Mad River Power Associates; Notice of Authorization for Continued Project Operation, 67464 [2022-24346]

Download as PDF 67464 Federal Register / Vol. 87, No. 215 / Tuesday, November 8, 2022 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 3253–000] Mad River Power Associates; Notice of Authorization for Continued Project Operation The license for the Campton Hydroelectric Project No. 3253 was issued for a period ending October 31, 2022. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the Commission, at the expiration of a license term, to issue from year-to-year an annual license to the then licensee(s) under the terms and conditions of the prior license until a new license is issued, or the project is otherwise disposed of as provided in section 15 or any other applicable section of the FPA. If the project’s prior license waived the applicability of section 15 of the FPA, then, based on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth at 18 CFR 16.21(a), if the licensee of such project has filed an application for a subsequent license, the licensee may continue to operate the project in accordance with the terms and conditions of the license after the minor or minor part license expires, until the Commission acts on its application. If the licensee of such a project has not filed an application for a subsequent license, then it may be required, pursuant to 18 CFR 16.21(b), to continue project operations until the Commission issues someone else a license for the project or otherwise orders disposition of the project. If the project is subject to section 15 of the FPA, notice is hereby given that an annual license for Project No. 3253 is issued to Mad River Power Associates for a period effective November 1, 2022, through October 31, 2023, or until the issuance of a new license for the project or other disposition under the FPA, whichever comes first. If issuance of a new license (or other disposition) does not take place on or before October 31, 2023, notice is hereby given that, pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is renewed automatically without further order or notice by the Commission, unless the Commission orders otherwise. If the project is not subject to section 15 of the FPA, notice is hereby given that Mad River Power Associates is authorized to continue operation of the Campton Hydroelectric Project under the terms and conditions of the prior license until the issuance of a new license for the project or other disposition under the FPA, whichever comes first. Dated: November 2, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–24346 Filed 11–7–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Effectiveness of Exempt Wholesale Generator Status Docket Nos. Kawailoa Solar, LLC ............................................................................................................................................... Sunflower Energy Center, LLC ............................................................................................................................... Chaparral Springs, LLC .......................................................................................................................................... Appaloosa Run Wind, LLC ..................................................................................................................................... Young Wind, LLC ................................................................................................................................................... Lacy Creek Wind, LLC ........................................................................................................................................... Inertia Wind Project, LLC ....................................................................................................................................... AES Energy Storage, LLC ...................................................................................................................................... MTSun LLC ............................................................................................................................................................. Hunt Energy Network Land Company, L.L.C ......................................................................................................... HEN Infrastructure, L.L.C ....................................................................................................................................... Eight Point Wind, LLC ............................................................................................................................................ Clearwater Energy Resources LLC ........................................................................................................................ Sun Valley Solar LLC ............................................................................................................................................. BT Cunningham Storage, LLC ............................................................................................................................... CPV Three Rivers, LLC .......................................................................................................................................... Take notice that during the month of October 2022, the status of the abovecaptioned entities as Exempt Wholesale Generators Companies became effective by operation of the Commission’s regulations. 18 CFR 366.7(a) (2021). Dated: November 2, 2022. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2022–24336 Filed 11–7–22; 8:45 am] lotter on DSK11XQN23PROD with NOTICES1 BILLING CODE 6717–01–P VerDate Sep<11>2014 16:56 Nov 07, 2022 Jkt 259001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #3 Take notice that the Commission received the following electric corporate filings: Docket Numbers: ER23–335–000. Applicants: NorthWestern Corporation. Description: § 205(d) Rate Filing: NorthWestern Corporation submits tariff filing per 35.13(a)(2)(iii: SA 296 6th Rev—NITSA with ExxonMobil Corporation to be effective 1/1/2023. Filed Date: 11/1/22. Accession Number: 20221101–5203. Comment Date: 5 p.m. ET 11/22/22. PO 00000 Frm 00029 Fmt 4703 Sfmt 4703 EG22–199–000 EG22–200–000 EG22–201–000 EG22–202–000 EG22–203–000 EG22–204–000 EG22–205–000 EG22–206–000 EG22–207–000 EG22–208–000 EG22–209–000 EG22–210–000 EG22–211–000 EG22–212–000 EG22–213–000 EG22–214–000 Docket Numbers: ER23–336–000. Applicants: NorthWestern Corporation. Description: § 205(d) Rate Filing: Revised Exhibits to Montana Intertie Agreement to be effective 10/1/2022. Filed Date: 11/1/22. Accession Number: 20221101–5212. Comment Date: 5 p.m. ET 11/22/22. Docket Numbers: ER23–337–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: 3599R1 Missouri Electric Commission NITSA NOA to be effective 1/1/2023. Filed Date: 11/1/22. Accession Number: 20221101–5214. Comment Date: 5 p.m. ET 11/22/22. Docket Numbers: ER23–338–000. E:\FR\FM\08NON1.SGM 08NON1

Agencies

[Federal Register Volume 87, Number 215 (Tuesday, November 8, 2022)]
[Notices]
[Page 67464]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-24346]



[[Page 67464]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 3253-000]


Mad River Power Associates; Notice of Authorization for Continued 
Project Operation

    The license for the Campton Hydroelectric Project No. 3253 was 
issued for a period ending October 31, 2022.
    Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the 
Commission, at the expiration of a license term, to issue from year-to-
year an annual license to the then licensee(s) under the terms and 
conditions of the prior license until a new license is issued, or the 
project is otherwise disposed of as provided in section 15 or any other 
applicable section of the FPA. If the project's prior license waived 
the applicability of section 15 of the FPA, then, based on section 9(b) 
of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth 
at 18 CFR 16.21(a), if the licensee of such project has filed an 
application for a subsequent license, the licensee may continue to 
operate the project in accordance with the terms and conditions of the 
license after the minor or minor part license expires, until the 
Commission acts on its application. If the licensee of such a project 
has not filed an application for a subsequent license, then it may be 
required, pursuant to 18 CFR 16.21(b), to continue project operations 
until the Commission issues someone else a license for the project or 
otherwise orders disposition of the project.
    If the project is subject to section 15 of the FPA, notice is 
hereby given that an annual license for Project No. 3253 is issued to 
Mad River Power Associates for a period effective November 1, 2022, 
through October 31, 2023, or until the issuance of a new license for 
the project or other disposition under the FPA, whichever comes first. 
If issuance of a new license (or other disposition) does not take place 
on or before October 31, 2023, notice is hereby given that, pursuant to 
18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is 
renewed automatically without further order or notice by the 
Commission, unless the Commission orders otherwise.
    If the project is not subject to section 15 of the FPA, notice is 
hereby given that Mad River Power Associates is authorized to continue 
operation of the Campton Hydroelectric Project under the terms and 
conditions of the prior license until the issuance of a new license for 
the project or other disposition under the FPA, whichever comes first.

    Dated: November 2, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-24346 Filed 11-7-22; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.