Transcontinental Gas Pipe Line Company, LLC; Notice of Application and Establishing Intervention Deadline, 52759-52761 [2022-18559]

Download as PDF 52759 Federal Register / Vol. 87, No. 166 / Monday, August 29, 2022 / Notices (Commission or FERC) is soliciting public comment on the currently approved information collection FERC– 577 (Natural Gas Facilities: Environmental Review and Compliance). Comments on the collection of information are due October 28, 2022. ADDRESSES: You may submit your comments (identified by Docket No. IC22–26–000) by one of the following methods: Electronic filing through https:// www.ferc.gov, is preferred. • Electronic Filing: Documents must be filed in acceptable native applications and print-to-PDF, but not in scanned or picture format. • For those unable to file electronically, comments may be filed by USPS mail or by hand (including courier) delivery: Æ Mail via U.S. Postal Service Only: Addressed to: Federal Energy Regulatory Commission, Secretary of the Commission, 888 First Street NE, Washington, DC 20426. Æ Hand (including courier) delivery: Addressed to: Federal Energy DATES: Regulatory Commission, Secretary of the Commission,12225 Wilkins Avenue, Rockville, MD 20852. Instructions: All submissions must be formatted and filed in accordance with submission guidelines at: https:// www.ferc.gov. For user assistance, contact FERC Online Support by email at ferconlinesupport@ferc.gov, or by phone at (866) 208–3676 (toll-free). Docket: Users interested in receiving automatic notification of activity in this docket or in viewing/downloading comments and issuances in this docket may do so at https://www.ferc.gov. FOR FURTHER INFORMATION CONTACT: Ellen Brown may be reached by email at DataClearance@FERC.gov, telephone at (202) 502–8663. SUPPLEMENTARY INFORMATION: Title: FERC–577, Natural Gas Facilities: Environmental Review and Compliance. OMB Control No.: 1902–0128. Type of Request: Three-year extension of the FERC–577 with no changes to the current reporting requirements. Abstract: The FERC–577 contains the Commission’s information collection pertaining to regulations which implement the National Environmental Policy Act (NEPA) as well as the reporting requirements for landowner notifications. These requirements are contained in 18 CFR parts 2, 157, 284, and 380. The information to be submitted includes draft environmental material in accordance with the provisions of part 380 of FERC’s regulations in order to implement the Commission’s procedures under NEPA. Without such information, the Commission would be unable to fulfill its statutory responsibilities under the Natural Gas Act (NGA), NEPA, and the Energy Policy Act of 2005. Specifically, these responsibilities include ensuring company activities remain consistent with the public interest, which is specified in the NGA and inherent in the other statutes. Type of Respondents: Companies proposing Natural Gas Projects under section 7 and Jurisdictional Gas Pipeline and Storage Companies. Estimate of Annual Burden: 1 The Commission estimates the annual public reporting burden and cost 2 for the information collection as follows. FERC–577, NATURAL GAS FACILITIES: ENVIRONMENTAL REVIEW AND COMPLIANCE Number of respondents Number of responses per respondent Total number of responses Average burden hours and average cost per response ($) (rounded) Total annual burden hours and total annual cost ($) (rounded) Cost per respondent ($) (rounded) (1) (2) (1) * (2) = (3) (4) (3) * (4) = (5) (5) ÷ (1) = (6) Gas Pipeline Certificates 3. Landowners Notification 4. khammond on DSKJM1Z7X2PROD with NOTICES Total ...................... 101 16 1,616 164 144 ........................ ........................ Comments: Comments are invited on: (1) whether the collection of information is necessary for the proper performance of the functions of the Commission, including whether the information will have practical utility; (2) the accuracy of the agency’s estimate of the burden and cost of the collection of information, including the validity of the methodology and assumptions used; (3) ways to enhance the quality, utility and clarity of the information collection; and (4) ways to minimize the burden of the collection of information on those 1 Burden is defined as the total time, effort, or financial resources expended by persons to generate, maintain, retain, or disclose or provide information to or for a federal agency. See 5 CFR 1320 for additional information on the definition of information collection burden. VerDate Sep<11>2014 17:01 Aug 26, 2022 Jkt 256001 23,616 193.52 hours; $17,610.32. 2 hours; $182 .............. 312,725 hours; $28,457,975. 47,232 hours; $4,298,112. 25,232 ..................................... 