Download as PDF Federal Register / Vol. 87, No. 198 / Friday, October 14, 2022 / Notices in accordance with submission guidelines at: https://www.ferc.gov. For user assistance contact FERC Online Support by email at ferconlinesupport@ ferc.gov, or by phone at (866) 208–3676 (toll-free). Docket: Users interested in receiving automatic notification of activity in this docket or in viewing/downloading comments and issuances in this docket may do so at https://www.ferc.gov. FOR FURTHER INFORMATION CONTACT: Ellen Brown may be reached by email at DataClearance@FERC.gov and telephone at (202) 502–8663. SUPPLEMENTARY INFORMATION: Title: FERC–539 (Gas Pipeline Certificates: Import & Export Related Applications). OMB Control No.: 1902–0062. Type of Request: Three-year extension of the FERC–539 with no changes to the current reporting requirements. Abstract: The purpose of FERC–539 is to implement information collections pursuant to Section 3 of the Natural Gas Act (NGA).1 This statute provides, in part, that ‘‘. . . no person shall export any natural gas from the United States to a foreign country or import any natural gas from a foreign country without first having secured an order from the Commission authorizing it to do so.’’ 2 This statute applies not only to natural gas imported and/or exported via pipeline but also to any import and/ or export of liquefied natural gas via a liquefied natural gas terminal. The 1992 62405 amendments to Section 3 of the NGA concern importation or exportation from/to a nation which has a free trade agreement with the United States, and requires that such importation or exportation: (1) Shall be deemed to be a ‘‘first sale’’, i.e., not a sale for a resale, and (2) Shall be deemed to be consistent with the public interest, and applications for such importation or exportation shall be granted without modification or delay. Estimate of Annual Burden: 3 The Commission estimates the annual public reporting burden for the information collection as: FERC–539, GAS PIPELINE CERTIFICATES: IMPORT & EXPORT RELATED APPLICATIONS Number of respondents Number of responses per respondent Total number of responses Average burden hours & average cost 4 per response ($) Total annual burden hours & total annual cost ($) Cost per respondent ($) (1) (2) (1) * (2) = (3) (4) (3) * (4) = (5) (5) ÷ (1) = (6) 6 ............................................. 2 12 15 hours; $1,305 .................. 180 hours; $15,660 .............. $2,610 Comments: Comments are invited on: (1) whether the collections of information are necessary for the proper performance of the functions of the Commission, including whether the information will have practical utility; (2) the accuracy of the agency’s estimates of the burden and cost of the collections of information, including the validity of the methodology and assumptions used; (3) ways to enhance the quality, utility and clarity of the information collections; and (4) ways to minimize the burden of the collections of information on those who are to respond, including the use of automated collection techniques or other forms of information technology. Dated: October 7, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–22364 Filed 10–13–22; 8:45 am] jspears on DSK121TN23PROD with NOTICES BILLING CODE 6717–01–P 1 15 U.S.C. 717–717w U.S.C. 717b 3 Burden is defined as the total time, effort, or financial resources expended by persons to 2 15 VerDate Sep<11>2014 17:22 Oct 13, 2022 Jkt 259001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 349–157] Alabama Power Company; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Non-Project Use of Project Lands and Waters. b. Project No.: 349–157. c. Date Filed: July 21, 2022, as supplemented on September 23, 2022. d. Applicant: Alabama Power Company. e. Name of Project: Martin Dam Hydroelectric Project. f. Location: The Martin Dam Hydroelectric Project is located on the Tallapoosa River (Lake Martin), in Tallapoosa, Elmore, and Coosa counties, Alabama, and occupies federal land administered by the U.S. Bureau of Land Management; the non-project use is located in Elmore County. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. generate, maintain, retain, or disclose or provide information to or for a federal agency. See 5 CFR 1320 for additional information on the definition of information collection burden. PO 00000 Frm 00047 Fmt 4703 Sfmt 4703 h. Applicant Contact: Unzell Kelley, Alabama Power Company at (205) 517– 0885 or ukelley@southernco.com. i. FERC Contact: Shana High at (202) 502–8674 or shana.high@ferc.gov. j. Deadline for filing motions to intervene and protests: November 7, 2022. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, 4 The Commission staff estimates that industry is similarly situated in terms of hourly cost (for wages plus benefits). Based on the Commission’s FY (Fiscal Year) 2021 average cost (for wages plus benefits), $87.00/hour is used. E:\FR\FM\14OCN1.SGM 14OCN1 jspears on DSK121TN23PROD with NOTICES 62406 Federal Register / Vol. 87, No. 198 / Friday, October 14, 2022 / Notices Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket number P–349–157. Comments emailed to Commission staff are not considered part of the Commission record. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person whose name appears on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Request: Alabama Power Company is requesting Commission authorization to permit Russell Lands, Inc. to expand Kowaliga Marina. As proposed, Kowaliga Marina would include 13 docks that would accommodate 258 boats and 45 personal watercraft, two forklift piers, a boat ramp, four breakwaters, a seawall, and riprap. l. Locations of the Application: This filing may be viewed on the Commission’s website at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. Agencies may obtain copies of the application directly from the applicant. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214, respectively. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. VerDate Sep<11>2014 17:22 Oct 13, 2022 Jkt 259001 o. Filing and Service of Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person commenting, protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. Any filing made by an intervenor must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. Dated: October 7, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–22367 Filed 10–13–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP17–40–006] Spire STL Pipeline LLC; Notice of Availability of the Final Environmental Impact Statement for the Spire STL Pipeline Project The staff of the Federal Energy Regulatory Commission (FERC or Commission) has prepared a final environmental impact statement (EIS) for the continued operation of the Spire STL Pipeline Project (Spire STL), proposed by Spire STL Pipeline LLC (Spire) in the above-referenced docket. Spire requests the Commission to reissue a Certificate of Public Convenience and Necessity authorizing operation of the Spire STL. The final EIS assesses the continued operation of the Spire STL in accordance with the requirements of the National Environmental Policy Act (NEPA). FERC staff concludes that impacts from the continued operation of the Spire STL would be less than significant, with the exception of climate change impacts resulting from GHG emissions that are not characterized as significant or insignificant. The final EIS addresses the potential environmental effects of the continued operation of the following project facilities: PO 00000 Frm 00048 Fmt 4703 Sfmt 4703 • 59.2 miles of 24-inch-diameter pipeline in Scott, Greene, and Jersey Counties, Illinois and St. Charles and St. Louis Counties, Missouri; • 6.0 miles of 24-inch-diameter pipeline (the North County Extension) in St. Louis County, Missouri; and • three new meter stations—the Rockies Express Pipeline LLC (REX) Receipt Station in Scott County, Illinois and the Laclede/Lange Delivery Station and Chain of Rocks station in St. Louis County, Missouri. The Commission mailed a copy of the Notice of Availability of the final EIS to federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American tribes; potentially affected landowners and other interested individuals and groups; and newspapers and libraries in the project area. The final EIS is only available in electronic format. It may be viewed and downloaded from the FERC’s website (www.ferc.gov), on the natural gas environmental documents page (https://www.ferc.gov/industriesdata/natural-gas/environment/ environmental-documents). In addition, the final EIS may be accessed by using the eLibrary link on the FERC’s website. Click on the eLibrary link (https:// elibrary.ferc.gov/eLibrary/search) select ‘‘General Search’’ and enter the docket number in the ‘‘Docket Number’’ field, excluding the last three digits (i.e., CP17–40). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC website (www.ferc.gov) using the eLibrary link. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription that allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to https://www.ferc.gov/ ferc-online/overview to register for eSubscription. E:\FR\FM\14OCN1.SGM 14OCN1

