Download as PDF 60674 Federal Register / Vol. 87, No. 193 / Thursday, October 6, 2022 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 10661–051] lotter on DSK11XQN23PROD with NOTICES1 Indiana Michigan Power Company; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Subsequent License. b. Project No.: 10661–051. c. Date filed: September 30, 2021. d. Applicant: Indiana Michigan Power Company. e. Name of Project: Constantine Hydroelectric Project (Constantine Project). f. Location: The Constantine Project is located on the St. Joseph River in the Village of Constantine in St. Joseph County, Michigan. The project does not occupy federal lands. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Jonathan Magalski, Environmental Supervisor, Renewables, Indiana Michigan Power Company; 1 Riverside Plaza, Columbus, Ohio 43215 at (614) 716–2240 or email at jmmagalski@aep.com. i. FERC Contact: Lee Emery at (202) 502–8379 or email at lee.emery@ ferc.gov. j. Deadline for filing comments, recommendations, terms and conditions, and prescriptions: 60 days from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice. The Commission strongly encourages electronic filing. Please file motions to intervene, protests, comments, recommendations, preliminary terms and conditions, and preliminary fishway prescriptions using the using the Commission’s eFiling system at https://ferconline.ferc.gov/FERCOnline. aspx. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://ferconline. ferc.gov/QuickComment.aspx. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you VerDate Sep<11>2014 17:46 Oct 05, 2022 Jkt 259001 may submit a paper request. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include docket number P–10661–051. The Commission’s Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application has been accepted for filing and is now ready for environmental analysis. The Council on Environmental Quality (CEQ) issued a final rule on April 20, 2022, revising the regulations under 40 CFR parts 1502, 1507, and 1508 that federal agencies use to implement the National Environmental Policy Act (NEPA) (see National Environmental Policy Act Implementing Regulations Revisions, 87 FR 23,453– 70). The final rule became effective on May 20, 2022. Commission staff intends to conduct its NEPA review in accordance with CEQ’s new regulations. l. The Constantine Project consists of: (1) an 525-acre reservoir with a storage capacity of 5,750 acre-feet at a water surface elevation of 782.94 feet National Geodetic Vertical Datum (NGVD); (2) a 561.25-foot-long dam consisting of, from east to west: (a) a 250-foot-long, 22.5foot-high embankment with a top elevation of 790 feet NGVD, (b) a 241.25-foot-long, 12-foot-high uncontrolled concrete overflow spillway dam with a fixed crest elevation of 781.96 feet NGVD, topped by 0.94-foothigh flashboards with a crest elevation of 782.90 feet NGVD, which includes a 4-foot sluice gate at the left abutment, and (c) a 70-foot-long earthen embankment; (3) a 650-foot-long, 20foot-high earthen detached dike that begins 1,500 feet east of the left abutment of the spillway dam, with a top elevation of 790 feet NGVD; (4) a 68foot-long, 20-foot-high concrete headgate structure consisting of seven wooden 15-foot-high vertical slide gates with a sill elevation of 770.00 feet NGVD with six 7.83-foot-long gates and one 6.75-foot-long gate located at the PO 00000 Frm 00034 Fmt 4703 Sfmt 4703 entrance to the power canal; (5) a 1,270foot-long power canal with a bottom width of 60 feet; (6) a 140-foot-long, 30foot-wide brick powerhouse; (7) trash racks in front of the forebay at the entrance to the powerhouse; (8) four vertical shaft Francis turbines each coupled to a 300-kilowatt generator, for a total installed capacity of 1.2 megawatts; (9) a switchyard adjacent to the powerhouse with three step-up transformers; (10) a 50-foot-long, 2.4kilovolt transmission line; and (11) appurtenant facilities. The Constantine Project is operated in a run-of-river mode with an estimated average annual energy production of 4,933 megawatt-hours. Indiana Michigan Power Company proposes to continue operating the project as a runof-river facility and does not propose any new construction to the project. m. A copy of the application can be viewed on the Commission’s website at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact FERC at FERCOnllineSupport@ferc.gov or call toll-free, (886) 208–3676 or TTY, (202) 502–8659. n. Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, and .