Transcontinental Gas Pipe Line Company, LLC; Notice of Application and Establishing Intervention Deadline, 52759-52761 [2022-18559]
Download as PDF
52759
Federal Register / Vol. 87, No. 166 / Monday, August 29, 2022 / Notices
(Commission or FERC) is soliciting
public comment on the currently
approved information collection FERC–
577 (Natural Gas Facilities:
Environmental Review and
Compliance).
Comments on the collection of
information are due October 28, 2022.
ADDRESSES: You may submit your
comments (identified by Docket No.
IC22–26–000) by one of the following
methods:
Electronic filing through https://
www.ferc.gov, is preferred.
• Electronic Filing: Documents must
be filed in acceptable native
applications and print-to-PDF, but not
in scanned or picture format.
• For those unable to file
electronically, comments may be filed
by USPS mail or by hand (including
courier) delivery:
Æ Mail via U.S. Postal Service Only:
Addressed to: Federal Energy
Regulatory Commission, Secretary of the
Commission, 888 First Street NE,
Washington, DC 20426.
Æ Hand (including courier) delivery:
Addressed to: Federal Energy
DATES:
Regulatory Commission, Secretary of the
Commission,12225 Wilkins Avenue,
Rockville, MD 20852.
Instructions: All submissions must be
formatted and filed in accordance with
submission guidelines at: https://
www.ferc.gov. For user assistance,
contact FERC Online Support by email
at ferconlinesupport@ferc.gov, or by
phone at (866) 208–3676 (toll-free).
Docket: Users interested in receiving
automatic notification of activity in this
docket or in viewing/downloading
comments and issuances in this docket
may do so at https://www.ferc.gov.
FOR FURTHER INFORMATION CONTACT:
Ellen Brown may be reached by email
at DataClearance@FERC.gov, telephone
at (202) 502–8663.
SUPPLEMENTARY INFORMATION:
Title: FERC–577, Natural Gas
Facilities: Environmental Review and
Compliance.
OMB Control No.: 1902–0128.
Type of Request: Three-year extension
of the FERC–577 with no changes to the
current reporting requirements.
Abstract: The FERC–577 contains the
Commission’s information collection
pertaining to regulations which
implement the National Environmental
Policy Act (NEPA) as well as the
reporting requirements for landowner
notifications. These requirements are
contained in 18 CFR parts 2, 157, 284,
and 380. The information to be
submitted includes draft environmental
material in accordance with the
provisions of part 380 of FERC’s
regulations in order to implement the
Commission’s procedures under NEPA.
Without such information, the
Commission would be unable to fulfill
its statutory responsibilities under the
Natural Gas Act (NGA), NEPA, and the
Energy Policy Act of 2005. Specifically,
these responsibilities include ensuring
company activities remain consistent
with the public interest, which is
specified in the NGA and inherent in
the other statutes.
Type of Respondents: Companies
proposing Natural Gas Projects under
section 7 and Jurisdictional Gas Pipeline
and Storage Companies.
Estimate of Annual Burden: 1 The
Commission estimates the annual public
reporting burden and cost 2 for the
information collection as follows.
FERC–577, NATURAL GAS FACILITIES: ENVIRONMENTAL REVIEW AND COMPLIANCE
Number of
respondents
Number of
responses per
respondent
Total
number of
responses
Average burden
hours and
average cost
per response
($)
(rounded)
Total annual
burden hours
and total
annual cost
($)
(rounded)
Cost per
respondent
($)
(rounded)
(1)
(2)
(1) * (2) = (3)
(4)
(3) * (4) = (5)
(5) ÷ (1) = (6)
Gas Pipeline Certificates 3.
Landowners Notification 4.
khammond on DSKJM1Z7X2PROD with NOTICES
Total ......................
101
16
1,616
164
144
........................
........................
Comments: Comments are invited on:
(1) whether the collection of
information is necessary for the proper
performance of the functions of the
Commission, including whether the
information will have practical utility;
(2) the accuracy of the agency’s estimate
of the burden and cost of the collection
of information, including the validity of
the methodology and assumptions used;
(3) ways to enhance the quality, utility
and clarity of the information collection;
and (4) ways to minimize the burden of
the collection of information on those
1 Burden is defined as the total time, effort, or
financial resources expended by persons to
generate, maintain, retain, or disclose or provide
information to or for a federal agency. See 5 CFR
1320 for additional information on the definition of
information collection burden.