359,957 hours; $32,756,087. who are to respond, including the use of automated collection techniques or other forms of information technology. Dated: August 23, 2022. Kimberly D. Bose, Secretary. $281,762.13 $26,208 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP22–495–000] [FR Doc. 2022–18566 Filed 8–26–22; 8:45 am] BILLING CODE 6717–01–P Transcontinental Gas Pipe Line Company, LLC; Notice of Application and Establishing Intervention Deadline Take notice that on August 9, 2022, Transcontinental Gas Pipe Line Company, LLC (Transco), Post Office Box 1396, Houston, Texas 77251, filed 2 The Commission staff estimates that industry is similarly situated in terms of hourly cost (for wages plus benefits). Based on the Commission’s FY (Fiscal Year) 2022 average cost (for wages plus benefits), $91.00/hour is used. PO 00000 Frm 00023 Fmt 4703 Sfmt 4703 3 Requirements are found in 18 CFR parts 2, 157, and 380. 4 Requirements are found in 18 CFR 157(d), 157(f), 2.55(a), 2.55(b), 284.11, and 380.15. E:\FR\FM\29AUN1.SGM 29AUN1 khammond on DSKJM1Z7X2PROD with NOTICES 52760 Federal Register / Vol. 87, No. 166 / Monday, August 29, 2022 / Notices an application under section 7(c) of the Natural Gas Act (NGA), and Part 157 of the Commission’s regulations to construct, install, modify, operate and maintain its Texas to Louisiana Energy Pathway Project (Project) and to authorize the conversion of 130,000 dekatherms per day (Dth/day) of capacity currently subject to Transco’s ‘‘IT Feeder System’’ to firm transportation capacity under the Project. Specifically, Transco requests authorization to (i) construct a new 15,900 horsepower (HP) compressor station in Fort Bend County, Texas, (ii) modify six existing compressor units at Compressor Station 40 in Hardin County, Texas, (iii) as well as perform programming updates at Compressor Station 23 in Victoria County, Texas to accommodate new flow conditions. Transco states that the capacity conversion, along with turnback capacity and incremental capacity, will yield the 364.4 million cubic feet per day (MMcf/d) of project capacity. Transco estimates the cost of the project to be $91,781,074, all as more fully set forth in the application which is on file with the Commission and open for public inspection. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. Any questions regarding the proposed project should be directed to Antauis Byrd, P.O. Box 1396, Houston, Texas 77251; by phone at (713) 215–3741; or by email to antauis.byrd@williams.com. Pursuant to Section 157.9 of the Commission’s Rules of Practice and Procedure,1 within 90 days of this Notice the Commission staff will either: complete its environmental review and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for 1 18 CFR (Code of Federal Regulations) 157.9. VerDate Sep<11>2014 17:01 Aug 26, 2022 Jkt 256001 Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or environmental assessment (EA) for this proposal. The filing of an EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Public Participation There are two ways to become involved in the Commission’s review of this project: you can file comments on the project, and you can file a motion to intervene in the proceeding. There is no fee or cost for filing comments or intervening. The deadline for filing a motion to intervene is 5:00 p.m. Eastern Time on September 13, 2022. Comments Any person wishing to comment on the project may do so. Comments may include statements of support or objections to the project as a whole or specific aspects of the project. The more specific your comments, the more useful they will be. To ensure that your comments are timely and properly recorded, please submit your comments on or before September 13, 2022. There are three methods you can use to submit your comments to the Commission. In all instances, please reference the Project docket number CP22–495–000 in your submission. (1) You may file your comments electronically by using the eComment feature, which is located on the Commission’s website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project; (2) You may file your comments electronically by using the eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select ‘‘General’’ and then select ‘‘Comment on a Filing’’; or PO 00000 Frm 00024 Fmt 4703 Sfmt 4703 (3) You may file a paper copy of your comments by mailing them to the following address below.2 Your written comments must reference the Project docket number (CP22–495–000). Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The Commission encourages electronic filing of comments (options 1 and 2 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. Persons who comment on the environmental review of this project will be placed on the Commission’s environmental mailing list, and will receive notification when the environmental documents (EA or EIS) are issued for this project and will be notified of meetings associated with the Commission’s environmental review process. The Commission considers all comments received about the project in determining the appropriate action to be taken. However, the filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding. For instructions on how to intervene, see below. Interventions Any person, which includes individuals, organizations, businesses, municipalities, and other entities,3 has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission’s orders in the U.S. Circuit Courts of Appeal. To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission’s Rules of Practice and Procedure 4 and the regulations under the NGA 5 by the intervention deadline for the project, which is September 13, 2022. