Hackett Mills Hydro Associates, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments, 56941-56942 [2022-20065]

Download as PDF Federal Register / Vol. 87, No. 179 / Friday, September 16, 2022 / Notices 2. American Climate Partners is now the exemptee of the Rapidan Mill Hydroelectric Project No. 8402. All correspondence must be forwarded to Mr. Michael Collins, American Climate Partners, 7026 Old Rapidan Road (State Rt. 673), Rapidan, Virginia 22960, Phone: (540) 672–2542, Email: info@ naturalcapital.us. Dated: September 12, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–20063 Filed 9–15–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER22–2824–000] khammond on DSKJM1Z7X2PROD with NOTICES Yellow Pine Solar, LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding of Yellow Pine Solar, LLC’s application for market-based rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is October 3, 2022. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically may mail similar pleadings to the VerDate Sep<11>2014 16:43 Sep 15, 2022 Jkt 256001 Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Dated: September 12, 2022. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2022–20075 Filed 9–15–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 6398–026] Hackett Mills Hydro Associates, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Subsequent Minor License. b. Project No.: P–6398–026. c. Date filed: August 31, 2022. d. Applicant: Hackett Mills Hydro Associates, LLC (Hackett Mills Hydro). e. Name of Project: Hackett Mills Hydroelectric Project. f. Location: On the Little Androscoggin River, in the towns of Poland and Minot, in Androscoggin County, Maine. The project does not occupy any federal land. PO 00000 Frm 00016 Fmt 4703 Sfmt 4703 56941 g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Matthew Nini, Hackett Mills Hydro Associates, LLC c/o Eagle Creek Renewable Energy, LLC, 7315 Wisconsin Avenue, Suite 1100W, Bethesda, Maryland 20814; phone: (973) 998–8171; email: matthew.nini@ eaglecreekre.com. i. FERC Contact: John Matkowski at (202) 502–8576 or john.matkowski@ ferc.gov. j. Cooperating agencies: Federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues that wish to cooperate in the preparation of the environmental document should follow the instructions for filing such requests described in item l below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See, 94 FERC ¶ 61,076 (2001). k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission’s regulations, if any resource agency, Indian Tribe, or person believes that an additional scientific study should be conducted in order to form an adequate factual basis for a complete analysis of the application on its merit, the resource agency, Indian Tribe, or person must file a request for a study with the Commission not later than 60 days from the date of filing of the application, and serve a copy of the request on the applicant. l. Deadline for filing additional study requests and requests for cooperating agency status: October 31, 2022. The Commission strongly encourages electronic filing. Please file additional study requests and requests for cooperating agency status using the Commission’s eFiling system at https:// ferconline.ferc.gov/FERCOnline.aspx. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. All filings must clearly identify the project name and docket number on the first page: Hackett Mills Hydroelectric Project (P– 6398–026). E:\FR\FM\16SEN1.SGM 16SEN1 khammond on DSKJM1Z7X2PROD with NOTICES 56942 Federal Register / Vol. 87, No. 179 / Friday, September 16, 2022 / Notices m. The application is not ready for environmental analysis at this time. n. The existing Hackett Mills Project consists of: (1) a 186-foot-long dam that consists of two spillway sections: a 101foot-long, 8-foot-high rock filled timber crib dam with an uncontrolled spillway (main spillway section) and a 85-footlong, 8-foot-high concrete gravity dam with three uncontrolled bays (secondary spillway section); (2) an obsolete sluice gatehouse that connects the main spillway and the secondary spillway sections; (3) a 3.5-mile-long, 60-acre impoundment with no useable storage capacity at a normal maximum water surface elevation of 234.75 feet National Geodetic Vertical Datum of 1929 (NGVD 29); (4) a canal intake gate structure containing five gates; (5) a 100-foot-long, 25-foot-wide, 10-foot-deep power canal; (6) a powerhouse located at the end of the canal containing one 485-kilowatt right angle drive bulb turbine-generator unit, with a minimum hydraulic capacity of 80 cubic-feet-per-second (cfs) and a maximum hydraulic capacity of 474 cfs; (7) a downstream fish passage facility; (8) a 200-foot-long, 12.5-kilovolt transmission line; and (9) appurtenant facilities. The Hackett Mills Project is currently