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. All filings must (1) bear in all capital letters the title ‘‘PROTEST’’, ‘‘MOTION TO INTERVENE’’, ‘‘COMMENTS,’’ ‘‘REPLY COMMENTS,’’ ‘‘RECOMMENDATIONS,’’ ‘‘PRELIMINARY TERMS AND CONDITIONS,’’ or ‘‘PRELIMINARY FISHWAY PRESCRIPTIONS;’’ (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) E:\FR\FM\06OCN1.SGM 06OCN1 Federal Register / Vol. 87, No. 193 / Thursday, October 6, 2022 / Notices otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions or prescriptions must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. o. The license applicant must file no later than 60 days following the date of issuance of this notice: (1) a copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification. Please note that the certification request must comply with 40 CFR 121.5(b), including documentation that a pre-filing meeting request was submitted to the certifying authority at least 30 days prior to submitting the certification request. Please note that the certification request must be sent to the certifying authority and to the Commission concurrently. p. Procedural schedule: The application will be processed according to the following schedule. Revisions to the schedule will be made as appropriate. Milestone Target date Deadline for Filing Protest, Motion to Intervene, Comments, Recommendations, Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions. Deadline for Filing Reply Comments .......................................................................................................................................... q. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of this notice. Dated: September 30, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–21762 Filed 10–5–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings lotter on DSK11XQN23PROD with NOTICES1 Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: Filings in Existing Proceedings Docket Numbers: RP20–614–005; RP20–618–002. Applicants: Transcontinental Gas Pipe Line Company, LLC, Transcontinental Gas Pipe Line Company, LLC. Description: Notice of Transcontinental Gas Pipe Line Company, LLC in Lieu of Pro Forma Tariff Filing. Filed Date: 9/29/22. Accession Number: 20220929–5193. Comment Date: 5 p.m. ET 10/5/22. Any person desiring to protest in any the above proceedings must file in accordance with Rule 211 of the Commission’s Regulations (18 CFR 385.211) on or before 5:00 p.m. Eastern time on the specified comment date. Filings Instituting Proceedings Docket Numbers: PR22–72–000. VerDate Sep<11>2014 17:46 Oct 05, 2022 Jkt 259001 Applicants: Permian Highway Pipeline LLC. Description: § 284.123 Rate Filing: Fuel Filing 10.01.2022 to be effective 10/1/2022. Filed Date: 9/29/22. Accession Number: 20220929–5171. Comment Date: 5 p.m. ET 10/20/22. Docket Numbers: PR22–73–000. Applicants: Centana Intrastate Pipeline, LLC. Description: § 284.123(g) Rate Filing: Centana SOC 7.0.0 to be effective 9/1/ 2022. Filed Date: 9/30/22. Accession Number: 20220930–5056. Comment Date: 5 p.m. ET 10/21/22 284.123(g) Protests: 5 p.m. ET 11/29/ 22. Docket Numbers: RP22–1258–000. Applicants: Colorado Interstate Gas Company, L.L.C. Description: § 4(d) Rate Filing: Negotiated Rate Agreement Filing (Northwestern Nov 22) to be effective 11/1/2022. Filed Date: 9/29/22. Accession Number: 20220929–5034. Comment Date: 5 p.m. ET 10/11/22. Docket Numbers: RP22–1259–000. Applicants: Ruby Pipeline, L.L.C. Description: § 4(d) Rate Filing: Negotiated Rate Agreements (SWG Oct and Nov) to be effective 10/1/2022. Filed Date: 9/29/22. Accession Number: 20220929–5037. Comment Date: 5 p.m. ET 10/11/22. Docket Numbers: RP22–1260–000. Applicants: El Paso Natural Gas Company, L.L.C. Description: § 4(d) Rate Filing: Negotiated Rate Agreements (Morgan_ ETC_Eco_EOG) to be effective 11/1/ 2022. PO 00000 Frm 00035 Fmt 4703 60675 Sfmt 4703 November 2022. January 2023. Filed Date: 9/29/22. Accession Number: 20220929–5041. Comment Date: 5 p.m. ET 10/11/22. Docket Numbers: RP22–1261–000. Applicants: Young Gas Storage Company, Ltd. Description: Compliance filing: Operational Purchase and Sale Report 2022 to be effective N/A. Filed Date: 9/29/22. Accession Number: 20220929–5050. Comment Date: 5 p.m. ET 10/11/22. Docket Numbers: RP22–1262–000. Applicants: Wyoming Interstate Company, L.L.C. Description: Compliance filing: Operational Purchase and Sale Report 2022 to be effective N/A. Filed Date: 9/29/22. Accession Number: 20220929–5052. Comment Date: 5 p.m. ET 10/11/22. Docket Numbers: RP22–1263–000. Applicants: Transcontinental Gas Pipe Line Company, LLC. Description: § 4(d) Rate Filing: List of Non-Conforming Service Agreements (CEC_VNG_Interim Svc) to be effective 11/1/2022. Filed Date: 9/29/22. Accession Number: 20220929–5053. Comment Date: 5 p.m. ET 10/11/22. Docket Numbers: RP22–1264–000. Applicants: Enable Gas Transmission, LLC. Description: § 4(d) Rate Filing: Fuel Tracker Filing—Effective November 1, 2022 to be effective 11/1/2022. Filed Date: 9/29/22. Accession Number: 20220929–5070. Comment Date: 5 p.m. ET 10/11/22. Docket Numbers: RP22–1265–000. E:\FR\FM\06OCN1.SGM 06OCN1