VerDate Sep<11>2014
17:01 Aug 26, 2022
Jkt 256001
23,616
193.52 hours;
$17,610.32.
2 hours; $182 ..............
312,725 hours;
$28,457,975.
47,232 hours;
$4,298,112.
25,232
.....................................
359,957 hours;
$32,756,087.
who are to respond, including the use
of automated collection techniques or
other forms of information technology.
Dated: August 23, 2022.
Kimberly D. Bose,
Secretary.
$281,762.13
$26,208
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP22–495–000]
[FR Doc. 2022–18566 Filed 8–26–22; 8:45 am]
BILLING CODE 6717–01–P
Transcontinental Gas Pipe Line
Company, LLC; Notice of Application
and Establishing Intervention Deadline
Take notice that on August 9, 2022,
Transcontinental Gas Pipe Line
Company, LLC (Transco), Post Office
Box 1396, Houston, Texas 77251, filed
2 The Commission staff estimates that industry is
similarly situated in terms of hourly cost (for wages
plus benefits). Based on the Commission’s FY
(Fiscal Year) 2022 average cost (for wages plus
benefits), $91.00/hour is used.
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
3 Requirements are found in 18 CFR parts 2, 157,
and 380.
4 Requirements are found in 18 CFR 157(d),
157(f), 2.55(a), 2.55(b), 284.11, and 380.15.
E:\FR\FM\29AUN1.SGM
29AUN1
khammond on DSKJM1Z7X2PROD with NOTICES
52760
Federal Register / Vol. 87, No. 166 / Monday, August 29, 2022 / Notices
an application under section 7(c) of the
Natural Gas Act (NGA), and Part 157 of
the Commission’s regulations to
construct, install, modify, operate and
maintain its Texas to Louisiana Energy
Pathway Project (Project) and to
authorize the conversion of 130,000
dekatherms per day (Dth/day) of
capacity currently subject to Transco’s
‘‘IT Feeder System’’ to firm
transportation capacity under the
Project. Specifically, Transco requests
authorization to (i) construct a new
15,900 horsepower (HP) compressor
station in Fort Bend County, Texas, (ii)
modify six existing compressor units at
Compressor Station 40 in Hardin
County, Texas, (iii) as well as perform
programming updates at Compressor
Station 23 in Victoria County, Texas to
accommodate new flow conditions.
Transco states that the capacity
conversion, along with turnback
capacity and incremental capacity, will
yield the 364.4 million cubic feet per
day (MMcf/d) of project capacity.
Transco estimates the cost of the project
to be $91,781,074, all as more fully set
forth in the application which is on file
with the Commission and open for
public inspection.
In addition to publishing the full text
of this document in the Federal
Register, the Commission provides all
interested persons an opportunity to
view and/or print the contents of this
document via the internet through the
Commission’s Home Page (https://
ferc.gov) using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. At this
time, the Commission has suspended
access to the Commission’s Public
Reference Room, due to the
proclamation declaring a National
Emergency concerning the Novel
Coronavirus Disease (COVID–19), issued
by the President on March 13, 2020. For
assistance, contact the Federal Energy
Regulatory Commission at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Any questions regarding the proposed
project should be directed to Antauis
Byrd, P.O. Box 1396, Houston, Texas
77251; by phone at (713) 215–3741; or
by email to antauis.byrd@williams.com.
Pursuant to Section 157.9 of the
Commission’s Rules of Practice and
Procedure,1 within 90 days of this
Notice the Commission staff will either:
complete its environmental review and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
1 18
CFR (Code of Federal Regulations) 157.9.
VerDate Sep<11>2014
17:01 Aug 26, 2022
Jkt 256001
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or environmental assessment (EA) for
this proposal. The filing of an EA in the
Commission’s public record for this
proceeding or the issuance of a Notice
of Schedule for Environmental Review
will serve to notify federal and state
agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
Public Participation
There are two ways to become
involved in the Commission’s review of
this project: you can file comments on
the project, and you can file a motion
to intervene in the proceeding. There is
no fee or cost for filing comments or
intervening. The deadline for filing a
motion to intervene is 5:00 p.m. Eastern
Time on September 13, 2022.
