Combined Notice of Filings #3, 67464-67465 [2022-24332]
Download as PDF
67464
Federal Register / Vol. 87, No. 215 / Tuesday, November 8, 2022 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 3253–000]
Mad River Power Associates; Notice of
Authorization for Continued Project
Operation
The license for the Campton
Hydroelectric Project No. 3253 was
issued for a period ending October 31,
2022.
Section 15(a)(1) of the FPA, 16 U.S.C.
808(a)(1), requires the Commission, at
the expiration of a license term, to issue
from year-to-year an annual license to
the then licensee(s) under the terms and
conditions of the prior license until a
new license is issued, or the project is
otherwise disposed of as provided in
section 15 or any other applicable
section of the FPA. If the project’s prior
license waived the applicability of
section 15 of the FPA, then, based on
section 9(b) of the Administrative
Procedure Act, 5 U.S.C. 558(c), and as
set forth at 18 CFR 16.21(a), if the
licensee of such project has filed an
application for a subsequent license, the
licensee may continue to operate the
project in accordance with the terms
and conditions of the license after the
minor or minor part license expires,
until the Commission acts on its
application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 3253
is issued to Mad River Power Associates
for a period effective November 1, 2022,
through October 31, 2023, or until the
issuance of a new license for the project
or other disposition under the FPA,
whichever comes first. If issuance of a
new license (or other disposition) does
not take place on or before October 31,
2023, notice is hereby given that,
pursuant to 18 CFR 16.18(c), an annual
license under section 15(a)(1) of the
FPA is renewed automatically without
further order or notice by the
Commission, unless the Commission
orders otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that Mad River Power Associates is
authorized to continue operation of the
Campton Hydroelectric Project under
the terms and conditions of the prior
license until the issuance of a new
license for the project or other
disposition under the FPA, whichever
comes first.
Dated: November 2, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–24346 Filed 11–7–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Effectiveness of Exempt
Wholesale Generator Status
Docket Nos.
Kawailoa Solar, LLC ...............................................................................................................................................
Sunflower Energy Center, LLC ...............................................................................................................................
Chaparral Springs, LLC ..........................................................................................................................................
Appaloosa Run Wind, LLC .....................................................................................................................................
Young Wind, LLC ...................................................................................................................................................
Lacy Creek Wind, LLC ...........................................................................................................................................
Inertia Wind Project, LLC .......................................................................................................................................
AES Energy Storage, LLC ......................................................................................................................................
MTSun LLC .............................................................................................................................................................
Hunt Energy Network Land Company, L.L.C .........................................................................................................
HEN Infrastructure, L.L.C .......................................................................................................................................
Eight Point Wind, LLC ............................................................................................................................................
Clearwater Energy Resources LLC ........................................................................................................................
Sun Valley Solar LLC .............................................................................................................................................
BT Cunningham Storage, LLC ...............................................................................................................................
CPV Three Rivers, LLC ..........................................................................................................................................
Take notice that during the month of
October 2022, the status of the abovecaptioned entities as Exempt Wholesale
Generators Companies became effective
by operation of the Commission’s
regulations. 18 CFR 366.7(a) (2021).
Dated: November 2, 2022.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2022–24336 Filed 11–7–22; 8:45 am]
lotter on DSK11XQN23PROD with NOTICES1
BILLING CODE 6717–01–P
VerDate Sep<11>2014
16:56 Nov 07, 2022
Jkt 259001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #3
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: ER23–335–000.
Applicants: NorthWestern
Corporation.
Description: § 205(d) Rate Filing:
NorthWestern Corporation submits tariff
filing per 35.13(a)(2)(iii: SA 296 6th
Rev—NITSA with ExxonMobil
Corporation to be effective 1/1/2023.
Filed Date: 11/1/22.
Accession Number: 20221101–5203.
Comment Date: 5 p.m. ET 11/22/22.
PO 00000
Frm 00029
Fmt 4703
Sfmt 4703
EG22–199–000
EG22–200–000
EG22–201–000
EG22–202–000
EG22–203–000
EG22–204–000
EG22–205–000
EG22–206–000
EG22–207–000
EG22–208–000
EG22–209–000
EG22–210–000
EG22–211–000
EG22–212–000
EG22–213–000
EG22–214–000
Docket Numbers: ER23–336–000.
Applicants: NorthWestern
Corporation.
Description: § 205(d) Rate Filing:
Revised Exhibits to Montana Intertie
Agreement to be effective 10/1/2022.
Filed Date: 11/1/22.
Accession Number: 20221101–5212.
Comment Date: 5 p.m. ET 11/22/22.