Agencies

[Federal Register Volume 87, Number 193 (Thursday, October 6, 2022)]
[Notices]
[Pages 60674-60675]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-21762]



[[Page 60674]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 10661-051]


Indiana Michigan Power Company; Notice of Application Accepted 
for Filing, Soliciting Motions To Intervene and Protests, Ready for 
Environmental Analysis, and Soliciting Comments, Preliminary Terms and 
Conditions, and Preliminary Fishway Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Subsequent License.
    b. Project No.: 10661-051.
    c. Date filed: September 30, 2021.
    d. Applicant: Indiana Michigan Power Company.
    e. Name of Project: Constantine Hydroelectric Project (Constantine 
Project).
    f. Location: The Constantine Project is located on the St. Joseph 
River in the Village of Constantine in St. Joseph County, Michigan. The 
project does not occupy federal lands.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Jonathan Magalski, Environmental Supervisor, 
Renewables, Indiana Michigan Power Company; 1 Riverside Plaza, 
Columbus, Ohio 43215 at (614) 716-2240 or email at [email protected].
    i. FERC Contact: Lee Emery at (202) 502-8379 or email at 
[email protected].
    j. Deadline for filing comments, recommendations, terms and 
conditions, and prescriptions: 60 days from the issuance date of this 
notice; reply comments are due 105 days from the issuance date of this 
notice.
    The Commission strongly encourages electronic filing. Please file 
motions to intervene, protests, comments, recommendations, preliminary 
terms and conditions, and preliminary fishway prescriptions using the 
using the Commission's eFiling system at https://ferconline.ferc.gov/FERCOnline.aspx. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
https://ferconline.ferc.gov/QuickComment.aspx. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper 
request. Submissions sent via the U.S. Postal Service must be addressed 
to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 
888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent 
via any other carrier must be addressed to: Kimberly D. Bose, 
Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, 
Rockville, Maryland 20852. The first page of any filing should include 
docket number P-10661-051.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted for filing and is now ready 
for environmental analysis.
    The Council on Environmental Quality (CEQ) issued a final rule on 
April 20, 2022, revising the regulations under 40 CFR parts 1502, 1507, 
and 1508 that federal agencies use to implement the National 
Environmental Policy Act (NEPA) (see National Environmental Policy Act 
Implementing Regulations Revisions, 87 FR 23,453-70). The final rule 
became effective on May 20, 2022. Commission staff intends to conduct 
its NEPA review in accordance with CEQ's new regulations.
    l. The Constantine Project consists of: (1) an 525-acre reservoir 
with a storage capacity of 5,750 acre-feet at a water surface elevation 
of 782.94 feet National Geodetic Vertical Datum (NGVD); (2) a 561.25-
foot-long dam consisting of, from east to west: (a) a 250-foot-long, 
22.5-foot-high embankment with a top elevation of 790 feet NGVD, (b) a 
241.25-foot-long, 12-foot-high uncontrolled concrete overflow spillway 
dam with a fixed crest elevation of 781.96 feet NGVD, topped by 0.94-
foot-high flashboards with a crest elevation of 782.90 feet NGVD, which 
includes a 4-foot sluice gate at the left abutment, and (c) a 70-foot-
long earthen embankment; (3) a 650-foot-long, 20-foot-high earthen 
detached dike that begins 1,500 feet east of the left abutment of the 
spillway dam, with a top elevation of 790 feet NGVD; (4) a 68-foot-
long, 20-foot-high concrete headgate structure consisting of seven 
wooden 15-foot-high vertical slide gates with a sill elevation of 
770.00 feet NGVD with six 7.83-foot-long gates and one 6.75-foot-long 
gate located at the entrance to the power canal; (5) a 1,270-foot-long 
power canal with a bottom width of 60 feet; (6) a 140-foot-long, 30-
foot-wide brick powerhouse; (7) trash racks in front of the forebay at 
the entrance to the powerhouse; (8) four vertical shaft Francis 
turbines each coupled to a 300-kilowatt generator, for a total 
installed capacity of 1.2 megawatts; (9) a switchyard adjacent to the 
powerhouse with three step-up transformers; (10) a 50-foot-long, 2.4-
kilovolt transmission line; and (11) appurtenant facilities.
    The Constantine Project is operated in a run-of-river mode with an 
estimated average annual energy production of 4,933 megawatt-hours. 
Indiana Michigan Power Company proposes to continue operating the 
project as a run-of-river facility and does not propose any new 
construction to the project.
    m. A copy of the application can be viewed on the Commission's 
website at https://www.ferc.gov using the ``eLibrary'' link. Enter the 
docket number excluding the last three digits in the docket number 
field to access the document.
    At this time, the Commission has suspended access to the 
Commission's Public Reference Room, due to the proclamation declaring a 
National Emergency concerning the Novel Coronavirus Disease (COVID-19), 
issued by the President on March 13, 2020. For assistance, contact FERC 
at [email protected] or call toll-free, (886) 208-3676 or 
TTY, (202) 502-8659.
    n. Anyone may submit comments, a protest, or a motion to intervene 
in accordance with the requirements of Rules of Practice and Procedure, 
18 CFR 385.210, .211, and .214. In determining the appropriate action 
to take, the Commission will consider all protests or other comments 
filed, but only those who file a motion to intervene in accordance with 
the Commission's Rules may become a party to the proceeding. Any 
comments, protests, or motions to intervene must be received on or 
before the specified comment date for the particular application.
    All filings must (1) bear in all capital letters the title 
``PROTEST'', ``MOTION TO INTERVENE'', ``COMMENTS,'' ``REPLY COMMENTS,'' 
``RECOMMENDATIONS,'' ``PRELIMINARY TERMS AND CONDITIONS,'' or 
``PRELIMINARY FISHWAY PRESCRIPTIONS;'' (2) set forth in the heading the 
name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person protesting or intervening; and (4)