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more 2 Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. 3 18 CFR 385.102(d). 4 18 CFR 385.214. 5 18 CFR 157.10. E:\FR\FM\29AUN1.SGM 29AUN1 khammond on DSKJM1Z7X2PROD with NOTICES Federal Register / Vol. 87, No. 166 / Monday, August 29, 2022 / Notices information about motions to intervene, refer to the FERC website at https:// www.ferc.gov/resources/guides/how-to/ intervene.asp. There are two ways to submit your motion to intervene. In both instances, please reference the Project docket number CP22–495–000 in your submission. (1) You may file your motion to intervene by using the Commission’s eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; first select ‘‘General’’ and then select ‘‘Intervention.’’ The eFiling feature includes a document-less intervention option; for more information, visit https://www.ferc.gov/docs-filing/efiling/ document-less-intervention.pdf.; or (2) You can file a paper copy of your motion to intervene, along with three copies, by mailing the documents to the address below.6 Your motion to intervene must reference the Project docket number CP22–495–000. Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The Commission encourages electronic filing of motions to intervene (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov. Protests and motions to intervene must be served on the applicant either by mail or email (with a link to the document) at: Antauis Byrd, P.O. Box 1396, Houston, Texas 77251; or by email: antauis.byrd@williams.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online. Service can be via email with a link to the document. All timely, unopposed 7 motions to intervene are automatically granted by operation of Rule 214(c)(1).8 Motions to intervene that are filed after the intervention deadline are untimely, and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and 6 Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. 7 The applicant has 15 days from the submittal of a motion to intervene to file a written objection to the intervention. 8 18 CFR 385.214(c)(1). VerDate Sep<11>2014 17:01 Aug 26, 2022 Jkt 256001 provide justification by reference to factors set forth in Rule 214(d) of the Commission’s Rules and Regulations.9 A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties. Tracking the Proceeding Throughout the proceeding, additional information about the project will be available from the Commission’s Office of External Affairs, at (866) 208– FERC, or on the FERC website at https:// www.ferc.gov using the ‘‘eLibrary’’ link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/docs-filing/ esubscription.asp. Intervention Deadline: 5:00 p.m. Eastern Time on September 13, 2022. Dated: August 23, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–18559 Filed 8–26–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2459–278] Lake Lynn Generation, LLC; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Application Type: Temporary Variance from Reservoir Elevation. b. Project No.: 2459–278. c. Date Filed: August 17, 2022. d. Applicant: Lake Lynn Generation, LLC. e. Name of Project: Lake Lynn Hydroelectric Project. 9 18 PO 00000 CFR 385.214(b)(3) and (d). Frm 00025 Fmt 4703 Sfmt 4703 52761 f. Location: The Lake Lynn Hydroelectric Project is located on the Cheat River in Monongalia County, West Virginia, and Fayette County, Pennsylvania. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)–825(r). h. Applicant Contact: Ms. Joyce Foster, Director, Licensing and Compliance, 7315 Wisconsin Avenue, Ste. 1100W, Bethesda, MD 20814, (804) 338–5110. i. FERC Contact: Zeena Aljibury, (202) 502–6065, zeena.aljibury@ferc.gov. j. Deadline for filing comments, motions to intervene, and protests: 20 days from the issuance date of this notice by the Commission. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, and protests using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/doc-sfiling/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852. The first page of any filing should include the docket number P–2459–278. Comments emailed to Commission staff are not considered part of the Commission record. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person whose name appears on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Request: The applicant requests Commission approval for a temporary variance from the reservoir elevation requirements at Lake Lynn. Due to lack of precipitation E:\FR\FM\29AUN1.SGM 29AUN1