Docket Numbers: ER23–337–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing:
3599R1 Missouri Electric Commission
NITSA NOA to be effective 1/1/2023.
Filed Date: 11/1/22.
Accession Number: 20221101–5214.
Comment Date: 5 p.m. ET 11/22/22.
Docket Numbers: ER23–338–000.
E:\FR\FM\08NON1.SGM
08NON1
lotter on DSK11XQN23PROD with NOTICES1
Federal Register / Vol. 87, No. 215 / Tuesday, November 8, 2022 / Notices
Applicants: Duke Energy Florida,
LLC, Duke Energy Carolinas, LLC.
Description: § 205(d) Rate Filing:
Duke Energy Florida, LLC submits tariff
filing per 35.13(a)(2)(iii: DEF—Revisions
to Joint OATT to Provide NFEETS to be
effective 12/31/9998.
Filed Date: 11/1/22.
Accession Number: 20221101–5216.
Comment Date: 5 p.m. ET 11/22/22.
Docket Numbers: ER23–339–000.
Applicants: South Carolina
Generating Company, Inc.
Description: § 205(d) Rate Filing:
Small Rate Increase GENCO to be
effective 1/1/2023.
Filed Date: 11/1/22.
Accession Number: 20221101–5219.
Comment Date: 5 p.m. ET 11/22/22.
Docket Numbers: ER23–340–000.
Applicants: El Paso Electric Company
(EPE).
Description: El Paso Electric Company
submits 2022 WECC Soft Price Cap
Justification Filing.
Filed Date: 10/28/22.
Accession Number: 20221028–5394.
Comment Date: 5 p.m. ET 11/18/22.
Docket Numbers: ER23–341–000.
Applicants: Concurrent LLC.
Description: Baseline eTariff Filing:
Concurrent LLC submits tariff filing per
35.12: Application for Market-Based
Rate Authorization to be effective 11/2/
2022.
Filed Date: 11/1/22.
Accession Number: 20221102–5000.
Comment Date: 5 p.m. ET 11/22/22.
Docket Numbers: ER23–342–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing: 4029
Panhandle Solar & SPS Facilities
Service Agreement to be effective 1/2/
2023.
Filed Date: 11/2/22.
Accession Number: 20221102–5004.
Comment Date: 5 p.m. ET 11/23/22.
Docket Numbers: ER23–343–000.
Applicants: Sirrius Energy LLC.
Description: Notice of Cancellation of
Market Based Rate Tariff of Sirrius
Energy LLC.
Filed Date: 11/1/22.
Accession Number: 20221101–5251.
Comment Date: 5 p.m. ET 11/22/22.
Docket Numbers: ER23–344–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: § 205(d) Rate Filing:
2022–11–02_SA 3321 METC-Isabella
Renewables I & II E&P (J717 J728) to be
effective 11/3/2022.
Filed Date: 11/2/22.
Accession Number: 20221102–5039.
Comment Date: 5 p.m. ET 11/23/22.
Docket Numbers: ER23–345–000.
VerDate Sep<11>2014
16:56 Nov 07, 2022
Jkt 259001
Applicants: Versant Power.
Description: § 205(d) Rate Filing:
Revised Attachment J Formula Rates for
MPD OATT to be effective 6/1/2023.
Filed Date: 11/2/22.
Accession Number: 20221102–5061.
Comment Date: 5 p.m. ET 11/23/22.
Docket Numbers: ER23–346–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Amendment to ISA, SA No. 1127;
Queue No. AD2–113/AD2–114 (amend)
to be effective 11/12/2019.
Filed Date: 11/2/22.
Accession Number: 20221102–5069.
Comment Date: 5 p.m. ET 11/23/22.
Docket Numbers: ER23–347–000.
Applicants: Tri-State Generation and
Transmission Association, Inc.
Description: § 205(d) Rate Filing:
Initial Filing of Rate Schedule No. 349
to be effective 10/3/2022.
Filed Date: 11/2/22.
Accession Number: 20221102–5091.
Comment Date: 5 p.m. ET 11/23/22.
Docket Numbers: ER23–348–000.
Applicants: New England Power
Company.
Description: § 205(d) Rate Filing:
2022–11–02 Filing of Revisions to New
England Power Company Tariff No. 1 to
be effective 1/1/2023.
Filed Date: 11/2/22.
Accession Number: 20221102–5093.
Comment Date: 5 p.m. ET 11/23/22.
Docket Numbers: ER23–349–000.
Applicants: New York Independent
System Operator, Inc.