operated in a run-of-river mode and generates 1,602 megawatt-hours annually. Hackett Mills Hydro proposes to continue operating the project as a run-of-river facility and does not propose any new construction to the project. o. A copy of the application can be viewed on the Commission’s website at https://www.ferc.gov, using the ‘‘eLibrary’’ link. Enter the docket number, excluding the last three digits in the docket number field, to access the document (P–6398). For assistance, contact FERC at FERCOnlineSupport@ ferc.gov, or call toll-free, (866) 208–3676 or (202) 502–8659 (TTY). You may also register online at https://ferconline.ferc.gov/ FERCOnline.aspx to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. p. Procedural schedule and final amendments: The application will be processed according to the following preliminary schedule. Revisions to the schedule will be made as appropriate. Additional Study Requests due— October 31, 2022 Issue Deficiency Letter (if necessary)— November 2022 Request Additional Information— November 2022 Issue Scoping Document 1 for comments—February 2023 VerDate Sep<11>2014 16:43 Sep 15, 2022 Jkt 256001 Comments on Scoping Document 1— March 2023 Issue Acceptance Notice and Letter— April 2023 Issue Scoping Document 2 (if necessary)—April 2023 Issue Notice of Ready for Environmental Analysis—April 2023 Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. Dated: September 12, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–20065 Filed 9–15–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC22–118–000. Applicants: Eastover Solar LLC, PGR 2021 Lessee 17, LLC. Description: Application for Authorization Under Section 203 of the Federal Power Act of Eastover Solar LLC. Filed Date: 9/9/22. Accession Number: 20220909–5209. Comment Date: 5 p.m. ET 9/30/22. Take notice that the Commission received the following exempt wholesale generator filings: Docket Numbers: EG22–217–000. Applicants: Yellow Pine Solar, LLC. Description: Yellow Pine Solar, LLC submits Notice of Self-Certification of Exempt Wholesale Generator Status. Filed Date: 9/9/22. Accession Number: 20220909–5166. Comment Date: 5 p.m. ET 9/30/22. Docket Numbers: EG22–218–000. Applicants: Mesquite Solar 4, LLC. Description: Mesquite Solar 4, LLC submits Notice of Self-Certification of Exempt Wholesale Generator Status. Filed Date: 9/12/22. Accession Number: 20220912–5049. Comment Date: 5 p.m. ET 10/3/22. Docket Numbers: EG22–219–000. Applicants: Mesquite Solar 5, LLC. Description: Self-Certification of EG for Mesquite Solar 5, LLC. Filed Date: 9/12/22. Accession Number: 20220912–5139. Comment Date: 5 p.m. ET 10/3/22. Take notice that the Commission received the following electric rate filings: PO 00000 Frm 00017 Fmt 4703 Sfmt 4703 Docket Numbers: ER22–2525–000. Applicants: Gridmatic Inc. Description: Supplement to July 29, 2022, Gridmatic Inc. tariff filing per 35.12: MBR Tariff Application. Filed Date: 9/7/22. Accession Number: 20220907–5119. Comment Date: 5 p.m. ET 9/19/22. Docket Numbers: ER22–2829–000. Applicants: American Electric Power Service Corporation, Ohio Power Company, AEP Ohio Transmission Company, Inc., PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: American Electric Power Service Corporation submits tariff filing per 35.13(a)(2)(iii: AEP submits Two FAs re: ILDSA SA No. 1336 to be effective 11/ 12/2022. Filed Date: 9/12/22. Accession Number: 20220912–5026. Comment Date: 5 p.m. ET 10/3/22. Docket Numbers: ER22–2830–000. Applicants: The Connecticut Light and Power Company. Description: § 205(d) Rate Filing: New York Transco LLC—Engineering, Design and Procurement Agreement to be effective 9/13/2022. Filed Date: 9/12/22. Accession Number: 20220912–5068. Comment Date: 5 p.m. ET 10/3/22. Docket Numbers: ER22–2831–000. Applicants: ISO New England Inc., Vermont Transco LLC. Description: § 205(d) Rate Filing: ISO New England Inc. submits tariff filing per 35.13(a)(2)(iii: Vermont Transco LLC; Tariff Clean-Up Filing to be effective 5/1/2022. Filed Date: 9/12/22. Accession Number: 20220912–5080. Comment Date: 5 p.m. ET 10/3/22. Docket Numbers: ER22–2832–000. Applicants: Cardinal Point LLC. Description: Baseline eTariff Filing: Reactive Power Compensation Baseline Filing to be effective 10/31/2022. Filed Date: 9/12/22. Accession Number: 20220912–5084. Comment Date: 5 p.m. ET 10/3/22. Docket Numbers: ER22–2833–000. Applicants: Alabama Power Company, Georgia Power Company, Mississippi Power Company Description: § 205(d) Rate Filing: Alabama Power Company submits tariff filing per 35.13(a)(2)(iii: Middleton Solar Farm LGIA Filing to be effective 8/26/2022. Filed Date: 9/12/22. Accession Number: 20220912–5091. Comment Date: 5 p.m. ET 10/3/22. Docket Numbers: ER22–2834–000. Applicants: ISO New England Inc., Green Mountain Power Corporation. E:\FR\FM\16SEN1.SGM 16SEN1