Agencies

[Federal Register Volume 87, Number 198 (Friday, October 14, 2022)]
[Notices]
[Pages 62405-62406]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-22367]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 349-157]


Alabama Power Company; Notice of Application Accepted for Filing 
and Soliciting Comments, Motions To Intervene, and Protests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Non-Project Use of Project Lands and 
Waters.
    b. Project No.: 349-157.
    c. Date Filed: July 21, 2022, as supplemented on September 23, 
2022.
    d. Applicant: Alabama Power Company.
    e. Name of Project: Martin Dam Hydroelectric Project.
    f. Location: The Martin Dam Hydroelectric Project is located on the 
Tallapoosa River (Lake Martin), in Tallapoosa, Elmore, and Coosa 
counties, Alabama, and occupies federal land administered by the U.S. 
Bureau of Land Management; the non-project use is located in Elmore 
County.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
    h. Applicant Contact: Unzell Kelley, Alabama Power Company at (205) 
517-0885 or [email protected].
    i. FERC Contact: Shana High at (202) 502-8674 or 
[email protected].
    j. Deadline for filing motions to intervene and protests: November 
7, 2022.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, and protests using the Commission's 
eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. 
Commenters can submit brief comments up to 6,000 characters, without 
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact 
information at the end of your comments. For assistance, please contact 
FERC Online Support at [email protected], (866) 208-3676 (toll 
free), or (202) 502-8659 (TTY). In lieu of electronic filing, you may 
submit a paper copy. Submissions sent via the U.S. Postal Service must 
be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE, Room 1A, Washington, DC 20426. 
Submissions sent via any other carrier must be addressed to: Kimberly 
D. Bose,

[[Page 62406]]

Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, 
Rockville, Maryland 20852. The first page of any filing should include 
docket number P-349-157. Comments emailed to Commission staff are not 
considered part of the Commission record.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person whose name appears on the official service 
list for the project. Further, if an intervenor files comments or 
documents with the Commission relating to the merits of an issue that 
may affect the responsibilities of a particular resource agency, they 
must also serve a copy of the document on that resource agency.
    k. Description of Request: Alabama Power Company is requesting 
Commission authorization to permit Russell Lands, Inc. to expand 
Kowaliga Marina. As proposed, Kowaliga Marina would include 13 docks 
that would accommodate 258 boats and 45 personal watercraft, two 
forklift piers, a boat ramp, four breakwaters, a seawall, and riprap.
    l. Locations of the Application: This filing may be viewed on the 
Commission's website at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. You may also register 
online at https://www.ferc.gov/docs-filing/esubscription.asp to be 
notified via email of new filings and issuances related to this or 
other pending projects. For assistance, call 1-866-208-3676 or email 
[email protected], for TTY, call (202) 502-8659. Agencies may 
obtain copies of the application directly from the applicant.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214, respectively. In determining the appropriate action to take, the 
Commission will consider all protests or other comments filed, but only 
those who file a motion to intervene in accordance with the 
Commission's Rules may become a party to the proceeding. Any comments, 
protests, or motions to intervene must be received on or before the 
specified comment date for the particular application.
    o. Filing and Service of Documents: Any filing must (1) bear in all 
capital letters the title ``COMMENTS'', ``PROTEST'', or ``MOTION TO 
INTERVENE'' as applicable; (2) set forth in the heading the name of the 
applicant and the project number of the application to which the filing 
responds; (3) furnish the name, address, and telephone number of the 
person commenting, protesting or intervening; and (4) otherwise comply 
with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, motions to intervene, or protests must set forth their 
evidentiary basis. Any filing made by an intervenor must be accompanied 
by proof of service on all persons listed in the service list prepared 
by the Commission in this proceeding, in accordance with 18 CFR 
385.2010.

    Dated: October 7, 2022.
Kimberly D. Bose,
Secretary.