Description: § 205(d) Rate Filing:
Section 205 Filing re: Bad Debt Loss
Allocation Calculation Revisions to be
effective 1/3/2023.
Filed Date: 11/2/22.
Accession Number: 20221102–5094.
Comment Date: 5 p.m. ET 11/23/22.
Take notice that the Commission
received the following electric
reliability filings.
Docket Numbers: RD23–1–000.
Applicants: North American Electric
Reliability Corporation.
Description: North American Electric
Reliability Corporation submits Petition
for Approval of Proposed Reliability
Standards EOP–011–3 and EOP–012–1
and Request for Expedited Action.
Filed Date: 10/28/22.
Accession Number: 20221028–5393.
Comment Date: 5 p.m. ET 12/1/22.
The filings are accessible in the
Commission’s eLibrary system (https://
elibrary.ferc.gov/idmws/search/
fercgensearch.asp) by querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
PO 00000
Frm 00030
Fmt 4703
Sfmt 4703
67465
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: November 2, 2022.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2022–24332 Filed 11–7–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC23–17–000.
Applicants: RWE Aktiengesellschaft,
Consolidated Edison, Inc., RWE
Renewables Americas, LLC, Con Edison
Clean Energy Businesses, Inc., Alpaugh
50, LLC, Battle Mountain SP, LLC,
Broken Bow Wind II, LLC, Campbell
County Wind Farm, LLC, CED
Timberland Solar, LLC, CED White
River Solar 2, LLC, CED Wistaria Solar,
LLC, Consolidated Edison Energy, Inc.,
Consolidated Edison Solutions, Inc.,
Copper Mountain Solar 1, LLC, Copper
Mountain Solar 2, LLC, Copper
Mountain Solar 3, LLC, Copper
Mountain Solar 4, LLC, Copper
Mountain Solar 5, LLC, Great Valley
Solar 1, LLC, Great Valley Solar 2, LLC,
Great Valley Solar 3, LLC, Mesquite
Solar 1, LLC, Mesquite Solar 2, LLC,
Mesquite Solar 3, LLC, Mesquite Solar
4, LLC, Mesquite Solar 5, LLC, Panoche
Valley Solar, LLC, Pleasant Hill Solar,
LLC, SEP II, LLC, Water Strider Solar
LLC, Watlington Solar, LLC.
Description: Joint Application for
Authorization Under Section 203 of the
Federal Power Act of RWE
Aktiengesellschaft.
Filed Date: 10/28/22.
Accession Number: 20221028–5314.
Comment Date: 5 p.m. ET 11/18/22.
Take notice that the Commission
received the following electric rate
filings:
E:\FR\FM\08NON1.SGM
08NON1
Agencies
[Federal Register Volume 87, Number 215 (Tuesday, November 8, 2022)]
[Notices]
[Pages 67464-67465]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-24332]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #3
Take notice that the Commission received the following electric
corporate filings:
Docket Numbers: ER23-335-000.
Applicants: NorthWestern Corporation.
Description: Sec. 205(d) Rate Filing: NorthWestern Corporation
submits tariff filing per 35.13(a)(2)(iii: SA 296 6th Rev--NITSA with
ExxonMobil Corporation to be effective 1/1/2023.
Filed Date: 11/1/22.
Accession Number: 20221101-5203.
Comment Date: 5 p.m. ET 11/22/22.
Docket Numbers: ER23-336-000.
Applicants: NorthWestern Corporation.
Description: Sec. 205(d) Rate Filing: Revised Exhibits to Montana
Intertie Agreement to be effective 10/1/2022.
Filed Date: 11/1/22.
Accession Number: 20221101-5212.
Comment Date: 5 p.m. ET 11/22/22.
Docket Numbers: ER23-337-000.
Applicants: Southwest Power Pool, Inc.
Description: Sec. 205(d) Rate Filing: 3599R1 Missouri Electric
Commission NITSA NOA to be effective 1/1/2023.
Filed Date: 11/1/22.
Accession Number: 20221101-5214.
Comment Date: 5 p.m. ET 11/22/22.
Docket Numbers: ER23-338-000.
[[Page 67465]]
Applicants: Duke Energy Florida, LLC, Duke Energy Carolinas, LLC.
Description: Sec. 205(d) Rate Filing: Duke Energy Florida, LLC
submits tariff filing per 35.13(a)(2)(iii: DEF--Revisions to Joint OATT
to Provide NFEETS to be effective 12/31/9998.
Filed Date: 11/1/22.
Accession Number: 20221101-5216.
Comment Date: 5 p.m. ET 11/22/22.
Docket Numbers: ER23-339-000.