Agencies

[Federal Register Volume 87, Number 179 (Friday, September 16, 2022)]
[Notices]
[Pages 56941-56942]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-20065]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 6398-026]


Hackett Mills Hydro Associates, LLC; Notice of Application 
Tendered for Filing With the Commission and Soliciting Additional Study 
Requests and Establishing Procedural Schedule for Relicensing and a 
Deadline for Submission of Final Amendments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Subsequent Minor License.
    b. Project No.: P-6398-026.
    c. Date filed: August 31, 2022.
    d. Applicant: Hackett Mills Hydro Associates, LLC (Hackett Mills 
Hydro).
    e. Name of Project: Hackett Mills Hydroelectric Project.
    f. Location: On the Little Androscoggin River, in the towns of 
Poland and Minot, in Androscoggin County, Maine. The project does not 
occupy any federal land.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Matthew Nini, Hackett Mills Hydro Associates, 
LLC c/o Eagle Creek Renewable Energy, LLC, 7315 Wisconsin Avenue, Suite 
1100W, Bethesda, Maryland 20814; phone: (973) 998-8171; email: 
[email protected].
    i. FERC Contact: John Matkowski at (202) 502-8576 or 
[email protected].
    j. Cooperating agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item l below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See, 94 FERC ] 
61,076 (2001).
    k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's 
regulations, if any resource agency, Indian Tribe, or person believes 
that an additional scientific study should be conducted in order to 
form an adequate factual basis for a complete analysis of the 
application on its merit, the resource agency, Indian Tribe, or person 
must file a request for a study with the Commission not later than 60 
days from the date of filing of the application, and serve a copy of 
the request on the applicant.
    l. Deadline for filing additional study requests and requests for 
cooperating agency status: October 31, 2022.
    The Commission strongly encourages electronic filing. Please file 
additional study requests and requests for cooperating agency status 
using the Commission's eFiling system at https://ferconline.ferc.gov/FERCOnline.aspx. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy. 
Submissions sent via the U.S. Postal Service must be addressed to: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via 
any other carrier must be addressed to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, 
Maryland 20852. All filings must clearly identify the project name and 
docket number on the first page: Hackett Mills Hydroelectric Project 
(P-6398-026).

[[Page 56942]]

    m. The application is not ready for environmental analysis at this 
time.
    n. The existing Hackett Mills Project consists of: (1) a 186-foot-
long dam that consists of two spillway sections: a 101-foot-long, 8-
foot-high rock filled timber crib dam with an uncontrolled spillway 
(main spillway section) and a 85-foot-long, 8-foot-high concrete 
gravity dam with three uncontrolled bays (secondary spillway section); 
(2) an obsolete sluice gatehouse that connects the main spillway and 
the secondary spillway sections; (3) a 3.5-mile-long, 60-acre 
impoundment with no useable storage capacity at a normal maximum water 
surface elevation of 234.75 feet National Geodetic Vertical Datum of 
1929 (NGVD 29); (4) a canal intake gate structure containing five 
gates; (5) a 100-foot-long, 25-foot-wide, 10-foot-deep power canal; (6) 
a powerhouse located at the end of the canal containing one 485-
kilowatt right angle drive bulb turbine-generator unit, with a minimum 
hydraulic capacity of 80 cubic-feet-per-second (cfs) and a maximum 
hydraulic capacity of 474 cfs; (7) a downstream fish passage facility; 
(8) a 200-foot-long, 12.5-kilovolt transmission line; and (9) 
appurtenant facilities.
    The Hackett Mills Project is currently operated in a run-of-river 
mode and generates 1,602 megawatt-hours annually. Hackett Mills Hydro 
proposes to continue operating the project as a run-of-river facility 
and does not propose any new construction to the project.
    o. A copy of the application can be viewed on the Commission's 
website at https://www.ferc.gov, using the ``eLibrary'' link. Enter the 
docket number, excluding the last three digits in the docket number 
field, to access the document (P-6398). For assistance, contact FERC at 
[email protected], or call toll-free, (866) 208-3676 or (202) 
502-8659 (TTY).
    You may also register online at https://ferconline.ferc.gov/FERCOnline.aspx to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    p. Procedural schedule and final amendments: The application will 
be processed according to the following preliminary schedule. Revisions 
to the schedule will be made as appropriate.
Additional Study Requests due--October 31, 2022
Issue Deficiency Letter (if necessary)--November 2022
Request Additional Information--November 2022
Issue Scoping Document 1 for comments--February 2023
Comments on Scoping Document 1--March 2023
Issue Acceptance Notice and Letter--April 2023
Issue Scoping Document 2 (if necessary)--April 2023
Issue Notice of Ready for Environmental Analysis--April 2023
    Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

    Dated: September 12, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-20065 Filed 9-15-22; 8:45 am]