Agencies

[Federal Register Volume 87, Number 166 (Monday, August 29, 2022)]
[Notices]
[Pages 52759-52761]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-18559]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP22-495-000]


Transcontinental Gas Pipe Line Company, LLC; Notice of 
Application and Establishing Intervention Deadline

    Take notice that on August 9, 2022, Transcontinental Gas Pipe Line 
Company, LLC (Transco), Post Office Box 1396, Houston, Texas 77251, 
filed

[[Page 52760]]

an application under section 7(c) of the Natural Gas Act (NGA), and 
Part 157 of the Commission's regulations to construct, install, modify, 
operate and maintain its Texas to Louisiana Energy Pathway Project 
(Project) and to authorize the conversion of 130,000 dekatherms per day 
(Dth/day) of capacity currently subject to Transco's ``IT Feeder 
System'' to firm transportation capacity under the Project. 
Specifically, Transco requests authorization to (i) construct a new 
15,900 horsepower (HP) compressor station in Fort Bend County, Texas, 
(ii) modify six existing compressor units at Compressor Station 40 in 
Hardin County, Texas, (iii) as well as perform programming updates at 
Compressor Station 23 in Victoria County, Texas to accommodate new flow 
conditions. Transco states that the capacity conversion, along with 
turnback capacity and incremental capacity, will yield the 364.4 
million cubic feet per day (MMcf/d) of project capacity. Transco 
estimates the cost of the project to be $91,781,074, all as more fully 
set forth in the application which is on file with the Commission and 
open for public inspection.
    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (https://ferc.gov) using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. At this time, 
the Commission has suspended access to the Commission's Public 
Reference Room, due to the proclamation declaring a National Emergency 
concerning the Novel Coronavirus Disease (COVID-19), issued by the 
President on March 13, 2020. For assistance, contact the Federal Energy 
Regulatory Commission at [email protected] or call toll-free, 
(886) 208-3676 or TYY, (202) 502-8659.
    Any questions regarding the proposed project should be directed to 
Antauis Byrd, P.O. Box 1396, Houston, Texas 77251; by phone at (713) 
215-3741; or by email to [email protected].
    Pursuant to Section 157.9 of the Commission's Rules of Practice and 
Procedure,\1\ within 90 days of this Notice the Commission staff will 
either: complete its environmental review and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or environmental 
assessment (EA) for this proposal. The filing of an EA in the 
Commission's public record for this proceeding or the issuance of a 
Notice of Schedule for Environmental Review will serve to notify 
federal and state agencies of the timing for the completion of all 
necessary reviews, and the subsequent need to complete all federal 
authorizations within 90 days of the date of issuance of the Commission 
staff's FEIS or EA.
---------------------------------------------------------------------------

    \1\ 18 CFR (Code of Federal Regulations) 157.9.
---------------------------------------------------------------------------

Public Participation

    There are two ways to become involved in the Commission's review of 
this project: you can file comments on the project, and you can file a 
motion to intervene in the proceeding. There is no fee or cost for 
filing comments or intervening. The deadline for filing a motion to 
intervene is 5:00 p.m. Eastern Time on September 13, 2022.

Comments

    Any person wishing to comment on the project may do so. Comments 
may include statements of support or objections to the project as a 
whole or specific aspects of the project. The more specific your 
comments, the more useful they will be. To ensure that your comments 
are timely and properly recorded, please submit your comments on or 
before September 13, 2022.
    There are three methods you can use to submit your comments to the 
Commission. In all instances, please reference the Project docket 
number CP22-495-000 in your submission.
    (1) You may file your comments electronically by using the eComment 
feature, which is located on the Commission's website at www.ferc.gov 
under the link to Documents and Filings. Using eComment is an easy 
method for interested persons to submit brief, text-only comments on a 
project;
    (2) You may file your comments electronically by using the eFiling 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to Documents and Filings. With eFiling, you can provide 
comments in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You will be asked to select the type of filing you 
are making; first select ``General'' and then select ``Comment on a 
Filing''; or
    (3) You may file a paper copy of your comments by mailing them to 
the following address below.\2\ Your written comments must reference 
the Project docket number (CP22-495-000). Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE, Washington, 
DC 20426.
---------------------------------------------------------------------------

    \2\ Hand delivered submissions in docketed proceedings should be 
delivered to Health and Human Services, 12225 Wilkins Avenue, 
Rockville, Maryland 20852.
---------------------------------------------------------------------------

    The Commission encourages electronic filing of comments (options 1 
and 2 above) and has eFiling staff available to assist you at (202) 
502-8258 or [email protected]
    Persons who comment on the environmental review of this project 
will be placed on the Commission's environmental mailing list, and will 
receive notification when the environmental documents (EA or EIS) are 
issued for this project and will be notified of meetings associated 
with the Commission's environmental review process.
    The Commission considers all comments received about the project in 
determining the appropriate action to be taken. However, the filing of 
a comment alone will not serve to make the filer a party to the 
proceeding. To become a party, you must intervene in the proceeding. 
For instructions on how to intervene, see below.