Applicants: South Carolina Generating Company, Inc.
Description: Sec. 205(d) Rate Filing: Small Rate Increase GENCO to
be effective 1/1/2023.
Filed Date: 11/1/22.
Accession Number: 20221101-5219.
Comment Date: 5 p.m. ET 11/22/22.
Docket Numbers: ER23-340-000.
Applicants: El Paso Electric Company (EPE).
Description: El Paso Electric Company submits 2022 WECC Soft Price
Cap Justification Filing.
Filed Date: 10/28/22.
Accession Number: 20221028-5394.
Comment Date: 5 p.m. ET 11/18/22.
Docket Numbers: ER23-341-000.
Applicants: Concurrent LLC.
Description: Baseline eTariff Filing: Concurrent LLC submits tariff
filing per 35.12: Application for Market-Based Rate Authorization to be
effective 11/2/2022.
Filed Date: 11/1/22.
Accession Number: 20221102-5000.
Comment Date: 5 p.m. ET 11/22/22.
Docket Numbers: ER23-342-000.
Applicants: Southwest Power Pool, Inc.
Description: Sec. 205(d) Rate Filing: 4029 Panhandle Solar & SPS
Facilities Service Agreement to be effective 1/2/2023.
Filed Date: 11/2/22.
Accession Number: 20221102-5004.
Comment Date: 5 p.m. ET 11/23/22.
Docket Numbers: ER23-343-000.
Applicants: Sirrius Energy LLC.
Description: Notice of Cancellation of Market Based Rate Tariff of
Sirrius Energy LLC.
Filed Date: 11/1/22.
Accession Number: 20221101-5251.
Comment Date: 5 p.m. ET 11/22/22.
Docket Numbers: ER23-344-000.
Applicants: Midcontinent Independent System Operator, Inc.
Description: Sec. 205(d) Rate Filing: 2022-11-02_SA 3321 METC-
Isabella Renewables I & II E&P (J717 J728) to be effective 11/3/2022.
Filed Date: 11/2/22.
Accession Number: 20221102-5039.
Comment Date: 5 p.m. ET 11/23/22.
Docket Numbers: ER23-345-000.
Applicants: Versant Power.
Description: Sec. 205(d) Rate Filing: Revised Attachment J Formula
Rates for MPD OATT to be effective 6/1/2023.
Filed Date: 11/2/22.
Accession Number: 20221102-5061.
Comment Date: 5 p.m. ET 11/23/22.
Docket Numbers: ER23-346-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: Amendment to ISA, SA No.
1127; Queue No. AD2-113/AD2-114 (amend) to be effective 11/12/2019.
Filed Date: 11/2/22.
Accession Number: 20221102-5069.
Comment Date: 5 p.m. ET 11/23/22.
Docket Numbers: ER23-347-000.
Applicants: Tri-State Generation and Transmission Association, Inc.
Description: Sec. 205(d) Rate Filing: Initial Filing of Rate
Schedule No. 349 to be effective 10/3/2022.
Filed Date: 11/2/22.
Accession Number: 20221102-5091.
Comment Date: 5 p.m. ET 11/23/22.
Docket Numbers: ER23-348-000.
Applicants: New England Power Company.
Description: Sec. 205(d) Rate Filing: 2022-11-02 Filing of
Revisions to New England Power Company Tariff No. 1 to be effective 1/
1/2023.
Filed Date: 11/2/22.
Accession Number: 20221102-5093.
Comment Date: 5 p.m. ET 11/23/22.
Docket Numbers: ER23-349-000.
Applicants: New York Independent System Operator, Inc.
Description: Sec. 205(d) Rate Filing: Section 205 Filing re: Bad
Debt Loss Allocation Calculation Revisions to be effective 1/3/2023.
Filed Date: 11/2/22.
Accession Number: 20221102-5094.
Comment Date: 5 p.m. ET 11/23/22.
Take notice that the Commission received the following electric
reliability filings.
Docket Numbers: RD23-1-000.
Applicants: North American Electric Reliability Corporation.
Description: North American Electric Reliability Corporation
submits Petition for Approval of Proposed Reliability Standards EOP-
011-3 and EOP-012-1 and Request for Expedited Action.
Filed Date: 10/28/22.
Accession Number: 20221028-5393.
Comment Date: 5 p.m. ET 12/1/22.
The filings are accessible in the Commission's eLibrary system
(https://elibrary.ferc.gov/idmws/search/fercgensearch.asp) by querying
the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: November 2, 2022.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2022-24332 Filed 11-7-22; 8:45 am]
BILLING CODE 6717-01-P