Comments
Any person wishing to comment on
the project may do so. Comments may
include statements of support or
objections to the project as a whole or
specific aspects of the project. The more
specific your comments, the more useful
they will be. To ensure that your
comments are timely and properly
recorded, please submit your comments
on or before September 13, 2022.
There are three methods you can use
to submit your comments to the
Commission. In all instances, please
reference the Project docket number
CP22–495–000 in your submission.
(1) You may file your comments
electronically by using the eComment
feature, which is located on the
Commission’s website at www.ferc.gov
under the link to Documents and
Filings. Using eComment is an easy
method for interested persons to submit
brief, text-only comments on a project;
(2) You may file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to Documents and
Filings. With eFiling, you can provide
comments in a variety of formats by
attaching them as a file with your
submission. New eFiling users must
first create an account by clicking on
‘‘eRegister.’’ You will be asked to select
the type of filing you are making; first
select ‘‘General’’ and then select
‘‘Comment on a Filing’’; or
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
(3) You may file a paper copy of your
comments by mailing them to the
following address below.2 Your written
comments must reference the Project
docket number (CP22–495–000).
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
The Commission encourages
electronic filing of comments (options 1
and 2 above) and has eFiling staff
available to assist you at (202) 502–8258
or FercOnlineSupport@ferc.gov.
Persons who comment on the
environmental review of this project
will be placed on the Commission’s
environmental mailing list, and will
receive notification when the
environmental documents (EA or EIS)
are issued for this project and will be
notified of meetings associated with the
Commission’s environmental review
process.
The Commission considers all
comments received about the project in
determining the appropriate action to be
taken. However, the filing of a comment
alone will not serve to make the filer a
party to the proceeding. To become a
party, you must intervene in the
proceeding. For instructions on how to
intervene, see below.
Interventions
Any person, which includes
individuals, organizations, businesses,
municipalities, and other entities,3 has
the option to file a motion to intervene
in this proceeding. Only intervenors
have the right to request rehearing of
Commission orders issued in this
proceeding and to subsequently
challenge the Commission’s orders in
the U.S. Circuit Courts of Appeal.
To intervene, you must submit a
motion to intervene to the Commission
in accordance with Rule 214 of the
Commission’s Rules of Practice and
Procedure 4 and the regulations under
the NGA 5 by the intervention deadline
for the project, which is September 13,
2022. As described further in Rule 214,
your motion to intervene must state, to
the extent known, your position
regarding the proceeding, as well as
your interest in the proceeding. For an
individual, this could include your
status as a landowner, ratepayer,
resident of an impacted community, or
recreationist. You do not need to have
property directly impacted by the
project in order to intervene. For more
2 Hand delivered submissions in docketed
proceedings should be delivered to Health and
Human Services, 12225 Wilkins Avenue, Rockville,
Maryland 20852.
3 18 CFR 385.102(d).
4 18 CFR 385.214.
5 18 CFR 157.10.
E:\FR\FM\29AUN1.SGM
29AUN1
khammond on DSKJM1Z7X2PROD with NOTICES
Federal Register / Vol. 87, No. 166 / Monday, August 29, 2022 / Notices
information about motions to intervene,
refer to the FERC website at https://
www.ferc.gov/resources/guides/how-to/
intervene.asp.
There are two ways to submit your
motion to intervene. In both instances,
please reference the Project docket
number CP22–495–000 in your
submission.
(1) You may file your motion to
intervene by using the Commission’s
eFiling feature, which is located on the
Commission’s website (www.ferc.gov)
under the link to Documents and
Filings. New eFiling users must first
create an account by clicking on
‘‘eRegister.’’ You will be asked to select
the type of filing you are making; first
select ‘‘General’’ and then select
‘‘Intervention.’’ The eFiling feature
includes a document-less intervention
option; for more information, visit
https://www.ferc.gov/docs-filing/efiling/
document-less-intervention.pdf.; or
(2) You can file a paper copy of your
motion to intervene, along with three
copies, by mailing the documents to the
address below.6 Your motion to
intervene must reference the Project
docket number CP22–495–000.
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
The Commission encourages
electronic filing of motions to intervene
(option 1 above) and has eFiling staff
available to assist you at (202) 502–8258
or FercOnlineSupport@ferc.gov.