[[Page 60675]]

otherwise comply with the requirements of 18 CFR 385.2001 through 
385.2005. All comments, recommendations, terms and conditions or 
prescriptions must set forth their evidentiary basis and otherwise 
comply with the requirements of 18 CFR 4.34(b). Agencies may obtain 
copies of the application directly from the applicant. A copy of any 
protest or motion to intervene must be served upon each representative 
of the applicant specified in the particular application. A copy of all 
other filings in reference to this application must be accompanied by 
proof of service on all persons listed in the service list prepared by 
the Commission in this proceeding, in accordance with 18 CFR 4.34(b) 
and 385.2010.
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    o. The license applicant must file no later than 60 days following 
the date of issuance of this notice: (1) a copy of the water quality 
certification; (2) a copy of the request for certification, including 
proof of the date on which the certifying agency received the request; 
or (3) evidence of waiver of water quality certification. Please note 
that the certification request must comply with 40 CFR 121.5(b), 
including documentation that a pre-filing meeting request was submitted 
to the certifying authority at least 30 days prior to submitting the 
certification request. Please note that the certification request must 
be sent to the certifying authority and to the Commission concurrently.
    p. Procedural schedule: The application will be processed according 
to the following schedule. Revisions to the schedule will be made as 
appropriate.

------------------------------------------------------------------------
                 Milestone                           Target date
------------------------------------------------------------------------
Deadline for Filing Protest, Motion to       November 2022.
 Intervene, Comments, Recommendations,
 Preliminary Terms and Conditions, and
 Preliminary Fishway Prescriptions.
Deadline for Filing Reply Comments.........  January 2023.
------------------------------------------------------------------------

    q. Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of this notice.

    Dated: September 30, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-21762 Filed 10-5-22; 8:45 am]