Village of Enosburg Falls, Vermont; Notice of Intent To Prepare an Environmental Assessment, 50078 [2022-17496]

Download as PDF 50078 Federal Register / Vol. 87, No. 156 / Monday, August 15, 2022 / Notices Service Agreement Nos. 48 & 49 to be effective 8/5/2022. Filed Date: 8/9/22. Accession Number: 20220809–5054. Comment Date: 5 p.m. ET 8/30/22. The filings are accessible in the Commission’s eLibrary system (https:// elibrary.ferc.gov/idmws/search/ fercgensearch.asp) by querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: August 9, 2022. Debbie-Anne A. Reese, Deputy Secretary. [FR Doc. 2022–17488 Filed 8–12–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2905–035] Village of Enosburg Falls, Vermont; Notice of Intent To Prepare an Environmental Assessment On April 30, 2021, the Village of Enosburg Falls, Vermont (Village) filed a relicense application for the 975kilowatt Enosburg Falls Hydroelectric Project No. 2905 (project). The project is located on the Missisquoi River in Franklin County, Vermont. The project does not occupy federal land. In accordance with the Commission’s regulations, on June 2, 2022, Commission staff issued a notice that the project was ready for environmental analysis (REA Notice). Based on the information in the record, including comments filed on the REA Notice, staff does not anticipate that licensing the project would constitute a major federal action significantly affecting the quality of the human environment. Therefore, staff intends to prepare an Environmental Assessment (EA) on the application to relicense the project. The EA will be issued and circulated for review by all interested parties. All comments filed on the EA will be analyzed by staff and considered in the Commission’s final licensing decision. The application will be processed according to the following schedule. Revisions to the schedule may be made as appropriate. Milestone Target date Commission issues EA ................................................................................................................................................................ Comments on EA ......................................................................................................................................................................... This is a supplemental notice in the above-referenced proceeding of Chaparral Springs, LLC’s application for market-based rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is August 29, 2022. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically may mail similar pleadings to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Hand delivered submissions in docketed proceedings should be delivered to Health and Human Services, 12225 Wilkins Avenue, Rockville, Maryland 20852. In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission’s Home Page (https:// www.ferc.gov) using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission’s Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659. 1 The Council on Environmental Quality’s (CEQ) regulations under 40 CFR 1501.10(b)(1) require that EAs be completed within 1 year of the federal action agency’s decision to prepare an EA. This notice establishes the Commission’s intent to prepare an EA for the Enosburg Falls Hydroelectric Project. Therefore, in accordance with CEQ’s regulations, the EA must be issued within 1 year of the issuance date of this notice. Any questions regarding this notice may be directed to John Baummer at (202) 502–6837 or john.baummer@ ferc.gov. Dated: August 9, 2022. Kimberly D. Bose, Secretary. [FR Doc. 2022–17496 Filed 8–12–22; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER22–2622–000] Chaparral Springs, LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization khammond on DSKJM1Z7X2PROD with NOTICES February 2023.1 March 2023. VerDate Sep<11>2014 17:24 Aug 12, 2022 Jkt 256001 PO 00000 Frm 00011 Fmt 4703 Sfmt 4703 E:\FR\FM\15AUN1.SGM 15AUN1

Agencies

[Federal Register Volume 87, Number 156 (Monday, August 15, 2022)]
[Notices]
[Page 50078]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-17496]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2905-035]


Village of Enosburg Falls, Vermont; Notice of Intent To Prepare 
an Environmental Assessment

    On April 30, 2021, the Village of Enosburg Falls, Vermont (Village) 
filed a relicense application for the 975-kilowatt Enosburg Falls 
Hydroelectric Project No. 2905 (project). The project is located on the 
Missisquoi River in Franklin County, Vermont. The project does not 
occupy federal land.
    In accordance with the Commission's regulations, on June 2, 2022, 
Commission staff issued a notice that the project was ready for 
environmental analysis (REA Notice). Based on the information in the 
record, including comments filed on the REA Notice, staff does not 
anticipate that licensing the project would constitute a major federal 
action significantly affecting the quality of the human environment. 
Therefore, staff intends to prepare an Environmental Assessment (EA) on 
the application to relicense the project.
    The EA will be issued and circulated for review by all interested 
parties. All comments filed on the EA will be analyzed by staff and 
considered in the Commission's final licensing decision.
    The application will be processed according to the following 
schedule. Revisions to the schedule may be made as appropriate.
---------------------------------------------------------------------------

    \1\ The Council on Environmental Quality's (CEQ) regulations 
under 40 CFR 1501.10(b)(1) require that EAs be completed within 1 
year of the federal action agency's decision to prepare an EA. This 
notice establishes the Commission's intent to prepare an EA for the 
Enosburg Falls Hydroelectric Project. Therefore, in accordance with 
CEQ's regulations, the EA must be issued within 1 year of the 
issuance date of this notice.

------------------------------------------------------------------------
                  Milestone                           Target date
------------------------------------------------------------------------
Commission issues EA........................  February 2023.\1\
Comments on EA..............................  March 2023.
------------------------------------------------------------------------

    Any questions regarding this notice may be directed to John Baummer 
at (202) 502-6837 or [email protected].

    Dated: August 9, 2022.
Kimberly D. Bose,
Secretary.
[FR Doc. 2022-17496 Filed 8-12-22; 8:45 am]