Protests and motions to intervene
must be served on the applicant either
by mail or email (with a link to the
document) at: Antauis Byrd, P.O. Box
1396, Houston, Texas 77251; or by
email: antauis.byrd@williams.com. Any
subsequent submissions by an
intervenor must be served on the
applicant and all other parties to the
proceeding. Contact information for
parties can be downloaded from the
service list at the eService link on FERC
Online. Service can be via email with a
link to the document.
All timely, unopposed 7 motions to
intervene are automatically granted by
operation of Rule 214(c)(1).8 Motions to
intervene that are filed after the
intervention deadline are untimely, and
may be denied. Any late-filed motion to
intervene must show good cause for
being late and must explain why the
time limitation should be waived and
6 Hand delivered submissions in docketed
proceedings should be delivered to Health and
Human Services, 12225 Wilkins Avenue, Rockville,
Maryland 20852.
7 The applicant has 15 days from the submittal of
a motion to intervene to file a written objection to
the intervention.
8 18 CFR 385.214(c)(1).
VerDate Sep<11>2014
17:01 Aug 26, 2022
Jkt 256001
provide justification by reference to
factors set forth in Rule 214(d) of the
Commission’s Rules and Regulations.9
A person obtaining party status will be
placed on the service list maintained by
the Secretary of the Commission and
will receive copies (paper or electronic)
of all documents filed by the applicant
and by all other parties.
Tracking the Proceeding
Throughout the proceeding,
additional information about the project
will be available from the Commission’s
Office of External Affairs, at (866) 208–
FERC, or on the FERC website at https://
www.ferc.gov using the ‘‘eLibrary’’ link
as described above. The eLibrary link
also provides access to the texts of all
formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. For more information and to
register, go to www.ferc.gov/docs-filing/
esubscription.asp.
Intervention Deadline: 5:00 p.m.
Eastern Time on September 13, 2022.
Dated: August 23, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022–18559 Filed 8–26–22; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2459–278]
Lake Lynn Generation, LLC; Notice of
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Application Type: Temporary
Variance from Reservoir Elevation.
b. Project No.: 2459–278.
c. Date Filed: August 17, 2022.
d. Applicant: Lake Lynn Generation,
LLC.
e. Name of Project: Lake Lynn
Hydroelectric Project.
9 18
PO 00000
CFR 385.214(b)(3) and (d).
Frm 00025
Fmt 4703
Sfmt 4703
52761
f. Location: The Lake Lynn
Hydroelectric Project is located on the
Cheat River in Monongalia County,
West Virginia, and Fayette County,
Pennsylvania.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Ms. Joyce
Foster, Director, Licensing and
Compliance, 7315 Wisconsin Avenue,
Ste. 1100W, Bethesda, MD 20814, (804)
338–5110.
i. FERC Contact: Zeena Aljibury, (202)
502–6065, zeena.aljibury@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests: 20
days from the issuance date of this
notice by the Commission.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, and protests using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/doc-sfiling/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, you
may submit a paper copy. Submissions
sent via the U.S. Postal Service must be
addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Room
1A, Washington, DC 20426.
Submissions sent via any other carrier
must be addressed to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 12225 Wilkins Avenue,
Rockville, Maryland 20852. The first
page of any filing should include the
docket number P–2459–278. Comments
emailed to Commission staff are not
considered part of the Commission
record.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. Description of Request: The
applicant requests Commission
approval for a temporary variance from
the reservoir elevation requirements at
Lake Lynn. Due to lack of precipitation
E:\FR\FM\29AUN1.SGM
29AUN1
Agencies
[Federal Register Volume 87, Number 166 (Monday, August 29, 2022)]
[Notices]
[Pages 52759-52761]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-18559]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP22-495-000]
Transcontinental Gas Pipe Line Company, LLC; Notice of
Application and Establishing Intervention Deadline
Take notice that on August 9, 2022, Transcontinental Gas Pipe Line
Company, LLC (Transco), Post Office Box 1396, Houston, Texas 77251,
filed
[[Page 52760]]
an application under section 7(c) of the Natural Gas Act (NGA), and
Part 157 of the Commission's regulations to construct, install, modify,
operate and maintain its Texas to Louisiana Energy Pathway Project
(Project) and to authorize the conversion of 130,000 dekatherms per day
(Dth/day) of capacity currently subject to Transco's ``IT Feeder
System'' to firm transportation capacity under the Project.
