please contact FERC Online Support at
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy.
Submissions sent via the U.S. Postal Service must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via
any other carrier must be addressed to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville,
Maryland 20852. All filings must clearly identify the project name and
docket number on the first page: Beaver Falls Hydroelectric Project (P-
1922-052).
m. The application is not ready for environmental analysis at this
time.
n. Project Description: The existing Beaver Falls Project consists
of two developments: Silvis and Beaver Falls. The Silvis development
consists of: (1) a 60-foot-high, 135-foot-long concrete-face, rock-
filled Upper Silvis Lake dam; (2) an 800-foot-long excavated rock
spillway channel leading from Upper Silvis Lake to Lower Silvis Lake;
(3) a 300-acre reservoir (Upper Silvis Lake) with gross storage
capacity of approximately 38,000 acre-feet; (4) a 980-foot-long
underground power tunnel connecting to a 342-foot-long, 36-inch-
diameter steel penstock that conveys water to the Silvis Powerhouse;
(5) a 30-feet by 40-feet by 25-feet-high Silvis powerhouse containing a
single Francis-type turbine with a rated capacity of 2.1 megawatts; (6)
a 150-foot-long trapezoidal shaped channel tailrace discharging into
Lower Silvis Lake; (7) a 2,900-foot-long, 5-kilovolt submarine cable
beneath Lower Silvis Lake; (8) a 7,000-foot-long, 34.5-kilovolt aerial
transmission line; and (9) appurtenant facilities.
The Beaver Falls development consists of: (1) a 32-foot-high, 140-
foot-long concrete-face, rock-filled Lower Silvis dam; (2) a spillway
with an ungated control weir and unlined rock discharge channel; (3) a
67.5-acre reservoir (Lower Silvis Lake) with gross storage capacity of
approximately 8,052 acre-feet; (4) a 3-foot-high, 40-foot-long concrete
diversion dam on Beaver Falls Creek; (5) a 3,800-foot-long underground
power tunnel connecting to a 3,610-foot-long above ground steel
penstock that conveys water from Lower Silvis Lake to the Beaver Falls
powerhouse and supplies water to Units 3 and 4 in the powerhouse; (6) a
225-foot-long adit that taps the 3,800-foot-long underground power
tunnel and discharges water into Beaver Falls Creek approximately 500-
feet upstream of the Beaver Falls diversion dam; (7) a 4,170-foot-long
above ground steel penstock that conveys water from the Beaver Falls
Creek diversion dam to the Beaver Falls powerhouse and supplies Unit 1
in the powerhouse; (8) a 30-feet by 147-feet by 25-feet-high Beaver
Falls powerhouse containing three horizontal Pelton generating units
with a total installed capacity of 5 MW (Units 1, 3 and 4; Unit 2 is
decommissioned); (9) a Beaver Falls substation; and (10) appurtenant
facilities. The project generates an annual average of 54,711,280
megawatt-hours.
o. In addition to publishing the full text of this notice in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this notice, as well
as other documents in the proceeding (e.g., license application) via
the internet through the Commission's Home Page (https://www.ferc.gov)
using the ``eLibrary'' link. Enter the docket number excluding the last
three digits in the docket number field to access the document (P-
1922). For assistance, contact FERC at [email protected] or
call toll-free, (866) 208-3676 or (202) 502-8659 (TTY).
You may also register online at https://ferconline.ferc.gov/FERCOnline.aspx to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. Procedural schedule and final amendments: The application will
be processed according to the following preliminary schedule. Revisions
to the schedule will be made as appropriate.
------------------------------------------------------------------------
------------------------------------------------------------------------
Additional Study Requests due......... December 2022.
Issue Deficiency Letter (if necessary) December 2022.
Request Additional Information (if December 2022.
needed).
Issue Notice of Acceptance............ March 2023.
Issue Scoping Document 1 for comments. April 2023.
Issue Scoping Document 2.............. June 2023.
Issue Notice of Ready for June 2023.
Environmental Analysis.
------------------------------------------------------------------------
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: November 2, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-24347 Filed 11-7-22; 8:45 am]
BILLING CODE 6717-01-P