Interventions

    Any person, which includes individuals, organizations, businesses, 
municipalities, and other entities,\3\ has the option to file a motion 
to intervene in this proceeding. Only intervenors have the right to 
request rehearing of Commission orders issued in this proceeding and to 
subsequently challenge the Commission's orders in the U.S. Circuit 
Courts of Appeal.
---------------------------------------------------------------------------

    \3\ 18 CFR 385.102(d).
---------------------------------------------------------------------------

    To intervene, you must submit a motion to intervene to the 
Commission in accordance with Rule 214 of the Commission's Rules of 
Practice and Procedure \4\ and the regulations under the NGA \5\ by the 
intervention deadline for the project, which is September 13, 2022. As 
described further in Rule 214, your motion to intervene must state, to 
the extent known, your position regarding the proceeding, as well as 
your interest in the proceeding. For an individual, this could include 
your status as a landowner, ratepayer, resident of an impacted 
community, or recreationist. You do not need to have property directly 
impacted by the project in order to intervene. For more

[[Page 52761]]

information about motions to intervene, refer to the FERC website at 
https://www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------

    \4\ 18 CFR 385.214.
    \5\ 18 CFR 157.10.
---------------------------------------------------------------------------

    There are two ways to submit your motion to intervene. In both 
instances, please reference the Project docket number CP22-495-000 in 
your submission.
    (1) You may file your motion to intervene by using the Commission's 
eFiling feature, which is located on the Commission's website 
(www.ferc.gov) under the link to Documents and Filings. New eFiling 
users must first create an account by clicking on ``eRegister.'' You 
will be asked to select the type of filing you are making; first select 
``General'' and then select ``Intervention.'' The eFiling feature 
includes a document-less intervention option; for more information, 
visit https://www.ferc.gov/docs-filing/efiling/document-less-intervention.pdf.; or
    (2) You can file a paper copy of your motion to intervene, along 
with three copies, by mailing the documents to the address below.\6\ 
Your motion to intervene must reference the Project docket number CP22-
495-000. Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE, Washington, DC 20426.
---------------------------------------------------------------------------

    \6\ Hand delivered submissions in docketed proceedings should be 
delivered to Health and Human Services, 12225 Wilkins Avenue, 
Rockville, Maryland 20852.
---------------------------------------------------------------------------

    The Commission encourages electronic filing of motions to intervene 
(option 1 above) and has eFiling staff available to assist you at (202) 
502-8258 or [email protected]
    Protests and motions to intervene must be served on the applicant 
either by mail or email (with a link to the document) at: Antauis Byrd, 
P.O. Box 1396, Houston, Texas 77251; or by email: 
[email protected]. Any subsequent submissions by an intervenor 
must be served on the applicant and all other parties to the 
proceeding. Contact information for parties can be downloaded from the 
service list at the eService link on FERC Online. Service can be via 
email with a link to the document.
    All timely, unopposed \7\ motions to intervene are automatically 
granted by operation of Rule 214(c)(1).\8\ Motions to intervene that 
are filed after the intervention deadline are untimely, and may be 
denied. Any late-filed motion to intervene must show good cause for 
being late and must explain why the time limitation should be waived 
and provide justification by reference to factors set forth in Rule 
214(d) of the Commission's Rules and Regulations.\9\ A person obtaining 
party status will be placed on the service list maintained by the 
Secretary of the Commission and will receive copies (paper or 
electronic) of all documents filed by the applicant and by all other 
parties.
---------------------------------------------------------------------------

    \7\ The applicant has 15 days from the submittal of a motion to 
intervene to file a written objection to the intervention.
    \8\ 18 CFR 385.214(c)(1).
    \9\ 18 CFR 385.214(b)(3) and (d).
---------------------------------------------------------------------------

Tracking the Proceeding

    Throughout the proceeding, additional information about the project 
will be available from the Commission's Office of External Affairs, at 
(866) 208-FERC, or on the FERC website at https://www.ferc.gov using the 
``eLibrary'' link as described above. The eLibrary link also provides 
access to the texts of all formal documents issued by the Commission, 
such as orders, notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. For more information and to register, go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Intervention Deadline: 5:00 p.m. Eastern Time on September 13, 
2022.

    Dated: August 23, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-18559 Filed 8-26-22; 8:45 am]
BILLING CODE 6717-01-P