Specifically, Transco requests authorization to (i) construct a new
15,900 horsepower (HP) compressor station in Fort Bend County, Texas,
(ii) modify six existing compressor units at Compressor Station 40 in
Hardin County, Texas, (iii) as well as perform programming updates at
Compressor Station 23 in Victoria County, Texas to accommodate new flow
conditions. Transco states that the capacity conversion, along with
turnback capacity and incremental capacity, will yield the 364.4
million cubic feet per day (MMcf/d) of project capacity. Transco
estimates the cost of the project to be $91,781,074, all as more fully
set forth in the application which is on file with the Commission and
open for public inspection.
In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and/or print the contents of this document via the
internet through the Commission's Home Page (https://ferc.gov) using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. At this time,
the Commission has suspended access to the Commission's Public
Reference Room, due to the proclamation declaring a National Emergency
concerning the Novel Coronavirus Disease (COVID-19), issued by the
President on March 13, 2020. For assistance, contact the Federal Energy
Regulatory Commission at [email protected] or call toll-free,
(886) 208-3676 or TYY, (202) 502-8659.
Any questions regarding the proposed project should be directed to
Antauis Byrd, P.O. Box 1396, Houston, Texas 77251; by phone at (713)
215-3741; or by email to [email protected].
Pursuant to Section 157.9 of the Commission's Rules of Practice and
Procedure,\1\ within 90 days of this Notice the Commission staff will
either: complete its environmental review and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or environmental
assessment (EA) for this proposal. The filing of an EA in the
Commission's public record for this proceeding or the issuance of a
Notice of Schedule for Environmental Review will serve to notify
federal and state agencies of the timing for the completion of all
necessary reviews, and the subsequent need to complete all federal
authorizations within 90 days of the date of issuance of the Commission
staff's FEIS or EA.
---------------------------------------------------------------------------
\1\ 18 CFR (Code of Federal Regulations) 157.9.
---------------------------------------------------------------------------
Public Participation
There are two ways to become involved in the Commission's review of
this project: you can file comments on the project, and you can file a
motion to intervene in the proceeding. There is no fee or cost for
filing comments or intervening. The deadline for filing a motion to
intervene is 5:00 p.m. Eastern Time on September 13, 2022.
Comments
Any person wishing to comment on the project may do so. Comments
may include statements of support or objections to the project as a
whole or specific aspects of the project. The more specific your
comments, the more useful they will be. To ensure that your comments
are timely and properly recorded, please submit your comments on or
before September 13, 2022.
There are three methods you can use to submit your comments to the
Commission. In all instances, please reference the Project docket
number CP22-495-000 in your submission.
(1) You may file your comments electronically by using the eComment
feature, which is located on the Commission's website at www.ferc.gov
under the link to Documents and Filings. Using eComment is an easy
method for interested persons to submit brief, text-only comments on a
project;
(2) You may file your comments electronically by using the eFiling
feature, which is located on the Commission's website (www.ferc.gov)
under the link to Documents and Filings. With eFiling, you can provide
comments in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You will be asked to select the type of filing you
are making; first select ``General'' and then select ``Comment on a
Filing''; or
(3) You may file a paper copy of your comments by mailing them to
the following address below.\2\ Your written comments must reference
the Project docket number (CP22-495-000). Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 888 First Street NE, Washington,
DC 20426.
---------------------------------------------------------------------------
\2\ Hand delivered submissions in docketed proceedings should be
delivered to Health and Human Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
---------------------------------------------------------------------------
The Commission encourages electronic filing of comments (options 1
and 2 above) and has eFiling staff available to assist you at (202)
502-8258 or [email protected]
Persons who comment on the environmental review of this project
will be placed on the Commission's environmental mailing list, and will
receive notification when the environmental documents (EA or EIS) are
issued for this project and will be notified of meetings associated
with the Commission's environmental review process.
The Commission considers all comments received about the project in
determining the appropriate action to be taken. However, the filing of
a comment alone will not serve to make the filer a party to the
proceeding. To become a party, you must intervene in the proceeding.
For instructions on how to intervene, see below.
Interventions
Any person, which includes individuals, organizations, businesses,
municipalities, and other entities,\3\ has the option to file a motion
to intervene in this proceeding. Only intervenors have the right to
request rehearing of Commission orders issued in this proceeding and to
subsequently challenge the Commission's orders in the U.S. Circuit
Courts of Appeal.
---------------------------------------------------------------------------
\3\ 18 CFR 385.102(d).
---------------------------------------------------------------------------
To intervene, you must submit a motion to intervene to the
Commission in accordance with Rule 214 of the Commission's Rules of
Practice and Procedure \4\ and the regulations under the NGA \5\ by the
intervention deadline for the project, which is September 13, 2022. As
described further in Rule 214, your motion to intervene must state, to
the extent known, your position regarding the proceeding, as well as
your interest in the proceeding. For an individual, this could include
your status as a landowner, ratepayer, resident of an impacted
community, or recreationist. You do not need to have property directly
impacted by the project in order to intervene. For more
[[Page 52761]]
information about motions to intervene, refer to the FERC website at
https://www.ferc.gov/resources/guides/how-to/intervene.asp.
---------------------------------------------------------------------------
\4\ 18 CFR 385.214.
\5\ 18 CFR 157.10.
---------------------------------------------------------------------------
There are two ways to submit your motion to intervene. In both
instances, please reference the Project docket number CP22-495-000 in
your submission.
(1) You may file your motion to intervene by using the Commission's
eFiling feature, which is located on the Commission's website
(www.ferc.gov) under the link to Documents and Filings. New eFiling
users must first create an account by clicking on ``eRegister.'' You
will be asked to select the type of filing you are making; first select
``General'' and then select ``Intervention.'' The eFiling feature
includes a document-less intervention option; for more information,
visit https://www.ferc.gov/docs-filing/efiling/document-less-intervention.pdf.; or
(2) You can file a paper copy of your motion to intervene, along
with three copies, by mailing the documents to the address below.\6\
Your motion to intervene must reference the Project docket number CP22-
495-000. Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street NE, Washington, DC 20426.
---------------------------------------------------------------------------
\6\ Hand delivered submissions in docketed proceedings should be
delivered to Health and Human Services, 12225 Wilkins Avenue,
Rockville, Maryland 20852.
---------------------------------------------------------------------------
The Commission encourages electronic filing of motions to intervene
(option 1 above) and has eFiling staff available to assist you at (202)
502-8258 or [email protected]
Protests and motions to intervene must be served on the applicant
either by mail or email (with a link to the document) at: Antauis Byrd,
P.O. Box 1396, Houston, Texas 77251; or by email:
[email protected]. Any subsequent submissions by an intervenor
must be served on the applicant and all other parties to the
proceeding. Contact information for parties can be downloaded from the
service list at the eService link on FERC Online. Service can be via
email with a link to the document.
All timely, unopposed \7\ motions to intervene are automatically
granted by operation of Rule 214(c)(1).\8\ Motions to intervene that
are filed after the intervention deadline are untimely, and may be
denied. Any late-filed motion to intervene must show good cause for
being late and must explain why the time limitation should be waived
and provide justification by reference to factors set forth in Rule
214(d) of the Commission's Rules and Regulations.\9\ A person obtaining
party status will be placed on the service list maintained by the
Secretary of the Commission and will receive copies (paper or
electronic) of all documents filed by the applicant and by all other
parties.
---------------------------------------------------------------------------
\7\ The applicant has 15 days from the submittal of a motion to
intervene to file a written objection to the intervention.
\8\ 18 CFR 385.214(c)(1).
\9\ 18 CFR 385.214(b)(3) and (d).
---------------------------------------------------------------------------
Tracking the Proceeding
Throughout the proceeding, additional information about the project
will be available from the Commission's Office of External Affairs, at
(866) 208-FERC, or on the FERC website at https://www.ferc.gov using the
``eLibrary'' link as described above. The eLibrary link also provides
access to the texts of all formal documents issued by the Commission,
such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. For more information and to register, go to
www.ferc.gov/docs-filing/esubscription.asp.
Intervention Deadline: 5:00 p.m. Eastern Time on September 13,
2022.
Dated: August 23, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-18559 Filed 8-26-22; 8:45 am]
BILLING CODE 6717-01-P